Top Banner
N N O O R R T T H H S S I I D D E E I I N N D D E E P P E E N N D D E E N N T T S S C C H H O O O O L L D D I I S S T T R R I I C C T T Facilities Construction Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION 2010 BOND July 2014 Boldt Elementary School
36

NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

May 29, 2018

Download

Documents

LeKhuong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

  

NNOORRTTHHSSIIDDEE         IINNDDEEPPEENNDDEENNTT      SSCCHHOOOOLL      DDIISSTTRRIICCTT 

   

Facilities Construction

  

 

 

Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS

Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

Paul Megerle DIRECTOR OF FACILITIES CONSTRUCTION

2010 BOND

July 2014

Boldt Elementary School

Page 2: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BERNAL MIDDLE SCHOOL (Formerly STEVENS RANCH AREA MIDDLE SCHOOL)

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Jim Berg Contractor – Bartlett Cocke, Inc. Construction Budget - $41,408,415.00 Construction Period - January 2013 – May 2014 Project Scope – New 1200 Student Middle School (97% Complete) Project was substantially complete on June 2, 2014. Punch list completion is in progress.

Page 3: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BERNAL MIDDLE SCHOOL (Aerial – June 6, 2014)

Page 4: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BERNAL MIDDLE SCHOOL (Perspective of Front Entrance)

Page 5: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BERNAL MIDDLE SCHOOL (May 6, 2014)

Page 6: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BERNAL MIDDLE SCHOOL (May 6, 2014)

Page 7: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BERNAL MIDDLE SCHOOL (May 6, 2014)

Page 8: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (Formerly CIELO VISTA SOUTH ELEMENTARY)

Architect – Garza Bomberger Architects Project Architect – Roy Lewis, AIA NISD Project Manager – Marilyn Sevedge CM @ Risk Contractor – Joeris General Contractor Construction Budget - $19,877,127.00 Construction Period - February 2013 – May 19, 2014 (98% Complete) Project Scope – 800 Student Elementary School Certificate of Occupancy issued May 20, 2014. Intrusion alarm installed. Additional PR’s in progress. 100% Completion of Substantial Completion Punch List, Landscaping and Commissioning in Progress.

Page 9: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (Aerial – May 19, 2014)

Page 10: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (Perspective of Front Entrance)

Page 11: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (June 11, 2014)

Page 12: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (May 12, 2014)

Page 13: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (May 12, 2014)

Page 14: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (May 12, 2014)

Page 15: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

ELLISON ELEMENTARY SCHOOL (May 12, 2014)

Page 16: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH)

Architect – Noonan Rittimann Project Architect – John Rittimann NISD Project Manager – Thomas Curiel Contractor – Joeris General Contractor Construction Budget - $20,000,000.00 Construction Period – February 2014 – May 22, 2015 (7% Complete) Project Scope – New 800 Student Elementary School Building layout, steel erection and building pad in progress.

Page 17: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) Aerial View (June 25, 2014)

Page 18: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

REDBIRD RANCH ELEMENTARY SCHOOL Front Entrance Perspective

Page 19: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (June 23, 2014)

Page 20: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (July 2, 2014)

Page 21: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

BOLDT ELEMENTARY SCHOOL (Formerly REDBIRD RANCH) (July 2, 2014)

Page 22: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

INSELMANN BASEBALL FIELD (Replacement of Existing Facilities)

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis, AIA NISD Project Manager – Christopher Parker Contractor – D. Wilson Construction Construction Budget - $2,700,000.00 Construction Period – May 2014 – December 2014 (3% Complete) Project Scope – Replacement of Existing Field and associated Facilities.

Demolition complete. Site work in Progress.

Page 23: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

INSELMANN BASEBALL FIELD (Bird’s Eye View)

Page 24: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

INSELMANN BASEBALL FIELD (July 2, 2014)

Page 25: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

INSELMANN BASEBALL FIELD (July 2, 2014)

Page 26: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

OAK HILLS ELEMENTARY SCHOOL - Art Room

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – Rohde General Contracting Construction Budget - $300,000.00 Construction Period – May 2014 – August 2014 (5% Complete) Project Scope – Provide a new Art Room to meet current NISD standards Schematic Design Approved by Building Committee. Construction started June 9, 2014.

Demolition is complete. Plumbing rough-in in progress. Electrical in progress and interior framing is complete. Exterior concrete in progress.

Page 27: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

OAK HILLS ELEMENTARY SCHOOL - Art Room (July 1, 2014)

Page 28: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

OAK HILLS ELEMENTARY SCHOOL - Art Room (July 1, 2014)

Page 29: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in
Page 30: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

SPORTS GYM

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $19,000,000.00 Construction Period - October 2014 – October 2015 Project Scope – Provide a District-Wide Sports Gymnasium at the Farris Complex. Design only project at this time.

Funding - Project to be funded from 2010 Bond Savings.

Page 31: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

SPORTS GYM Site Plan

Page 32: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

KALLISON RANCH HIGH SCHOOL

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – Jim Berg Contractor – Joeris General Contractor Estimated Construction Budget - $105,000,000.00 Tenative Construction Period – September 2014 – May 2017 Project Scope – New 2800 Student High School Design is 95% complete. Construction Budget - $105,000,000.00 in 2014 Bond

Page 33: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

KALLISON RANCH HIGH SCHOOL Aerial Plan

Page 34: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

KALLISON RANCH HIGH SCHOOL Schematic Design Site Plan

Page 35: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

KALLISON RANCH HIGH SCHOOL (Front Entry Perspective)

Page 36: NORTHSIDE INDEPENDENT SCHOOL DISTRICT · NORTHSIDE INDEPENDENT SCHOOL DISTRICT ... Punch list completion is in progress. ... Completion Punch List, Landscaping and Commissioning in

KALLISON RANCH HIGH SCHOOL Schematic Design Auditorium