OBG PRESENTS: PreBid Meeting – Contract # NAT17001DAMCONST Improvements to Delaware Dams March 8, 2017, 10:00 am
67

OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Jun 17, 2018

Download

Documents

hadan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

OBG PRESENTS:Pre‐Bid Meeting – Contract # NAT17001‐DAMCONSTImprovements to Delaware DamsMarch 8, 2017, 10:00 am

Page 2: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

AGENDAGeneral Bid Information

Project Overview

Improvements to Chipmans Pond Dam

Improvements to Concord Pond Dam

Improvements to Craigs Pond Dam

Bid Form and Contract Requirements

Questions

2

Page 3: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Project Participants

3

DNREC Division of Fish and Wildlife

Owner / Funding

DNREC Division of Watershed Stewardship

Project Administrator

David Twing, P.E.

Janice Shute, P.E.

Delaware Department of Transportation

Owner

O’Brien & Gere Engineers, Inc.

Project Engineer

Robert Bowers, P.E.Dana Pizarro, P.E.James QuinnStephen Szewczak, P.E.

DNREC Division of Fish and Wildlife

DNREC Division of Watershed Stewardship

Delaware Department of Transportation

O’Brien & Gere Engineers, Inc.

Owner Project Administrator / Funding

Owner Project Engineer

David Twing, P.E.Janice Shute, P.E.

Robert Bowers, P.E.Dana Pizarro, P.E.James QuinnStephen Szewczak, P.E.

Page 4: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Bid Information

Sealed bids are due Wednesday, March 29, 2017 at 3 pm 

Bids received at the reception desk of the DNREC Office at 89 Kings Highway, Dover, DE 19901

Bidders MUST purchase Contract Documents to Bid

• Contract Documents can be obtained from Colleen Ponden at the DNREC Office at 89 Kings Highway, Dover, DE for $50

• Checks made payable to ‘DNREC’4

Page 5: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Completion Time:

500 calendar days

Bid Information

Bids must include ALL attachments• Subcontractor List• Non‐Collusion Statement• Affidavit of Employee Drug Testing Program

• Bid Security• Summary Control of Water Plan for Chipmans Pond Dam

5

Page 6: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Notes to Bidders

There will be no site walkthrough with the Owner. All sites are public and bidders are encouraged to inspect the sites on their own.

Attention is called to the Instructions to Bidders, General Conditions, Supplementary General Conditions and General Requirements in Division 00 of the Contract Documents.

Prevailing wage rates apply to this contract.

Owner has obtained environmental permits for the project. Contractor to obtain construction dewatering permits from DNREC.

Available Geotechnical Data has been provided as reference drawings.

6

Page 7: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Bidder Questions

Questions must be submitted in writing to DNREC• Address questions to Janice Shute• Email is acceptable: [email protected]

All questions must be received by Friday, March 17, 2017

Addenda will be posted to bids.delaware.gov

Pre‐Bid Meeting Attendee List will be posted to bids.delaware.gov

7

Page 8: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Project Overview

• Chipmans Pond Dam in Laurel, DE• Concord Pond Dam and Craigs Pond Dam in Seaford, DE

Improvements to 3 dams in Sussex 

County, DE

• Provide operable gates and low level outlets• Improve operational safety and efficiency• Repair minor deficiencies• Address public safety issues

Project Goals:

8

Page 9: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

9

Page 10: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Additional Project Scope

Control of Water

Traffic Management / Detours

Erosion and Sediment Control Measures

Engineer’s field offices

Site restoration

Boat Ramp at Craigs Pond Dam

10

Page 11: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Chipmans Pond Dam

11

Chipmans Pond Dam

Page 12: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

12

Page 13: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

13

Page 14: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

14

Page 15: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

15

Page 16: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

16

Page 17: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

17

Page 18: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

18

Page 19: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

19

Page 20: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Chipmans Pond Dam – General Scope of ImprovementsSelective Demolition

Concrete Repairs – Headwall and Slab

Steel H‐Piles and Concrete Grade Beam

Structural Steel Gate Support

New Gates – 1 Slide, 2 Weir

Steel Access Platform

Miscellaneous Handrails & Signage

20

Page 21: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Proposed Improvements

21

Page 22: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Chipmans Pond Dam – Key Constraints 

Control of Water – Existing Outlet Configuration• Summary Control of Water Plan REQUIRED with Bid

• Detailed Control of Water Plan prior to mobilization

Overhead Utilities Primary Engineer’s Field Office Location

DelDOT Approved Detour Plan Bridge Load Restrictions Adjacent Property Owner 

– Construction Easement

22

Page 23: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Chipmans Pond Parking Area

23

Page 24: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Concord Pond Dam

24

Page 25: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

25

Page 26: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

26

Page 27: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

27

Page 28: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

28

Page 29: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

29

Page 30: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

30

Page 31: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

31

Page 32: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

32

Page 33: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

33

Page 34: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

34

Page 35: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Concord Pond Dam – General Scope of Improvements

Selective Demolition

Steel H‐Piles/Columns and Concrete Gate Sills

Structural Steel Gate Supports

New Gates – 2 Slide, 6 Weir

Trashracks, Miscellaneous Fabrications and signage

Supplemental Riprap and Dam Warning Buoys35

Page 36: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

36

Page 37: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

37

Page 38: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Concord Pond Dam – Key Constraints 

Control of Water –One set of gates 

must be operational

Overhead Utilities Bridge Load Restrictions

DelDOT Approved Detour Plan

Limited staging and laydown area

Condition of underwater sheet piling is unknown –Allowance Item

38

Page 39: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Craigs Pond Dam

39

Page 40: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

40

Page 41: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

41

Page 42: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

42

Page 43: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

43

Page 44: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

44

Page 45: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

45

Page 46: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

46

Page 47: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

47

Page 48: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

48

Page 49: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

49

Page 50: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Craigs Pond Dam – General Scope of Improvements

Selective Demolition

Concrete Filled Pipe Piles and Concrete Pile Caps

Precast Concrete Gate Boxes and Access Walkway

New Gates – 1 Slide, 1 Weir

Concrete slope protection, Sheet Pile Toe Walls

Supplemental Riprap and Dam Warning Buoys

Parking Lot Improvements

New Concrete Boat Ramp50

Page 51: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Proposed Improvements

51

Page 52: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Proposed Improvements

52

Page 53: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Proposed Improvements

53

Page 54: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Craigs Pond Dam – Key Constraints 

Control of Water Culvert Load Restrictions

DelDOT Approved TMP –No road closure

Minimize damage to parking area

54

Page 55: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Bid Award will be based on Grand Total Bid (Base Bid) and accepted Alternate Items. 

Unit Prices and Allowances are the same for all Bidders. 

Bid Format

Grand Total (Base Bid) Items

• Fixed Lump Sum Item•Lump Sum Items

Alternates

Unit Prices

Allowances55

Page 56: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Grand Total Bid Items

Fixed Lump Sum Item

• Mobilization and Demobilization $75,000

Lump Sum Items

• Improvements to Chipmans Pond Dam

• Improvements to Concord Pond Dam

• Improvements to Craigs Pond Dam

56

Page 57: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Alternates

Only one alternate for this project. Bidders to include a Deduct to delete the improvements associated with the southwest gates at Concord Pond Dam.

Owner’s intention is to perform the base bid, but may use this alternate if price or schedule require.

57

Page 58: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Unit Prices and Allowances

Unit Prices given are the Contract amount that will be paid for work indicated on the Contract Drawings where the quantity indicated is increased by appropriate field modification order.

Allowance Items are to be used only to address additional work that is NOT indicated on the Contract Drawings and is not a Unit Price Item. This is generally to include repairs or rehabilitation of existing features that will not be visible until Control of Water measures are in place.

58

Example:

Overexcavation to remove soft 

material below the subgrade elevation indicated on the drawings as 

directed by the Project Engineer

Page 59: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Subcontractor List

Traffic Control Structural Steel/Metal Fabrication Structural Steel Erection

Water Control Gate Manufacturer/Supplier Pile Driving Sheet Pile Driving

Control of WaterConcrete (Including Repairs and Rehabilitation)

Hot Mix Asphalt Paving

59

Page 60: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Summary Control of Water Plan – Chipmans Pond

A Summary Control of Water Plan for Chipmans Pond Dam MUST be included with the Bid Form

Details, including basis of design, are included in Section 31 52 00, 1.3.A

60

Page 61: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

61

Key Contract Provisions

The following provides an overview of key provisions in the Contract that the Owner wishes to emphasize. The Bidders must be familiar with all requirements contained in the Project Manual and the Contract Drawings.

Page 62: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Contract Length

Contract Length will be 500 calendar days

Contract length based on the following:• Assumed lead times of 12 – 16 weeks for gate fabrication• Provides for sequential work at each site during critical control of water activities

• Includes two summer seasons between May 2017 and September 2018 to overcome weather delays

62

Page 63: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Traffic Management Plan (TMP) During Construction

63

DelDOT approved plans include:

• Detour plans for Chipmans Pond Dam and Concord Pond Dam

• TMP (no road closure) for Craigs Pond Dam 

Contractor requested revisions will require DelDOT approval

Detours and TMP shall only be in place when active work is being performed on a site

Traffic controls require daily inspections

Advance notice of detours is required ‐ Contractor will be responsible for coordination with DelDOT

Page 64: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Field Offices

Successful Bidder to furnish field office trailers for the Engineer

Primary office trailer to be at the Chipmans Pond parking area for the duration of the project.

Smaller secondary office trailers to be provided at Concord Pond and Craigs Pond (Only required while work is ongoing at these sites)

Requirements included in Section 01 51 50 

64

Page 65: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Work by Others

Water level gages to be removed by DEOS prior to construction. Owner will schedule work after receipt of construction schedule.

Reservoir Drawdowns – In anticipation of heavy storms, DNREC typically lowers reservoir levels to prevent overtopping• No drawdown capability at Craigs Pond Dam• If the site is actively under construction, DNREC will direct the Contractor to open existing gates or otherwise drawdown the water level per the COW plan

• If the site is not active, DNREC will perform the drawdown

65

Page 66: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

Reminder

Questions must be submitted in writing to DNREC

• Address questions to Janice Shute• Email is acceptable: [email protected]

All questions must be received by Friday, March 17, 2017

Responses and addenda will be posted to bids.delaware.gov

The Pre‐Bid Meeting Attendee List will be posted to bids.delaware.gov 

66

Thank you for your interest in the project!

Page 67: OBG PRESENTS: –Contract DAMCONST Delaware Damsbidcondocs.delaware.gov/NAT/NAT_17001Damconst_pb-pres.pdf · Chipmans Pond Dam –Key Constraints Control of Water –Existing ...

67

QUESTIONS