Page 1
VISVESVARAYA TECHNOLOGICAL UNIVERSITY Belagavi-590014, Karnataka
A Project Report on
“NON-DESTRUCTIVE TESTING OF CONCRETE IN STRUCTURES” In partial fulfillment of the requirement for the award of the degree in
Bachelor of Engineering in Civil Engineering
Submitted by
CHIRANTH P L 1NH13CV023
MOHAMMED OWAIS QURAISHI 1NH13CV143
SHANIL PARAMBATH 1NH13CV114
PRAVAL SETH 1NH13CV080
Under the guidance of
Mr Vijay N.C
Assistant Professor,
Department of Civil Engineering,
N.H.C.E, Bangalore.
Department of Civil Engineering
NEW HORIZON COLLEGE OF ENGINEERING (ISO-9001:2000 certified, Accredited by NAAC „A‟,
Permanently affiliated to VTU) Outer Ring Road, Panathur Post, Near Marathalli,
Bangalore – 560103
Page 2
NEW HORIZON COLLEGE OF ENGINEERING (ISO-9001:2000 certified, Accredited by NAAC ‘A’,permanently affiliated to VTU)
Outer Ring Road, Panathur Post, Near Marathalli,Bangalore – 560103
DEPARTMENT OF CIVIL ENGINEERING
CERTIFICATE Certified that the project work entitled “NON-DESTRUCTIVE TESTING OF CONCRETE
STRUCTURES” carried out by Chiranth P L(1NH13CV023), Mohammed Owais
Quraishi(1NH13CV143), Shanil Parambath(1NH13CV114), Praval Seth(1NH13CV080), Bonafide
students NEW HORIZON COLLEGE OF ENGINEERING, in partial fulfillment for the award of
Bachelor of Engineering in Department of Civil Engineering of the Visvesvaraya Technological
University, Belagavi during the year 2016-2017. It is certified that all corrections/suggestions indicated
for Internal Assessment have been incorporated in the report deposited in the departmental library. The
project report has been approved as it satisfied the academic requirements in respect of project work
prescribed for the said degree.
Dr. NIRANJAN P.S Mr. Vijay N.C Dr. MANJUNATHA
Head of Department Project Guide Principal
Department of Civil Engineering Assistant Professor NHCE
NHCE NHCE
Name of the Examiners Signature with Date
1.____________________ ________________
2.____________________ ________________
Page 3
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 3
NEW HORIZON COLLEGE OF ENGINEERING (ISO-9001:2000 certified, Accredited by NAAC ‘A’,permanently affiliated to VTU)
Outer Ring Road, Panathur Post, Near Marathalli,Bangalore – 560103
DEPARTMENT OF CIVIL ENGINEERING
DECLARATION
We, the undersigned students of VIII
th semester of Civil Engineering from New Horizon College of
Engineering, declare that our project work entitled “NON-DESTRUCTIVE TESTING OF
CONCRETE”, has been prepared by us under the guidance of Mr. Vijay N.C, Assistant Professor,
Department of Civil Engineering, NHCE. This work has been submitted for the partial fulfillment of
the requirement for the award of Bachelor of Engineering Degree. We also declare that this project was
not entitled for submission to any other university in the past and shall remain the only submission made
and will not be submitted by us to any other university in the future.
Name USN Signature
CHIRANTH.P.L 1NH13CV023
MOHAMMED OWAIS 1NH13CV143
QURAISHI
SHANIL PARAMBATH 1NH13CV114
PRAVAL SETH 1NH13CV080
Place: Bengaluru
Date:
Page 4
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 4
ACKNOWLEDGEMENT
Firstly, we are thankful to our college New Horizon College of Engineering for providing us an
opportunity to work on this project as part of academics. This seminar would not have been possible
without the guidance and the help of several individuals, who in one way or another contributed and
extended their valuable assistance in the preparation and completion of this study.
First and foremost, we would like to thank Dr. MOHAN MANGHNANI, Chairman of New
Horizon Educational Institutions for providing the brilliant infrastructure and facilities which enabled us
to work in a very productive environment which was directly responsible in the completion of this
report.
We would like to thank Dr. MANJUNATH, Principal of New Horizon College of Engineering
for providing us extended use of the college facilities which played an important role in the preparation
of this project.
We would like to express utmost gratitude to our beloved guide, Dr. NIRANJAN P.S Head of
Department of Civil Engineering, New Horizon College of Engineering for his invaluable support,
suggestion, precious advice and patient guidance, helped us to prepare this project.
I wish to express my sincere gratitude to my teacher and guide Mr. Vijay, Asst. Professor in the
Department of Civil Engineering, NHCE, for his valuable suggestions, guidance, care & attention shown
during the planning, conduction stages of this seminar work.
Our special thanks to all my friends for their valuable support provided throughout the course of
preparation of project.
We also express our sincere gratitude to all those who were involved with us directly or
indirectly during our project work.
CHIRANTH P L 1NH13CV023
MOHAMMED OWAIS QURAISHI 1NH13CV143
SHANIL PARAMBATH 1NH13CV114
PRAVAL SETH 1NH13CV080
Page 5
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 5
SYNOPSIS
The basic method of verifying whether concrete complies with specification is to test its strength
using cubes or cylinders made from samples of fresh concrete. It must be noted that non-compliance by
a single test specimen or even by group, does not necessarily mean that the concrete from which the test
specimens have been made is inferior to that specified; the engineer‟s reaction should be to investigate
the concrete further. This necessitates Non-Destructive tests on the concrete in the structure.
Nondestructive testing methods have been used on civil engineering structures such as dams and bridges
since the 1960‟s. In NDT, the development has taken place to such an extent that it is now considered as
a powerful method for evaluating existing concrete structure with regard to their strength, durability,
investigation of crack depth, micro cracks and progressive deterioration are also studied by this method.
The aim of the present paper is to describe, how the NDT is done using ultrasonic pulse velocity
for assessing concrete strength that are widely used in structural field. The main purpose of this test is to
detect and identify defects in materials, measure its dimension and estimate its strength as well as to
decide whether it is to be accepted or rejected.
Page 6
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 6
NON-DESTRUCTIVE TESTING OF CONCRETE IN
STRUCTURES
1 INTRODUCTION
The testing of hardened concrete plays an important role in controlling and confirming the quality
of cement concrete used at site has developed the required strength. The quality of the product was
checked and evaluated by NDT methods. Most material in building, bridges, dams, tunnethrrt are world
lords of theorem and hearer content and another are world all was the less, etc., are made of concrete.
This construction requires concrete of high quality in terms of strength and durability. NDT has the
ability to determine the strength and durability of critical construction without damaging them and the
test can be carried on site (Bungey, 1989).
To monitor the service behavior of concrete structure over a long period, it was imperative that
tests be nondestructive. There are several NDT methods applicable to concrete structures. The
importance of NDT is checking certain properties according to the type of structure. The NDT methods
applicable for concrete inspection include ultrasonic, rebound hammer and cover meter tests. It is clear
that ultrasonic method has a superior capability in the sense that it is capable of providing more
information on concrete parameters as compared with other methods.
The main advantage of non destructive method is that the strength and durability and other
factors such as corrosion of bars, number of bars, bar spacing, quality of concrete, etc. can be easily
determined, without damaging the concrete structure. All these factors are determined with less time and
less cost by this method. In other words, we can get complete information of the old and the newly
constructed concrete structure.
Page 7
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 7
2 SCOPE OF WORK
1. Detailed observation of the building and study of structural system.
2. Detailed study of available Architectural and Structural drawing.
3. Carrying out Ultrasonic Pulse Velocity Test on identified beams and columns at random for
assessment of in-situ strength of concrete.
4. Carrying out Rebound Hammer Test on identified r c slab for assessment of surface
hardness and strength of concrete.
5. Carrying out Theoretical analysis and design verification for assessment of structural
soundness.
6. Working out appropriate strengthening measures for deficient r c members along with
specifications and sketches.
7. Furnishing detailed report with sketches, specifications and photographs.
3 NEED FOR TESTING
The need for testing may arise from a variety of causes, which include (Chapman and Hall);
1. Proposed change of usage or extension of a structure.
2. Acceptability of a structure for purchase or insurance.
3. Assessment of structural integrity or safety following material deterioration or structural
damage such as caused by fire, blast, fatigue or overload.
4. Serviceability or adequacy of members known or suspected to contain material that does not
meet specifications or with design faults.
5. Assessment of cause and extent of deterioration as a preliminary to the design of repair or
remedial schemes.
6. Monitoring of strength development in relation to formwork stripping, curing, Prestressing
or load application.
7. Monitoring long-term changes in materials properties and structural performance.
Page 8
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 8
4 METHODOLOGY
IS: 13311 (part I) specifies non-destructive testing method using ultrasonic pulse velocity and
part II specifies rebound hammer method. But the test selection procedure will be based on a
combination of factors such as non-destructiveness, cost, speed and reliability, and may conveniently
follow a procedure such as that shown in Table1.
TYPES OF TESTINGS:
1. Non-destructive tests
2. Destructive tests
3. Semi/partial destructive test
Table1: Test selection procedure
Inspection schedule Methods
First survey
History of structure
Visual inspection
Second survey
Ultrasonic testing
Rebound hammer
Cover test
Arrangement of bars
Other NDT (if necessary)
Third survey
Core test
Vibration test
Displacement test
5 NON DESTRUCTIVE TESTING METHODS
5.1 Ultrasonic Pulse Velocity
Fig.1 Ultrasonic pulse velocity equipment
Page 9
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 9
It was found that the velocity depended primarily upon the elastic properties of the material and
was almost independent of geometry.
Portable ultrasonic non-destructive digital indicative technique (PUNDIT) is an apparatus for non
destructive evaluation of concrete quality by ultrasonic pulse velocity (UPV) measurement method. The
equipment consists of a pair of transducers (probes) of different frequencies, electrical pulse generator,
and electrical timing device and cables (Fig.1). It is used to measure the transmission time of ultrasonic
pulses in the test specimen by placing transducers, from which the velocity can be computed. A set of
UPV readings can be used for further interpretations of structural concrete. The equipment is designed to
comply with the recommendations of IS-13311 (Part I) 1992.
Three types of waves are generated by an impulse applied to a solid mass. Surface waves having
an elliptical particle displacement are the lowest, whereas shear or transverse waves with particles
displacement at right angles to the direction of travel are faster. Longitudinal waves with particle
displacement in the direction of travel (some times known as compression waves) are the most
important since these are the fastest and provide more useful information. Electro-acoustical transducers
produce waves primarily of this type; other type generally cause little interference because of their lower
speed.
As we said earlier that velocity depends upon the elastic properties and mass of the medium, and
hence if the mass and velocity of wave propagation are known it is possible to assess the elastic
properties.
Transducers with natural frequencies between 20 kHz and 150 kHz are the most suitable for use
with concrete, and these may be of any type, although the piezo-electric crystal is most popular.
An alternative form is the exponential probe transducer, which makes a point contact, and offers
operating advantages over flat transducers on rough or curved surfaces. The time delay adjustment must
be used to set the zero reading for the equipment before use, and this should also be regularly checked
during and at the end of each period of use.
Page 10
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 10
5.1.1 Methods of testing
There are three methods of testing generally adopted at site depending on the accessibility of
structural members (Shetty, 2002).
1. Direct transmission
2. Indirect transmission and
3. Semi-direct transmission
Fig.2: Types of transmittions
In direct transmission method pulse velocity will be measured in concrete by placing transducers
across the member exactly opposite to each other. Since the maximum pulse energy is transmitted at
right angles to the face of the transmitter, the direct method is the most reliable from the point of view of
transit time measurement. Also, the path is clearly defined and can be measured accurately, and this
approach should be used wherever possible for assessing concrete quality.
In indirect transmission method pulse velocity will be measured in concrete by placing
transducers on the same plane of members. This method is definitely the least satisfactory, since the
received signal amplitude may be less than 3% of that for a comparable direct transmission. The
received signal is dependent upon scattering of the pulse by discontinuities and is thus highly subjected
to errors. The surface zone concrete, which may not be representative of the body, and the exact path
length is uncertain will predominantly influence the pulse velocity. A special procedure is necessary to
account for this lack of precision of path length, requiring a series of readings with the transmitter fixed
and the receiver located at a series of fixed incremental points along a chosen radial line. This is the least
reliable method of testing to ascertain the quality or strength of concrete. This method will be adopted
only when there is no other option.
concrete concrete concrete
Direct Semi-direct Indirect
Page 11
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 11
In semi-direct transmission method pulse velocity will be measured in concrete by placing
transducers intermediate between those of the other two methods. This method is sometimes be used
satisfactorily if the angle between the transducers is not too great, and if the path length is not large. The
sensitivity will be smaller, and if these requirements are not met it is possible that no clear signal will be
received because of attenuation of the transmitted pulse. The path length is also less clearly defined due
to the finite transducer size, but it is generally regarded as adequate to take this from center to center of
transducer faces. This is a moderately reliable method of testing to ascertain the quality or strength of
concrete.
5.1.2 How PUNDIT works?
Concrete is a multi-phase material. Speed of sound in concrete depends on the relative
concentration of its constituent materials, degree of compacting, moisture content, and the amount of
discontinuities present. The instrument generates pulses of ultrasonic frequency, which are coupled into
the concrete specimen under test by the transmitting transducer. The receiving transducer is used to
detect these pulses and to convert them back into electrical pulses. Suitable coupling media are used to
minimize losses due to acoustic mismatch at the transducer-specimen interfaces. A 10 MHz quartz time
base ensures accurate measurement of pulse transit time (T) with a resolution of 0.1 microseconds. The
path length (L) can be measured with a tape and hence the Ultrasonic Pulse Velocity (UPV) in the
specimen under test can be computed as
V = L / T
Pulse Velocity in concrete will be represented in km/Sec.
Appropriate correction factors to be applied depending on site condition and factors influencing velocity
of pulse. There are many factors relating to measurements made on in-situ concrete. which may further
influence result.
1. Temperature
2. Stress history
3. Path length
4. Moisture conditions
5. Reinforcement
Page 12
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 12
Table2: Acceptance criteria
Pulse Velocity (km/sec) Concrete Quality Grading (as per
IS:13311 (Part-1)-1992)
Above 4.5
3.5 to 4.5
3.1 to 3.5
below 3.0
Excellent
Good
Poor
Very poor
To evaluate strength of concrete based on the pulse velocity an appropriate calibration chart can
be established based on the laboratory tests. The equipment is used for estimation of properties of
concrete such as strength, uniformity, crack depths, etc. This is the most appropriate and reliable method
of testing to ascertain the quality or strength of concrete.
5.1.3 Reliability and limitation
Ultrasonic pulse velocity measurement has been found to be a valuable and reliable method of
examining the interior of a body of concrete in a truly non-destructive manner. Even though this test
method has limitations, UPV method of test is generally preferred to assess the strength / quality of
concrete in structural members. The method provides the only readily available method of determining
the extent of cracking within concrete; however, the use for detection of flaws within the concrete is not
reliable when the concrete is wet.
5.1.4 Applications
The applications of pulse velocity measurements are so wide-ranging that it would be impossible
to list or describe them all. The principal applications are outlined below-the method can be used both in
the laboratory and on site with equal success.
1. Laboratory applications
2. In-situ applications
Measurement of concrete uniformity
Detection of cracking and honeycombing
Strength estimation
Page 13
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 13
Assessment of concrete deterioration
Measurement of layer thickness
Measurement of elastic modulus
Strength development monitoring.
5.2 Rebound Hammer Technique
Fig.3 Rebound hammer
One of many factors connected with the quality of concrete is its hardness. The Schmidt rebound
hammer is basically a surface hardness test with little apparent theoretical relationship between the
strength of concrete and the rebound number of the hammer. The only known instrument to make use of
the rebound (impact) principle for concrete testing is the Schmidt hammer, which weighs about 1.8 kg
and is suitable for both laboratory and field work. It consists of a spring-controlled hammer mass that
slides on a plunger within a tubular housing. The plunger retracts against a spring when pressed against
the concrete surface and this spring is automatically released when fully tensioned, causing the hammer
mass to impact against the concrete through the plunger. When the spring-controlled mass rebounds, it
takes with it a rider, which slides along a scale and is visible through a small window in the side of the
casing. The rider can be held in position on the scale by depressing the locking button. The equipment is
simple to use, and may be operated either horizontally or vertically. The plunger is pressed strongly and
steadily against the concrete at right angles to its surface, until the spring-loaded mass is triggered from
its locked position. After the impact, the scale index is read while the hammer is still in the test position.
The scale reading is known as the rebound number, and is an arbitrary measure since it depends on the
Page 14
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 14
energy stored in the given spring and on the mass used. This equipment is most suitable for concretes in
the 20-60 Mpa strength range. The reading is very sensitive to local variations in the concrete, especially
to aggregate particles near to the surface. It is therefore necessary to take several readings at each test
location, and to find their average. IS: 13311 recommends 15 readings taken over an area not exceeding
300mm square, with the impact points not less than 20mm from each other or from an edge. The use of a
grid to locate these points reduces operator bias. The surface must be smooth, clean and dry, and should
preferably be formed, but if trowelled surfaces are unavoidable they should be rubbed smooth with the
carborundum stone usually provided with the equipment. Loose material can be ground off, but areas,
which are rough from poor compaction, grout loss, spalling or tooling, must be avoided since the results
will be unreliable.
The test is based on the principle that the rebound of an elastic mass depends on the hardness of the
surface upon which it impinges, and in this case will provide information about a surface layer of the
concrete defined as no more than 30mm deep. The results give a measure of the relative hardness of this
zone, and this cannot be directly related to any other property of the concrete. Many factors influence
results but must all are considered if rebound number is to be empirically related to strength.
Fig.4: Testing by rebound hammer
The hammer is forced against the surface of the concrete by the spring and the distance of rebound is
measured on a scale. The test surface can be horizontal, vertical or at any angle but the instrument must
be calibrated in this position.
5.2.1 Factors influencing test results
Results are significantly influenced by all the following factors.
1. Mix characteristics
Page 15
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 15
Cement type
Cement content
Coarse aggregate type.
2. Member characteristics
Mass
Compaction
Surface type
Age, rate of hardening and curing type
Surface carbonation
Moisture condition
Stress state and temperature.
5.2.2 Advantages
The Schmidt hammer provides an inexpensive, simple and quick method of obtaining an indication
of concrete strength, but accuracy of ±15 to ±20 percent is possible only for specimens cast cured and
tested under conditions for which calibration curves have been established.
5.2.3 Applications
The useful application of surface hardness measurements can be divided into four categories.
1. Checking the uniformity of concrete quality.
2. Comparing a given concrete with a specified requirement
3. Approximate estimation of strength
4. Abrasion resistance classification.
Page 16
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 16
5.2.4 Limitation of rebound hammers
Whatever the application, it is essential that the factors influencing test results are standardized or
allowed for, and it should be remembered that results relate only to the surface zone of the concrete
under test. A further overriding limitation related to testing at early ages or low strengths, because the
rebound numbers may be too low for accurate reading and the impact may also cause damage to the
surface. It is therefore not recommended that the method is used for concrete which has a cube strength
of less than 10Mpa or which is less than 7 days old, unless of high strength.
It has serious limitations and these must be recognized (Shetty, 2002). The results are affected by:
1. Size, shape and rigidity of the specimen.
2. Age of specimen.
3. Surface and internal moisture condition of the concrete.
4. Carbonation of concrete surface.
5.3 Cover Meter Test
Fig.5 Profometer
The fig.5 shows the locating the reinforcing bars in side the concrete with the help of profometer, which
is advance instrument. Diameter and position of reinforcement in concrete structure are important
parameters for evaluation of the durability and the stability of structure.
The profometer locates reinforcing bars, spacing of bars, diameter of the bar and measures concrete
cover – quickly, simply and with complete accuracy. It also helps in preparing structural drawing or
Page 17
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 17
mapping of structural members in the absence of details about the building. The identified concrete
surface will be cleaned such that it is free from dust, oil and any surface defects to facilitate for
scanning. This instrument, when moved on the concrete member in a structure, it produce a sound when
it comes near the reinforcement bar and in the details of the member is appears on the profometer
screen.
The profometer reinforcement locator is a lightweight, compact unit. It works with non-destructive
pulse-induction that is largely insensitive to external interference i.e., electromagnetic principle. Also
before using the instrument it should be calibrated with the help of the standard given steel rod, which is
20cm long, and 10mm in diameter (Malhotra, 1986).
Limitations of the equipment
1. Only peripheral rebars can be detected.
2. Second layer (if any) of rebars cannot be detected.
3. The accuracy of the diameter of rebar will vary generally in the range of 10 to 20%.
4. The actual numbers and position of rebars cannot be located if the rebars are closely spaced in
one location.
5. If the depth of cover concrete is beyond 60 mm then the estimation of diameter of rebars will not
be accurate or possible.
Page 18
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 18
6.0 CASE STUDY
NON DESTRUCTIVE TESTS FOR STRUCTURAL MEMBERES AT
GROUND FLOOR LEVEL OF THE PROPOSED POST METRIC SC/ST BOY‟S HOSTEL BUILDING LOCATED AT MASTI IN MALLUR TOWN.
Fig No. 1:- General Views Of The Proposed Post Metric Sc/St Boys Hostel Building Located At Masti.
Page 19
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 19
Non Destructive Test conducted at Ground floor level of meadow
in the sun
Fig 2 General view of proposed construction of meadow in the sun
Page 20
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 20
7.0 INTRODUCTION
With reference to the above, the Boy‟s Hostel Block has to be inspected by the concerned quality control
Engineers.
During the inspection, the discussions have to be held with contractor and client.
Then, It was decided to conduct the Non Destructive Tests on Structural members at Ground level
Columns, Beams & Slab of the Boy‟s Hostel Block to assess the compressive strength.
Non Destructive Tests at Ground and First floor levels for Columns, Beams & Slab area were conducted
on 22nd
April.
During conducting Non Destructive Tests
The following personnel were present:
1. Quality control Engineer
2. Contractor
3. Government agencies or Private agencies
Page 21
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 21
8.0 PHYSICAL INSPECTION
8.1 MALUR BOY’S HOSTEL BLOCK
A detailed physical inspection was carried out from 22nd April 2017 the following observations were
made:
1. The NDT conducted The Boy‟s Hostel Block is of RCC framed structure, consist of Ground
floor and First Floor.
2. General views of The Boy‟s Hostel Block are shown in Fig No.1.
3. The Non Destructive Tests namely Rebound Hammer Test and Ultrasonic Pulse Velocity Test
were conducted Columns, Beams & Slab area at Ground and first floor of Boy‟s Hostel Block.
4. As per the Drawings we received, the grade of concrete in tested Columns, Beams and Slab area
is mentioned as M20.
5. Non Destructive Tests conducted at Ground and first floor level are shown in:
(a) Rebound Hammer Test
(b) Ultrasonic Pulse Velocity Test
Page 22
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 22
8.2 THE PROPOSED CONSTRUCTION OF MEADOW IN THE SUN AT
HARALUR VILLAGE, EAST-BENGALURU
A detailed physical inspection was carried out on 29th April 2017 the following observations were made:
-
1. The NDT conducted to the proposed construction of meadow in the sun at haralur village, East-
Bengaluru-560035 is of RCC framed structure, Ground floor is partially built.
2. General views of the Building are shown in Fig No.1 to 2
3. The Non Destructive Test namely Ultrasonic Pulse Velocity Test is conducted for Columns, at
Ground floor level which is partially built.
4. As per the Drawings we received, the grade of concrete in tested Columns, is mentioned as M40.
Non Destructive Test conducted at Ground floor level of meadow in the sun
Page 23
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 23
9.0 PHOTOGRAPHS AND DRAWINGS
Fig No.3:-Rebound Hammer Test on Columns is in Progress
Fig No 4:- Rebound Hammer Test on Columns is in Progress
Page 24
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 24
Fig No 5:- Ultrasonic pulse velocity Test on Columns is in Progress
Fig No 6- Ultrasonic pulse velocity Test on Columns is in Progress
Page 25
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 25
Fig7 Markings Done on the Columns
Page 26
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 26
Fig 8 Ultrasonic Pulse Velocity on Columns is going on
10 CONDUCTING OF NON DESTRUCTIVE TESTS:
The following Non Destructive Tests were conducted:
1) Rebound Hammer Test.
2) Ultrasonic Pulse Velocity Test.
10.1 Rebound hammer test:
The Rebound Hammer Test was carried out at Ground and First floor levels of Columns, Beams
& Slab area using the versatile Schmidt Hammer from M/s Proceq, Switzerland. The tests were
conducted as per the guidelines in Indian Standards IS: 13311 (Part-2) 1992 (Reaffirmed in
2004).
The test results are presented in Table.3 along with compressive strength of concrete.
10.2 Ultrasonic pulse velocity test:
Page 27
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 27
Ultrasonic Pulse Velocity test was conducted at Ground and first floor level of Columns, Beams
& Slab area in order to assess the quality / strength of in-situ concrete. The tests were conducted
using PUNDIT (Portable Ultrasonic Non- Destructive Digital India (Tester) equipment from
M/s. Proceq, Switzerland. The guidelines as per Indian Standards IS: 13311-(Part-I)-1992-
(Reaffirmed in 2004) was followed.
The tests results are presented in Table 4.
1-1 REFERENCE STRENGTH CHART FOR REBOUND HAMMER TEST
Technical reference : Based on the Lab Calibration
Rebound
number
Estimated compressive strength
range (n/sq.m.m)
22 to 26 10 to 14
26 to 30 14 to 18
30 to 34 18 to 22
34 to 36 22 to 26
Page 28
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 28
1-2 VELOCITY CRITERIONS FOR CONCRETE QUALITY GRADING
(I S: 13311 (Part 1): 1992 – Non Destructive testing of concrete: Methods of tests,
Part 1 – Ultrasonic Pulse Velocity test (First reprint September 1996)
No. Pulse Velocity
By cross probing (km / sec) Concrete Quality Grading
1. Above 4.5 Excellent
2. 3.5 to 4.5 Good
3. 3.0 to 3.5 Medium
36 to 42 26 to 34
42 to 46 34 to 36
Page 29
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 29
4. Below 3.0 Doubtful
Note: In case of “doubtful” quality it may be necessary to carry out further tests.
Pulse Velocity (Km / Sec)
Estimated Compressive Strength
(Based on Lab Calibration)
(N / Sq.mm)
2.70 to 2.99 10 – 14
3.0 to 3.3 14 – 16
3.3 to 3.5 16 – 18
3.5 to 3.7 18 – 22
3.7 to 4.0 22 – 26
4.0 to 4.3 26 – 28
4.3 to 4.5 28 – 30
4.5 to 4.7 30 - 32
4.7 to 4.9 32 - 35
Page 30
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 30
Table.1: Rebound Hammer Test Results
IS: 13311 (Part 2):1992
Floor Level : Ground & First floor level
Project : Boy‟s Hostel Block In Karnataka Government Technical Training Institute at Gulbarga
Date : 22nd
April 2017
Table.1: Rebound Hammer Test Results
IS: 13311 (Part 2):1992
Floor Level : Ground floor level
Project : Boys‟ Hostel Block Malur.
Date : 22nd April 2017
Sl
No
Structural
Members Position
Rebound
Hammer
Number
Average
Rebound
Hammer
Number
Probable
Strength
Of Concrete
in N/mm2
Remarks
1 Column
24 R
Top
Middle
Bottom
30
31
31
31 18 - 20
Page 31
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 31
2
Column
23 N
Top
Middle
Bottom
32
32
31
32 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
3
Beam
23 NS
1
2
3
30
30
31
30 18 - 20
4
Column
22 R
Top
Middle
Bottom
30
31
30
30 18 - 20
5
Beam R
22 - 24
1
2
3
32
31
32
32
18 - 20
6
Slab Area
@
R – U
22 - 19
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
30
32
32
32
32
32 18 - 20
7 Round Column
18 T
Top
Middle
Bottom
30
30
31
30 18 - 20
8 Column
19 x
Top
Middle
32
32 32 18 - 20
Page 32
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 32
Bottom 31
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
9 Round Column
C9
Top
Middle
Bottom
31
30
30
30 18 - 20
10 Round Column
16 Q
Top
Middle
Bottom
32
31
32
32 18 - 20
11 Round Column
14 Q
Top
Middle
Bottom
31
31
32
31 18 - 20
12 Round Column
12 T
Top
Middle
Bottom
32
32
31
32 18 - 20
13 Column
13 Z
Top
Middle
Bottom
30
30
31
30 18 - 20
14 Round Column
16 Z
Top
Middle
Bottom
32
32
31
32 18 - 20
15 Round Column
18 Y
Top
Middle
Bottom
30
30
31
30 18 - 20
16 Round Column
19 N
Top
Middle
Bottom
31
31
32
31 18 - 20
17 Round Column Top 30 31 18 - 20
Page 33
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 33
18 M Middle
Bottom
30
31
18 Round Column
18 N
Top
Middle
Bottom
30
30
31
30 18 - 20
19 Round Column
18 I
Top
Middle
Bottom
32
32
31
32 18 - 20
20 Round Column
15 E
Top
Middle
Bottom
31
30
30
30 18 - 20
21 Round Column
12 F
Top
Middle
Bottom
30
31
31
31 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
22 Round Column
12 J
Top
Middle
Bottom
30
30
31
30 18 - 20
23 Round Column
12 N
Top
Middle
Bottom
31
31
32
31 18 - 20
24 Column
19 L
Top
Middle
Bottom
31
32
31
31 18 - 20
25
Beam L
19 - 22
1
2
3
30
30
31
30 18 - 20
Page 34
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 34
26 Column
22 G
Top
Middle
Bottom
32
32
31
32 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
27
Beam G
19 - 20
1
2
3
31
31
32
31 18 - 20
28
Slab Area
@
D – G
19 - 22
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
32
32
31
32 18 - 20
29
Slab Area
@
S – T
18 - 19
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
31
31
31
31
30
31 18 - 20
30
Slab Area
@
A – Y
18 - 19
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
31
30
30
30
31
30 18 - 20
31 Slab Area a – b 32 32 18 - 20
Page 35
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 35
@
A – Z
13 - 15
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
31
32
32
31
32
Slab Area
@
T – W
11 - 12
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
31
30
30
31
30
30 18 - 20
33
Slab Area
@
N – S
10 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
31
32
32
31
31
31
31 18 - 20
34
Slab Area
@
P –Q
15 - 16
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
31
30
31
30
31
31
31 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
35
Slab Area
@
A – M
18 - 19
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
31
32
31
31
31
31 18 - 20
Page 36
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 36
36
Slab Area
@
C – E
14- 16
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
31
32
32
32
31
32 18 - 20
37
Slab Area
@
F – J
11- 12
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
31
30
30
30
31
31 18 - 20
38 Column
20 D
Top
Middle
Bottom
30
31
30
30
39
Slab Area
@
B – D
17- 21
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
31
31
31
32 18 - 20
40 Column
15 C
Top
Middle
Bottom
31
31
32
31
41
Slab Area
@
A – C
15- 17
a – b
b – c
a1 – b1
b1 – c1
32
32
31
31
32 18 - 20
Page 37
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 37
a2 – b2
b2 – c2
31
31
42
Beam
A – C
15
1
2
3
30
30
31
30 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
43
Beam
C
13 - 15
1
2
3
31
31
32
31 18 - 20
44
Slab Area
@
A – C
13- 15
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
31
32
32
32 18 - 20
45 Column
15 B
Top
Middle
Bottom
30
30
31
30 18 - 20
46 Column 13 D
Top
Middle
Bottom
32
32
31
32 18 - 20
47
Slab Area
@
B – E
8 - 13
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
30
30
31
30
30
30 18 - 20
Page 38
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 38
b2 – c2 31
48 Column 11 G
Top
Middle
Bottom
31
32
31
31 18 - 20
49
Slab Area
@
D – G
7 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
30
31
31
30
30
30 18 - 20
50
Beam
G
7 - 11
1
2
3
32
32
31
32 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
51
Beam
L
7 - 11
1
2
3
31
30
30
30 18 - 20
52
Slab Area
@
G – L
7 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
31
32
31
32
32
32 18 - 20
53 Slab Area
@
a – b
b – c
31
31 31 18 - 20
Page 39
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 39
L – N
11 - 12
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
31
54 Column
11 N
Top
Middle
Bottom
32
32
31
32 18 - 20
55
Slab Area
@
S – U
11 - 12
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
31
31
32
31
31
31 18 - 20
56
Beam
Q - U
7
1
2
3
32
31
31
31 18 - 20
57 Column
11 X
Top
Middle
Bottom
30
31
30
30 18 - 20
58
Beam
11 X U
1
2
3
31
30
31
31 18 - 20
59
Slab Area
@
X– U
7 - 11
a – b
b – c
a1 – b1
b1 – c1
32
31
31
32
31 18 - 20
Page 40
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 40
a2 – b2
b2 – c2
31
31
60 Column
A 9
Top
Middle
Bottom
30
30
31
30 18 - 20
61
Beam
X
7 - 11
1
2
3
32
32
31
32 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
62
Slab Area
@
A – X
7 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
31
30
30
31
30
30
30 18 - 20
63 Column
A 13
Top
Middle
Bottom
32
31
32
32 18 – 20
64
Slab Area
@
A – C
7 - 13
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
31
31
32
31 18 – 20
65 Column
13 C
Top
Middle
Bottom
31
32
31
31 18 – 20
66 Slab Area a – b 30 30 18 – 20
Page 41
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 41
@
B – D
13 - 15
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
31
30
31
30
67 Column
15 B
Top
Middle
Bottom
32
32
31
32 18 – 20
68
Beam
15 – 18
B
1
2
3
31
30
30
30 18 – 20
69 Column
17 C
Top
Middle
Bottom
32
31
32
32 18 - 20
70
Beam
A – C
17
1
2
3
31
31
32
31 18 - 20
71
Slab Area
@
A –C
15- 17
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
31
32
32
32 18 - 20
72 Column
17 A
Top
Middle
Bottom
30
30
31
30 18 - 20
Ref chart 1-1
Page 42
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 42
73
Slab Area
@
A – C
16 - 20
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
31
32
32
32 18 - 20
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
74
Slab Area
@
X – T
19 - 22
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
30
31
30
31
30
30 18 - 20
75
Beam
X – T
22
1
2
3
31
31
32
31 18 – 20
76 Column
P 7
Top
Middle
Bottom
30
30
31
31 18 – 20
77
Column
Q 7
Top
Middle
Bottom
30
30
31
30 18 – 20
78
Column
P 6
Top
Middle
Bottom
32
32
31
32 18 – 20
79 Top 31 30 18 – 20
Page 43
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 43
Column
Q 6
Middle
Bottom
30
30
80
Column
U 6
Top
Middle
Bottom
32
31
32
32 18 - 20
81
Beam
U
3 - 6
1
2
3
32
32
31
32 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
82
Column
X 6
Top
Middle
Bottom
30
30
31
30 18 - 20
83
Beam
X
3 - 6
1
2
3
32
32
31
32 18 - 20
84
Slab Area
@
U – X
3 - 6
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
30
31
30
31
30
30 18 - 20
85 1 31 31 18 - 20
Page 44
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 44
Beam
X T
6
2
3
31
32
86
Column
3 U
Top
Middle
Bottom
32
32
31
32 18 - 20
87
Beam
U
1 - 3
1
2
3
30
30
31
30 18 - 20
88
Column
3 X
Top
Middle
Bottom
32
32
31
32 18 - 20
89
Beam
X
1 - 3
1
2
3
30
30
31
30 18 - 20
90
Column
1 X
Top
Middle
Bottom
31
31
32
31 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
91
Column
Top
Middle
31
32 31 18 - 20
Page 45
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 45
1 U
Bottom 31 as per Indian standard
13311-Part-2
92
Beam
Q – U
2
1
2
3
30
30
31
30 18 - 20
93
Slab Area
@
X - T
1 - 3
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
32
31
31
32
32
32 18 - 20
94
Slab Area
@
Q - U
2 - 4
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
30
30
31
31
30
30
30 18 - 20
95
Column
P 2
Top
Middle
Bottom
32
31
31
31 18 - 20
96
Column
1 Q
Top
Middle
Bottom
32
31
31
31 18 - 20
97 Top 32 31 18 - 20
Page 46
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 46
Column
M 4
Middle
Bottom
30
31
98
Column
M 2
Top
Middle
Bottom
30
30
31
30 18 - 20
99
Beam
Q – U
4
1
2
3
32
32
31
32 18 - 20
100
Slab Area
@
Q - M
2 - 4
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
31
30
30
31
30
30
30 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
101
Column
H 4
Top
Middle
Bottom
32
31
32
32 18 - 20
102
Double Column
H 2
Top
Middle
Bottom
31
31
32
31 18 - 20
103
Column
1 D
Top
Middle
Bottom
32
32
31
32 18 - 20
Page 47
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 47
104
Column
1 H
Top
Middle
Bottom
30
30
31
30 18 - 20
105
Column
4 D
Top
Middle
Bottom
32
32
31
32 18 - 20
106
Column
5 D
Top
Middle
Bottom
30
30
31
30 18 - 20
107
Column
6 D
Top
Middle
Bottom
31
31
32
31 18 - 20
108
Column
6 H
Top
Middle
Bottom
30
30
31
31 18 - 20
109
Lintel Beam
D – H
1
1
2
3
30
30
31
30 18 - 20
110
Lintel Beam
1
2
32
32 32 18 - 20
Page 48
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 48
P – M
2
3 31
111
Column
5 H
Top
Middle
Bottom
31
30
30
30 18 - 20
Ref chart 1-1
± 25 % of design
strength is permissible
as per Indian standard
13311-Part-2
112
Slab Area
@
D - H
2 - 6
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
32
31
32
31
32
32
32 18 - 20
113
Lintel Beam
H
2 - 4
1
2
3
32
32
31
32 18 - 20
114
Column
G 22
Top
Middle
Bottom
32
32
31
32 18 - 20
115
Column
A 22
Top
Middle
Bottom
30
30
31
30 18 - 20
116
Column
Top
Middle
32
32 32 18 - 20
Page 49
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 49
B 21
Bottom 31
117
Column
A 15
Top
Middle
Bottom
30
30
31
30 18 - 20
118
Column
D 6
Top
Middle
Bottom
31
31
32
31 18 - 20
119
Column
D 1
Top
Middle
Bottom
30
30
31
31 18 - 20
120
Column
A 1
Top
Middle
Bottom
30
30
31
30 18 - 20
121
Column
A 3
Top
Middle
Bottom
32
32
31
32 18 - 20
Page 50
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 50
Table.2: Ultrasonic Pulse Velocity Test Results IS: 13311 (Part 1):1992
Sl.
No
Structural
Members Position
Ultrasonic Pulse
Velocity in Km/Sec
Average Velocity
Km / Sec
Concrete Quality Grading As Per IS – 13311- PART-1
Remarks
Ref chart 1-2
1 Column
24 R
Top
Middle
Bottom
3.63
3.62
3.65
3.63
Good
2
Column
23 N
Top
Middle
Bottom
3.62
3.64
3.68
3.64
Good
3
Beam
23 NS
1
2
3
3.67
3.62
3.69
3.66
Good
4
Column
22 R
Top
Middle
Bottom
3.67
3.69
3.61
3.65
Good
5
Beam R
22 - 24
1
2
3
3.67
3.69
3.61
3.65
Good
6
Slab Area
@
R – U
a – b
b – c
a1 – b1
3.56
3.58
3.54
3.55
Page 51
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 51
22 - 19 b1 – c1
a2 – b2
b2 – c2
3.52
3.52
3.58
Good
7 Round Column
18 T
Top
Middle
Bottom
3.66
3.65
3.64
3.65
Good
8 Column
19 x
Top
Middle
Bottom
3.69
3.67
3.61
3.65
Good
9 Round Column
C9
Top
Middle
Bottom
3.60
3.62
3.66
3.62
Good
10 Round Column
16 Q
Top
Middle
Bottom
3.56
3.54
3.55
3.55
Good
11 Round Column
14 Q
Top
Middle
Bottom
3.66
3.68
3.67
3.67
Good
12 Round Column
12 T
Top
Middle
Bottom
3.69
3.64
3.61
3.64
Good
13 Column
13 Z
Top
Middle
Bottom
3.59
3.63
3.60
3.60
Good
14 Round Column
16 Z
Top
Middle
Bottom
3.61
3.66
3.65
3.64
Good
Page 52
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 52
15 Round Column
18 Y
Top
Middle
Bottom
3.67
3.69
3.68
3.68
Good
16 Round Column
19 N
Top
Middle
Bottom
3.60
3.59
3.57
3.58
Good
17 Round Column
18 M
Top
Middle
Bottom
3.60
3.59
3.58
3.59
Good
18 Round Column
18 N
Top
Middle
Bottom
3.55
3.56
3.54
3.55
Good
19 Round Column
18 I
Top
Middle
Bottom
3.59
3.57
3.56
3.57
Good
20 Round Column
15 E
Top
Middle
Bottom
3.66
3.65
3.64
3.65
Good
21 Round Column
12 F
Top
Middle
Bottom
3.59
3.57
3.51
3.55
Good
22 Round Column
12 J
Top
Middle
Bottom
3.60
3.59
3.58
3.59
Good
23 Round Column
12 N
Top
Middle
Bottom
3.66
3.69
3.64
3.63
Good
Page 53
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 53
24 Column
19 L
Top
Middle
Bottom
3.56
3.54
3.50
3.53
Good
25
Beam L
19 - 22
1
2
3
3.56
3.58
3.59
3.57
Good
26 Column
22 G
Top
Middle
Bottom
3.66
3.68
3.64
3.66
Good
27
Beam G
19 - 20
1
2
3
3.61
3.59
3.57
3.59
Good
28
Slab Area
@
D – G
19 - 22
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.51
3.56
3.58
3.54
3.57
3.55
3.55
Good
29
Slab Area
@
S – T
18 - 19
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.56
3.58
3.54
3.52
3.52
3.58
3.55
Good
30 Slab Area
@
a – b
b – c
3.66
3.65 3.66
Page 54
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 54
A – Y
18 - 19
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.69
3.68
3.69
3.64
Good
31
Slab Area
@
A – Z
13 - 15
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.50
3.56
3.55
3.57
3.54
3.55
3.54
Good
32
Slab Area
@
T – W
11 - 12
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
33
Slab Area
@
N – S
10 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.59
3.58
3.56
3.59
3.56
3.58
Good
34
Slab Area
@
P –Q
15 - 16
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.56
3.55
3.52
3.59
3.52
3.58
3.55
Good
Page 55
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 55
35
Slab Area
@
A – M
18 - 19
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
36
Slab Area
@
C – E
14- 16
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.66
3.69
3.68
3.64
3.66
3.61
3.65
Good
37
Slab Area
@
F – J
11- 12
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.55
3.52
3.51
3.58
3.50
3.59
3.54
Good
38 Column
20 D
Top
Middle
Bottom
3.60
3.59
3.58
3.59
Good
39
Slab Area
@
B – D
17- 21
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.50
3.56
3.55
3.57
3.54
3.55
3.54
Good
40 Column Top 3.60 3.59
Page 56
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 56
15 C Middle
Bottom
3.59
3.58
Good
41
Slab Area
@
A – C
15- 17
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.66
3.69
3.68
3.64
3.66
3.61
3.65
Good
42
Beam
A – C
15
1
2
3
3.60
3.59
3.58
3.59
Good
43
Beam
C
13 - 15
1
2
3
3.66
3.69
3.64
3.63
Good
44
Slab Area
@
A – C
13- 15
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.55
3.52
3.51
3.58
3.50
3.59
3.54
Good
45 Column
15 B
Top
Middle
Bottom
3.55
3.56
3.54
3.55
Good
46 Column 13 D
Top
Middle
Bottom
3.59
3.57
3.56
3.57
Good
47 Slab Area
@
a – b
b – c
3.66
3.69 3.65
Page 57
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 57
B – E
8 - 13
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.68
3.64
3.66
3.61
Good
48 Column 11 G
Top
Middle
Bottom
3.56
3.54
3.55
3.55
Good
49
Slab Area
@
D – G
7 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.59
3.58
3.56
3.59
3.56
3.58 Good
50
Beam
G
7 - 11
1
2
3
3.56
3.54
3.55
3.55
Good
51
Beam
L
7 - 11
1
2
3
3.66
3.68
3.67
3.67
Good
52
Slab Area
@
G – L
7 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
53 Slab Area a – b 3.61 3.58 Good
Page 58
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 58
@
L – N
11 - 12
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.59
3.58
3.56
3.59
3.56
54 Column
11 N
Top
Middle
Bottom
3.56
3.58
3.59
3.57
Good
55
Slab Area
@
S – U
11 - 12
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
56
Beam
Q - U
7
1
2
3
3.56
3.54
3.55
3.55
Good
57 Column
11 X
Top
Middle
Bottom
3.66
3.68
3.67
3.67
Good
58
Beam
11 X U
1
2
3
3.69
3.64
3.61
3.64
Good
59
Slab Area
@
X– U
7 - 11
a – b
b – c
a1 – b1
b1 – c1
3.61
3.62
3.66
3.68
3.65
Good
Page 59
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 59
a2 – b2
b2 – c2
3.69
3.64
60 Column
A 9
Top
Middle
Bottom
3.55
3.56
3.54
3.55 Good
61
Beam
X
7 - 11
1
2
3
3.59
3.57
3.56
3.57 Good
62
Slab Area
@
A – X
7 - 11
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
63 Column
A 13
Top
Middle
Bottom
3.69
3.67
3.61
3.65
Good
64
Slab Area
@
A – C
7 - 13
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
65 Column
13 C
Top
Middle
Bottom
3.56
3.58
3.59
3.57
Good
66 Slab Area a – b 3.61 3.65 Good
Page 60
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 60
@
B – D
13 - 15
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.62
3.66
3.68
3.69
3.64
67 Column
15 B
Top
Middle
Bottom
3.56
3.58
3.59
3.57
Good
68
Beam
15 – 18
B
1
2
3
3.56
3.58
3.54
3.56
Good
69 Column
17 C
Top
Middle
Bottom
3.56
3.58
3.59
3.57
Good
70
Beam
A – C
17
1
2
3
3.56
3.58
3.59
3.57
Good
71
Slab Area
@
A –C
15- 17
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.61
3.62
3.66
3.68
3.69
3.64
3.65
Good
72 Column
17 A
Top
Middle
Bottom
3.61
3.59
3.57
3.59 Good
Page 61
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 61
73
Slab Area
@
A – C
16 - 20
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.66
3.69
3.68
3.64
3.66
3.61
3.65 Good
74
Slab Area
@
X – T
19 - 22
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.55
3.52
3.51
3.58
3.50
3.59
3.54 Good
75
Beam
X – T
22
1
2
3
3.56
3.58
3.59
3.57
Good
76 Column
P 7
Top
Middle
Bottom
3.66
3.68
3.64
3.66
Good
77
Column
Q 7
Top
Middle
Bottom
3.61
3.59
3.57
3.59
Good
78
Column
P 6
Top
Middle
Bottom
3.52
3.51
3.57
3.53
Good
Page 62
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 62
79
Column
Q 6
Top
Middle
Bottom
3.56
3.58
3.59
3.57
Good
80
Column
U 6
Top
Middle
Bottom
3.66
3.68
3.64
3.66
Good
81
Beam
U
3 - 6
1
2
3
3.61
3.59
3.57
3.59
Good
82
Column
X 6
Top
Middle
Bottom
3.52
3.51
3.57
3.53
Good
83
Beam
X
3 - 6
1
2
3
3.56
3.58
3.59
3.57 Good
84
Slab Area
@
U – X
3 - 6
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.66
3.69
3.68
3.64
3.66
3.61
3.65 Good
85 3.55 3.55
Page 63
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 63
Beam
X T
6
1
2
3
3.56
3.54
Good
86
Column
3 U
Top
Middle
Bottom
3.59
3.57
3.56
3.57
Good
87
Beam
U
1 - 3
1
2
3
3.66
3.65
3.64
3.65
Good
88
Column
3 X
Top
Middle
Bottom
3.69
3.67
3.61
3.65
Good
89
Beam
X
1 - 3
1
2
3
3.55
3.56
3.54
3.55
Good
90
Column
1 X
Top
Middle
Bottom
3.59
3.57
3.56
3.57
Good
91
Column
1 U
Top
Middle
Bottom
3.66
3.65
3.64
3.65
Good
92
Beam
1
2
3.69
3.67
3.65
Good
Page 64
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 64
Q – U
2
3 3.61
93
Slab Area
@
X - T
1 - 3
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.69
3.62
3.62
3.69
3.65
3.63
3.65
Good
94
Slab Area
@
Q - U
2 - 4
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.66
3.65
3.69
3.68
3.69
3.64
3.66 Good
95
Column
P 2
Top
Middle
Bottom
3.66
3.68
3.67
3.67 Good
96
Column
1 Q
Top
Middle
Bottom
3.69
3.64
3.61
3.64 Good
97
Column
M 4
Top
Middle
Bottom
3.59
3.63
3.60
3.60 Good
98
Column
Top
Middle
3.61
3.66 3.64 Good
Page 65
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 65
M 2 Bottom 3.65
99
Beam
Q – U
4
1
2
3
3.55
3.56
3.54
3.55
Good
100
Slab Area
@
Q - M
2 - 4
a – b
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.69
3.62
3.62
3.69
3.65
3.63
3.65
Good
101
Column
H 4
Top
Middle
Bottom
3.60
3.59
3.57
3.58 Good
102
Double Column
H 2
Top
Middle
Bottom
3.60
3.59
3.58
3.59 Good
103
Column
1 D
Top
Middle
Bottom
3.55
3.56
3.54
3.55 Good
104
Column
1 H
Top
Middle
Bottom
3.59
3.57
3.56
3.57
Good
105 Top 3.66 3.65
Page 66
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 66
Column
4 D
Middle
Bottom
3.65
3.64
Good
106
Column
5 D
Top
Middle
Bottom
3.69
3.67
3.61
3.65
Good
107
Column
6 D
Top
Middle
Bottom
3.60
3.59
3.57
3.58 Good
108
Column
6 H
Top
Middle
Bottom
3.60
3.59
3.58
3.59 Good
109
Lintel Beam
D – H
1
1
2
3
3.60
3.59
3.58
3.59 Good
110
Lintel Beam
P – M
2
1
2
3
3.56
3.54
3.55
3.55
Good
111
Column
5 H
Top
Middle
Bottom
3.55
3.56
3.54
3.55
Good
112 Slab Area a – b 3.66 3.66 Good
Page 67
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 67
@
D - H
2 - 6
b – c
a1 – b1
b1 – c1
a2 – b2
b2 – c2
3.65
3.69
3.68
3.69
3.64
113
Lintel Beam
H
2 - 4
1
2
3
3.56
3.54
3.55
3.55
Good
114
Column
G 22
Top
Middle
Bottom
3.66
3.68
3.67
3.67 Good
115
Column
A 22
Top
Middle
Bottom
3.69
3.64
3.61
3.64 Good
116
Column
B 21
Top
Middle
Bottom
3.59
3.57
3.56
3.57
Good
117
Column
A 15
Top
Middle
Bottom
3.69
3.65
3.68
3.67
Good
118
Column
D 6
Top
Middle
Bottom
3.56
3.54
3.55
3.55
Good
Page 68
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 68
119
Column
D 1
Top
Middle
Bottom
3.66
3.68
3.67
3.67 Good
120
Column
A 1
Top
Middle
Bottom
3.69
3.64
3.61
3.64 Good
121
Column
A 3
Top
Middle
Bottom
3.56
3.54
3.55
3.55
Good
Ultrasonic Pulse Velocity Test
Floor Level : Ground Floor Level
Project : The Proposed construction of Meadow in the sun at Haralur
village, East-Bengaluru-560035
Date : 29th April 2017
Table.2: Ultrasonic Pulse Velocity Test Results
IS: 13311 (Part 1):1992
Sl. No
Structural Members
Position Pulse
Velocity (m/Sec)
Average Pulse
Velocity (m/Sec)
Concrete Quality Grading As Per IS –
13311- PART-1 Remarks
Ref chart 1-2
GROUND FLOOR
Page 69
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 69
COLUMNS
1
Column E11Y
Top Middle Bottom
4.35 4.33 4.31
4.33 Good
2 Column
E11X
Top Middle-1 Middle-2 Bottom
4.30 4.39 4.28 4.24
4.30 Good
3 Column E11W
Top Middle-1 Middle-2 Bottom
4.35 4.32 4.34 4.20
4.30 Good
4 Column
E11V
Top Middle-1 Middle-2 Bottom
4.41 4.41 4.38 4.36
4.39 Good
5 Column
E11T
Top
Middle-1 Middle-2 Bottom
4.54 4.44 4.40 4.10
4.37 Good
6 Column
E11S
Top Middle-1 Middle-2 Bottom
4.59 4.58 4.51 4.46
4.53 Excellent
7 Column
E11R
Top Middle Bottom
4.47 4.25 4.25
4.32 Good
8 Column
E11Q
Top Middle Bottom
4.44 4.42 4.30
4.38 Good
9 Column
E11N
Top Middle Bottom
4.36 4.32 4.32
4.33 Good
10 Column
E11M
Top
Middle
4.48 4.45 4.30
4.41 Good
14
Page 70
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 70
Bottom
11 Column
E9M
Top Middle Bottom
4.48 4.39 4.37
4.41 Good
12 Column
E9N
Top
Middle Bottom
4.34 4.34 4.30
4.32 Good
13 Column
E9Q
Top
Middle Bottom
4.56 4.46 4.30
4.44 Good
14 Column
E9R
Top
Middle Bottom
4.58 4.56 4.48
4.54 Excellent
15 Column
E9S
Top
Middle-1 Middle-2 Bottom
4.59 4.54 4.57 4.41
4.52 Excellent
16 Column
E9T
Top
Middle-1 Middle-2 Bottom
4.50 4.44 4.40 4.37
4.42 Good
17 Column
E9V
Top
Middle-1 Middle-2
4.59 4.35 4.30 4.20
4.36 Good
Page 71
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 71
Bottom
18 Column
E9W
Top
Middle-1 Middle-2 Bottom
4.40 4.38 4.35 4.35
4.37 Good
19 Column
E9X
Top Middle-1 Middle-2 Bottom
4.44 4.44 4.48 4.38
4.43 Good
20 Column
E9Y
Top Middle Bottom
4.50 4.50 4.48
4.49 Good
21 Column
E8Y
Top Middle Bottom
4.40 4.38 4.35
4.37 Good
22 Column
E8X
Top Middle-1 Middle-2 Bottom
4.40 4.38 4.36 4.30
4.36 Good
23 Column
E8W
Top
Middle-1 Middle-2 Bottom
4.41 4.39 4.35 4.34
4.37 Good
24 Column
E8V
Top Middle-1 Middle-2 Bottom
4.40 4.34 4.32 4.30
4.34 Good
25 Column
E8T
Top Middle-1 Middle-2 Bottom
4.39 4.38 4.38 4.28
4.35 Good
26 Column
E8S Top
Middle 4.35 4.31
4.30 Good
Page 72
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 72
Bottom 4.25
27 Column
E8R
Top Middle Bottom
4.41 4.40 4.38
4.39 Good
28 Column
E8Q
Top
Middle Bottom
4.38 4.38 4.33
4.36 Good
29
Column E8N
Top Middle Bottom
4.42 4.40 4.39
4.40 Good
30 Column
E8M
Top Middle Bottom
4.45 4.41 4.36
4.40 Good
Page 73
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 73
11. INFERENCES:-
11.1 MALUR BOY’S HOSTEL:
Based on the NDT tests results & interpolating the values for compressive strength of Columns Beams
& Slab area Tested in Boy‟s Hostel Block at Ground Floor.
The following inference is drawn:-
The assessed Compressive Strength of hardened Concrete tested in the Columns, Beams & Slab area
Tested in Boy‟s Hostel Block at Ground floor on an average, is as follows:
Ground and First floor level:-
Columns Tested = 26 - 28 N / mm2
Beam Tested = 26 - 28N / mm2
Slab area Tested = 26 - 28 N / mm2
11.2 PROPOSED CONSTRUCTION OF MEADOW IN THE SUN AT HARALUR
VILLAGE, EAST-BENGALURU
Based on the NDT test results for concrete quality grading for Columns tested for Proposed
construction of Meadow in the sun at Haralur village, East-Bengaluru-560035 Building at Ground floor
level.
The following inference is drawn:-
Page 74
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 74
The assessed concrete quality grading of hardened Concrete tested in the Columns, of the Proposed
construction of Meadow in the sun at Haralur village, East-Bengaluru-560035, as an average is as
follows:
AT GROUND FLOOR LEVEL:-
Columns Tested = Concrete quality grading is GOOD
Dr. M.Keshva Murthy Dr. Sadath Ali Khan Zai,
ME (Psc.) Ph.D. MISTE M.E.(Const.Tech),Ph.D.,MISTE.
Associate Professor, Associate Professor,
Department of Civil Engineering, Department of Civil Engineering,
U.V.C.E, Jnana Bharathi U.V.C.E, Jnana Bharathi
Bangalore University Bangalore University
Bangalore - 560056 Bangalore - 560056
Page 75
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 75
12 . CONCLUSIONS
1. Although nondestructive tests are relatively simple to perform, the analysis and interpretation of
the test data are not so easy because concrete is a complex material. The user is therefore
cautioned that interpretation of the test data must always be carried out by specialists in this field
rather than by technicians performing the tests.
2. If used properly, nondestructive test can form a very important link in the chain of testing and
evaluation of concrete and concrete structures, which commences with the breaking of test
cylinders and may end with the “load testing” of a finished structure.
3. In a structure, strength attained is different from that specified. They depend on real compaction
and consolidation conditions. An attempt is made to know approximate strength of concrete after
the structure has been occupied by using Non-Destructive Testing methods.
4. The first instrument used in NDT is the ultrasonic pulse velocity instrument. Even though this
test method has limitations, UPV method of test is generally preferred to assess the strength or
quality of concrete and other many properties in structural members. NDT is now considered as a
powerful method for evaluating existing concrete structure with regard to their strength,
durability, investigation of crack depth, micro cracks and progressive deterioration are also
studied by this method. But the rebound hammer testing methods are used to co-relate the results
obtained from the ultrasonic pulse velocity method.
5. Cover meter is the method from which approximate mapping of the rebars in structure can be
done. Even though this equipment has limitations still it is very widely used all over the world to
generate the structural details of R.C members, especially in the absence of structural drawings.
Page 76
DEPT OF CIVIL ENGINEERING, NHCE, BANGALORE. Page 76
REFERENCES
1. Bungey, J.H, (1989), “Testing of Concrete in Structure”, Surrey University pres, USA: Chapman
and Hall, New York.
2. Chapman and Hall, “Testing during Concrete Construction”, proceedings of an International
RILEM Workshop, New York.
3. IS: 13311 (part 1) - 1992, “Methods of non-destructive testing of concrete- Ultrasonic pulse
velocity”, BIS, New Delhi.
4. IS: 13311 (part 2) - 1992, “Methods of non-destructive testing of concrete- rebound hammer”,
BIS, New Delhi.
5. Malhotra, V.M, (1986), “Testing Hardened Concrete- Non Destructive Methods”, ACI and
IOWA State University Press, US.
6. Neville, A.M. (1996), “Properties of Concrete”, ELBS, New Delhi.
7. Shetty M.S, (2002),”Concrete Technology theory and practice”, S. Chand and Company Ltd.
Ramnagar, New Delhi.