2015 DISTRICT 12 CONSTRUCTION PROGRAM
2016 CONSTRUCTION PROGRAM
SERVING CUYAHOGA, GEAUGA AND LAKE COUNTIES.
OHIO DEPARTMENT OF TRANSPORTATION
DISTRICT 12
JOHN R. KASICH, OHIO GOVERNOR | JERRY WRAY, ODOT DIRECTOR | MYRON S. PAKUSH, DISTRICT DEPUTY DIRECTOR
Lake County……………………………............................. Page 35
Regional Projects…………………………………………. Page 41
Local-Let Projects………………………………………… Page 43
2016 DISTRICT 12 CONSTRUCTION PROGRAM
OVERVIEW 2
Taking Care of What We Have
Most people notice when ODOT builds something new. However, we
actually spend 93% of our time and resources taking care of what we have.
We apply that 93% to more than 43,000 miles of roads and 14,000 bridges
in the state.
Unfortunately, repair costs have gone up while funding has not. What cost
$1 to fix in 2006 costs $1.56 today. So with little additional funding on the
horizon, we have to look at how we can stretch our dollars further.
How do we stretch funds, support the economy and maintain safety
while preserving our system?
ODOT has spent the last 10 years moving to a more data-focused approach to managing and improving our
transportation system. With this 2016 construction season, we are implementing new, smarter ways to
improve safety and protect the huge investment Ohioans have in our roads and bridges. Our innovative, three-pronged approach will allow us to
redirect an estimated $300 million toward more preservation over the next six years.
This approach includes state-of-the-art technology for better
decision-making, aggressive preservation treatments and more
collaboration across ODOT’s divisions. We are switching gears
from fixing the “worst first” to a preservation strategy. It makes
good business sense to get out in front of problems before they
occur. That’s why we’ll be cleaning, sweeping, sealing, painting
and resurfacing statewide on an even more aggressive schedule
than ever before. We’re striving for a new level of consistency
across the state, so we can keep repeating best practices and
eliminate practices that aren’t effective in terms of cost, time and
quality. With greater collaboration and more information about
our transportation assets, we can identify and address concerns faster to keep our roads and bridges in better shape.
We spend 93% of our time
and resources taking care
of what we have.
Innovators. Again.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
OVERVIEW 3
Aggressive Preservation Treatments Instead of traditional (and more expensive) treatments for roads and bridges, ODOT districts across the state are including a variety of more frequent
and cost-effective strategies in their annual construction work plans, such as:
Bridge deck sealing
Bridge cleaning and sweeping
Crack sealing
Chip/micro/smooth sealing
Underdrain clean-outs
A big change in our preservation strategies is more chip seal and microsurfacing to extend surface life. Chip seal allows ODOT to maintain roads at a
fourth of the cost of conventional overlays. With chip seal overlays, we extend the time between full-depth replacements. This lowers costs over the
long term, enabling ODOT to resurface more roads and provide a smoother ride for more people.
We won’t chip seal just any road.
We’ll consider several factors,
including average daily traffic (no
chip seal on roads with more than
2,500 or truck traffic of 250) and the
overall condition of the road. We’ll
use treatments when and where they
are appropriate. We’ll do more
inspections on chip seals to improve
quality and guarantee performance.
We’re also more proactively cleaning and sealing bridges to keep the joints, side structure, surfaces and drains in good repair and extend surface life.
If we don’t clean a bridge regularly, the dirt and water sit on the steel, which can make it rust and deteriorate more rapidly. Bridges are very
expensive. Keeping them lasting longer is smart and cost-effective.
Ensuring Quality.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
OVERVIEW 4
The Ohio Department of Transportation, District 12 is responsible for the maintenance and construction
of all interstates, U.S. and State Routes in unincorporated municipalities in Cuyahoga, Geauga and Lake
counties. Every spring, we shift our focus from snow and ice removal to the construction and repair of
our roadways.
The 2016 Construction Guide includes information about major construction projects in the District 12,
tri-county area. Projects to which ODOT has contributed money but are administered by local agencies
are listed at the back of the book. Tentative start and completion dates are included to provide you with
a project timeline.
As with every construction season, we ask motorists to use caution when traveling
through work zones. By obeying posted speed limits and exercising caution,
motorists can do their part to keep both our construction employees and fellow
motorists safe.
For the latest on ODOT’s three major Cleveland Urban Core Projects and to sign-up
to receive project related e-mails, motorists are encouraged to log-on to the
following website:
George V. Voinovich Bridge and the entire downtown Cleveland
“Innerbelt” Corridor: www.Innerbelt.org. For questions or concerns, call the project
hotline at 216.344.0069 (855.803.5280 toll-free) or e-mail the team
Noise barrier replacement on I-71 northbound at various locations in Middleburg Heights and on the I-271 southbound ramp to I-480 westbound in the city
of Warrensville Heights and village of North Randall. Shoulder and off-peak lane closures. Estimated start: July 2016. Estimated complete: November
2016.
Map # 14 – State Route 10/Lorain-Carnegie (Hope Memorial) Bridge, Cuyahoga County
PROJECT I.D.: 99756 - BID AMOUNT: $1,623,000
Replace the overhead street lighting and add debris netting to the underside of the Hope Memorial Bridge in the city of Cleveland. Minor impacts to
traffic. Started: January 2015. Estimated complete: May 2016.
Map # 23 – Interstate 77, Cuyahoga County
PROJECT I.D.: 77419 - BID AMOUNT: $27,373,449
Replace the I-77 bridge deck and parapets over the Cuyahoga River, Canal Road, SR 17 and the Ohio Canal in the city of Independence and village of
Cuyahoga Heights. Off-peak lane and shoulder closures. Started: June 2013. Estimated complete: June 2017.
Map # 23 – Interstate 77, Cuyahoga County
PROJECT I.D.: 87855 - ESTIMATED COST: $18,100,000
Bridge painting on I-77 over the Cuyahoga River, Canal Road, State Route 17 and the Ohio Canal in the cities of Independence and Cuyahoga Heights.
Estimated start: May 2016. Estimated complete: October 2017.
Map # 32 – Interstate 90, Cuyahoga County
PROJECT I.D.: 90759 - BID AMOUNT: $2,976,350
Noise barrier replacement on I-90 between East 96th Street and Coit Road in the village of Bratenahl. Off-peak lane closures. Started: September 2015.
Estimated complete: October 2016.
Map # 40 – State Route 87, Cuyahoga County
PROJECT I.D.: 80988 - BID AMOUNT: $671,774
Traffic management system installation including decorative signal poles, traffic signs and traffic controllers on SR 87 between I-271 and Belmont Road
in the village of Woodmere. Traffic will be maintained. Started February 2016. Estimated complete: June 2016.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 7
PROJECTS WITH MINIMAL IMPACTS TO TRAFFIC
Map # 41 – Interstate 271, Cuyahoga County
PROJECT I.D.: 100791 - BID AMOUNT: $835,549
Build a noise barrier on I-271 southbound between Woodland Road and Shaker Boulevard in the city of Beachwood. Off-peak lane closures. Estimated
start: April 2016. Estimated complete: September 2016.
The following projects are in various locations across Cuyahoga County:
Interstate 80, Cuyahoga County
PROJECT I.D.: 98622 - ESTIMATED COST: $3,951,500
Noise barrier installation on I-80 at various locations in the cities of Strongsville, North Royalton and Olmsted Falls and Olmsted Township. Estimated
start: September 2016. Estimated complete: October 2017.
Cleveland Heights Safe Routes to School, Cuyahoga County
PROJECT I.D.: 98324 - ESTIMATED COST: $155,000
Safe Routes to School project to improve pedestrian crossings, signage, speed feedback signs and bike racks at various schools in the city of Cleveland
Heights. Estimated start: July 2016. Estimated complete: September 2016.
East Cleveland Safe Routes to School, Cuyahoga County
PROJECT I.D.: 93609 - BID AMOUNT: $406,400
East Cleveland Safe Routes to School safety upgrades including signage, crosswalks, pedestrian signals and sidewalks in the city of East Cleveland.
Start: September 2015. Estimated complete June 2016.
Lakewood Traffic Signals Upgrades, Cuyahoga County
PROJECT I.D.: 82797 - ESTIMATED COST: $2,649,686
Lakewood traffic signal upgrade in the city of Lakewood. Estimated start: June 2016. Estimated complete: October 2017.
Lyndhurst Safe Routes to School, Cuyahoga County
PROJECT I.D.: 96347 - ESTIMATED COST: $50,000
Safe Routes to School project to improve crosswalks, ADA ramps, school flashers and sidewalks at Sunview Elementary in the city of Lyndhurst.
Estimated start: August 2016. Estimated complete: December 2016.
South Euclid Safe Routes to School, Cuyahoga County
PROJECT I.D.: 96348 - ESTIMATED COST: $273,500
Safe Routes to School project to improve crosswalks, sidewalk and bike paths & drop-off areas at four schools in the city of South Euclid. Estimated
start: September 2016. Estimated complete: February 2017.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 8
PROJECTS WITH MINIMAL IMPACTS TO TRAFFIC
Various Locations, Cuyahoga County
PROJECT I.D.: 100168 - ESTIMATED COST: $490,000
Storm sewer cleaning at various locations in Cuyahoga County. Estimated start: TBD. Estimated complete: September 2016.
Various Locations, Cuyahoga County
PROJECT I.D.: 100013 - BID AMOUNT: $712,747
Bridge approach pavement repairs at various locations on I-90 and I-480 in Cuyahoga County. Start: September 2015. Estimated complete: June
2016.
Various Locations, Cuyahoga County
PROJECT I.D.: 100417 - BID AMOUNT: $595,389
Bridge approach pavement repairs at various locations on I-77, I-90, I-271 and I-480 in Cuyahoga County. Estimated start: April 2016. Estimated
complete: June 2016.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 9
MAP NUMBER 1 MAP NUMBER 2
LOCATION: Interstate 90,
Westlake
ESTIMATED COST: $1,320,000
ESTIMATED START DATE: June 2016
ESTIMATED COMPLETION
DATE: October 2016
LOCATION: Interstate 71,
Strongsville and Middleburg
Heights
ESTIMATED START DATE:
June 2016
ESTIMATED COMPLETION
DATE: October 2016
PROJECT I.D.: 22198
ESTIMATED COST: $5,235,000
DESCRIPTION: Resurface I-90 between the Cuyahoga/Lorain county line
and Canterbury Road in the city of Westlake.
IMPACT: Off-peak lane closures.
PROJECT I.D.: 85508
DESCRIPTION: Resurface I-71 between the Cuyahoga/Medina county
line and U.S. 42 (Pearl Road) in the cities of Strongsville and Middleburg
Heights.
IMPACT: Off-peak lane and ramp closures.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 10
MAP NUMBER 3 MAP NUMBER 6
LOCATION: Interstate 71 & State
Route 82, Strongsville
BID AMOUNT: $1,027,719
ESTIMATED START DATE: June 2016
ESTIMATED COMPLETION
DATE: October 2016
LOCATION: Snow Road, Brook
Park
ESTIMATED COST: $3,202,698
ESTIMATED START DATE: June 2016
ESTIMATED COMPLETION
DATE: October 2017
PROJECT I.D.: 99435
PROJECT I.D.: 100238
DESCRIPTION: Widen the SR 82 (Royalton Road) eastbound entrance
ramp to I-71 northbound to two lanes in the city of Strongsville.
DESCRIPTION: Resurface Snow Road between SR 237 and West 130th
Street in the city of Brook Park.
IMPACT: Traffic will be maintained utilizing flaggers. IMPACT: Traffic will be maintained on all entrance and exit ramps
utilizing traffic shifts.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 11
MAP NUMBER 7 MAP NUMBER 8
LOCATION: State Route 237,
Lakewood
BID AMOUNT: $1,529,867
START DATE: April 2015
ESTIMATED COMPLETION
DATE: June 2016
LOCATION: Warren Road,
Cleveland
ESTIMATED COST: $1,403,000
ESTIMATED START DATE:
May 2016
ESTIMATED COMPLETION
DATE: October 2016
PROJECT I.D.: 18741
PROJECT I.D.: 100159
DESCRIPTION: Resurface Warren Road between Munn Road and I-90 in
the city of Cleveland.
IMPACT: One lane of traffic will be maintained in each direction.
DESCRIPTION: Replace the SR 237 bridge deck over I-90 in the city of
Lakewood.
IMPACT: Riverside Drive southbound will be closed for approximately 90
days between Indianola Avenue and Hilliard Road. Motorists will be
detoured via Detroit Road to Wooster Road to Hilliard Road. One lane of
northbound traffic will be maintained. Lane closures on I-90 are expected
during off-peak hours.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 12
MAP NUMBER 9 MAP NUMBER 10
LOCATION: West 150th Street,
Cleveland
ESTIMATED START DATE:
May 2016
ESTIMATED COMPLETION
DATE: October 2016
LOCATION: Royalview Drive,
Parma
ESTIMATED START DATE: June 2015
ESTIMATED COMPLETION
DATE: October 20165
ESTIMATED COST: $3,124,000
BID AMOUNT: $639,021
PROJECT I.D.: 100160 PROJECT I.D.: 89063
DESCRIPTION: Resurface West 150th Street between Industrial Parkway
and SR 10 (Lorain Avenue) in the city of Cleveland.
IMPACT: West 150th Street will be closed to southbound traffic between
Puritas Avenue & Industrial Parkway for approximately 60 days. Detours
will be posted. West 150th Street between Puritas Avenue and Lorain
Avenue will be maintained with one lane of traffic in each direction.
DESCRIPTION: Replace the Royalview Drive bridge over Big Creek,
west of Ridge Road, in the city of Parma.
IMPACT: Traffic will be maintained.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
CUYAHOGA COUNTY 13
MAP NUMBER 11 MAP NUMBER 12
LOCATION: Wetzel Avenue,
Cleveland
BID AMOUNT: $749,000
PROJECT I.D.: 97497
ESTIMATED START DATE:
March 2016
ESTIMATED COMPLETION
DATE: July 2016
LOCATION: Cleveland Memorial
Shoreway, Cleveland
BID AMOUNT: $41,496,959
START DATE: April 2015
ESTIMATED COMPLETION
DATE: June 2018
PROJECT I.D.: 86482
DESCRIPTION: Replace the Wetzel Avenue bridge – west of State Road
– in the city of Cleveland.
IMPACT: Wetzel Avenue will be closed for approximately 45 days.
Motorists will be detoured via State Road, Burger Avenue and West 44th
Street.
DESCRIPTION: Major pavement rehabilitation along the west Shoreway
between Clifton Boulevard and the Main Avenue Bridge as part of the
Cleveland Lakefront West project. This project also includes the permanent
closure of the West 28th Street eastbound entrance ramp to the Shoreway
and the realignment of the westbound exit ramp to West 28th Street.
IMPACT: Lane and ramp closures are expected. Visit
www.lakefrontwest.transportation.ohio.gov for more info.
DESCRIPTION: Resurface I-90 between the Lake/Cuyahoga county line
and Rockefeller Road in the cities of Wickliffe and Willoughby Hills.
IMPACT: Off-peak lane and ramp closures.
PROJECT I.D.: 80976
DESCRIPTION: Bike trail installation between SR 84 and Norton
Parkway and enhancements to the I-90 and SR 615 interchange in the city
of Mentor.
IMPACT: Short-term lane closures on SR 615, SR 84 and Norton Parkway
are expected.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
LAKE COUNTY 38
MAP NUMBER 203 MAP NUMBER 204
LOCATION: State Route 615,
Mentor
ESTIMATED COST: $480,000
PROJECT I.D.: 94337
ESTIMATED START DATE:
May 2016
ESTIMATED COMPLETION
DATE: October 2016
LOCATION: Auburn Road and
Crile Road, Concord Township
START DATE: June 2015
ESTIMATED COMPLETION
DATE: October 2016 BID AMOUNT: $8,713,039
PROJECT I.D.: 89046
DESCRIPTION: Bridge repair on SR 615 (Center Street) over the Norfolk
Southern Railroad in the city of Mentor.
IMPACT: At least one lane of traffic will be maintained.
DESCRIPTION: Build a connector road between Auburn & Crile Roads
near the SR 44/Auburn Rd intersection, reconfigure the SR 44/Auburn Rd
intersection and the Auburn Rd/Crile Rd intersection in Concord Township.
IMPACT: Auburn Road at Capital Parkway will be closed for
approximately 60 days; Crile Road at Auburn Road will be closed for
approximately 45 days; and northbound Auburn Road between Concord-
Hambden Road and Crile Road will be closed for the duration of the
project. Detours will be posted.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
LAKE COUNTY 39
MAP NUMBER 205 MAP NUMBER 206
LOCATION: State Route 44,
Concord Township
ESTIMATED COST: $1,645,000
ESTIMATED START DATE:
March 2016
ESTIMATED COMPLETION
DATE: October 2016
LOCATION: State Route 84 and
State Route 86, Concord and
Painesville Townships
ESTIMATED START DATE:
June 2016
ESTIMATED COMPLETION
DATE: September 2016
PROJECT I.D.: 96593
ESTIMATED COST: $1,000,000
DESCRIPTION: Resurface SR 44 between the Lake/Geauga county line
and I-90 in Concord Township.
IMPACT: Two-way traffic will be maintained utilizing flaggers on two-
lane section. Off-peak single lane closures on divided highway section.
PROJECT I.D.: 85608
DESCRIPTION: Resurface SR 84 (Johnnycake Ridge Road) between
Carrington Drive and SR 86 (Painesville Warren Road) in Concord and
Painesville Townships.
IMPACT: Two-way traffic will be maintained utilizing flaggers.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
LAKE COUNTY 40
MAP NUMBER 207 MAP NUMBER 208
LOCATION: State Route 283,
Painesville Township and Grand
River Village
ESTIMATED START DATE:
June 2016
ESTIMATED COMPLETION
DATE: September 2016
LOCATION: Interstate 90,
Madison Township
ESTIMATED COST: $320,000
ESTIMATED START DATE: May 2016
ESTIMATED COMPLETION
DATE: October 2016 BID AMOUNT: $1,632,270
PROJECT I.D.: 101048
PROJECT I.D.: 89235
DESCRIPTION: Routine bridge maintenance on I-90 over the Grand
River in Madison Township.
IMPACT: Traffic will be maintained utilizing temporary lane shifts.
DESCRIPTION: Resurface SR 283 (Lakeshore Boulevard/Singer Avenue,
River Street) between SR 44 (Heisley Road) and SR 535 (Richmond Street)
in Painesville Township and Grand River Village.
IMPACT: Two-way traffic will be maintained utilizing flaggers.
2016 DISTRICT 12 CONSTRUCTION PROGRAM
LAKE COUNTY 41
LOCATION: State Route 307,
Madison Township
ESTIMATED COST: $170,000
PROJECT I.D.: 100450
ESTIMATED START DATE:
July 2016
ESTIMATED COMPLETION
DATE: October 2016
LOCATION: State Route 84,
Madison Township
ESTIMATED START DATE: May 2016
ESTIMATED COMPLETION
DATE: October 2016
ESTIMATED COST: $290,000
PROJECT I.D.: 95321
DESCRIPTION: Resurface SR 307 (Warner Road) between SR 528
(Madison Road) the Lake/Ashtabula county line in Madison Township.
IMPACT: Two-way traffic will be maintained utilizing flaggers.
DESCRIPTION: Culvert repairs on SR 84 at Townline Road and west of
Dayton Road in Madison Township.
IMPACT: Two-way traffic will be maintained utilizing a temporary traffic
signal.
MAP NUMBER 209 MAP NUMBER 210
2016 DISTRICT 12 CONSTRUCTION PROGRAM
REGIONAL PROJECTS 42
DISTRICT 12 REGIONAL PROJECTS
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 87469
Guardrail repairs on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Lane closures expected during off-peak hours. Begin:
April 2015/Complete: April 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97219
Sign structure maintenance on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Begin: April 2015/Complete: Complete: May
2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 94078
Lighting upgrades on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Begin: May 2015/Complete: May 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97221
Traffic signal repairs on various routes in Lake County and as needed in other District 12 locations. Traffic will be maintained. Lane closures expected during
off-peak hours. Begin: July 2015/Complete: June 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 98602
Pavement repairs at various locations in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Lane closures expected during off-peak hours. Begin:
May 2016/Complete: October 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97300
Sign structure repairs on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Begin: June 2016/Complete: October 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 94082
Lighting upgrades on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Begin: June 2016/Complete: October 2016
2016 DISTRICT 12 CONSTRUCTION PROGRAM
REGIONAL PROJECTS 43
DISTRICT 12 REGIONAL PROJECTS
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97372
Bridge repair at locations in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Lane closures expected during off-peak hours. Begin: May
2016/Complete: October 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 99993
Bridge maintenance at locations in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Lane closures expected during off-peak hours. Begin: June
2016/Complete: October 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97291
Pavement markings on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Begin: December 2015/Complete: Complete:
November 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97301
Traffic signal repairs on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Lane closures expected during off-peak hours.
Begin: May 2016/Complete: November 2016
Various Routes, Cuyahoga, Geauga and Lake Counties
PROJECT I.D.: 97311
Guardrail repairs on various routes in Cuyahoga, Geauga and Lake counties. Traffic will be maintained. Lane closures expected during off-peak hours. Begin: