Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012
27

Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Jun 27, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Northwest Light Rail Extension

Pre-Construction/Final Design

Public Meeting November 27 & 29, 2012

Page 2: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

2

6:00 – 6:30 p.m. – Open House

6:30 – 7:00 p.m. – Presentation

7:00 – 8:00 p.m. – Open House

Page 3: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Project Overview

Carla Kahn

Community Outreach Coordinator

3

Page 4: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Agenda

• Introduction of Project Team

• Project Overview

• Construction Scope of Work

• Preliminary Construction Schedule

• Questions

4

Page 5: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Community Outreach Team

Carla Kahn’s Role

Community Outreach Coordinator

• Liaison between the project & community

• Knows & understands the community

• Issue resolution

• Creates project updates

Gary Flunoy’s Role

Business Assistance Specialist

• Contact for business assistance programs

• Knows & understands the community

5

Page 6: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Project Team

6

• John Taylor

– Valley Metro, Project Manager

• Brian Mason

– Valley Metro, Resident Engineer

• Erik Yingling

– Sundt/Stacy & Witbeck, Project Manager

• Albert Santana

– City of Phoenix, Light Rail Project Administrator

Page 7: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Route

7

Page 8: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Project Status

• Design Complete

• Contractor

• Sundt/Stacy & Witbeck Joint Venture

– Received notice to proceed

– Begin work January 2013

8

Page 9: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Construction Outreach Plan

• Communication/notification – 24-hour hotline

– Personal contact

– Public meetings

– Doorhangers & mailers

– Email blasts • Sign-up by contacting Carla

– Social media • Facebook/METROrailconstruction

• Twitter - #Northwest

– Website • www.valleymetro.org/northwest

9

Page 10: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Business Assistance Toolbox

• METRO Max Rewards Program

• General marketing & advertising support

• Multi-media marketing campaigns

• Business-to-business resources & consulting

• Community Advisory Board (CAB)

• Business access signage

• Business Access Coordinator 10

Page 11: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Construction Scope of Work

Brian Mason, PE

Resident Engineer

11

Page 12: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Utility Relocation & Road Widening

• Activities include:

– Utility relocation

– Demolition of existing

roadway, grading &

re-paving

– Construction of traffic lanes,

curbs, gutter, sidewalks,

streetscape & lighting

12

Page 13: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Track & Station Installations

• Activities include:

– Installation of track

– Installation of overhead

power lines

– Construction of stations &

integration of artwork

– Construction of park & ride

facility and traction power

substations

13

Page 14: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Light Rail Testing/Operations

• Activities include:

– Signals & communication

– Traction power substation

testing

– Overhead contact system

testing

– Safety certification

14

Page 15: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

What to Expect

• Access maintained to businesses &

residential

• Notification & coordination of construction

activities

• Modification to traffic lanes & sidewalks

• Day & night time work

• Temporary utility interruptions

– Coordination 15

Page 16: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Preliminary Construction

Schedule

Sundt/Stacy Witbeck JV

Erik Yingling

Project Manager

16

Page 17: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Sundt/Stacy and Witbeck JV

17

Page 18: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Sundt/Stacy & Witbeck JV

• Line Section 4

• Line Section 5

• Maintenance &

Operations Facility

18

Page 19: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Northwest Extension

19

• 45,000 lineal feet waterline materials

• 16,000 lineal feet sewerline materials

• 22,000 lineal feet drainage materials

Storm drain

36” water line

Page 20: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

20

Northwest Extension

• 214,000 tons aggregate materials

• 30,000 cubic yard ready mix

Roadway milling

Bus pullouts

New sidewalks

Page 21: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

21

Northwest Extension

• Mainline track 31,000 track

feet single crossovers

• 1 double crossover

750 pressure welds

500 thermite welds

Track crossing 56th Street and Washington

Page 22: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

22

Setting traction power substation

Signals & communication

Overhead catenary system

Page 23: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Early Construction Activities

• Begins January 2013

• Relocation of utilities including:

– Water mains/services

– Sanitary sewer/Storm sewer

– Gas main services

– SRP/Private irrigation

– Power (overhead conversion)

– Phone/Cable (overhead conversion) 23

Page 24: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Construction Schedule

24

Page 25: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Planned Construction Schedule

25

Page 26: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Upcoming Events

• Public Art Meeting –

December 5, 2012

• Peer to Peer Business Forum –

December 12, 2012

• Groundbreaking Event –

January 12, 2013

26

Page 27: Northwest Light Rail Extension Pre-Construction/Final Design · Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 . 2 6:00 – 6:30

Carla Kahn

Community Outreach Coordinator

Direct Line: (602) 744-5552

Cell number: (623) 261-2605

Email: [email protected]

Gary Flunoy

Business Assistance Specialist

Direct Line: (602) 322-4457

Cell Number: (602) 291-7670

Email: [email protected]

27

Questions