Top Banner

of 11

Ocean Electricity

Apr 03, 2018

Download

Documents

Madhu Naani
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/29/2019 Ocean Electricity

    1/11

    OCEAN ELECTRICITY (pelamis)

    A NON-CONVENTIONAL ENERGY SOURCE

    AVR & SVR COLLEGE OF ENGINEERING

    AND TECHNOLOGY

    NANDYAL (KURNOOL.DIST)

    PRESENTATION BY:

    FURQUAN NADEEM,

    III EEE,

    8500783663,AVR & SVR CET,

    NANDYAL, KURNOOL (dist), [email protected].

    V.DINESH,

    III EEE,

    9160836151,

    AVR & SVR CET,

    NANDYAL, KURNOOL (dist), A.P.

    [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/29/2019 Ocean Electricity

    2/11

    Abstract:

    Over the last few years development associated with low or even

    zero based greenhouse gas emitting energy sources is on its

    peak. More recently volatility in the price of oil and gas has

    increased the number of problems of low greenhouse gas

    emitting energy sources. Our paper mainly concerns in this

    aspect to produce electricity with the lowest p/kWh with no-fuel

    and delivers power at round the clock without any pollution at88% efficiency with 750Kw rated value . Hence we go for Ocean

    energy with Gaint Sea Snake - ( Pelamis Wave Energy

    Converter).

    About Wave Energy:

    Wave energy is a concentrated form of solar energy: the Sunproduces temperature differences across the globe, causing

    winds that blow over the ocean surface. These cause ripples,

    which grow into swells. Such waves can then travel thousandsof miles with virtually no loss of energy. Dont confuse these

    deepwater waves with the waves you see breaking onthe

    beach. When a wave reaches shallow water (roughly when thedepth of the water is less than half a wavelength), it slows

    down, its wavelength decreases and it grows in height, whichleads to breaking. The major losses of energy are through

    breaking and through friction with the seabed, so only afraction of the resource reaches the shore.A wave carries both

    kinetic and gravitational potential energy. The total energy ofa wave depends on two factors: its height H and its period

    T.The power carried by the wave is proportional to H*H andto T, and is usually given in watt per meter of incident wave

    front.P=(H)square*(T)/2 KW/m.

    Pelamis Wave Power Ltd :

    Pelamis Wave Power (www.pelamiswave.com) has been

    developing the Pelamis technology for the past 10 years,Headquartered in Edinburgh,Scotland. The prototype for

    the Portuguese machines was launched in February 2004 andfirst supplied electricity to the UK grid in August 2004. The

    company has worked closely with a wide range ofPortuguese suppliers in the development of this project and

    with a view to the onward commercial roll out of thetechnology in Portugal. And successfully Pelamis power

    plant was established in jan-2007 with commercial success at

    PORTUGAL.

    Developing of Pelamis

    Engineering development:

    1998 2003: 1/20 and 1/33-scale models tested tophysically validate numerical simulations of wave

    energy absorption efficiency and mooring loads

    (survivability).

    2001 ongoing: 1/7-scale model tested in large tank(regular waves) and Firth of Forth (random waves) to

    develop control system

    2002 ongoing: Full-scale power module bench rig

    tested to qualify mechanical and electrical

    components and to assess MTBF (reliability) andcontrol system performance

    Commercial Devolopment:

    Two main requirements governed the design of the Pelamismachine: survivability and availability .A wave energy

    converter should be designed to resist any sea state, even themost extreme one, and then designed to maximize the power

    capture. In addition,Pelamis is designed to use readilyavailable components; it is innovative in its over-all design

    and assembly. Pelamis Wave Power were very thorough in

    their development of Pelamis. They used severalnumerical (computer) models of different levels of

    complexity, and many scale models were built and tested inwave tanks to validate the numerical predictions .In 2004 a

    full-scale prototype was tested in the

    North Sea and later installed in the European Marine EnergyCentre. The success of the test programme led to the sale of

    three machines to a Portuguese consortium lead by Enersis.These machines have been assembled in a shipyard in

    Portugal and they are being installed about now (autumn2007). A second stage with 27 more machines is already

    planned. The next few years will determine if the new waveenergy industry can emulate what has been created for wind

    energy in the recent past. The technology exists, conditionshave never been better and the sea has been waiting for far too

    long.

    Pelamis Wave Energy converter:

    The Pelamis Wave Energy Converter also known as GAINT

    SEA SNAKE - (Pelamis Wave Power, 2009) was developed

    by Pelamis Wave Power Ltd (previously Ocean Power

    Delivery). This is worlds first medium scale commercial

    successfully running wave/ocean energy power plant

    producing 1,407 MWH/year with a rated capacity of 750kw

    at a efficiency of 88% . Depending on the wave resource,machines will on average produce 25-40% of the full rated

    output over the course of a year. Each machine can provide

    sufficient power to meet the annual electricity demand of

    Approximately 500 homes

  • 7/29/2019 Ocean Electricity

    3/11

    Fig: Pelamis wave enery convertor in off-shore sea level.

    The device is a semi-submerged structure composed of

    cylindrical sections linked by hinged joints. The wave-induced

    motion of these joints is resisted by hydraulic rams, whichpump high-pressure fluid through hydraulic motors via

    smoothing accumulators. The hydraulic motors drive

    electrical generators to produce electricity. Power from all the

    joints is fed down a single umbilical cable to a junction on the

    sea bed. Several devices can be connected together and linked

    to shore through a single seabed cable.

    Single Unit Details

    Fig: Pelamis unit at the service center in portugal.

    Current units are 140 m long and 3.5 m in diameter with 3power conversion modules per machine. Each unit is rated at

    750 kW. Conditions of the installation site affect the amountof energy produced by Pelamis. (Pelamis Wave Power, 2009).

    The units provide hands free operation. No maintenance isneeded to be carried out offshore and no offshore intervention

    is required. According to the developers it has a built insurvivability. The technology has been developed and tested

    for a number of years, so it has been verified and insured. Thefirst stage of production is manufacturing power conversion

    modules which contain power capture systems. The module

    consists of a fabricated and painted steel structure that is

    populated with systems that include motor generator set,

    hydraulic cylinders, accumulators, reservoirs and electrical

    control cabinets. These systems are delivered to the modulepopulation facility where they are installed, assembled and the

    completed power conversion module commissioned. The

    main structural fabrication consists of steel tubes, nose andyoke sections. The nose section is installed with transformer,

    switchgear and control systems and is commissioned. Eachtube is fitted with cabling and connecting transits as well as

    ballast to ensure the correct displacement and trim of themachine. The machine is assembled of modules and tube

    segments which are joined together. These joints can be madeboth on land and in the water depending on the facilities used.

    The fully assembled machine then undergoes quaysidecommissioning prior to sea-trials and on-site installation at the

    wave farm.

    Offshore infrastructure:

    The offshore infrastructure consists of three main componentswhich are necessary to install:

    (i)Mooring spreads(ii) Mubsea power cables and

    (iii)Latch assembly which connects the main moorings to the

    dynamic cables.The latch assembly provides a single point toconnect the Pelamis units to both the main moorings and the

    power cables. All components and sub-systems within thePelamis power take-off and conversion systems have been.

    Pelamis has been designed to be a fault tolerant generatingsystem with the incorporation of multiple levels of

    redundancy throughout all systems (structural, moorings,hydraulics, electrical and control) and with all failure paths

    ending with inherently safe modes so that the survivability,

    station-keeping and in most cases; generating functionality ofthe system is not compromised. This unique, fault tolerantcapacity is central to operating and maintaining a generator in

    the harshest of environments, where opportunities formaintenance interventions can be very limited, especially

    through heavy storm seasons (Pelamis Wave Power, 2009).

    There are several projects both ongoing and planned whichinvolve Pelamis device deployment:

    (i) Aguuadoura, Portugal (Power Technologies, 2009) the first multiunit wave farm, with three machines

    in operation,

    (ii) planned Orcadian Wave Farm, UK four Pelamismachines planned to be installed in Orkneymainland, Scotland,

    (iii) Wave Hub, UK the UK first offshore facility forthe demonstration and proving of the operation of

    arrays of wave energy generation devices (PelamisWave Power, 2009).

  • 7/29/2019 Ocean Electricity

    4/11

    How does it work?

    Ocean Power Deliverys solution is named Pelamis, after

    Pelamis platuru s, a meter-long sea snake which lives in the

    Indian and Pacific Oceans. The Pelamis wave energy

    converter is 150 m Long and has a diameter of 3.5 m. 74

    members of staff work on Current projects and are also

    developing future generations of Machines. The Pelamis is asemi-submerged, articulated floating structure composed of

    four long cylindrical sections linked by hinged joints. At each

    joint there is a power conversion module. Its mooring

    System ensures that the Pelamis machine aligns itself head-onwith incoming waves. How does Pelamis make electricity?

    As waves travel down the length of the machine the structure

    Bends around the joints.

    This motion pushes hydraulic rams that pump high-pressure

    oilThrough hydraulic motors.

    The hydraulic motors drive generators to produce electricity.

    Power from all the joints is fed down a single umbilicalcable to a junction on the seabed.

    fig: power generating unit.

    The Technologies

    The WEC device chosen for the San Francisco point design isthe Pelamis from Ocean Power Delivery (OPD). The device

    consists of a total of 4 cylindrical steel sections, which areconnected together by 3 hydraulic power conversion modules

    (PCM). Total length of the device is 120m and device

    diameter is 4.6m. Figure 7 shows the device being tested off

    the Scottish coast. Individual units are arranged in wave farmsto meet specific energy demands in a particular site as

    illustrated in Figure.

    Figure : Pelamis pre-production prototype undergoingsea-trials

    Figure : A typical Pelamis wave farm

    The following sections provide a high level overview of the

    different subsystems that are device specific. Subsystemscovered include the power conversion modules (PCM), the

    structural steel sections and the mooring system. The summary

    table below shows the key specifications of the Pelamis.

    Table 1: Pelamis Device Specifications

    Structure

    Overall Length 123 m

    Diameter 4.6m

    Displacement 700 tons

    Nose 5m long conical drooped

    Power Take Off 3 independent PCMs

  • 7/29/2019 Ocean Electricity

    5/11

    Total Steel Weight 380 tons

    Power Conversion Module (PCM)

    Power Take Off 4 x

    hydraulic rams (2 heave, 2

    sway)

    Ram Speed

    0 0.1 m/s Power Smoothing Storage

    High pressure Accumulators

    Working Pressure 100 350 barsPower Conversion 2 xvariable displacement

    motors

    Generator

    2 x 125kW Generator speed

    1500 rpm

    Power

    Rated Power 750kW

    Generator Type Asynchronous

    System Voltage 3-phase,415/690VAC 50/60Hz

    Transformer 950kVA stepup to required voltage

    Site Mooring

    Water depth > 50m

    Current Speed < 1 knot

    Mooring Type Compliant slack moored

    Fig 1: System Level Design of PCM at San Francisco

    Offshore Wave Power Plant.

    As illustrated in Figure-2, a total of 3 power conversion

    modules (PCMs) connect the 4 individual steel tubes forming

    a Pelamis device. Each PCM contains a heave and sway joint.

    The modular power-pack is housed in a second fully sealed

    compartment

    behind the ram

    bay so that in the

    event of seal

    failure only the

    hydraulic rams

    are immersed.

    Access to all

    system

    components is via

    a hatch in the top

    of the power

    conversion

    module.

    Maximum

    individual The

    wave- component

    weight is less than

    3 tons to allowreplacement using

    light lifting

    equipment

    induced motion of

    each joint is

    resisted by sets of

    hydraulic rams

    configured as

    pumps. These

    pump oil into

    smoothingaccumulators

    which then drain

    at a constant rate

    through a

    hydraulic motor

    coupled to an

    electrical

    generator.

    Table 2 : Pilot Plant Pelamis Performance

    Device Rated Capacity 750kW

    Annual Energy Absorbed 1,229 MWh/year

    Device Availability 85%

    Power Conversion Efficiency 80%

    Performance Reduction to

    demo-site (35m)80%

    Annual Generation at bus bar 668 MWh/year

    Average Power Output at busbar

    760kW

    Table 5: Commercial Plant Pelamis Performance

    Device Rated Capacity 500kW

    Annual Energy Absorbed 1,683 MWh/year

    Device Availability 95%

    Power Conversion Efficiency 88%

    Annual Generation at bus bar 1,407 MWh/year

    Average Electrical Power at

    bus bar161 kW

    Pelamis required to meettarget 300,000 MWh/yr

    213

    The Power Conversion Module (PCM)

    _______________________________________

  • 7/29/2019 Ocean Electricity

    6/11

    Fig 2: 3-power generating units of Pelamis.

    The accumulators are sized to allow continuous, smooth output

    across wave groups. An oil-to-water heat exchanger isincluded to dump excess power in large seas and provide the

    necessary thermal load in the event of loss of the grid. Overallpower conversion efficiency ranges from around 70% at

    low power levels to over 80% at full capacity. Each of thethree generator sets are linked by a common 690V, 3 phase

    bus running the length of the device. A single transformer is

    used to step-up the voltage to an appropriate level fortransmission to shore. High Voltage power is fed to the sea

    bed by a single flexible umbilical cable, then to shore via a

    conventional sub-sea cable.

    Manufacturing & Assembly

    Each Pelamis machine is made up of a number of similar

    sections, each of which contains an identical joint assemblyand power take off equipment. The modular design of the

    machine allows PWP to maximise build efficiency and allowsfor easy transition to significant production volumes.

    Pelamis machines are an assembly of off the shelf proventechnology. This use of existing technology widens the

    supply chain options and increases component reliability.PWP choose suppliers and manufactures who work to the

    highest quality, safety and sustainability practices. We arecommitted to developing strong relationships with both new

    and existing suppliers to share and develop knowledge.

    .Fig: Internal parts of PCM.

    The key stages of manufacturing

    Sub assembly of major power take-off components

    Hydraulic cylinders, motors, generators, reservoirs,accumulators and associated piping and wiring are assembled

    and commissioned. A key difference between the P2 andearlier designs is that the power modules are assembled on

    an open frame before posting into the tube sections. Thisminimizes costs and speeds up manufacture.

  • 7/29/2019 Ocean Electricity

    7/11

    Photo above: PWP engineers assemble the motor

    generator sets.

    Structural steel tube and power module fabrication:

    Tube fabrication can be carried out close to the site of the

    project to minimise transport costs.

    Photo above: Steel cans are welded together to form

    longer tubes at PWPs facility in Leith photo courtesy of

    Rob McDougall.

    Tube assembly and painting:

    The power modules are joined to the tubes and installation ofthe sub assemblies and wiring is completed.

    Tube Launch:

    The tubes are currently individually lifted into the water prior

    to mating the joints. In future, a slipway could be used to

    cheaply and quickly launch fully assembled machines orindividual sections.

    Photo above: A tube section (with integrated power

    module) is lifted into the water.

    Final assembly & Commissioning:

    Tubes are joined together, bearing attachments are made andcable transits completed. Once in the water the machines are

    ballasted to the desired level of submergence. Over half themachines final weight is ballast. The machine is then

    commissioned at the quayside before being towed to theprojectsit

    The first P2 Pelamis machine, owned by E.ON, arrives in

    Orkney.

    Installation of Pelamis WEC Plant

    Prior to Pelamis machines being installed on site and gridconnected the wave farm site must first be prepared to receivethe machines. This work includes:

    Pelamis Related Offshore Infrastructure:

    There are three main components to the offshore infrastructurethat it is necessary to install to support a Pelamis wave farm:

    Mooring Spreads:

    Each machine requires its own individual mooring spread

    consisting of the main moorings and a yaw restraint line. Themain moorings consist of a number of anchors connected to a

    central point. The yaw restrain line is a simple single anchorand mooring line configuration. There is scope for

    neighboring mooring spreads to share anchor points,depending on the anchoring techniques employed at the site.

    The Pelamis mooring spread has been designed to minimize

    its footprint area, allowing the highest concentration of MWcapacity to seabed space and reducing infrastructure costs (on

  • 7/29/2019 Ocean Electricity

    8/11

    a typical site up to 30MW of generating capacity could be

    installed within 1km2).

    Fig: Mooring Arrangement of Pelamis

    Subsea Power Cables:

    A power export cable is required to take the power from siteto shore. The export cable is laid by contracted cable installersin the manner and route identified in the development and

    specification stage (note larger projects may require more thanone power export cable). From each array of Pelamis

    machines a dynamic down feeder cable connects to the exportcable, with the machines in the array connected together via

    dynamic inter-connector cables. The dynamic cables areinstalled after the mooring spreads are complete and are then

    connected to the export cable. This split allows the exportcable to be installed ahead of the other offshore infrastructure,

    in turn allowing work on the onshore sub-station to beconducted in parallel with the offshore work. Once connected,

    the subsea cable network can be commissioned and tested forintegrity from the substation, prior to machine installation.

    Fig: Sub Sea Cables

    Latch Assembly:

    PWP has developed a latching assembly which connects themain moorings to the dynamic cables. This latch assembly

    then provides a single point to connect the Pelamis machines

    to both the main moorings and the power cables. The latchassembly is the last piece of infrastructure to be installed.

    PWP has conducted all installation engineering necessary for

    the site construction work completed to date and has now useda wide range of installation vessels.

    The modularization in the design of the offshore infrastructureprovides the greatest flexibility in the specification for the

    required installation vessels, which in turn also providesflexibility in the programming of the work and the ability to

    minimize installation costs (depending upon vessel

    availability and current market rates). It is worth noting thatthis flexibility also applies to decommissioning a Pelamisinstallation, something which PWP has already completed

    successfully.

    System Design Single Unit:

    Pelamis WEC device is floating on the surface and moored in

    a water depth of 35m. An umbilical riser cable is connecting

    the Pelamis to a junction box on the ocean floor. From thisjunction box, a double armored 3 phase cable is buried into

  • 7/29/2019 Ocean Electricity

    9/11

    the soft ocean floor sediments and brought to the sewer pipe

    outfall, which extends 3.75 miles out from the shore. Thecable landing site for the demonstration site is at the San

    Francisco Oceanside wastewater treatment facility. The

    wastewater treatment facility is connected by a 12kVdistribution line to the nearest substation, which can be used

    to feed power into the grid.

    System Design - Commercial Scale Wave Power Plant:

    Whereas the conceptual design of the demonstration plantsystem focused on finding existing easements, allowing the

    installation of a small demonstration system in a cost effectivemanner, the commercial scale wave plant design focused on

    establishing a solidcosting base case, and assessing manufacturing and true

    operational costs for a the commercial-scale plant. Thecommercial scale cost numbers were used to compare energy

    costs to commercial wind farms to come to a conclusion on

    the cost competitiveness of wave power in this particular

    location. While the demonstration plant lying within the SFexclusion zone of the Monterey Bay National Marine

    Sanctuary provides an excellent demonstration opportunity, alocation further offshore will yield better economics for the

    commercial plant as the wave power level is higher. Thefollowing subsections outline the electrical system setup, the

    physicallayout and the operational and maintenance requirements of

    such a deployment.

    Electrical Interconnection and Physical Layout:

    the commercial system with a total of 4 clusters, each one

    containing53 or 54 Pelamis units (213 Pelamis WEC devices), connectedto sub-sea cables. Each cluster consists of 3 rows with 17 or

    18 devices per row. Four sub-sea cables connect the fourclusters to shore. The electrical interconnection of the devices

    is accomplished with flexible jumper cables, connecting theunits in mid-water.The introduction of four independent sub-

    sea cables and the interconnection on the surface will provide

    some redundancy in the wave farm arrangement. The 4

    clusters are each 2.67 km long and 1.8 km wide, covering anocean stretch of roughly 11 km. The 4 arrays and their safety

    area occupy roughly 20 square kilometers. Furtherdevice stacking of up to 4 rows might be possible reducing the

    array length, but is not considered in this design, assubsequent rows of devices will likely see a diminished wave

    energy resource and therefore yield a lower output. Sucheffects and their impacts on

    performance are not well understood at present.

    Based on the above setup the following key site parameters

    emerged:

    Array Length 11 km

    Array Width 1.8 km

    Device Spacing 150m

    Number of Rows 3

    System Voltage 26kV

    Operations & Maintenance

    Remote Control & Monitoring:

    Once Pelamis machines have been installed on site, operation

    of the machines is handed over to shore control. Pelamismachines are operated via a bespoke SCADA system with the

    capability of project operation to be incorporated withinclients existing generator operating platforms. This has been

    successfully demonstrated in the Aguadoura project bymachine control from the Pelamis offices in Edinburgh and

    real time data feed into the Enersis SCADA system. Forfurther information see news story.

    Safety:

    Pelamis dedication to safety begins at the conceptual designand strategy stage. In terms of O & M strategy this means

    maintenance is done offsite at an appropriate operations base

    and machine handling techniques are designed to minimisemanual intervention and proximity of vessels and machines to

    each other. Similarly Pelamis has developed throughexperience many tools and techniques for installation,

    surveying, modification and decommissioning of subseainfrastructure without the use of divers and full consideration

    of the many factors affecting safety at sea.

    Rapid hands-free connection and disconnection:

    Crucial to achieving high operability rates is Pelamis strategyof offsite maintenance and development of a rapid hands-

    free connection and disconnection system. In bothconnection and disconnection the only manual intervention is

    the connection of slack synthetic ropes on the surface prior tocontrolling the latching and unlatching mechanisms by remote

    wifi link from the tow vessel. This system has increased theweather conditions in which marine operations can take place

    and significantly reduce the time necessary for intervention.

    Connection and disconnection is now a matter of minutes

    allowing the use of much shorter weather windows whichoccur more frequently. Pelamis has successfully performed

    these operations in waves of over 2m significant height and iscurrently engineering developments to stretch the limiting

    weather criteria for recovery to 3.5m significant wave height.

    Reliability & Multiple Redundancy:

    Unlike many generators, which lose all generating capacity

    through single point failures, Pelamis has been designed to be

  • 7/29/2019 Ocean Electricity

    10/11

    a fault tolerant system with the incorporation of multiple

    levels of redundancy throughout all systems (structural,moorings, hydraulics, electrical and control). Additionally

    failure paths , where possible, have been engineered to end

    with inherently safe modes so that the survivability, station-keeping and in most cases generating functionality of the

    system is not compromised. Pelamis can therefore continuegenerating electricity safely, in many cases with little or no

    loss of performance, with multiple failures within its systems.Intervention strategy can then be tailored to maximise

    economic performance of the farm using in-house softwarewhich Pelamis has developed rather than being driven by a

    simple need for earliest possible recovery.

    Preventative Maintenance:

    Pelamis uses risk-based methodology to determine inspectionand preventative maintenance intervals and is gaining

    valuable in-application reliability data on its componentsthrough the operation of full scale working machines. Planned

    maintenance is carried out at a suitable O & M facility such as

    the one established in Leixes harbor with the work targetedto occur during the months of lower wave energy.

    Vessels:

    Pelamis Wave Power has gained tremendous experience inapplying a broad range of vessels from large offshore anchor

    handlers to small workboats and survey vessels and optimizedsystems and procedures to suit. Developing this in depth

    knowledge of the vessel markets involved and the capabilitiesand working practices of the vessels and their crew has

    allowed Pelamis to tailor procedures and design to maximize

    operational efficiency and safety whilst building the flexibilityneeded to take advantage of market conditions to minimisecost. In doing so, Pelamis has also built effective relationships

    with key players in the industry.

    dvantages of pelamis wave power

    Pelamis offers technological, economic and environmentaladvantages including:

    Low cost of investment is less

    It also displace above 2000 carbon dioxide emissions

    tons per year

    Avoids pollution

    There is going to be only starting investment.

    Minimum environmental impact.

    Plenty of space plus high 'power-density'.

    Survivability - 100 year wave.

    100% available technology.

    Hydraulic Power Take Off.

    Power smoothing.

    Tunable.

    Maximum site flexibility.

    Minimum work on-site.

    Off-site maintenance.

    Major advantage is no requirement of fuel.

    Challenges

    Disturbance or destruction of marine life (includingchanges in the distribution and types of marine life

    near the shore)

    Possible threat to navigation from collisions due to

    the low profile of the wave energy devices above thewater, making them undetectable either by direct

    sighting or by radar. Also possible is the interferenceof mooring and anchorage lines with commercial and

    sport-fishing.

    Degradation of scenic ocean front views from waveenergy devices located near or on the shore, and fromonshore overhead electric transmission lines

    Conclusion:

    In India there are many power plants producing electricity Forproduction of electricity tones of coal is going to used but

    there is no land requirement and fuel cost for the pelamispower plant.. there is only needs to invest amount for

    installation and runs at very low operating cost. And thepower plants 24 hrs and can provided electricity without

    interruption.so compared to all power plants this the bestpower plant producing electricity 24hrs in a day without

    pollution.

    Offshore Demonstration Wave Power plant for a lot of

    reasons, including but not limited to:

    Good wave climate

    Nearby harbor facilities offering marine engineering andlocal infrastructure

    Forward looking city leaders with a renewable energy vision Supportive public who voted for a bond measure to

    implement renewable energy by a large percentage Existing wastewater outflow pipe reducing the cost of

    landing the transmission cableAnd reducing the difficulty of permitting

    Existing marine sanctuary exclusion zone useful fordemonstration plant with

    Minimum permitting issues Existing environmental monitoring program provides the

    capability of determining

  • 7/29/2019 Ocean Electricity

    11/11

    References:

    1. Boud R., 2003, Status and Research and DevelopmentPriorities, Wave and Marine Accessed Energy, UK Dept.

    of Trade and Industry (DTI), DTI Report # FES-R-132,

    AEAT Report # AEAT/ENV/1054, United KingdomEnergy Systems Research Unit, 2009, website accessed14/01/2009.

    www.esru.strath.ac.uk/EandE/Web_sites/0102/RE_info/wave%20power.htm.

    2. Pelamis wave power ltd, which an UK based powergenerating company www.pelamiswave.com.

    3. San Fransico Pelamis conceptual Report: E2I EPRI

    Global 006A SF,Principal Investigator: Mirko

    Previsic, Contributors: Roger Bedard, George

    Hagerman and Omar Siddiqui.

    4. Portuguese organizations including AICEP-PortugalGlobal (www.investinportugal.pt), Instituto Hidrogr.fico

    (www.hidrografico.pt ), Wave Energy Centre (www.wave-energy-centre.org), INESC Porto (www.inescporto.pt)

    and INETI (www.ineti.pt).

    5. From the blog of Joao Cruz is a mechanical engineer atPelamis Wave Power in Edinburgh, where he developssoftware and methods to better characterise and predict the

    state of the sea. He and his colleagues will be monitoringthe worlds first wave energy farm which will be installed

    later this year (2007) in Portugal.www.pelamiswave.com.

    http://www.esru.strath.ac.uk/EandE/Web_sites/0102/RE_info/wave%20power.htmhttp://www.esru.strath.ac.uk/EandE/Web_sites/0102/RE_info/wave%20power.htmhttp://www.pelamiswave.com/http://www.pelamiswave.com/http://www.hidrografico.pt/http://www.inescporto.pt/http://www.ineti.pt/http://www.ineti.pt/http://www.pelamiswave.com/http://www.pelamiswave.com/http://www.pelamiswave.com/http://www.esru.strath.ac.uk/EandE/Web_sites/0102/RE_info/wave%20power.htmhttp://www.esru.strath.ac.uk/EandE/Web_sites/0102/RE_info/wave%20power.htmhttp://www.pelamiswave.com/http://www.hidrografico.pt/http://www.inescporto.pt/http://www.ineti.pt/http://www.pelamiswave.com/