VOCATIONAL TRAINING PROJECT WORK PROJECT TITLE: SIPAT SUPER THERMAL POWER STATION DURATION: FROM 21/06/2012 TO18/06/2012 DETAILS OF STUDENT: NAME: KHAGESH KUMAR CHANDRA ROLL NO: 3353710033 COLLEGE: SSITM, BHILAI YEAR: 2012 PROJECT LOCATION: NTPC LIMITED, SIPAT DISTT: BILASPUR CHHATTISGARH - 495555
39

Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

May 20, 2015

Download

Education

haxxo24

Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

VOCATIONAL TRAINING PROJECT WORK

PROJECT TITLE: SIPAT SUPER THERMAL POWER STATION

DURATION: FROM 21/06/2012 TO18/06/2012

DETAILS OF STUDENT:

NAME: KHAGESH KUMAR CHANDRA

ROLL NO: 3353710033

COLLEGE: SSITM, BHILAI

YEAR: 2012

PROJECT LOCATION:

NTPC LIMITED, SIPAT

DISTT: BILASPUR

CHHATTISGARH - 495555

Page 2: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

ACKNOWLEDGEMENT I am truly thankful to all the faculties/guides that imparted the lectures on various subjects/topics and took us to the plants in a guided study along with the detailed explaining about the plant and the machinery.

I would also like to thank the Human resource department for permitting and organizing the training program for us.

Signature

Date- 18/06/2012

Name- KHAGESH KUMAR CHANDRA

Roll no. - 3353710033

College- SSITM, BHILAI.

Branch- MECHANICAL

Year- 2012

Page 3: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i
Page 4: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

CERTIFICATETHIS IS TO CERTIFY THAT MR. KHAGESH KUMAR CHANDRA HAS ATTENDED THE VOCATIONAL TRAINING PROGRAM FROM 18 may TO 21 June YEAR 2012 AND HAS PREPARED THE PROJECT REPORT.

HIS/HER CONDUCT HAS BEEN “GOOD” DURING THE RAINING DURATION.

PROJECT GUIDED:

NAME

DESIGNATION

DEP/SECTION

Page 5: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

DECLARATION

THE PROJECT WORK TITLED: SIPAT THERMAL POWER PROJECT

HAS BEEN CARRIED OUT AND THE REPORT PREPARED BY ME DURING 21 may TO 18 June UNDER THESUPERVISION OF GUIDES AT NTPC LTD/SIPAT SUPER THERMAL POWER PROJECT AND ORGANISED BY EMPLOYEE DEVELOPMENT CENTER, HUMAN RESOURCE DEPARTMENT.

THIS IS THE ORIGINAL WORK CARRIED OUT BY ME AND HAS NEITHER BEEN TAKEN FROM ANY OTHER SOURCE NOR BEEN SUBMITTED TO ANY INSTITUTE OR ORGANISATION AS A FULFILMENT OF ANY OTHER CURRICULUM.

SIGNATURE

DATE: 18/06/2012

NAME: KHAGESH KUMAR CHANDRA

ROLL NO. : 3353710033

COLLEGE: SSITM, BHILAI

BRANCH: MECHANICAL

YEAR/SEM: 2ND/4TH

Page 6: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

PROJECT WORKLOCATION: NTPC LTD, SIPAT

DURATION: FROM 21/06/2012 TO 18/06/2012

DISCIPLINE: MECHANICAL ENGINEERING

TOPICS COVERED:

1.

Overview of power plant

2.

Super critical technology

3.

Power plant equipments

4.

Boiler

5.

Turbine and its maintenance

SIGNATURE

DATE: 18/06/2012

Page 7: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

NAME: KHAGESH KUMAR CHANDRA:

ROLL NO. : 335371003

COLLEGE: SSITM, BHILAI

BRANCH: MECHANICAL

YEAR/SEM: 2ND/4TH

INDEX

S. No.

TOPIC

1. NTPC and its joint ventures

2. Super critical technology

3. Basic of power plant

4. Boiler

5. Turbine

6. Working of steam turbine

Page 8: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

7. condenser

8. Turbine maintenance

9.

10.

11.

oUR vISION:

”tO bE tHE

Page 9: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

wORLD’S lARGEST aND bEST pOWER

pRODUCER, pOWERING

iNDIA’S gROWTH.”

NTPC limitedA maharatan company.

Established in November 1975 for the nation’s sustainable power development.

Page 10: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Core business is engineering, construction and operation of power generating plant and providing consultancy to power utilities.

Listed on BSE and government of India holds a stake of 84.5%.

Total installed capacity of 34194 MW (as on 31 march 2011) with 15 coal based & 7 gas based station and set to become 1, 28,000 MW company by 2032.

Capacity under construction 14740 MW (approx) & PPA for more than 66000 MW.

With a share of 17.75% of India’s installed capacity. Generates about 27.4% of India’s total generation.|~|

Ranked 138th position in Fortune 500 in 2009.

NTPC Limited and Its Joint Ventures

NTPC hydro is formed to enter into hydel power sector.

Page 11: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

NTPC Electric Supply Company Ltd is formed to enter into power distribution & rural electrification.

NTPC Vidyut Vyapar Nigam Limited formed for power trading.

Bhartiya Rail Bijlee Company Ltd formed to construct & operate power plants for railways.

Three joint Venture Company with SAIL to operate and maintain its captive power plants.

To sustain the generation NTPC Ltd is also foraying in to coal mining.

JV with ALsthom Power Generation AG to take up renovation and modernization of power plants.|~|

Utility Power tech Ltd a JV with BSES to take up construction, erection and supervision works in power sector.

NTPC Tamilnadu Energy Company Ltd (JV).

Ratnagiri Gas & Power pvt ltd (JV).

Page 12: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Meja Urja Nigam pvt ltd (JV).

Aravali power company pvt ltd (JV).

NTPC-BHEL Power projects pvt ltd (JV).

SIPAT SUPER THERMAL POWER STATION

Sipat thermal power project is a cynosure of power generation of India.

Situated in the vicinity of Bilaspur city.

Pioneer of adopting super critical technology in India.

India’s first 765 KV transmissions.

Installed capacity 2890 MW

Stage 1-3*660 MW

Stage 2-2*500 MW

Water source – Hasdeo right bank canal

Coal linkage – Dipika mines, SECL.

Page 13: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

WHY SUPER-CRITICAL TECHNOLOGY?

To reduce emission for each Kwh of electricity generated: Superior Environmental.

1% rise in efficiency reduces the CO2 emission by 2-3%.

The most economical way to enhance efficiency.

To achieve fuel cost saving: Economical

Operating Flexibility.

Reduces the boiler size/MW.

To reduce start-up time.

Page 14: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Basics of a thermal Power Plant:

Page 15: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

UNDERSTANDING SUB-SUPER CRITICAL TECNOLOGY:

Page 16: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Water when heated to sub critical temperature, pressure increases until it starts boiling.

This temperature remains constant till all the water converted to steam.

When all liquid converted to steam than again temperature starts rising.

Sub critical boiler typically has a mean (boiler drum) to separate steam and water.

The mass of this boiler drum, which limits the rate at which the sub critical boiler responds to the load changes.

Page 17: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Too great a firing rate will result in high thermal stresses in the boiler drum.

UNDERSTANDING SUPER CRITICAL TECHNOLOGY:

When Water is heated at constant pressure above the critical pressure, its temperature will never be constant.

No distinction between the liquid and gas, the mass density of the two phases remain same.

No stage where the water exists as two phases and requires separation: No Drum.

The actual location of the transition from liquid to steam in a once through super critical boiler is free to move with different condition: Sliding Pressure Operation.

Page 18: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

BOILER DEFINITION:

Steam Boiler are defined as ‘Any closed vessel exceeding 22.75 liters in capacity which is used expressively for generating steam under pressure and includes any mounting or other fitting attaches to such vessel, which is wholly, or partly under pressure when the steam is shut off.

BOILER SPECIFICATIONS:

Controlled Circulation with Rifle Tubing, Dry Bottom, Radiant Reheat, Single Drum, and Top Supported, Balanced Draft Furnace. (BHEL)

Tilting, Tangential type firing.

Steam Generating Cap. Of 1675 T/Hr at 172 ksc & 540oc.

Furnace volume 16424 m3.

Depth = 15.8m

Page 19: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Width = 19.2m

Efficiency = 84.4%

Sucks flue gas and Throws out via Chimney.

Creates Negative Pr. in Ducts & Furnace.

Maintain Furnace draft.

Double Suction & Single Discharge Radial Fan.

Arrangement of Main Boiler

Economizer (3 stage)

Boiler drum

Down comers & BCW pumps

Water wall & SCWs

LTSH

Divisional panel

Final SH

Reheater

Page 20: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Safety valves

Burner and igniters

BAHs

Economizer

Boiler economizers are feed-water heater in which the heat from waste gases is recovered to raise the temperature of feed-water supplied to the boiler.

6oc raise in feed water temperature, by economizers corresponds to 1% saving in

fuel consumption.

220 C reduction in flue gas temperature increases boiler efficiency by 1%.

Location and Arrangement:

Ahead of air-heater in 2nd pass below LTSH

Page 21: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Following the primary super-heater

Counter-flow arrangement

Horizontal placement (facilitate draining)

Supported to prevent sagging, undue deflection and expansion.

Stop valve and non-return valves incorporated to ensure recirculation in case of no feed-flow.

Ash hopper below as flue gas takes a turn.

Boiler Arrangement:

Page 22: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Super heater Specifications:

LTSH Divisional Panel

Platen Stage

No. of rubber 744 432 400

Outer Dia 44.5 44.5 54

Joining Butt Butt Butt

Max Steam Temp

405K(H)

444K(P)

513K 553K

Page 23: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Max Gas Temp

405(H)

469(P)

524K 629K

TURBINE AND ITS AUXILLARIES

Steam Turbines of following OEM’S are running in NTPC

LMZ (Russia)

KWU, Siemens (Germany)

ABB-Alston (Germany)

GEC-Alston (UK)

SKODA, (chezkoslovakia)

MHI (Japan)

GE(USA)

ANSALDO(Italy)

Page 24: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

TYPES OF TURBINE

IMPULSE TURBINE- In a stage of Impulse turbine the pressure/enthalpy drop takes place only in fixed blades and not in the moving blades.

REACTION TURBINE- In a stage of Reaction Turbine the Pressure/Enthalpy drop takes place in both the fixed and moving blades.

WORKING OF STEAM TURBINE:

A steam turbine works on the principle of conversion of high pressure & temperature steam into high kinetic energy, thereby giving torque to a moving rotor.

For above energy conversion there is a requirement of converging/converging-

Page 25: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

diverging sections.

Such above requirement is built up in the space between two consecutive blades of fixed of fixed and moving blades rows.

THURST BALANCING

Thurst bearing.

IP/LP double flow(axial thurst-nullified)

Balancing disc.

TURBINE LUBE OIL SYSTEM

MOP: when turbine speed is>2840 rpm, MOP will take over

Turbine lube oil is supplied by MOP pr. Is 2.6 ksc.

MOPS also supply---1.governing oil 2.make up to seal oil system 3.barring gear oil 4.oil for LP bypass.

Page 26: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

AOP1: When turbine trips, AOP1 will come into service if speed<2840rpm or header pr<4.8ksc

AOP2: will come into service if pr<4.5 ksc or AOP1 trips

EOP: if pr< 1.1 ksc, in case of total AC failure

JOP: cut in-510 rpm. Barring gear v/v-cut in 210 rpm, cut out 240 rpm.

Condenser (it is a heat exchanger)

Specification: 76mm of hg vacuum (-0.9 ksc gauge pr) is maintained in condenser.

Page 27: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

For maintaining vacuum we need:

CW flow (provided by CW p/p, CW flow 3000 m3/hour)

Air evacuation system(ejectors & turbine sealing system)

Reduce steam loading (load, any v/v to condenser passing).

Dirty tube.

STEAM TURBINE

Generator rated speed 3000 rpm

Generator manufacturer Electrosila

No. of bleedings 8

Length of the turbine 36.362m

No. of stages

HPT 17

IPT 11x2

Page 28: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

LPT1 5x2

LPT2 5x2

Total 59

TURBINE MAINTAINNACE

Steam Turbine Blading

Steam turbines produce power by converting the energy in steam provided from a boiler or heat recovery steam generator (HRSG) into rotational energy as the steam passes through a turbine Stage. A turbine stage normally consists of a row of stationary blading and a row of rotating Blading. The purpose of the stationary blading is to direct the flow of the passing steam to the Rotating blading at the proper angle and velocity for the highest efficiency and extraction of Power. The purpose of the rotating blading is to convert the directed mass flow and steam Velocity into rotational speed and torque. Stationary blading may be referred to as

Page 29: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

nozzles, Vanes, stators, partitions, and stationary blading while rotating blades may be referred to as Buckets, blades, and rotating blading. A turbine may have a single row or stage of stationary and rotating blading or may have multiple rows or stages of blading.|~|

Why to go to location regularly?

ALL PARAMETERS ARE NOT AVAILABLE IN UCB

Page 30: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

PERSONAL RELATIONSHIP WITH EQUIPMENTS

PHYSICAL STATUS IS NOT KNOWN

TO IDENTIFY ABNORMAL BEHAVIOR

INSTRUMENTATION STATUS

LEAKAGES

Turbine

Main Turbine

HP

IP

LP

Turbine driven BFP

Points to check for

Abnormal sound

Vibration

Expansions

Page 31: Ntpc (national thermal power corporation) sipat mechanical vocational training report 3 haxxo24 i~i

Leakages (Oil, Steam, Water)

Oil flows

Pressures and Temperatures

--------------|~|---------------