NS 999 Electric / Hybrid Locomotive Research Gibson Barbee, P.E. Sr. Energy Engineer June 22, 2015
16

NS 999 Electric / Hybrid Locomotive Research

Dec 08, 2016

Download

Documents

tranbao
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NS 999 Electric / Hybrid Locomotive Research

NS 999 Electric / Hybrid Locomotive Research

Gibson Barbee, P.E.Sr. Energy EngineerJune 22, 2015

Page 2: NS 999 Electric / Hybrid Locomotive Research

Outline NS Low Emissions Locomotive Research NS Background / NS Locomotive Fleet Locomotive Emissions Federal

Requirements Locomotive Basics – In Series Hybrid

NS 5052 – Compressed Natural Gas NS 999, Battery Electric Design

NS 999, Initial 2009 Challenges, Improvements NS 999 Battery Limits / Cycle Testing / Modeling

Page 3: NS 999 Electric / Hybrid Locomotive Research

Norfolk Southern System

Page 4: NS 999 Electric / Hybrid Locomotive Research

Locomotive Fleet3700 Units2350 Road-Intercity Freight1350 Yard and Local Service

Two Primary Builders GE and EMD Road Fleet

EMD, 26.8%

GE, 73.2%

EMD GE

Page 5: NS 999 Electric / Hybrid Locomotive Research

NOx(g/bhp‐hr)

PM(g/bhp‐hr)

1.5

4.5

3.0

7.5

9.0

6.0

12.0

10.5

15.0

13.5

0.25 0.50

Tier 0 (14.0, 0.72)

Tier 0+ (11.8, 0.26)Tier 1 (11.0, 0.54)

Tier 1+ (11.0, 0.26)

Tier 2+ (8.1, 0.13)

Tier 3 (5.0, 0.10)

0.75

Locomotive Emissions Standards – Switcher

Tier 4 (1.3, 0.03)

EPA Standards(g/bhp‐hr) NOx P0.2M

Tier 0  (1973‐2001) 14.0 0.72

Tier 0+ (1973‐2001) 11.8 0.26

Tier 1 (2002‐2004) 11.0 0.54

Tier 1+ (2002‐2004) 11.0 0.26

Tier 2 (2005  andlater) 8.1 0.24

Tier 2+ (2005‐2010) 8.1 0.13

Tier 3 (2011‐2014) 5.0 0.10

Tier 4 (2015 and later) 1.3 0.03

GenSet 2.9 0.15

0.00.3750.125 0.625

Tier 2 (8.1, 0.24)

GenSet

Page 6: NS 999 Electric / Hybrid Locomotive Research

6

Diesel-Electric LocomotivesDiesel-Electric Power Generation

Page 7: NS 999 Electric / Hybrid Locomotive Research

7

Engine Coupled to GeneratorEngine

Generator

Page 8: NS 999 Electric / Hybrid Locomotive Research

NS is Investigating Compressed Natural Gas North American Shale Gas

Cost Competitive, Reduced Emissions? Installing Energy Conversions Inc kit on an

EMD GP 38-2, 645 Engine Natural Gas Slug

Page 9: NS 999 Electric / Hybrid Locomotive Research

NS 5053 Assembly

April 27, 2015 NS 5053 Initial Startup

Four Stage CompressorGas Injection to Cylinder

799 CNG Storage Slug

Monitoring Cylinder Exhaust Temperature

Page 10: NS 999 Electric / Hybrid Locomotive Research

Green Goat BMEX 259 TestingGenset

Electric Locomotive Research Multiengine

Configurations BMEX 259 - Brookville

Regenerative Braking NS 999, Hydrogen Fuel

Cell

Page 11: NS 999 Electric / Hybrid Locomotive Research

NS 999 Zero Point Source Emission Locomotive Battery Configuration (54 Batteries in Series

‘Strings’, 16 Multiple Strings in Parallel) Initial NS 999 - Several Design Issues

Poor Battery Management Difficult to Maintain Packaging

NS 999 Data – Battery Management Challenges Capacity Heating

Page 12: NS 999 Electric / Hybrid Locomotive Research

2009 Battery Management System Desired BMS Functionality

• Equalize Long Strings of Batteries Like State of Charge (SOC)

• Monitor for Fault Conditions• Isolate Battery Strings (If needed)

Failure to Maintain Uniform State of Charge (SOC) =• Reduced Power Output• Shortened Battery Life• Potential Risk of Fire (Overcharging)

I

BMS not adequately charging batteries 1, 7, or 13 location (Unequal load on strings).

Page 13: NS 999 Electric / Hybrid Locomotive Research

Gen 2.0 Battery Management System Simple Charge

Discharge Profile Channels:

54 Terminal Voltages 18 Temperature

Channels Current

Very Low Variation 0.03V Range, Minimal Temperature Change

0 1 2 3 4 5 6 7 8

x 104

11

12

13

14

X: 1.212e+04Y: 12.56

April 30, 2015

Volts

0 1 2 3 4 5 6 7 8 9

x 105

-30

-20

-10

0

10

20

Am

p

0 1 2 3 4 5 6 7 8

x 104

0

10

20

30

Tem

p C

Page 14: NS 999 Electric / Hybrid Locomotive Research

Battery Management System (TMV Gen 2) Customized ISO Container (Battery Storage) Advanced Lead Carbon Batteries (Axion PbC®) Removable IntraPack Battery Trays Individual Battery String Control (IGBTs) RCL / OBN / Dashboard (Remote Monitoring) 480VAC Wayside Charging Station(s)

NS 999 All Electric Switcher LocomotiveGen 2.0 - Juniata Locomotive Shop

Page 15: NS 999 Electric / Hybrid Locomotive Research

Battery Testing & Modeling• Battery Test Program

HLS (Roanoke, VA) Penn State University (PTI Labs)

• Evaluating Alt. Battery Technologies Charge Acceptance Thermal Characteristics Cycle Life

• MATLAB Energy Modeling Over-the-Road Load Profiles Evaluate Hybrid Locomotive Configuration(s) Hardware-in-the-Loop (HIL) Testing

Hybrid Locomotive Simulator (HLS)

Penn State: PTI Laboratory

Page 16: NS 999 Electric / Hybrid Locomotive Research

R. S. Runyon, P.E.

Special Thanks to…

Questions?