N N O O R R T T H H S S I I D D E E I I N N D D E E P P E E N N D D E E N N T T S S C C H H O O O O L L D D I I S S T T R R I I C C T T Facilities Construction Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION 2010 BOND July 2014 Boldt Elementary School
36
Embed
NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION
2010 BOND
July 2014
Boldt Elementary School
BERNAL MIDDLE SCHOOL (Formerly STEVENS RANCH AREA MIDDLE SCHOOL)
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – Bartlett Cocke, Inc. Construction Budget - $41,408,415.00 Construction Period - January 2013 – May 2014 Project Scope – New 1200 Student Middle School (97% Complete) Project was substantially complete on June 2, 2014. Punch list completion is in progress.
BERNAL MIDDLE SCHOOL (Aerial – June 6, 2014)
BERNAL MIDDLE SCHOOL (Perspective of Front Entrance)
BERNAL MIDDLE SCHOOL (May 6, 2014)
BERNAL MIDDLE SCHOOL (May 6, 2014)
BERNAL MIDDLE SCHOOL (May 6, 2014)
ELLISON ELEMENTARY SCHOOL (Formerly CIELO VISTA SOUTH ELEMENTARY)
Architect – Garza Bomberger Architects Project Architect – Roy Lewis, AIA NISD Project Manager – Marilyn Sevedge CM @ Risk Contractor – Joeris General Contractor Construction Budget - $19,877,127.00 Construction Period - February 2013 – May 19, 2014 (98% Complete) Project Scope – 800 Student Elementary School Certificate of Occupancy issued May 20, 2014. Intrusion alarm installed. Additional PR’s in progress. 100% Completion of Substantial Completion Punch List, Landscaping and Commissioning in Progress.
ELLISON ELEMENTARY SCHOOL (Aerial – May 19, 2014)
ELLISON ELEMENTARY SCHOOL (Perspective of Front Entrance)
ELLISON ELEMENTARY SCHOOL (June 11, 2014)
ELLISON ELEMENTARY SCHOOL (May 12, 2014)
ELLISON ELEMENTARY SCHOOL (May 12, 2014)
ELLISON ELEMENTARY SCHOOL (May 12, 2014)
ELLISON ELEMENTARY SCHOOL (May 12, 2014)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH)
Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Thomas Curiel Contractor – Joeris General Contractor Construction Budget - $20,000,000.00 Construction Period – February 2014 – May 22, 2015 (7% Complete) Project Scope – New 800 Student Elementary School Building layout, steel erection and building pad in progress.
REDBIRD RANCH ELEMENTARY SCHOOL Front Entrance Perspective
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (June 23, 2014)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (July 2, 2014)
BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (July 2, 2014)
INSELMANN BASEBALL FIELD (Replacement of Existing Facilities)
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis, AIA NISD Project Manager – Christopher Parker Contractor – D. Wilson Construction Construction Budget - $2,700,000.00 Construction Period – May 2014 – December 2014 (3% Complete) Project Scope – Replacement of Existing Field and associated Facilities.
Demolition complete. Site work in Progress.
INSELMANN BASEBALL FIELD (Bird’s Eye View)
INSELMANN BASEBALL FIELD (July 2, 2014)
INSELMANN BASEBALL FIELD (July 2, 2014)
OAK HILLS ELEMENTARY SCHOOL - Art Room
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – Rohde General Contracting Construction Budget - $300,000.00 Construction Period – May 2014 – August 2014 (5% Complete) Project Scope – Provide a new Art Room to meet current NISD standards Schematic Design Approved by Building Committee. Construction started June 9, 2014.
Demolition is complete. Plumbing rough-in in progress. Electrical in progress and interior framing is complete. Exterior concrete in progress.
OAK HILLS ELEMENTARY SCHOOL - Art Room (July 1, 2014)
OAK HILLS ELEMENTARY SCHOOL - Art Room (July 1, 2014)
SPORTS GYM
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $19,000,000.00 Construction Period - October 2014 – October 2015 Project Scope – Provide a District-Wide Sports Gymnasium at the Farris Complex. Design only project at this time.
Funding - Project to be funded from 2010 Bond Savings.
SPORTS GYM Site Plan
KALLISON RANCH HIGH SCHOOL
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor Estimated Construction Budget - $105,000,000.00 Tenative Construction Period – September 2014 – May 2017 Project Scope – New 2800 Student High School Design is 95% complete. Construction Budget - $105,000,000.00 in 2014 Bond
KALLISON RANCH HIGH SCHOOL Aerial Plan
KALLISON RANCH HIGH SCHOOL Schematic Design Site Plan
KALLISON RANCH HIGH SCHOOL (Front Entry Perspective)
KALLISON RANCH HIGH SCHOOL Schematic Design Auditorium