Avion solaire 1 1 May 19 th 2016 NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND WHILE REDUCING COST OF ELECTRICITY
7

NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

Sep 10, 2018

Download

Documents

vantu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

Avion solaire

1 1

May 19th 2016

NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND WHILE REDUCING COST OF ELECTRICITY

Page 2: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

2

ELECTRICAL DEMAND

2000

2500

3000

3500

4000

4500

5000

01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 00:00

Lo

ad

[M

Wel]

Time of day

Typical load curves Morocco (summer and winter) working days and weekend

Wednesday 18-janv 2012

Sunday 22-janv 2012

Wendnesday 11-juil 2012

Sunday 15-juil 2012

Daily evening peak demand Need of storage

Mid-day summer peak demand Maximum solar generation

Winter WE Winter Week Summer WE Summer Week

Page 3: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

3

HIGH SOLAR RESOURCES AND WATER SCARCITY

Water scarcity

• Mobilized water in 2013 in Morocco 650 m3

per capita (minimum required more than

1000 m3 par capita)

• Lower water availability in potential solar

sites

High solar irradiation all over the Kingdom

• GHI between 1 800 and 2300 kWh/y

• DNI higher than 2 300 kWh/y in dozens of

sites and more than 2 600 kWh/y in some

suitable sites

Page 4: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

4

Different technical and market studies to select appropriate technology/site for the development of prior project

PRELIMINARY STUDIES TO SELECT MOST SUITABLE TECHNOMOGIES

PV technologies

CSP Technologies

Process to identify and select suitable technology / sites (technology comparison for each site)

CSP PV hybrid solutions

Storage

Page 5: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

PV LCOE DECREASE IN THE LAST 2 YEARS

Page 6: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

0

50

100

150

200

Heure (h)

Pro

du

ctio

n (

MW

h)

PV CSP hybride solution

Series1 Series2 Series3

6

PV-CSP combination

NEW CONCEPT

An hybrid solution

LCOE increase vs capacity factor decrease A PV CSP Hybrid typical load curve (sunny day)

𝐿𝐶𝑂𝐸PV CSP = 𝐿𝐶𝑂𝐸PV + ( 𝐿𝐶𝑂𝐸CSP − 𝐿𝐶𝑂𝐸PV ) × ECSP

ETotal

A PV CSP Hybrid solution LCOE Approximation

Page 7: NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND ...€¦ · avion solaire 1 1 may 19th 2016 noor : pv-csp hybridization to respond electrical demand while reducing cost of

7

Thank you for your attention

May 19st 2016

NOOR : PV-CSP HYBRIDIZATION TO RESPOND ELECTRICAL DEMAND WHILE REDUCING COST OF ELECTRICITY