First International Seminar on the Design & Construction of PENANG SECOND BRIDGE 15-16 November 2011 Superstructure Design of Approach Bridge RB International Formerly Benaim (Malaysia) In Association with RB Perunding Sdn Bhd By: Mr. Afshin Forouzani / Mr. David Collings The Legend Hotel Kuala Lumpur
82
Embed
No Slide · PDF fileFirst International Seminar on the Design & ... – Segmental precast & erected to form individual spans ... • Increases selfweight,
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
First International Seminar on the Design &
Construction of PENANG SECOND BRIDGE
15-16 November 2011
Superstructure Design of Approach Bridge
RB International Formerly Benaim (Malaysia)
In Association with RB Perunding Sdn Bhd
By: Mr. Afshin Forouzani / Mr. David Collings
The Legend Hotel Kuala Lumpur
• Project Description: Alignment, Design Features, Statistics, etc.
• Options Considered for Deck
• Deck Articulation & Form
• Options Considered for Prestressing
Introduction
Project Alignment
Work Packages
• Tot. Deck Area: ≈ 461,000 m2
• Tot. Length: ≈ 16 km
• Typ. Span: 55 m
• Number of Piers: 289
• Carriageway Width: 14.5 m
• Number Segments: 8,092 No.
• Design & Construction Programme: 45 months (March 2013)
• Segment Weight: 120 tons max.
Package 2: Design Features & Statistics
Options Considered - Deck
• Beam & Slab Deck:
– Cheaper in terms of superstructure costs but:
• Will require many more piers in water and similar number of piles per
pier. More pilecaps & more operations
• Will require substantial in situ concreting works (deck slab & beam
connection) → slower in terms of programme
• Will require around 4500 beams to be erected
• Will require around 9000 bearings with their associated maintenance
problems
• Will require many erection gantries and / or falsework
• Aesthetically inferior
Beam & Slab Deck
• .
Beam & Slab Deck
• .
Typical ‘T’ Beam Design
• .
Options Considered - Deck
• Steel Beams / Box Girder:
– Ruled out due to cost of steelwork & substantial maintenance
requirements
• Concrete Box Girder:
– Economical Deck
– Optimum use of substructure
– Fast to construct if precast & erected using a gantry
– Aesthetically pleasing & environmentally friendly with minimum
requirement for in situ work
– Has been used on many similar projects in the past in Malaysia &
worldwide (e.g. KL: STAR LRT, SPRINT Highway , New Pantai
Expressway, Pasir Panjang Semi-Expressway Singapore, etc.)
Concrete Box Girder
• .
Span Arrangement
• Reference made to a study in 2003 recommending spans of
around 40-60m & highlighting marginal difference in 40-60m
span range (2-3%)
• Factors taken into account:
– Number of piers in water
– Construction programme implications of using more piers
– Safety and convenience of small boats traffic navigating below deck
– Ease of segment precasting, handling (weight) and erection
– Use of flat soffit for ease of precasting & better aesthetics
– Environmental impact of number of piers in water
• Conclusion: 55m span is chosen as optimum & practical
Cost Comparisons for various spans
• Span Length Study (2003)
Possible Forms of Construction
• Span by span the only feasible option given the total length of
bridge:
– Whole beam precast in a long line mould
– Whole beam precast in segments stitched together in a long line
mould (e.g. Tagus 2nd Crossing)
– Segmental precast & erected to form individual spans
• Balanced cantilever:
– In situ: too slow & too much work over water
– Precast: less work over water but still too slow as deck erection is
much slower (around 1-1.5 weeks per span)
Typical Balanced Cantilever Construction
• .
Typical Balanced Cantilever Construction
• .
Whole Span Precasting
• Whole span precasting:
– Likely to be much faster in terms of beam erection per work front (1
span per day is easily achievable) → huge advantage.
– Elegant for a project of this size
– Fewer operations in terms of load out & beam erection.
– Fewer operations during erection & simpler logistics
– Slightly more efficient in terms of materials (5-10%) compared to
segmental construction
– Requires heavy cranage (1200T) at precast yard & foundations
– Requires a heavy & expensive marine crane for beam erection
– Has risk of single floating crane mechanical breakdown &
associated delays
Typical Whole Span Erection Using Launcher
• .
Whole Span Precasting
• Whole span precasting:
– Requires a higher level of technology & it has never been done in
Malaysia
– Highly specialists operations during erection without residual value
in terms of transfer of technology & local participation
– More expensive due to heavy cranage requirements for precasting &
erection
– Crane will require more water depth → more dredging
– Higher risk due to having 1 substantial marine crane (breakdowns,
etc.)
Whole Span Precasting
• Whole beam precast in segments stitched together in a long line
mould:
– Very similar to whole span casting except that it allows casting of
deck in segments first
– Is more versatile for decks with curved alignment
– Utilises more standard segment moulds
– Requires a few long line stitching bed only & not a whole span
mould
– Faster in terms of beam production per long line mould / bed
Example of Whole Span Beam Precasting
• .
Example of Whole Span Beam Segmental
Precasting
• .
Example of Whole Span Beam Erection
• .
Example of Whole Span Beam Erection
• .
Span by Span Segmental
• Can be erected very fast using a modest gantry supported off the
substructure
• Requires less sophisticated construction methodology & it has
been done in Malaysia before.
• Maximises local participation
• Will be less costly due to cheaper precasting & erection by
avoiding:
– Heavy overhead gantry cranes in precast yard
– Heavy foundations for gantry crane rails & casting bed
– Expensive floating crane for erection
Whole Span Segmental
• Gantry cranes & Moulds will have value after project ends as
they can be used for future projects → future asset
• It is relatively easy to achieve curved alignment
• Launching Gantry does not require any water depth → not critical
to dredging. Only require minimal dredging for segment transport
barges
• Less susceptible to delays as a result of failure and / or break
down of gantry crane as there will be 4 work fronts
Deck Articulation & Form
• Twin box girder used to keep segment weight down for maximum
economy
• Use of expansion joints minimised to reduce maintenance costs
& associated delays in replacing joints
• Initially typical 15-Span modules (825m) considered economical
& near optimum from the deck point of view
• Number of bearings minimised through the use of monolithic
connection between deck & columns over central 4 piers
• However due to seismic requirements (“no collapse” for 2500
year return period earthquake) deck articulation revised:
– 6-Span module (330m long)
– Elastomeric High Damping Rubber Bearings were adopted
Initial Deck Articulation: 15-Span Module
• .
Final Deck Articulation & Bearing layout on typical 6
span module
Deck-Bearing-Pier Interface
Deck-Bearing-Pier Interface
•Interaction & Coordination
•Seismic Risk
•Analysis & design
Alignment
Longitudinal Section
Granite bedrock
Soft mud
Risk
•Ship impact,
construction barges,
short term
•Seismic criteria 1:475
increases to 1:2500 Risk
Time
Ship impact Ship impact
Seismic
Risk
•Ship impact,
construction barges,
short term
•Seismic criteria
1:475 increases to
1:2500
Risk
Time
Ship impact Ship impact
Seismic
Seismic performance levels
475 year
return
(Serviceability)
2500 year
return
(Ultimate)
Bridge deck,
piers, piles
Minimal
Damage
No Collapse
Bearings Minimal
Damage
No Collapse
Joints Repairable
damage
No Collapse
Earthquake locations near Malaysia
Penang
Subduction Zone
Seismic Study
•Seismic assessment study by
University Teknologi Malaysia for
CCCC Highway Consultants
•Local site effect analysis report by IEM,
CEA
Time history Analysis
Seismic Study
•Seismic assessment study by University
Teknologi Malaysia for CCCC Highway
Consultants
•Local site effect analysis report by
Institute of Engineering Mechanics,
China Earthquake Administration
Effects of soft soil – higher accelerations
Design accelerations
1:475 year PGA 0.055g
at bedrock
1:2500 year PGA 0.110g
at bedrock
Design issues
Deck isolation by rubber bearings reduces forces at
pile cap level.
Previous use of rubber bearings
Bearing elastomer requirement for P2X with and
without preset
Asymmetric seismic effects
330m
Asymmetric seismic effects
Asymmetric seismic effects at joints
Use of dowels to limit movement
Stainless steel dowels
Options Considered for Prestressing
• Fully Internal:
– Relatively efficient in terms of prestressing due to high eccentricity of
cables
– Less economical in terms of deck concrete as use of ducts in webs:
• Penalises web performance and adds to web thickness & weight
• Increases selfweight, prestress & reinforcement quantities as a result
– Precasting is more complicated due to
• Interference of prestressing tendons with reinforcement
• Requirements for concrete blister anchor blocks
Options Considered for Prestressing
• Mix of Internal & External Prestress
– Most optimum in terms of:
• Prestress design (around 10%)
• Selfweight
• Reinforcement
– Still requires glue (slows down gantry erection cycle by a day) →
increase in erection programme number of gantries
– Precasting slightly more complicated due to
• Interference (clash!) of prestressing tendons with reinforcement
• Requirements for concrete blister anchor blocks
Options Considered for Prestressing
• Fully Externally Prestressed
– Considered “State of Art Technology”
– Although not so optimum in terms of prestress design (around 10%)
– Dry Joints
– HDPE ducts are:
• Very durable as they are thick, continuous & impervious, with better
overall quality
• Inspectable
• Replaceable
– Lends itself to tropical climates in which freeze/thaw cycles do not
exist, and de-icing salts are not used
– Segment erection is very fast using dry joints (1.5-2 spans a week
per gantry are possible)
Typical External Prestressing Ducts
• .
Typical External Prestressing Ducts
• .
Options Considered for Prestressing
– Leads to simple segments:
• Without internal blisters
• Fast to precast
• However concessionaire required the use of epoxy in segment
joints for additional safety
• Finally a mixture of internal & external prestressing was used
• Segments were still kept relatively simple:
– no blisters except at deviators
– relatively straight internal tendons
Typical Spans – Segment Arrangement
• .
Method of Deck Erection
• Using overhead launching gantry
• Segments delivered below on barges
• Segments to be assembled using temporary prestress (glued