Top Banner
Sept. 30, 2015 Sewer Rate Study Update Presented by: Shawn Koorn Associate Vice President HDR Engineering, Inc. City of Oak Harbor
13

Oak Harbor Rate Study

Mar 03, 2017

Download

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Oak Harbor Rate Study

Sept. 30, 2015

Sewer Rate Study Update

Presented by:Shawn KoornAssociate Vice PresidentHDR Engineering, Inc.

City of Oak Harbor

Page 2: Oak Harbor Rate Study

2

Overview of the Presentation

• Review of the previous sewer rate analyses

• Summary of the updated analysis

• Overview of the rate scenarios

• Questions and answers

Page 3: Oak Harbor Rate Study

3

Prior Sewer Rate Analyses

3

• Established initial projections during the 2009 rate study– Used conservative borrowing assumptions and

estimated capital costs• Updated the analysis for financing scenarios in

2012 for the feasibility study– Updated O&M and other capital assumptions– Updated revenue projections– Various funding sources (loans/bonds/grants)– Based on project cost estimates at that time

• Updated the analyses for planned long-term debt issuance

Page 4: Oak Harbor Rate Study

4

Overview of the Updated Sewer Analysis

4

• Analysis reviews the 2016 – 2021 time period• Updated revenue projections based on current

customer information and adopted rates– Rates were adopted through 2016 (last adjustment in

December 2015)• Updated O&M expenses

– Based on current budgeted O&M– Estimated O&M for the new WWTF– Annual inflation assumed at 3.5%

• Updated the capital improvement plan– Items other than the WWTF

• Updated fund balances (reserves)

Page 5: Oak Harbor Rate Study

5

WWTF Capital Cost Scenarios

5

• Based on the current financing scenarios– 2015 and 2016 SRF loans– 2015/16 revenue bond and close-out bond– Grants– Use of reserves (capital and SDCs)

• Developed three rate scenarios– Low project cost ($90 million)– Mid project cost ($98 million)– High project cost ($110 million)

• Each scenario results in different long-term debt amounts and annual debt service payments

• Developed rate adjustments to meet DSC ratios and minimum target reserve funds

Page 6: Oak Harbor Rate Study

6

Capital Plan Summary

• Project costs are based on preliminary estimates– May not reflect actual year of total costs

• 2018 through 2021 reflects typical annual capital– Approximately $500,000 per year on average

$0

$10,000,000

$20,000,000

$30,000,000

$40,000,000

$50,000,000

$60,000,000

$70,000,000

$80,000,000

2015 2016 2017 2018 2019 2020 2021

Low Mid High

Page 7: Oak Harbor Rate Study

7

• Key difference is the annual debt service payments– Ability to maintain required DSC ratios

• All three options maintain target minimum reserve levels

• Rate adjustments would be implemented the December prior to the year effective

• Reserves are utilized in several years (2018 & 2019) to fund annual deficiencies (both O&M and capital needs)

Summary of the Proposed Sewer Rate Transition Plans

7

2017 2018 2019 2020 2021

Low Estimate 15.0% 12.0% 10.0% 10.0% 8.0%

Mid Estimate 15.0% 15.0% 15.0% 10.0% 9.5%

High Estimate 20.0% 15.0% 15.0% 15.0% 15.0%

Page 8: Oak Harbor Rate Study

8

Residential Customer Bill Impacts

• Developed approximate monthly residential customer bill impacts based the scenarios

• 2015 is the current residential customer rate• 2016 is the adopted residential customer rate

– 12.5% adjustment effective Jan 1, 2016

8

2015 2016 2017 2018 2019 2020 2021

Low Estimate $57.50 $64.75 $74.46 $83.40 $91.74 $100.91 $108.98

Mid Estimate $57.50 $64.75 $74.46 $85.63 $98.48 $108.32 $118.62

High Estimate $57.50 $64.75 $77.70 $89.36 $102.76 $118.17 $135.90

Page 9: Oak Harbor Rate Study

9

Residential Customer Bill Impacts(cont’d)

9

$40.00$50.00$60.00$70.00$80.00$90.00

$100.00$110.00$120.00$130.00$140.00

2015 2016 2017 2018 2019 2020 2021

Low Mid High

Page 10: Oak Harbor Rate Study

10

Preliminary Debt Service Coverage Ratios

• Combined utility (water and sewer) calculation– Actual calculation will exclude utility taxes

• Minimum of 1.0• Target of 1.25 and above

0

0.5

1

1.5

2

2.5

3

3.5

2016 2017 2018 2019 2020 2021

Low Mid High

Page 11: Oak Harbor Rate Study

11

Summary of the Reserve Funds• Target minimums vary based on total revenue

– Operating fund is 25% of total revenues, including additional revenues from rate adjustments

– Target is approximately $2.2 million in 2015 increasing to $3.6 million in 2021

• Reserve funds exclude the SDC fund

$0

$1,000,000

$2,000,000

$3,000,000

$4,000,000

$5,000,000

$6,000,000

2015 2016 2017 2018 2019 2020 2021

Low Mid High Target

Page 12: Oak Harbor Rate Study

12

Summary of the Updated Analysis

• Annual rate adjustments vary depending on final project cost and total borrowing

• Rates provide required DSC ratios and meet minimum target reserve funds

• Additional low cost borrowing (low interest loans) and grants will reduce overall rate impacts

• Through 2018 rate impacts are similar to what was provided during the feasibility study– Final three years (2019 – 2021) were not included in

the prior analyses

Page 13: Oak Harbor Rate Study

13