CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Part II

Introduction to

Offshore Structures

Hodjat ShiriCentre for Offshore Foundation Systems (COFS)

July 2009

Page 2: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Offshore Installation of Fixed Platforms:

• Topsides :

• Jackets :

Lifting by HLV

Floatover by FLB

Page 3: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:• HLV Positioning & Mooring• Transportation Barge approach• Transportation Barge Mooring alongside HLV• Lifting rig connection• Slings Tensioning• Sea-fastening cutting• Topside lifting• Transportation Barge release• HLV Re-positioning • Deck mating• Installation Completion

Page 4: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

HLV

Topside Barge

Page 5: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 6: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 7: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 8: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 9: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 10: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:• HLV Positioning & Mooring• Transportation Barge approach• Transportation Barge Mooring alongside HLV• Lifting rig connection• Slings Tensioning• Sea-fastening cutting• Topside lifting• Transportation Barge release• HLV Re-positioning • Deck mating• Installation Completion

Page 11: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

• FLB Anchoring• FLB Approach to Jacket• FLB Enter Jacket Inside• FLB Mooring to Jacket• Sea-Fastening Cutting• Barge Ballasting• Deck Mating & Load Transfer (Jacking, Ballasting…)• Mating Completion• FLB Release• FLB Anchor recovery• Installation Completion

Topside Float Over Installation:

Page 12: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 13: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:

Page 14: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

• HLV Positioning & Mooring• Transportation Barge approach• Transportation Barge Mooring alongside HLV• Lifting rig connection• Slings Tensioning• Sea-fastening cutting• Jacket lifting and upending• Transportation Barge release• HLV Re-positioning • Jacket positioning ( Position, Orientation, Direction)• Pile Driving• Installation Completion

Jacket Lifting Installation:

Page 15: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:• Launch Barge Anchoring • Launching Arms Preparation• Buoyancy Tanks check• Barge Approach to right position• Sea-fastening Cutting• Barge Ballasting and Tilting• Jacket Sliding & Barge Moving• Jacket launching & Floating• Jacket Upending (Lifting or Self-Upending)• Jacket Positioning ( Tugs or HLVs)• Pile Driving• Installation Completion

Page 16: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:• Launch Barge Anchoring • Launching Arms Preparation• Buoyancy Tanks check• Barge Approach to right position• Sea-fastening Cutting• Barge Ballasting and Tilting• Jacket Sliding & Barge Moving• Jacket launching & Floating• Jacket Upending (Lifting or Self-Upending)• Jacket Positioning ( Tugs or HLVs)• Pile Driving• Installation Completion

Page 17: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:

Page 18: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:

Page 19: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Launching Analysis:

Launching

Self-UpendingBarge Release

1 2 3

4 5

Page 20: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Pile Driving :

• Pile Transportation Barge comes alongside HLV• Pile Preparation• Jacket Preparation• Hammer Preparation • Pile Lead Section lifting up and Stabbing into jacket leg or Sleeve• Hammer lift up and stabbing on top of pile • Pile driving according to engineering sequences• Lifting up the First add-on, Stabbing to Lead section, Welding• Non Destructive Tests on Welds (NDT)• Pile Stopper Removal and Driving first add-on• Regular check of Jacket level ness • Continuos Blow Count and Dynamic Stress Applied on Pile• Continue to Finish Pile Driving• Installation of Crown Plates• Installation of Transition Pieces

Page 21: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Pile Driving :

Hydraulic Hammer Diesel Hammer

Pile Lift Up

Piles Arrangement

Hammer Stabbing

Page 22: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Pile Driving :

Completed Jacket Pile Cut-off Crown Plate Welding

Pile in Driving

Page 23: Offshore Structures Slides

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

End of Part Two