November, 2008 Montana Department of Transportation Transportation Management Plans
Dec 17, 2015
MDT Work Zone Safety and Mobility
Policy and Guidance – September 2007 Training for Design Staff – early 2008 Presentations to Construction Staff – early
2008 Transportation Management Plan
Development Team – started March 2008
TMP Development Team
MDT Highways Bureau & Road Design MDT Traffic and Safety MDT Consultant Design MDT Construction Traffic Control Engineer MDT District Traffic Engineer MDT District Construction Reviewer FHWA Safety/Traffic Design Engineer
TMP Data Sheet
Intended for project design team Guide discussion among preconstruction and
construction staff Help develop Traffic Control Plan and
Special Provisions (TCP and TO) Help develop Public Involvement for
preconstruction and construction Help estimate project costs
BACKGROUND INFORMATION:
$0 = #DIV/ 0!
IMPACT Level I Level II Level III NAState HighwayRampsLocal County RdLocal City Street
PREPARED BY:Name:Title:Organization:Telephone:email:Date:
APPROVED BY:Name:Title:Organization:Telephone:email:Date:
Project Cost:TMP Estimate:
Estimated End Date:OF THE PROJECT COST
<- CN total with mobilization
Duration: working days
TRANSPORTATION MANAGEMENT PLAN (TMP) DATA SHEET
Project ID:Project Location:Project Control No:Work Type:
TMP worksheets revised 07/11/2008Fill out all green shaded areas. All other cells utilize automatic formulas, and are locked.
Construction periodEstimated Start Date:
Details (Please explain traffic impact) :
TMP SECTIONS ESTIMATE SUMMARY
Cost is obtained from TMP Elements Table, and will be filled in automatically.
TMP SECTION COST
1. Temporary Traffic Control Plan $0
1A Construction/Control Strategies $0
1B Traffic Control Devices $0
1C Project Coordination, Contracting and Innovative Construction Strategies $0
1D Pedestrian, Bicycle, and ADA accommodations $0
2. Transportation Operations Component $0
2A Demand Management Strategies $0
2B Corridor/Network Management Strategies $0
2C Work Zone Safety Management Strategies $0
2D Traffic/Incident Management and Enforcement Strategies $0
3. Public Information Component $0
3A Public Awareness Strategies $0
3B Motorist Information Strategies $0
3C Special Events $0
4. Other Strategies $0
TOTAL COST OF TRANSPORTATION MANAGEMENT PLAN = $0
COST
Describe:
TMP ELEMENTS TABLEAn "X" in the check box means the item will be included in the project. A "?" in the box means this will need to be checked into. A "blank" box means the item is not needed at this time based on the information received.
TMP ELEMENT
Ramp
Connector
Extended Weekend Closures
Total Facility Closures
Lane
Street
This TMP presumes work is planned as follows:
If Yes, for which of the following elements:
Flagging
Shoulder
Regular working hours
Night work
Weekend work
Work hour restrictions for peak travel
Work hour/day restrictions for special events
Are lane closure charts required? (Y or N)
11A
X Cost:
Adjust intersection operations
Alternate route detour signing
On-site, offset detour/diversion
Local street use (PSA or MOU may be required)
Parking restrictions
Alternate route roadway improvements
Use of frontage roads for Interstate mainline closures
Reversible lanes
Construction/Control Strategies
Lane shift to shoulder/median to maintain number of lanes
One-lane, two-way operation
Two-way traffic on one side of divided facility (crossover)
Reduced shoulder width to maintain number of lanes
Shoulder closures to provide worker safety
Off-site detours/use of alternate routes
Adjust intersection operations
Temporary Traffic Control Plan
Brief
Construction phasing/staging
Reduced lane widths to maintain number of lanes (constriction)
Lane closures to provide worker safety
Ramp closures/relocation
Lane shifts or closures
Short-term
Long-term
Full roadway closures
Parking restrictions
Freeway to freeway interchange closures
Pedestrian/bicycle access provisions
Use of ramps for Interstate mainline closures
Business access provisions
1B
$0
Flaggers
Temporary traffic signals
Lighting devices
SUBTOTAL
Lump sum
Channelization devices
Warning
Regulatory
Changeable message signs
Guide/information
Temporary signs
Arrow panels
Traffic Control Devices
Temporary pavement markings
Pedestrian Devices
Barriers
Fencing
Ramps
Pilot cars
Barricades
Positive Protection Barriers
1C
$0
1D
$0
$0
Lump sum
Innovative construction techniques
Describe:
Accelerated schedule
Project Coordination, Contracting and Innovative Construction Strategies
Utilities coordination
Design-build
Adjust intersection operations
Signed detours
Temporary ramps
SUBTOTAL
TEMPORARY TRAFFIC CONTROL PLAN TOTAL
Dedicated/protected detours (barrier)
Coordination with other transportation infastructure
Contracting strategies
Lane rental
Pedestrian, Bicycle, and ADA accommodations
Coordination with other projects
Project coordination
A+B bidding
Incentive/disincentive clauses
Right-of-Way coordination (construction easement to accomodate traffic or ped use)
SUBTOTAL
Warranty
Railroad flaggers
Coordination with Railroad
22A
$0
2B
$0
Railroad crossings controls
Separate truck lanes
Dynamic lane closure system
Temporary ramp metering
Ramp closures
Transit
Turn restrictions
Parking restrictions
Truck/heavy vehicle restrictions
Signal timing/coordination improvements
Temporary traffic signals
Street/intersection improvements
Variable work hours
Parking supply management
Bus turnouts
Coordination with adjacent construction sites
Demand Management StrategiesTransportation Operations Component
Corridor/Network Management Strategies
Shuttle services
Transit services improvements
Park-and-ride promotion
Carpool/vanpool
Telecommuting
Ridesharing/carpooling incentives
Public Transit Support/Improvements/Shuttle Service
SUBTOTAL
SUBTOTAL
2C
$0
Automated Flagger Assistance Devices (AFADs)
Project task force/committee
Construction safety supervisors/inspectors
TMP monitor/inspection team
Temporary rumble strips
Intrusion alarms
Warning lights
Temporary traffic signals
Temporary traffic barrier
Movable traffic barrier systems
Crash-cushions
Speed limit reduction/variable speed limits
Team meetings
Project on-site safety training
Safety awards/incentives
Windshield surveys
SUBTOTAL
Work Zone Safety Management Strategies
2D Traffic/Incident Management and Enforcement Strategies
ITS for traffic monitoring/management
Transportation management center
Surveillance
Closed-circuit television
Loop detectors
Radar
Traffic screens
Call boxes
Mile post markers
Tow/freeway service patrol
Total station survey units
Coordination with the media
Local detour routes
Contract support for incident management
Incident/emergency management coordinator
Incident/emergency response plan
Dedicated (paid) police enforcement
Cooperative police enforcement
SUBTOTAL $0
TRANSPORTATION OPERATIONS COMPONENT TOTAL $0
33A
$0
Planned lane closure website
Project website
Public meetings/hearings
Work zone education and safety campaigns
Work zone safety highway signs
Rideshare promotions
Media
Public Awareness Strategies
Community task forces
Local agencies
Telephone hotline
Schools
Emergency services
Notification/coordination with stakeholders/targeted groups:
Tribal governments
Public land agencies
Motorcycle organizations
SUBTOTAL
U.S. Postal Service
Brochures and mailers
Press releases/media alerts
Commercial trucking industry
Visual Information (videos, slide shows, etc.) for meetings and web
Public Information Component
Paid advertisements
Businesses
Public information center/kiosk/wireless hot spot
Organizations representing people with disabilities
Bicycle organizations
Rideshare organizations
3B
$0
3C
$0
$0
SUBTOTAL
Bicycle and pedestrian information (e.g. detour maps)
Changeable message signs (stationary) - list general locations:
511 traveler information systems (wireless handhelds)
Dynamic speed message sign
Media blitz
Special Events
Traffic radio
Motorist Information Strategies
PUBLIC INFORMATION COMPONENT TOTAL
Transportation management center
Highway information network (web-based)
Changeable message signs (portable) - list general locations:
Highway advisory radio
Extinguishable signs
Freight travel information
Temporary motorist information signs
SUBTOTAL
Coordination with special event host
4
$0
$0
Other Strategies
TOTAL COST OF TRANSPORTATION MANAGEMENT PLAN =
Other
Innovative products
OTHER STRATEGIES TOTAL
Application of new technology
TMP Help Guide
Step by step instructions and definitions Took text from FHWA guidance Developed additional text to clarify Assigned sections to team members for
editing and clarifying Will be a stand-alone document
TMP Implementation
Test projects recently constructed Pilot projects for future construction Training for design staff Encourage documentation
Contact Information
Lesly Tribelhorn, Highways Design [email protected]
406.444.6242
Jim Wingerter, Construction Traffic Control [email protected]
406.444.7628
http://www.mdt.mt.gov/other/const/external/manuals_guidelines/workzone_safety_mobility.pdf