Top Banner
19 BURRUP NITRATES PTY LTD Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 5 Project Description This chapter provides a detailed description of the various elements of the Technical Ammonium Nitrate Production Facility (TANPF) Project to assist in evaluating the associated potential environmental impacts. The TANPF Project description is based on Burrup Nitrates Pty Ltd (BNPL)’s project concept study. The Engineering, Procurement and Construction (EPC) Contractor has not yet been determined, and as such, certain details of engineering, design and construction are yet to be finalised. Despite this, the design is sufficiently developed to allow for the assessment of potential environmental impacts associated with the TANPF Project. 5.1 Project Overview BNPL is proposing to construct a TANPF with a production capacity of (circa) 350,000 TPA or 915 MTPD of technical ammonium nitrate (TAN). TAN will be delivered principally to mining customers in the Pilbara, to help make up the basic component of ANFO (ammonium nitrate‐fuel oil) used for explosives. The TANPF will be located at Site D in the King Bay/Hearson Cove Industrial Precinct on the Burrup Peninsula, approximately 13 km northwest of Karratha (the Site), see Figure 1.1 and Figure 4.2. This Precinct lies within the greater Burrup Industrial Estate (BIE), where the WA Government has allocated about 1,400 Ha of strategic heavy industrial land to prospective tenants. The Site is approximately 79 Ha in size and is located adjacent to the existing Burrup Fertilisers Pty Ltd (BFPL) ammonia plant, with site access from Village Road, Burrup Peninsula. The choice of location for the proposed TANPF enables significant sharing of services and utilities between BFPL and BNPL. This will reduce environmental impacts by allowing a smaller project footprint (eg. independent ammonia storage, transport and supply) and permitting the incorporation of technical and design efficiencies. The main feedstock for the proposed TANPF is liquid ammonia, which will be transferred via pipeline from the BFPL plant. The proposed TANPF will require about 35 Ha of the 79 Ha Site. The TANPF will contain three major process units, each producing a separate product in the manufacturing process: a Nitric Acid (NA) plant to convert ammonia and atmospheric air into NA; an Ammonium Nitrate (AN) Solution plant to convert ammonia and NA into AN solution; and a TAN plant to convert AN solution into TAN prills (final product). The key characteristics of the TANPF Project are outlined in Table 5.1. The boundary locations of the Site are presented in Table 5.2 and Table 5.3. Table 5.1 Key Characteristics of the TANPF Criteria Key Characteristics of the TANPF Project Purpose To produce TAN from ammonia using advanced production technology for sale to mostly local markets Project Life 20+ years Construction Period Approximately 30 months Project Value Approximately US $600 million TANPF Capacity 350,000 TPA Area of Project Lease 79 Ha (Site D) Area of Disturbance 35 Ha Plant Facilities Main Process Units Nitric Acid (NA) Plant Ammonium Nitrate (AN) Solution Plant Technical Ammonium Nitrate (TAN) Prilling Plant Storage, Loading and Transport Facilities Liquid Ammonia pipeline between BFPL and BNPL plants Bagged TAN storage building Bulk TAN storage building TAN Bagging facility Truck bulk loading system Nitric acid buffer storage Ammonium nitrate solution storage Other Facilities Sea Water Cooling Tower Closed Loop Water Cooling System Wastewater handling facility Electrical Power distribution system Instrument and plant air system Control room Steam grid Administration, maintenance and warehouse unit Fire system Plant Operations The TANPF is designed to operate 24/7, with an average plant availability of 90% (328.5 days per year) excluding any downtime due to market reasons or other reasons not related to operation. Shutdown Time An annual turnaround of about one week is foreseen. Additional downtime may be caused by a combination of planned stops (e.g. cleaning) and unplanned stops (eg. process, cyclone etc.) Product Storage Bagged TAN storage building with a capacity of 1,800 MT Bulk TAN storage building with a capacity of 12,000 MT Nitric acid buffer storage, two tanks with a total capacity of 3,000 m 3 located in a bunded area with acid resistant surface Ammonium nitrate solution storage (8092%), 1 tank with a capacity of 500 MT Potable Water 2m 3 /hr from Water Corporation Seawater 456 m 3 /hr from Water Corporation
24

Nitrat de Amonio

Jan 18, 2016

Download

Documents

Rosalyn Vargas
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Nitrat de Amonio

 

19 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

5 Project Description   

This  chapter  provides  a  detailed  description  of  the  various elements  of  the  Technical  Ammonium  Nitrate  Production Facility  (TANPF)  Project  to  assist  in  evaluating  the  associated potential  environmental  impacts.  The  TANPF  Project description is based on Burrup Nitrates Pty Ltd (BNPL)’s project concept study. The Engineering, Procurement and Construction (EPC)  Contractor  has  not  yet  been  determined,  and  as  such, certain details of engineering, design and construction are yet to be finalised. Despite this, the design is sufficiently developed to allow  for  the  assessment  of  potential  environmental  impacts associated with the TANPF Project. 

5.1 Project Overview 

BNPL  is  proposing  to  construct  a  TANPF  with  a  production capacity  of  (circa)  350,000  TPA  or  915  MTPD  of  technical ammonium nitrate  (TAN).  TAN will  be  delivered principally  to mining  customers  in  the  Pilbara,  to  help  make  up  the  basic component  of  ANFO  (ammonium  nitrate‐fuel  oil)  used  for explosives.   The  TANPF will  be  located  at  Site  D  in  the  King  Bay/Hearson Cove Industrial Precinct on the Burrup Peninsula, approximately 13 km  northwest  of  Karratha  (the  Site),  see  Figure 1.1  and Figure 4.2.  This  Precinct  lies  within  the  greater  Burrup Industrial Estate (BIE), where the WA Government has allocated about 1,400 Ha of strategic heavy industrial land to prospective tenants.   The Site is approximately 79 Ha in size and is located adjacent to the  existing  Burrup  Fertilisers  Pty  Ltd  (BFPL)  ammonia  plant, with  site  access  from  Village  Road,  Burrup  Peninsula.    The choice  of  location  for  the  proposed  TANPF  enables  significant sharing  of  services  and utilities  between BFPL  and BNPL. This will reduce environmental impacts by allowing a smaller project footprint  (eg.  independent  ammonia  storage,  transport  and supply)  and  permitting  the  incorporation  of  technical  and design efficiencies. The main feedstock for the proposed TANPF is  liquid  ammonia, which will  be  transferred  via  pipeline  from the BFPL plant.  The proposed TANPF will require about 35 Ha of the 79 Ha Site. The  TANPF  will  contain  three  major  process  units,  each producing a separate product in the manufacturing process: 

• a  Nitric  Acid  (NA)  plant  to  convert  ammonia  and atmospheric air into NA; 

• an  Ammonium  Nitrate  (AN)  Solution  plant  to  convert ammonia and NA into AN solution; and 

• a  TAN  plant  to  convert  AN  solution  into  TAN  prills  (final product). 

The  key  characteristics  of  the  TANPF  Project  are  outlined  in Table 5.1.  The  boundary  locations  of  the  Site  are  presented  in Table 5.2 and Table 5.3.  Table 5.1  Key Characteristics of the TANPF  

Criteria  Key Characteristics of the TANPF 

Project Purpose  To produce TAN from ammonia using advanced production technology for sale to mostly local markets 

Project Life  20+ years 

Construction Period  Approximately 30 months 

Project Value  Approximately US $600 million 

TANPF Capacity  350,000 TPA 

Area of Project Lease  79 Ha (Site D) 

Area of Disturbance  35 Ha 

Plant Facilities  Main Process Units 

• Nitric Acid (NA) Plant  • Ammonium Nitrate (AN) Solution Plant  • Technical Ammonium Nitrate (TAN) Prilling 

Plant  

  Storage, Loading and Transport Facilities 

• Liquid Ammonia pipeline between BFPL and BNPL plants 

• Bagged TAN storage building  • Bulk TAN storage building  • TAN Bagging facility  • Truck bulk loading system • Nitric acid buffer storage • Ammonium nitrate solution storage 

  Other Facilities 

• Sea Water Cooling Tower • Closed Loop Water Cooling System • Wastewater handling facility  • Electrical Power distribution system • Instrument and plant air system • Control room • Steam grid • Administration, maintenance and warehouse 

unit • Fire system 

Plant Operations  The TANPF is designed to operate 24/7, with an average plant availability of 90% (328.5 days per year) excluding any downtime due to market reasons or other reasons not related to operation.  

Shutdown Time  An annual turnaround of about one week is foreseen. Additional downtime may be caused by a combination of planned stops (e.g. cleaning) and unplanned stops (eg. process, cyclone etc.) 

Product Storage  Bagged TAN storage building with a capacity of 1,800 MT 

Bulk TAN storage building with a capacity of 12,000 MT 

Nitric acid buffer storage, two tanks with a total capacity of 3,000 m3 located in a bunded area with acid resistant surface 

Ammonium nitrate solution storage (80‐92%), 1 tank with a capacity of 500 MT 

Potable Water  2 m3/hr from Water Corporation 

Seawater  456 m3/hr from Water Corporation 

Page 2: Nitrat de Amonio

 

20 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Criteria  Key Characteristics of the TANPF 

Power Requirement  8.5 MW will be required. Of this, about 5 MW will be imported from BFPL. 

The remaining power will be generated by excess steam from the operation of the nitric acid plant (about 3.5 MW). 

Emergency Power  In case of a power outage emergency power will be provided by diesel generators 

Energy Input  5 MW from BFPL  

Discharge Pipeline  Connecting to the Water Corporation facility 

Ammonia Pipeline  710 m from BFPL Ammonia plant (storage tanks) to the TANPF (within BNPL and BFPL leases) 

Catalysts  Platinum (Pt)/ Rhodium (Rh) gauzes for the ammonia combustion 

Recovery system for the Pt/Rh gauzes 

N2O catalyst 

NOx catalyst 

Expected Maximum Emissions under Normal Operations: 

Daily Load (kg/day) 

Per tonne TAN (kg/MT  TAN) 

Annual Load (kg/year) 

NOx  370  0.40  28,318 

N2O  466  0.51  161,563 

CO2 (produced)  1,279  1.40  515,670 

CO  131  0.15  41,987 

SO2  trace  ‐  trace 

VOC (CH4)  51  0.06  17,697 

NH3  208  0.22  68,339 

AN Dust (Particulate matter)   130  0.14  42,705 

Wastewater   11,661 kg/h Process Condensate (non‐contaminated) to sea water blow down. Contaminated water (from cleaning equipment etc) will be sent directly to the contaminated surface water pond. 

The non‐contaminated water will be sent to Water Corporation via a pipeline (approximately 3,100 ML/year).  

The contaminated water is evaporated in a designated pond which is a closed system (eg. no discharge).  Accumulation of unspecified volumes of sludge from the contaminated surface water pond will be collected for disposal as required (estimated once every two years). 

Solid Waste  Off spec coating removal barrels (expected 120 kg/day max) 

Workforce numbers (direct)  Construction: Average 400, peak 650 Operation: 60 (full time) 

5.2 Project Location 

The TANPF Project will be located at Site D (the Site) within the BIE, approximately 13 km northwest of Karratha (Figure 1.1 and Figure 4.2).  Geographic coordinates of the proposed Site and the proposed  area  of  disturbance  are  provided  in  Table 5.2  and Table 5.3 respectively.  Table 5.2  Site D Boundary Coordinates 

Latitude  Longitude 

degrees  minutes  seconds  degrees  minutes  seconds 

20  37  17.815  116  47  8.044 

20  37  20.638  116  47  36.463 

20  37  57.086  116  47  23.843 

20  38  2.246  116  47  7.988 

 

Northings  Eastings 

477660.256 mE  7719713.884 mN 

478479.474 mE  7719628.771 mN 

478116.860 mE  7718500.870 mN 

477660.230 mE  7718348.890 mN 

 Table 5.3  TANPF Boundary Coordinates (Area of 

Disturbance) 

Latitude  Longitude 

degrees  minutes  seconds  degrees  minutes  seconds 

‐20  37  17.815  116  47  8.044 

‐20  37  20.638  116  47  36.463 

‐20  37  32.2206  116  47  32.445 

‐20  37  35.0904  116  47  17.0586 

‐20.626406  37  35.061  116  47  8.0478 

 Northings  Eastings 

477660.256 mE  7719713.884 mN 

478479.474 mE  7719628.771 mN 

478366.280 mE  7719271.240 mN 

477924.010 mE  7719182.250 mN 

477660.090 mE  7719183.670 mN 

5.2.1 Land Ownership and Tenures 

Lots  within  BIE  are  available  for  lease  to  strategic  heavy industry  through  the  WA  Department  of  State  Development (DSD),  which  allocate  sites  through  a  lease  arrangement  from LandCorp (WA's land and property development agency).   The Site has been allocated to BNPL, subject to the approval of a risk report to be submitted to the WA Department of Mines and Petroleum (DMP) in the coming months. 

5.2.2 Zoning 

The  Site  is  zoned  ‘Strategic  Industrial’  under  the  Roebourne Shire Town Planning Scheme (TPS) No.8. As outlined within the TPS  the  purpose  of  the  ‘Strategic  Industry’  zone  is  to accommodate  such  industries  as  the  TANPF.  In  considering applications  for  planning  approval  in  the  strategic  industry zone,  the  Shire  of  Roebourne  Council  shall  ensure  that  the industry (Shire of Roebourne, 2008): 

a) ‘Optimises  the  effectiveness  of  the  zone  as  a  strategic industrial area and…. creates a symbiosis with other industries or includes resource processing industry; 

b) ‘is significant to the regional and/or state economies; or 

c) ‘Provides  goods  and  services  which  directly  support  or complement industries described in a) and b) above; and 

d) ‘Minimises or offsets impacts on local infrastructure, economic and community development.’ 

 As noted in Section 2.2.1 planning approval will be sought from the  Shire  of  Roebourne  Council  following  completion  of environmental approvals. 

Page 3: Nitrat de Amonio

 

21 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

5.2.3 Land Required 

Approximately  35 Ha  of  land  within  the  project  lease  will  be disturbed  as  part  of  the  TANPF  Project  (see Figure 4.2).  There will  be  no  additional  temporary  land  requirements  for  the construction phase, as construction laydown areas will be used throughout  the  operational  phase.  This  land  is  required  to accommodate: 

• Processing plants (NA, AN Solution and TAN production) 

• Utilities area 

• Storages for bagged TAN, bulk TAN, AN solution, nitric acid and chemical store (general process chemicals) 

• Truck bulk loading system/Bagging unit  

• Off –spec treatment unit 

• Other facilities, including: − Sea Water Cooling Tower − Closed Loop Water Cooling System − Clean  surface  water  pond  (discharge  to  Water 

Corporation) − Contaminated surface water pond (evaporation pond) − Desalinated/ fire water storage − Control room / Office / Administration − Miscellaneous (internal roads, etc.) 

• Lay down areas and access roads.   Based  on  the  land  requirements  of  the  TANPF,  laydown  areas and  internal  roads  it  is  planned  that  earthworks  will  be undertaken as described in Table 5.4.  Table 5.4  Earthworks and Associated Cut and Fill 

Type of Earthworks  Volume of Cut/Fill (approximate) 

Growth removal  350,000 m2 

Strip topsoil & stockpile  19,500 m3 

Cut soil  61,900 m3 

Load soil/haul/place  92,500 m3 

Imported engineered fill  is not foreseen 

5.2.4 Adjacent Land Uses 

Adjacent  land  uses  for  the  TANPF  Project  are  shown  in Figure 5.1  and  include  industrial  facilities  present  to  the  south and  west  of  the  Site  while  the  proposed  Burrup  Peninsula Conservation Reserve occurs to the north and south of the Site, with Hearson Cove to the east.   The Burrup Peninsula has developed as a major  industrial and port  site  in  Australia.  Buildings,  infrastructure  and  sensitive receptors  within  close  proximity  to  the  Site  are  listed  in Table 5.5.  

Table 5.5  List of Facilities Adjacent to the Proposed TANPF 

Facility / Sensitive Receptors  Approximate Distance from TANPF (m) 

North West Shelf Venture  3,200 m 

Woodside LNG Pluto Development  2,200 m 

Dampier Port Authority  4,000 m 

King Bay Supply Base  3,000 m 

Schlumberger Supply Base  2,100 m 

BFPL  Adjacent, ammonia tanks ~ 600 m 

Hearson Cove (visitors)  900 – 1,300 m 

Deep Gorge  1,300 m 

Nearest Rock Art Site  Approximately 400 m 

Nearest Rock Art Site within National Heritage Boundary 

Approximately 400 m 

 The  north‐south Burrup Road  service  corridor  (see Figure 5.1) extends to the North West Shelf Venture LNG plant in the north and  incorporates  a  power  transmission  network,  a  domestic water  pipeline  and  two  high  pressure  underground  gas pipelines,  the  Dampier  to  Bunbury  Natural  Gas  Pipeline (DBNGP).   Currently the BFPL and the Water Corporation multi‐user (both part  of  the  same plot)  facilities  exist within King Bay/Hearson Cove  Industrial  Precinct,  with  the  potential  inclusion  of  Dyno Nobel and Woodside Energy yet to be confirmed.  No buildings or infrastructure currently exists within the Site. 

5.3 Project Schedule 

The  TANPF  is  scheduled  to  begin  operations  by  last  quarter 2013.  This  schedule  is  based  around  the  following  key milestones in Table 5.6.  Table 5.6  Project Development Schedule 

Project Phase  Schedule Timing 

Submission of Environmental Scoping Document (ESD) to OEPA  July 2009 

EPA SU and DEWHA review ESD   July‐September 2009 

BNPL submits revised ESD   September 2009 

OEPA approves final ESD   October 2009 

Submission of PER to EPA SU (and DEWHA)  October 2009 

EPA SU comments on PER  October‐December 2009 

BNPL revises PER document  December 2009 

Approval of PER release for public review  December 2009 

Public review period of PER (8 weeks)  January‐February 2010 

BNPL prepares submission summary and response   March‐April 2010 

EPA SU reviews response to submissions  April‐May 2010 

OEPA report and recommendations published  May‐July 2010 

Appeal period on OEPA’s report and recommendations  July 2010 

State Minister decision   August 2010 

Commonwealth Minister decision  August 2010 

Construction   Last quarter 2010 

Commissioning   June 2013 

Operation  Last quarter 2013 

Page 4: Nitrat de Amonio

Environmental Resources Management Australia Pty Ltd6th Floor, 172 St Georges Tce, Perth, WA, 6000Telephone +61 9 321 5200

Figure 5.1Adjacent Land Uses to theProposed TANPF

Client:Project:Drawing No:Date:

Drawn by:

Source:Scale:

Burrup Nitrates Pty LtdPER0086269p_GIS04_PER21/12/2009

DD

Base information LANDGATE1:40 000

Suffix No:Drawing size:

Reviewed by:

R1A4

BC

[N

B U R R U PP E N I N S U L A

King Bay

Withnell Bay

CowieCove

Nickol Bay

ProposedDevelopment

Site

0 380 760 1,140m

Legend

Site D Boundary

National Heritage Listed Place (Site ID 105727)

HEARSON COVE RD

VILLAGE RD

BURRUP

RD

North WestShelf Venture

PlutoOperations

DampierPort Authority

SchlumbergerSupply Base

PlutoSupply Base

Hearson Cove

BFPLAmmonia

Plant

Beach & Picnic Area

DeepGorge

Page 5: Nitrat de Amonio

 

23 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

5.4 Characteristics and Properties of the TANPF’s Main Raw Materials and Product 

5.4.1 Nitric Acid  

Nitric acid  is a colourless, yellow, or red,  fuming liquid with an acrid  odour.  The  acid  is  often  used  in  an  aqueous  solution. Fuming  nitric  acid  is  concentrated  nitric  acid  that  contains dissolved nitrogen dioxide.  Table 5.7  Properties of Nitric Acid 

Nitric Acid (HNO3) 

Chemical Abstracts Service (CAS) Number  7697‐37‐2 

Registry of Toxic Effects of Chemical Substances (RTECS) Number 

QU5775000 

Immediately Dangerous to Life or Health (IDLH) 

25 ppm 

Exposure Limits  National Institute for Occupational Safety and Health (NIOSH) Recommended Exposure Limit (REL): Time weighted average (TWA) 2 ppm (5 mg/m3) 

Occupation Safety and Health Administration (OSHA) permissible exposure limits (PEL): TWA 2 ppm (5 mg/m3) 

National Pollution Inventory (NPI) Ranking  43 of 90 

Molar mass  63.012 g/mol 

Physical Description  Colourless, yellow, or red, fuming liquid with an acrid odour 

Freezing Point  At 60% conc.:  –22oC 

Boiling Point  At 60% conc.:  120oC 

Specific Gravity  At 60% conc. and at 25oC:  1,360 kg/m3 

Solubility in water  completely miscible 

Flash point  Non‐combustible Liquid, but increases the flammability of combustible materials 

Dangerous Substances Directive   Oxidant, Corrosive 

5.4.2 Ammonia 

Anhydrous  ammonia  is  a  colourless  non‐flammable  liquefied gas. Its vapour is lighter than air [(vapour density of 0.6) air = 1] and  has  the  same  pungent  odour  as  household  ammonia. Although ammonia vapour  is  lighter  than air,  vapours  from an accidental leak are likely to hug the ground appearing as a white cloud.  Chemically  ammonia  is  82%  nitrogen  (N)  and  18% hydrogen (H).  

Table 5.8  Properties of Ammonia 

Ammonia (NH3) 

CAS Number  7664‐41‐7 

RTECS Number  BO0875000 

IDLH  300 ppm 

Exposure Limits  NIOSH REL: TWA 25 ppm (18 mg/m3) 

OSHA PEL: TWA 50 ppm (35 mg/m3) 

National Pollution Inventory (NPI) Ranking  45 of 90 

Molar mass  17.031 g/mol 

Physical Description  Colourless gas with strong pungent odour. It is easily liquefied under pressure 

Freezing Point  ‐77oC 

Boiling Point  ‐33oC 

Solubility in water  1176 g/100 mL (0°C) 

702 g/100 mL (20°C) 

88 g/100 mL (100°C) 

Flash point  Non‐combustible as a Gas 

Dangerous Substances Directive   Toxic, Corrosive, Dangerous for the environment (if released uncontrolled) 

5.4.3 Technical Ammonium Nitrate 

The chemical compound ammonium nitrate (NH4NO3) is a salt of ammonia  and  nitric  acid.  Ammonium  nitrate  (AN)  is  a colourless,  crystalline  substance  and  has  a  melting  point  of 169°C and decomposes above 210°C. It is highly soluble in water and  soluble  in  alcohol  and  liquid  ammonia.  AN  is  not  in  itself combustible  but,  as  it  is  an  oxidising  agent  it  can  assist  other materials to burn, even if air is excluded.  AN  can  be  manufactured  into  several  different  grades  to  suit different  purposes.  Fertiliser‐grade  AN  is  manufactured  in  a solid  form  (granules/  prills),  with  low  porosity,  in  order  to achieve  more  stability  and  less  sensitivity  to  detonation. Technical  grade AN, or TAN,  is developed  into prills which are made  to  be  porous  for  better  absorption  of  fuel  and  higher reactivity when mixed with fuel oil and used as an explosive, see Figure 5.2.  Figure 5.2  Photo of TAN Prills 

Scale (mm)

0 4 8

Scale (mm)

0 4 8

Scale (mm)

0 4 8

 

Page 6: Nitrat de Amonio

 

24 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

TAN  will  be  the  main  product  from  the  TANPF  Project.  TAN prills  will  be  produced  with  specifications  similar  to  that  in Table 5.9.  The TAN prills will be used in the local market for use in ANFO (ammonium nitrate‐fuel oil) explosives.  Table 5.9  Specifications of TAN Prills (typical) 

Technical Ammonium Nitrate Prills (TAN) 

CAS Number  6484‐52‐2 

RTECS Number  BR9050000 

Molar mass  80.043 g/mol 

Physical Description  White Solid 

PH  5 

Melting Point  169°C 

Boiling Point  approx. 210°C decomposed 

Solubility in water  118 g/100 ml (0°C) 

150 g/100 ml (20°C) 

297 g/100 ml (40°C) 

410 g/100 ml (60°C) 

576 g/100 ml (80°C) 

1024 g/100 ml (100°C) 

Shock/Friction Sensitivity  Very low 

Nitrogen Content  34.5% w 

Bulk Density  0.70 – 0.83 kg/L 

Free Moisture  0.03‐0.16%w 

Oil Absorption  8%‐14%w 

 AN is classified as a Class 5.1 oxidising agent and is designated in  the  III  packaging  group  (minor  danger)  in  the  Australian Dangerous Group code.  There  are  three  main  hazards  associated  with  ammonium nitrate: 

• fire due to its oxidising nature; 

• decomposition; and  

• explosion resulting from rapid deflagration, or detonation.  The most  important  parameters  that  influence  the  hazard  and increase sensitivity to explosion are: 

• particle size; 

• particle density/bulk density/porosity; 

• contamination with  organic  substances,  certain metals  and chlorides; and 

• confinement. 

Fire 

AN itself does not burn. As an oxidiser, however, it can support combustion  and  intensify  a  fire  even  in  the  absence  of  air,  but only as long as fuel or combustible matter is also present. Gases are  then  emitted,  especially  nitrogen  oxides.  In  addition,  AN melts  at  169°C,  when  pure.  The  melting  absorbs  some  of  the energy  received  and  the melted  product  often  flows  away  and escapes the external energy source. 

Decomposition 

Pure  AN  can  undergo  thermal  decomposition  if  it  receives enough  energy.  Gases  are  then  emitted,  especially  nitrogen oxides and ammonia, both toxic. Heating in confinement is a risk when ventilation is inadequate. The rapid decomposition of the AN leads to a considerable pressure build‐up that can eventually cause an explosion. With proper ventilation, the decomposition stops as soon as the energy flow stops. The decomposition rate is  not  dangerously  high  at  moderate  temperatures,  and  the overall  thermal  effect  is  not  significant  since  the  exothermic reactions  are  accompanied  by  endothermic  disassociation, which  can  in  turn give  rise  to a  steady  state  reaction provided the  gases  produced  can  escape  freely  and  the  system  is adiabatic.  The  decomposition  is  catalysed  by  a  number  of substances  such  as  chlorides,  which  can  affect  the  above balance. 

Explosion 

AN can produce an explosion by one of three mechanisms:  

• heating in confinement; 

• run‐away reaction; and  

• detonation.   The effects of heating of AN are described above.  A runaway reaction is achieved when the heat generated by the reaction exceeds the heat loss by a significantly high margin. For pure  AN,  these  circumstances  are  difficult  to  achieve  given  its low  decomposition  rate  and  endothermic  effect  when unconfined.  Pure AN is not shock or friction sensitive and cannot be induced to detonate under normal storage conditions; detonation, which are  characterised  by  a  supersonic  pressure  wave  moving through  the  material,  can  occur  only  if  the  dimensions  of  the material are greater than some particular value known as “The critical  charge  diameter”.  For  solid  AN  this  diameter  is  more than 1 m and decreases with decreasing bulk density of the solid AN. The corresponding diameter for decomposing molten AN is about 10 cm.   Uncontaminated and unconfined AN is very difficult to detonate. Neither flame, nor spark nor friction can cause a detonation.   Deflagration  is  not  constrained  by  dimensions  and  is  said  to occur  when  a  subsonic  combustion  generated  pressure  wave moves through the material.   The consensus of opinion on AN hazards is that, in the event of a large fire at an AN store, a pool of liquid ammonium nitrate will be  formed at  the  side of  the  stack  that  is nearest  to  the  fire.  If this pool is struck by a high speed missile (eg. something falling or part of a drum that has exploded) then a local explosion may occur sending a shock wave into the main AN stack that has not melted and that could lead to deflagration.  

Page 7: Nitrat de Amonio

 

25 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Stacks  of  AN  in  the  open  are  assumed  to  be  incapable  of exploding  because  the  probability  of  an  explosion  trigger  such as a girder falling into a molten pool is very low. 

5.5 Design Considerations 

5.5.1 HES Design Standards 

The  Health  Environment  and  Safety  (HES)  premises  for  the TANPF  Project  provide  a minimum  set  of  standards  to  ensure that  identified  risks  to  people,  assets,  environment  and reputation  have  been  addressed  in  the  project  design.  The design mitigations together with the management measures will ensure they are acceptable to As Low As Reasonably Practicable (ALARP) levels.  The  HES  requirements  of  the  TANPF  Project  start  with compliance  with  the  applicable  Commonwealth  and  WA legislation  and  relevant  international  agreements  to  which Australia  is  a  party,  as  specified  in  Annex C.  In  addition,  Yara Policies,  Standards,  Procedures  and  Guidelines  have  also  been applied, with the stricter of the standards always applying.  The design of  the TANPF Project adheres to sound engineering practice and is based on the most recent standards and/or codes as summarised below: 

• Australian regulatory requirements. 

• Applicable International Codes, Standards and Guidelines. 

• Applicable  Yara  standards  and  guidelines  for  this  kind  of facility. 

• Applicable BFPL standards. 

5.5.2 Emissions Reduction 

The design of the TANPF incorporates a number of measures to reduce its emissions and carbon footprint.  The TANPF will use BAT to minimise emissions  to ALARP. The majority of emissions that will occur from the TANPF will come from the main process units: 

• Nitric Acid (NA) Plant; 

• Ammonium Nitrate (AN) Solution Plant; and 

• Technical Ammonium Nitrate (TAN) Prilling Plant.  The  following Best Available Technology  (BAT) will be used  to help reduce air emissions from the TANPF.   

Nitric Acid Plant 

The NA plant will use the dual pressure process, which ensures optimal  conditions  in  the  combustion  as  well  as  in  the absorption  stages  to  accommodate  stringent  environmental pollution  control  requirements.  In  addition,  the  NA  plant  will apply BAT for further abatement of N2O and NOx.   In  the NA plant  some N2O will  be  formed  in  the burner where ammonia  is  oxidised  by  burning with  air  in  the  presence  of  a catalyst.  The  formation  of  N2O  is  minimised  by  proper  raw material  filtering,  gas  mixing  and  distribution  to  the  catalytic gauzes  in  the  ammonia  burner  (the  optimal  conditions  to minimise  N2O  formation  are  to  be  considered  in  the  final process  design  phase).  N2O  emissions  also  follow  the  process stream  and  ends  up  in  the  tail  gas  (waste  gas  emitted  to  the atmosphere). With N2O  already  being  reduced  through  the NA process,  N2O  in  the  tail  gas  is  further  reduced  by  catalytic reduction.  This  technology  is  to  be  finalised  as  part  of  the process design. While some final design is still required to take place, BNPL will ensure that the emissions of N2O in the tail gas (after catalytic abatement) vented to the atmosphere will be less than  100 ppm  (as  a  minimum),  which  corresponds  to  a maximum emission of 6.1 t/h of CO2e and an overall  reduction of CO2e emissions of approximately 90%.  The catalytic process for N2O reduction requires the use of some natural  gas,  with  the  maximum  consumption  to  be  50 Nm3/h. This  use  of  gas  will  result  in  CO2  formation,  with  a maximum emission  of  0.064 t/h.  Some  slippage  of  methane  will  occur which will  correspond  to  a maximum  value  of  0.045 t/h  CO2e. These  additional  emissions  from  the  use  of  a  N2O  reduction catalyst  are  required  as  they  result  in  a  far  greater  CO2e reduction  (approximately  90%  reduction)  than  operations without a N2O reduction catalyst.  The  NA  plant  will  have  no  boiler  installed  for  continuous production  of  steam  or  electricity  as  the  process  itself  is exothermic and generates its own requirements for steam which is used to generate electricity. In addition BFPL will provide the utilities  where  required  for  start  up  steam  and  energy. Consequently,  there will be no Scope 1 CO2 emissions  from the NA  plant  resulting  from  burning  of  fossil  fuels  except  as mentioned  above  for N2O  abatement where  a  small  amount  of natural gas is used via BFPL’s facility. 

Ammonium Nitrate Solution Plant 

The  AN  solution  plant  will  use  a  Neutra  (vacuum)  synthesis process to provide lower reactor temperatures that will result in increased  safety,  reduced  level  of  aerosols  and  very  clean condensates (levels around 15 ppm NA and 15 ppm NH3).   Furthermore,  all  vapours  produced  in  the  process  will  be condensed  and  the  condensate  reused  to  avoid  unnecessary emissions to the atmosphere. 

Page 8: Nitrat de Amonio

 

26 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Technical Ammonium Nitrate Prilling Plant 

The  TAN  prilling  plant  will  also  use  BAT  to  minimise atmospheric emissions. The prill tower of the TAN prilling plant will  be  designed  with  a  recycle  air  closed  loop  air  recycling system  to  minimise  the  total  amount  of  air  rejected  to  the atmosphere  (less  than  1/3  compared  to  open  loop  prilling).  This gives one single emission point expected to be well below European  Fertilizer  Manufacturers  Association  (EFMA)  Best Available Techniques 2000  levels.  In addition,  all  exhaust  from the  prill  tower  will  be  cleaned  in  two  stages  using  efficient abatement systems.  

5.5.3 Safety and Security 

As  well  as  environmental  aspects,  safety  and  security considerations  have  significantly  influenced  the  design  of  the TANPF.  Yara  has  developed  Technical  and  Operational Standards  (TOPS)  that  will  be  implemented  in  the  design  and engineering as well as for the operation and maintenance of the TANPF. Yara’s  TOPS  have  been  developed  following  over  40  years  of operational  experience  of  TAN  plants  to  provide  safe  and reliable design  and operation of  equipment,  individual process units  and  plants.  The  standards  are  divided  into  different categories: 

1) Standards applicable to all Yara/BNPL operations 

2) Maintenance 

3) Nitric acid 

4) Ammonium nitrate 

5) Industrial/CO2 

6) Transport, loading/unloading  TOPS  does  not  replace  the  TANPF  Project’s  compliance  with national  and  international  codes  and  standards,  but  are supplementary  and provide  specific  know how and experience acquired by Yara from designing and operating similar facilities for  extended  periods.  Statutory  regulations  shall  always  be complied  with.  In  the  case  of  a  difference  between  statutory requirements and TOPS, the more stringent shall apply.  Generally,  all  raw materials  and  chemicals  used  in  the  TANPF will  be  controlled  according  to  TOPS  to  ensure  correct  quality and to avoid contamination of areas that may jeopardise safety and health. In addition, a number of analyses (both on‐line and regular spot checks) will be performed during operation of  the TANPF  to  ensure  correct  and  safe  operating  conditions,  to assess  the  possible  presence  of  contaminants  and  to maintain product  quality.  Critical  operating  parameters  in  the  various process units that make up the TANPF will also have automatic controls with trip functions to shut down the process safely if a set safety limit is exceeded. Cameras for surveillance of the main process  plants  and  product  storage  areas will  be  installed  and monitored. 

TANPF Main Process Units 

The  dual  pressure  nitric  acid process  has  been  selected  for  its reliability,  long  on‐stream  time  and  efficiency.  The  turbo‐machinery,  as  well  as  other  key  equipment,  will  be  designed with  emphasis  on  reliability  and  safety.  In  compliance  with stringent  internal  pollution  abatement  requirements  an N2O/NOx catalyst based abatement system will also be installed (as discussed in Section 5.5.2).  The AN solution plant technology selected represents a reliable process  characterised  by  using  forced  circulation  over  the reactor to avoid local overheating and to allow operation at low temperature.  The  pH  of  all  product  will  be  automatically controlled  at  several  points  to  ensure  safe  conditions  and,  if required,  ammonia  would  be  added  to  maintain  correct conditions. The quality of the acid fed to the neutraliser, as well as  the AN solution produced, will  also be checked on a  regular basis to ensure possible contaminants do not exceed acceptable limits.   The  TAN  prilling  plant will  use  an  organic  internal  additive  to achieve optimal product characteristics. For safety reasons very low levels of organic material  in the TAN solution/product will be allowed. A number of control mechanisms (on‐line as well as manual) will  be  implemented  to  ensure  that organic  limits  are not exceeded.   

TAN Storage 

TAN product will be stored on site as bulk and bagged product. More  details  on  the  storage  of  TAN  product  is  described  in Section 5.6.5 below.  As part of the evaluation of risk associated with storing of TAN at  the  Site,  internationally  renowned  Dutch  research  institute, TNO,  a  specialist  in  assessing  risks  of  these  types  of  storages, was  consulted.  Based  on  simulations  by  TNO,  it  has  been concluded  that  for  two  separated  bulk  piles  of  TAN  the occurrence  of  a  sympathetic  detonation  is  extremely  unlikely, even  for  separation  distances  smaller  than  1  metre  (m).  A consequence  of  this  is  that  the  bulk  product  will  be  stored  in several  smaller  piles,  and  not  one  large  pile,  with  a  clear separation  distance  (about  1 m).  Additionally,  no  solid  objects will  be  located  between  the  piles  since  such  objects  could  be strongly  accelerated  by  a  blast  wave  and  could  subsequently impact with other piles of TAN and generate very high pressure in the acceptor resulting in a potential detonation.   For bagged TAN product storage similar simulations have been performed  by  TNO  to  calculate  the  safe  distance  between product  stacks  as  well  as  configuration  of  the  stacks.  The optimal bag configuration (bags of 750 kg to 1250 kg) is a bulk‐wise  stacking  (eg.  12+9+6),  with  each  consecutive  layer  is 1.5 bags  staggered  towards  the  centre  (giving  a  pyramidal shape),  see  Figure 5.3.  With  this  configuration  a  separation distance  of  7  –  9 m  (depending  on  product  grade)  will  be sufficient  to  prevent  a  sympathetic  detonation  between  two stacks.  The  big  bags  will  therefore  be  stacked  in  a  bulk‐wise 

Page 9: Nitrat de Amonio

 

27 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

configuration with 3  layers and about 300  tons or  less  in each stack and with a distance of 7 – 9 m between the stacks.   Floor marking will ensure that safe stacking zones are maintained.  Figure 5.3  Optimal TAN Bag Stacking Configurations 

 

 

Plant Operation 

The  process  safety  and  all  relevant  procedures  of  the  TANPF Project  will  be  set  out  in  a  document  that  describes  the minimum requirements to be implemented.  In  addition  to  process  safety,  there  will  be  a  focus  on housekeeping since this is considered of paramount importance to  avoid  contamination  of  products,  raw  materials  and chemicals that could have adverse effects on safety in the TANPF or later in the product handling chain.  Safe plant operation is a key focus of BNPL and ensuring proper maintenance  is  a  key  to  safe  operation.  Important  elements  in achieving  optimum  safety,  performance  and  reliability  of operating equipment are systematic maintenance and condition monitoring. Details on how this is done will be described in the TOPS  for  maintenance,  which  will  be  implemented  for  the TANPF.  Other  important  elements  are  modifications/ management  of  change,  work  permits  and  associated  risk assessment/job  safety  analysis.  All  modifications  of  process systems and process equipment will have to be approved based on a systematic review of HES issues.  

Fire  prevention  requirements  have  also  been  included  in  the design  of  the  TANPF  (eg.  use  of  materials).  This  is  related  to process  units,  buildings,  and  material  handling  and  product storages. Prior to commissioning and operations, a detailed fire risk assessment will be carried out and the Site will be classified into  fire  cells  with  respect  to  probability  and  potential consequence  of  a  fire.  Based  on  this,  necessary  fire  protection will  be  implemented  (eg.  fire  wall/barrier,  conveyor  belt material, fire detection systems, fire extinguishing systems).  To  ensure  safe  management  of  the  product  from  the  TANPF, BNPL will apply the principles and requirements of the EFMA’s Product  Stewardship  program,  considered  to  be  European accepted  practice.  This  will  involve  management  of  the  TAN product  throughout  all  stages  of  its  lifecycle  (development, materials procurement, manufacturing, distribution and use) in a  safe  way  with  respect  to  health,  environment,  occupational and  public  safety,  and  security.  As  an  example,  dedicated carrier(s) will be used for  transporting TAN, with all operators (drivers),  as  well  as  vehicles,  to  be  certified  for  the  particular purpose. The Product Stewardship program will comply with all Commonwealth  and  State  legislation  and  where  the  program and legislation cross over, the stricter of the two will apply.   An  annual  safety  program will  be  designed  and  established  to maintain a safe and healthy work environment for all employees and contractors. All  employees will be  required  to  successfully complete a safety training program prior to gaining approval to work on the TANPF Project to achieve and maintain the level of competence required. Safety training will also be mandatory for all contractors on site. 

TANPF Security 

The  core  of  the  security  network  for  the  TANPF  will  be surveillance  cameras  for  the  complete  fenced  perimeter  and  a gatehouse  that  will  be  manned  24/7  to  control/register  all incoming/outgoing  traffic  (vehicles  as  well  as  individuals). Different  areas  within  the  TANPF  will  have  different classification  (eg.  access  granted  to  authorised  personnel  only, access  when  accompanied  by  an  employee,  limited  access outside normal working hours etc.).  Employees  will  be  equipped  with  ID/access  cards  to  be  worn and clearly displayed at all times. All employees and temporary staff will  receive necessary  security  training. The  site manager will  ensure  that  temporary  staff  from outside BNPL,  as well  as suppliers  of  goods  and  services  to  BNPL,  are  certified  by checking credentials following established procedures.   Prior to commissioning and operations, an emergency plan will be  developed  for  the  TANPF  for  handling  of  accidents  and incidents  with  risk  to  life,  property  and  the  environment.  The TANPF  will  be  certified  to  ISO 9001  (quality),  ISO 14001 (environment)  and  to  OHS AS18001  (safety)  standards  to ensure  the  highest  quality  of  safety  and  environmental management.  

Page 10: Nitrat de Amonio

 

28 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

The TANPF will also be audited on a regular basis using internal and/or external auditors to ensure compliance with the various TOPS  as  well  as  regulations,  codes,  standards  and WA  and/or Commonwealth Ministerial conditions. 

5.5.4 Unplanned Events 

An  Emergency  Response  Plan  covering  all  credible  HES emergency  scenarios  (including  tropical  cyclone  response) during  all  phases  of  the project  and  the  escalation potential  of any  emergency  situation  will  be  developed  for  the  TANPF Project and is discussed further in Section 8.11.4.  All  process  structures  and  vessels will  be  designed  for  seismic actions, eg. earthquakes, in accordance with AS 1170.4‐2007. 

5.5.5 Extreme Weather Events ­ Cyclone Design and Precautions 

Throughout  the  design  of  the  TANPF  Project  extreme weather events have been extensively analysed to ensure that the TANPF will withstand extreme weather events.  The  TANPF  has  been  designed  for  an  operating  life  of  20  plus years. Accepted international design criteria have been used for proper  sizing  of  equipment,  buildings  and  other  structures considering  the  extreme  weather  conditions  likely  to  be experienced at the Site. Storm‐water drains have been designed for 105 mm/h rainfall. The buildings will also be built to handle wind velocities up to 300 km/h  in any direction at 10 m above ground.  

In  the  event  of  flooding  due  to  a  heavy  rainfall  and/or  storm surge,  the  TANPF  (including  clean  surface  water  ponds  and other areas of potential areas of contamination) will be raised to at  least  5.5 m AHD  to  avoid  any  serious  safety  and/or environmental  accidents  associated  with  these  events  (see Annex E).   The clean surface water pond will have an area of 40 m by 25 m, and a depth of 1.5 m.  The contaminated surface water pond will have an area of 70 m by 70 m, and a depth of 1.5 m – both ponds will  be  bunded.    Preliminary  plans  of  the  drainage  design  are shown in Annex F.   The TANPF design level incorporates the potential for future sea level  rise  for  the  20  year  plus  operational  phase.  The  TANPF may be further raised depending on the outcome of geotechnical work to be undertaken prior to construction.  

5.6 TAN Process Description and Associated Infrastructure 

5.6.1 Introduction 

The TANPF will be positioned in the northwest corner of the Site (Figure 4.2).    The  plant  layout  is  shown  in  Figure 5.4  and Figure 5.5.      

Figure 5.4  3D Model of Plant 

  

Page 11: Nitrat de Amonio
Page 12: Nitrat de Amonio

 

30 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

The  TANPF  will  comprise  of  the  following  main  project elements:  

• Main Process Units, including: − Nitric Acid (NA) Plant; − Ammonium Nitrate (AN) Solution Plant; − Technical Ammonium Nitrate (TAN) Prilling Plant; 

• Storage, Loading and Transport Facilities; 

• Other Facilities and Buildings; and 

• Supporting Infrastructure and Communications.  Figure 5.6 below represents a simplified visual illustration of the TAN  production  process.    This  is  followed  by  an  overview  of each main processing unit within the TANPF.   Figure 5.6  TAN Production Process 

  

5.6.2 Nitric Acid Plant 

The  NA  plant  will  be  based  on  the  dual  pressure  process  and will: 

• Have a capacity of 760 MTPD NA (as 100 wt %);  

• Require ammonia and oxygen (air) as raw materials; 

• Generate about 3.5 MW of power from excess process steam which will be used to drive compressors in the NA plant;  

• Be designed to operate between 70 and 100% load; and  

• Produce NA (approximately 60% concentration) that will be sent to the AN solution plant. 

 The  following  outlines  the  various  unit  operations  and processes within the proposed NA plant. Additional information is contained in Table 5.10. 

Ammonia / Air Pre­Treatment 

Air  is  initially  filtered  in  a  two‐stage  filter  system.  This  is followed  by  compression  in  an  air  compressor  that  does  not require any inter‐stage cooling. The compressed air is then split into  two  sections  with  the  primary  air  going  to  the  ammonia burner while the secondary air is sent to the nitric acid bleacher.  Liquid ammonia feed is evaporated, superheated (using steam) and filtered to remove impurities. The superheated ammonia is then injected into the primary air and mixed before being fed to the ammonia burner.  

Nitric Acid Synthesis 

The  compressed  air/ammonia  mixture  enters  the  burner  and passes  through  a  gas  distribution  system.  At  the  platinum gauzes,  ammonia  is  combusted  to  Nitrogen  Oxide  (NOx)  at  a temperature around 890 to 900°C.   In the downstream piping and equipment, NO is oxidised to NO2 generating  additional  heat  that  is  used  in  the  heat  recovery network.  The  gas  is  cooled  down  further  and  condensed,  forming  nitric acid  with  around  40%  by weight  in  the weak  acid  condenser. The acid is then separated from the process gas and pumped to the appropriate tray in the absorption tower.   The  process  gas  is  compressed  to  the  selected  absorption pressure. The compressed gas is used to heat the tail gas. In the absorption  tower,  NOx  gases  are  absorbed  into  water  to  form NA. The gas leaving the absorber (tail gas) is expected to have a NOx content of approximately 400 ppm, depending on pressure and chilled water temperatures.  The  tail  gas  will  then  enter  the  abatement  reactor  (N2O/NOx reduction unit). This reduction unit utilises BAT, and the tail gas vented  to  the  atmosphere  from  the  TANPF  will  comply  with statutory requirements and environmental guidelines.  After  the  abatement  reactor  the  tail  gas will  enter  the  tail  gas turbine  where  it  is  expanded  to  recover  70%  of  the  power demand for the compressor train.  The acid concentration will be optimised to match the AN plant requirements,  but will  be  approximately  60%  by weight.  Heat generated from the acid production operation is partly used for the production of steam and for the generation of electricity and only  the  remaining heat  is  removed  into  the  chilled water  and sweet water cooling loops.  

Page 13: Nitrat de Amonio

 

31 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Table 5.10  NA Plant Summary Development  

Nitric Acid Plant 

Inputs/quantities or volumes 

Outputs/Products  Outputs/Wastes & Emissions 

Ammonia:  

8,977 kg/h 

Air:  

160,359 kg/h or 51,629 m3 /hr 

Water (saline, potable): 

No consumption directly in process 

Power:  

3.5 MW internal generation (Steam from NA Plant)  

0.38 MW internal consumption  

Produce NA (approx. 60% concentration) – 52,778 kg/h or 39.8 m3/hr as an intermediate product that will be sent to the AN solution plant 

1) Air Emissions 

• N2O   

- Normal operation 100ppm or 19.4 kg/hr 

- Max1 2,000 ppm or 180 kg/hr  

• NOx  

- Normal operation 75ppm or 15 kg/hr calculated as NO2  

- Max1 700 ppm or 100 kg/hr calculated as NO2  

• CO2  

- Normal operation 250ppm or 49.5 kg/hr  

- Max1 400 ppm or 79.42 kg/hr 

• CO  

- Normal operation < 40ppm or < 4.45 kg/hr 

- Max1 40 ppm or  4.45 kg/hr 

• CH4 

- Normal operation 30ppm or 2.1 kg/hr 

- Max1 100 ppm or 7.1 kg/hr 

• NH3 

- Normal operation 1 ppm or 0.08 kg/hr 

- Max1 5 ppm or 0.4kg/hr 

• H2S 

- Normal operation, traces only 

- Max1, traces only 

2) Liquid Emissions 

• Oil residue and sludge from the heat exchangers and storage tanks, minimal quantities  

3) Catalysts • The Pt/Rh catalyst gauzes and 

the catchment system will be completely changed and recycled approximately two times a year. 

• The NOx and N2O catalyst has a life time of approximately 10 years and will be returned to the manufacturer  

1. Max values are associated with upset conditions and include start‐up and shutdown, which do not generally last more than 4 hours. 

5.6.3 Ammonium Nitrate Solution Plant 

The  AN  solution  plant  will  apply  the  vacuum  neutralisation technology and will: 

• Have a capacity of 965 MTPD AN (as 100 wt %) to match the NA plant capacity; 

• Require ammonia and nitric acid as raw materials; and 

• Produce AN  solution  that  is  either  sent  to  the TAN prilling plant or stored. 

 The  following  is  an overview of  the AN  solution plant process. Additional information is contained in Table 5.11. 

Ammonium Nitrate Synthesis 

Superheated  gaseous  ammonia  at  about  90°C  and  preheated liquid  nitric  acid  (approximately  60 wt%)  at  about  65°C  are injected into the bottom part of a forced circulation neutraliser.  The reaction is exothermic in nature and requires good control of  feeds.  The  molar  ratios  of  reactants  are  controlled automatically.  Nitric  acid  flow  controls  the  main  flow  of ammonia.   The  circulating  stream  leaving  the neutraliser  enters  a  cyclone separator  operating  under  slight  vacuum  providing  flash evaporation  of  the  solution  giving  a  concentration  of  about 93 wt%. The temperature rise  in the neutraliser will be limited to 145°C.    Table 5.11  AN Solution Plant Summary Development  

Ammonium Nitrate Solution Plant 

Inputs/ quantities or volumes 

Outputs/Products  Outputs/Wastes & Emissions 

Ammonia:  

8,630 kg/h   

Nitric Acid: 

52,756 kg/h as 60% concentration 

Water (saline, potable): 

no water consumption 

Power: 

(BFPL or internal) ‐ 105 KW  

Produce AN solution: 43,300 kg/h max and 40,300 kg/h nominal as 93% will be used for TAN production. 

1) Air Emissions 

• None  

2) Liquid Emissions 

• Clean condensate (15 ppm N from both ammonia and AN) is used in the scrubber and as make‐up water  

• Blow down, containing suitable contamination concentrations to be exported to the Water Corporation (about 12 m3/h).  

1. Max values are associated with upset conditions and include start‐up and shutdown, which do not generally last more than 4 hours.   

2. Nitric acid emissions of off vapours can be produced from the neutralisation reactor in the TAN plant.  However, all off vapours produced will be condensed back into the system, ie. it is a closed system, therefore there will be no emissions. 

5.6.4 Technical Ammonium Nitrate Prilling Plant 

The  TAN  prilling  plant  will  be  designed  based  on  the  Yara process  for  final  evaporation  and  prilling/drying/cooling,  and will: 

• have a capacity of 915 MTPD prilled TAN (as 100 wt %); 

• require AN solution as raw materials; and, 

• produce TAN prills  that are either bagged or stored  in bulk and then sent via truck to customers. 

 In  order  to  generate  products  of  the  specified  properties,  a number  of  unit  operations  and  processes  are  required,  as described  below.  Additional  information  is  contained  in Table 5.12. 

Page 14: Nitrat de Amonio

 

32 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Ammonium Nitrate Solution Concentration 

The  AN  solution  from  the  neutraliser  is  sent  to  a  falling  film evaporator that operates under vacuum. Evaporation ultimately results in a product concentration up to 96.5 wt% AN.   

Additive Preparation   

To produce  the higher density grade AN, an additive known as permalene  is  required.  This  permalene  solution  (25%)  is prepared from the raw materials boric acid, ammonium sulfate and diammonium phosphate. On  the other hand,  lower density AN is produced by the introduction of an organic additive. Note that  for  safety  reasons,  this  organic  additive  is  introduced  just before the prill nozzle.  The additives are either produced on site or are delivered as ready‐made chemicals. 

Prilling 

The AN solution is pumped to the top of the prilling tower. Here, the solution flows by gravity to the prilling nozzles where they form  droplets  that  crystallise  as  they  fall  from  the  top  of  the tower.   The cooling air  required  for crystallisation of  the AN  is recycled  to  limit atmospheric emissions, while cool and hot air generated is reused via a series of unit operations.  

Drying  

Prills  exiting  the  prill  tower  are  directed  to  the  drying  section for  reducing  the  moisture  content  from  3  –  4 wt%  to  0.05  – 0.2 wt%,  depending  on  grade.  This  is  achieved  via  either  co‐current or counter current dryers. This unit operation removes most of the water present and results in a porous product.  

Cooling and Conditioning 

Dried  prills  are  screened  before  being  fed  to  the  fluidised  bed cooler. Oversizes and fines are removed and recycled while the on‐spec  prills  are  cooled  to  the  optimal  storage  temperature. The fluidised bed cooler is a two stage cooler with intermediate air  recycle.  The  air  usage  in  this  section  is  also  integrated  to other sections of the facility, which is a good means of achieving higher  economic  and  environmental  viability.  The  cooled product  is  finally  sent  to  a  coating  drum  where  anti  caking agents are sprayed on.  Table 5.12  TAN Prilling Plant Summary 

Technical Ammonium Nitrate Prilling Plant 

Inputs/ quantities or volumes 

Outputs/Products  Outputs/Wastes & Emissions 

AN solution:  

40,300 kg/h as 93% concentration  

Nitric Acid: 

290 kg/h as 60% conc. 

 

Produce Prilled TAN 38190 kg/h 

1) Air Emissions 

• AN Dust particles 

- Normal operation 2.8 kg/hr  

- Max1 5.4 kg/hr 

• NH3 

- Normal operation 2.3 kg/hr 

- Max1 8.7 kg/hr 

Technical Ammonium Nitrate Prilling Plant 

Inputs/ quantities or volumes 

Outputs/Products  Outputs/Wastes & Emissions 

Prill Coating: 

38.5 kg/h 

Internal Additive: 

26.5 kg/h  (2 types organic or inorganic)  

Water (saline, potable)  

2 m3/hr desalinated water 

Power  

BFPL or internal) ‐ 3.04 MW 

  • Continuous emissions will be cleaned in several stages culminating in a common scrubber that vents to the atmosphere to meet statutory requirements. During normal operation the ammonium nitrate and ammonia emission to atmosphere will be 2.3 and 2.8 kg/h, respectively. 

2) Liquid Emissions 

• Occasional floor washings, drains, drips rainwater etc (about 4 m3/day). 

• Atmospheric moisture condensation from plant air‐conditioning, about 1.9 m3/h 

1. Max  values  are  associated with  upset  conditions  and  include  start‐up  and  shut‐down, which do not generally last more than 4 hours 

5.6.5 Storage, Loading and Transport Facilities 

Bulk TAN Storage Building and Truck Bulk Loading System  

The  bulk  TAN  storage will  have  a  capacity  of  12,000 MT.  The storage/layout  of  the  product  piles  are  based  on recommendations  from  the  world  renowned  Dutch  research institute  TNO  to  ensure  safe  conditions  (see  Section 5.5.3  for further details). As a consequence the storage will have several bulk  piles  with  a  distance  of  about  1  m  to  avoid  sympathetic detonation.  Due  to  the  ambient  temperature  of  the  Pilbara region, the bulk storage will have a special roof construction to maintain  temperatures  within  acceptable  levels.  Air dehumidification  or  conditioning  is  likely  to  be  further considered to improve the storage if deemed necessary.   The  final  TAN  product  leaving  the  TAN  prilling  plant  will  be conveyed  to  the  bulk  storage  or  directly  to  the  truck  loading area (including weight bridge). The truck loading can also be fed from  the  bulk  storage  using  a  front  end  loader  and  conveying system.   Bulk TAN will be transported  to the consumers by trucks only, which will be loaded using a system consisting of front loaders, bucket elevators and silos in combination with a truck weighing system.  Approximately  25  trucks  will  operate  per  day  for  the transport  of  products  (including  bulk,  bagged  and  solution), with  all  trucks  fully  authorised  with  licensed/certified operators.  

Bagged TAN Storage Building and Bagging Facility  

The  storage  for  bagged  TAN  product  will  have  a  capacity  of 1,800 MT. The product will be stored in stacks of about 300 MT or less and with minimum 7 ‐ 9 metres between the stacks using a stacking configuration recommended by TNO (see Section 5.5.3 for further details).     

Page 15: Nitrat de Amonio

 

33 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

The bagging facility will have a capacity to bag TAN into 1,000 – 1,250 kg  bags.  Product  that  is  to  be  bagged  will  also  be reclaimed  from  the  bulk  storage  and  conveyed  to  the  bagging plant. Forklifts will be used to transport bagged products to the bagged  TAN  storage  building.  Bagged  products  will  be transported to customers using trucks as discussed above.  

Nitric Acid Buffer Storage  

Two tanks with a total capacity of 3,000 m3 will be located in a bunded area with an acid resistant surface. 

Ammonium Nitrate Solution Storage  

Excess AN solution will be stored at concentrations of 80 – 92% within a 500 MT tank that will be located in a bunded area.  AN solution may be loaded on trucks from the AN storage tank which will  be provided with  a necessary  loading  system.  If AN solution is sold, it will be transported to customers using trucks as discussed above. 

Chemical Storage  

As  part  of  the  TAN  production  process,  certain  organic  and inorganic  chemicals  will  be  required  to  be  stored  on  site  for numerous process requirements. The chemicals to be stored on site are described below, including any requirement for bunding or  other  specialised  storage  procedures  required.  Unless otherwise specified, all chemicals not being used will be stored in the chemical storage building. 

• Inorganic  internal  additives  ‐  These  are  required  to  be stored  as  dry  material  on  site.  These  materials  will  be bagged  and  handled  by  forklifts  for  the  preparation  of  the additive solution that will be directly pumped  into the TAN process  (approx  1.5  month  consumption).    The  major inorganic additives to be stored on site are: − 20 MT Boric acid in 1 MT big bags. − 20 MT Di Ammonium Phosphate in 1 MT big bags. − 5 MT Ammonium Sulfate in 25 kg small bags. 

• Organic  internal  additives  ‐  Organic  additives  have  the potential  to interact with TAN and other products on site  if not  carefully managed. Organic  additives  shall  be  stored  in separate bunded areas to prevent mixing with product.  The chemicals  shall  be  delivered  in  truck/containers  and pumped  into  the  storage.  The  key  organic  additive  to  the TAN process will be: 

− Sulphonated  naphthalene  –  20 MT  in  powder  form  in 500 kg bags (to be used to prepare a solution that will be pumped  into  the  process),  or  25 MT  of  ready  made solution (approx 1.5 month consumption). 

− Coating  Agent  (Amine  wax)  –  35 MT  as  melted  wax pumped directly into the process. This shall be delivered as a wax that may need heating for transfer into storage tank (approx 1.5 month consumption). 

• Laboratory chemicals ‐ Most of the laboratory analysis shall be  performed  in  the  main  laboratory,  located  at  the  BFPL plant  site.  The  only  frequent  analysis  requiring  chemicals that  shall  be performed on  the premises of  the TANPF will be  moisture  content  using  the  Karl  Fischer  method  that requires the following chemicals, which will be stored in the chemical store: − Methanol 200L (equivalent to one year of usage). − Karl  Fisher  reagent  20L  (equivalent  to  one  year  of 

usage). 

• Chemicals for NA plant – The following chemicals, when not being used, will be stored in the chemical store: − Hydrogen  (99%  conc.)  –  Will  be  used  to  ignite  the 

burners  in  the  NA  plant.  Approximately  twenty  50L bottles will be required in first year, with 12 bottles per year after that.  Approximately four bottles will be stored at the nitric acid plant and the remaining in the chemical store. 

− Nitrogen (99.5% conc.) ‐ Will be used for utility stations and  purging  of  equipment.  Four  40L  bottles  will  be stored in the chemical store for annual use. 

• Calibration gases for the tail gas analysers of the NA plant ‐ Consumption  will  be  based  on  the  intervals  of  calibration (yet to be determined). The following gases will be used with each to be stored in 40L bottles:  − Nitrogen ‐ Consumption about 4 bottles per year. − N2O/NO/CH4/N2 mix  ‐  consumption  about  1  bottle  per 

year. − N2O/NO/N2 ‐ consumption about 1 bottle per year. − NO2/Air mix ‐ consumption about 1 bottle per year.  One  complete  set  (one  of  each  above)  of  calibration  gases will  be  installed  in  the  analyser  container  in  the  NA  plant. The other remaining bottles for the yearly consumption will be stored in the chemical store. 

• Other chemicals – Other chemicals to be used on site are as follows, with all chemicals to be stored in the chemical store unless otherwise specified: − Trisodium  phosphate  ‐  For  pH  adjustment  of  boiler 

water. Consumption of about 100 kg per year. − Oxygen scavenger (Eliminox) ‐ for removing rest oxygen 

in the boiler feed water. Consumption of about 100 L per year.  

− Cleaning  chemicals  like  acetone  for  removing  of  oil. Consumption of about 200L per year.  

− Chemicals  for  neutralisation  of  acidic  wastes  (NaOH). Consumption of about 200L per year. To be stored near the  contaminated  surface  water  ponds  in  appropriate storage.  

− Chemicals  for  neutralisation  of  alkali  wastes  (HNO3). Consumption of about 200L per year. To be stored near the  contaminated  surface  water  ponds  in  appropriate storage. 

− Corrosion  inhibitor  Natriumhypochlorid  (NaOCL)  to  be stored  in  the  NA  plant  in  a  30 m3  tank.  Continuous consumption during operation of about 3.5 kg/h. 

Page 16: Nitrat de Amonio

 

34 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

− Biocide ‐ To be mainly stored in a 1 m3 container at the NA plant from where a 300L day tank will be fed. There will  be  continuous  consumption  during  operation  of about  0.5 L/h.  Depending  on  delivery  more  containers may be stored in the chemical store.  

− Scale inhibitor ‐ To be mainly stored in a 1 m3 container at the NA plant from where a 300L day tank will be fed. There will be continuous consumption during operation of  about  0.75 L/h.  Depending  on  delivery  more containers may be stored in the chemical store. 

Diesel Storage 

An  onsite  above  ground  diesel  fuel  store  of  a  capacity  of approximately  12 m3 will  be  installed  to  provide  refuelling  for the  payloaders  and  possible  feed  to  the  emergency  diesel generator day tank. This tank will be located in an appropriately bunded area.  During  pre‐commissioning,  commissioning  and  start  up  some additional  quantities  of  diesel  may  be  required.  These  will  be stored appropriately as described above. 

Liquid Ammonia Pipeline 

The TANPF will receive liquid ammonia from the adjacent BFPL plant via a 710 m long, insulated 4 inch diameter pipeline, to run between the BFPL and TANPF sites within each respective lease (see Figure 4.2). To reduce the release of ammonia in case of an accidental  leak or rupture of the  line, an emergency shut down will take place resulting in isolation of the line into 3 sections. 

5.6.6 Water Supply and Treatment 

Water Corporation’s Desalination and Seawater Supplies Project 

In  order  to  service  the  needs  of  industrial  facilities  on  the Burrup  Peninsula,  the  Water  Corporation  constructed  a Desalination and Seawater Supply Facility. This facility supplies seawater  (capacity  of  280 ML/d)  and  desalinated  water (4 ML/d),  as  well  as  providing  a  brine  discharge  line,  which includes disposal of treated industrial and domestic wastewater (208 ML/d)  for  local  strategic  industries  in  the  King  Bay  ‐ Hearson Cove Industrial Area.   The Water Corporation  facility was  issued with WA Ministerial approval  in  June  2002  (Statement  No. 594),  with  the  license conditions outlining specific wastewater criteria to be achieved by  the Water Corporation prior  to discharge of brine  into King Bay  (see  Annex F  for  Water  Corporation  conditions).  The commitments  also  state  that wastewater will  only  be  accepted from industries under the License and Ministerial Conditions for those industries.  

The Water  Corporation  as  owners  and  managers  of  the  brine and  wastewater  discharge  system  monitor  and  report  on  the individual  effluent  streams  entering,  and  the  combined discharge  leaving,  the  system.  The  Water  Corporation  has committed  to  implement  (and  is  implementing)  an Environmental Management Program that includes appropriate monitoring  and  reporting,  encompassing  water,  sediment  and biota, for the wastewater system and the ambient environment. The  Water  Corporation  has  also  committed  to  impose contractual  obligations  on  system  users  (which  will  include BNPL)  with  respect  to  the  flow  and  composition  of  their discharge  into  the  multiuser  discharge  system.  The  Water Corporation  also  independently  sample  and  analyse  the individual discharges on a regular basis to validate the accuracy of the data provided by system users. 

Sea Water Supply and Cooling Tower 

Sea water will be  supplied by  the Water Corporation and shall be used  solely as make up water  for  the sea water closed  loop cooling  towers  to  be  installed  on  the  premises  of  the  TANPF.  About 450 m3/h shall be imported and a blow down of 350 m3/h shall be exported back to the Water Corporation  in accordance with approved Ministerial and  licence conditions  for  release of water to the Water Corporation return line.  The cooling towers will also comply with the Health (Air Handling and Warm Water Systems) Regulations 1994. 

Desalination Water and Potable Water Supply 

Potable  water  shall  be  provided  directly  by  the  Water Corporation, with desalinated water to be provided by BFPL.  A total of 2 m3/h of potable water will be supplied from the Water Corporation.  Desalinated  water  will  be  used  for  fire  fighting  and  utility stations and for the closed loop fresh water cooling system. An adequate volume for fire fighting water is foreseen.   Potable water obtained from the Water Corporation will be used for safety showers, utilities and domestic purposes. 

Closed Loop Fresh Water Cooling System 

The  cooling  requirements  of  the  process  elements  within  the TANPF will  partially  be  provided  by  a  closed  loop  fresh water cooling  system.    Process  heat  exchangers  requiring  cooling water will normally be fed from this system, with 6,545 m3/h of fresh water  to be within  the  loop system with  the exception of the steam condenser in the NA plant. The hot fresh water will be cooled  with  seawater  from  the  cooling  towers.  The  steam condenser  of  the  NA  plant  shall  be  fed  directly  from  the seawater loop system.  The  heat  from  the  TANPF  process  operations  is  taken  out through  the use of  the  cooling  system by evaporation of  about 100 m3/h of seawater in the cooling towers.  

Page 17: Nitrat de Amonio

 

35 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Water Ponds 

A  clean  surface water  pond  and  a  contaminated  surface water pond will be utilised at the facility to manage the various liquid streams.  The  clean  surface  water  pond  will  store  rainwater  collected from  roofs  and  parking  areas  as  well  as  clean  condensates. About  24.6 ML/y  of  water  from  the  clean  surface  water  pond will be transferred to the Water Corporation facility. The water will  be  analysed  prior  to  discharge  from  the  BNPL  facility  to ensure  it  complies  with  approved  Ministerial  and  licence conditions of the Water Corporation.   Contaminated water  (eg. miscellaneous  drips/drains/floor  and equipment  washings)  will  be  neutralised  and  collected  in  a contaminated  surface  water  pond  for  evaporation.  This  is  a closed  system (eg. no  liquid will be discharged), with  the  solid salts/ sludge created by evaporation to be treated and handled as  special  waste  in  accordance  with  all  relevant  statutory requirements. This waste will be  sent offsite  for disposal  at  an appropriate  facility  by  an  approved  and  licensed  waste contractor.    The  contaminated  surface  water  pond  will  be divided  into  two  sections  so  that  one  section  can  remain  in operation while the other is being cleaned of residual salts.  The pond  is  sized  to  be  able  to  cope  (evaporate)  with  the  normal flow  of  wastewater  from  the  TANPF  estimated  to  be  about 9,735 t/year  and  additional  flows  in  connection  with  tropical cyclones.  The water  ponds will  be  located  at  an  altitude  above  sea  level sufficient  to  secure  against  ingress  of  flood  waters  or  storm surge.    The  ponds  will  comply  with  Department  of  Water requirements  for  constructing  contaminated  surface  water ponds,  and  the  need  for  measures  to  deter  birds  from  these ponds will be investigated.  

Drainage 

Drainage  design  cannot  be  finalised  until  the  project  is  at  the detailed  design  stage.    At  this  stage,  consultation  on  drainage design will be undertaken with DEC.  However, the overarching principles  are  known  and  a  preliminary  plan  is  shown  in Annex F.  Natural drainage on the Site will be diverted to ensure that flows continue  into  the  salt  flats.    BNPL  will  consult  with  DEC  over drainage  design  to  ensure  that  there  is  a  minimal  impact  on natural flows.  Wastewater and rain water will be collected on site, and will be segregated to drain to either the clean or contaminated surface water  pond  (as  discussed  above).    Water  quality  will  be controlled  and  monitored  using  conductivity  and  pH measurements,  and  water  will  be  routed  to  the  appropriate pond.  Water from the clean surface water pond which does not exceed the Water Corporation’s agreed Ministerial limits will be sent to the Water Corporation.  

The  TANPF  shall  comprise  a  network  of  bunded  areas  and trenches  so  that  any  potentially  contaminated  water  is  kept completely  isolated  from  rainwater.  All  storage  tanks  and  all main  plant  units  will  be  bunded.    Bunded  areas  within  the complex shall  in most cases  include a collecting pit  from which wastewater is sent to the contaminated surface water pond.    Some  bunded  areas  that  may  contain  special  components (coating  agent  for  example)  shall  be  emptied  using  trucks  and drained content shall be treated as special waste. These wastes will not be connected to the contaminated surface water pond.   Clean  surface  water,  such  as  rainwater,  shall  be  collected through  a  separate  trench  and  gutter  network  and  sent  to  the clean surface water pond.  

Wastewater Streams 

A total of 3,105 ML/y of water (including sea water blow down and clean surface water) will be sent  to  the Water Corporation in  compliance  with  the  Water  Corporation  Ministerial conditions.  This level of discharge will be well within the Water Corporation discharge line capacity of 208 ML per day, with the current use of  the discharge  line being  less  than 50% capacity (pers comm. Brett Jago, 2009).  All  contaminated  streams  (waste)  shall  be  sent  to  the contaminated surface water pond.   For example, purge streams from  ammonia  heat  exchangers  shall  be  collected  in  barrels.  These barrels are either treated (neutralised) when possible or removed  as  special  waste;  trace  amounts  may  be  sent  to  the contaminated surface water pond.   There  may  also  be  exceptional  drainage  of  bunded  areas containing  water  that  is  possibly  contaminated  by  special substances.  These  shall  be  treated  as  special  waste.    All wastewater disposals will comply with the Health (Treatment of Sewage  and Disposal  of Effluent  and  Liquid Waste) Regulations 1974.  At this stage there are no plans for the use of any recycled water,  however,  if  this  is  required  this  will  be  carried  out  in accordance  with  the  National  Water  Quality  Management Strategy  Australian  Guidelines  for  Water  Recycling:  Managing Health and Environmental Risks (Phase 1) 2006.  

5.6.7 Power Generation Treatment 

Power Generation and Emergency Power 

Approximately  8.5 MW  of  power  will  be  required  to  run  the TANPF.  About  5 MW  of  the  total  8.5 MW  requirement  for  the TANPF will be imported from BFPL, which produces power from the use of Natural Gas. The  remaining power  (approx 3.5 MW) will be generated by excess steam from the operation of the NA plant.   

Page 18: Nitrat de Amonio

 

36 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Once operating,  the synthesis of nitric acid gives off  significant waste heat  that will be  transferred  to a steam system. Some of this  steam will  be  used  in  the process  units  of  the TANPF  (for example air heaters), with the remaining excess heat to be sent through to a high efficiency turbine to generate electrical power through the use of steam. This allows for a significant decrease in  the  energy  required  to  operate  the  TANPF  and  thereby significantly  reduces  the  air  emissions  and  greenhouse  gases produced.   In  case  of  a  power  outage,  emergency  power  (for  lighting  and safe  plant  shut  down)  will  be  provided  by  on‐site  diesel generators. 

Steam Grid 

In normal operation,  the TANPF will have  its own independent steam grid comprising several  levels of pressure (ranging  from 46 to 6.5 bar). This steam will be produced from the operation of the NA plant.   Due to the self‐sufficient nature of  the NA plant steam process, the TANPF will  require  steam  imports  from BFPL  to  help  pre‐heat certain units and feed the steam turbines during start up of the NA plant.  Start‐up of  the NA plant will  require  an  external steam supply from BFPL with a peak demand of 40 t/h of steam at 46 bar pressure and 388°C temperature. 

5.6.8 Instrument and Plant Air System 

Three  electric  driven  compressors,  each  designed  for  50%  of maximum  air  consumption,  will  provide  compressed  air  that will  be dried  and used  for  instrument  and general work  (tools etc).  The  capacity  of  each  compressor  will  be  about 1,000 Nm3/h. 

5.6.9 Support Facilities 

Support facilities that will be required for the TANPF are shown on Figure 5.4 and include: 

• Administration office and staff amenities. 

• Chemical  /raw material  store – The  chemical/raw material store will be used  to store given quantities of  raw material and  chemicals  to  allow  for  about  1.5  months  of  normal consumption (see Section 5.6.5 for further details). 

• Spare parts store ‐ The spare part store will be used to store sets  of  replacement  parts  for  machinery  or  full machines/devices that are deemed critical for the operation of the TANPF. The spare part store may also contain day‐to‐day maintenance consumables. 

• Workshop ‐ Existing facilities at the BFPL plant will be used. The  workshop  will  be  used  for  day  to  day  maintenance activities  and  will  contain  all  the  tools  and  lifting  devices necessary to perform maintenance tasks.    

• Central  control  room  ‐  The  control  room will  be  used  as  a central  control  centre where  the  technical  operation  of  the TANPF will be managed. The control room will be blast, fire and weatherproof.  The  control  room will  consist  of  a  fully distributed and advanced control system to ensure the safe operation and management of the TANPF. The control room will be manned by at least one person at all times. 

• Field  laboratory  ‐ The  laboratory within  the TANPF will be used to analyse product/samples from the process units and for storage so that product quality and safe operation can be monitored. A main laboratory, located at the existing facility at BFPL will be used for most analysis. 

• Safety,  First Aid  and Fire  Station building  – The  safety  and First  Aid  facilities  will  be  used  to  host  emergency medical and safety equipment/gear so that First Aid can be provided on the premises of the TANPF.  The Fire Station will host the fire‐fighting  brigade  that  shall  be  specially  trained  and equipped  for  the  specific  hazards  of  the  TANPF.  These services  for  fire  will  be  provided  by  the  existing  services located at BFPL which will be retro fitted if required to meet all requirements of the TANPF. 

• Gatehouse ‐ A gatehouse will be provided at the entrance to the Site for the purposes of security. 

Transport, Roads and Parking 

Site  access  for  the  TANPF  Project  will  be  via  Village  Road,  an existing two lane bitumen access road constructed to service the already operational BFPL ammonia plant (Figure 1.1).   Transport  of  TAN  (bulk  and  bagged  product)  to  local  and regional  customers will predominately be via  the existing  local road network.   A  connecting  internal  road  from  the  TANPF  to  the  existing Village Road, north of the Site will be constructed as part of the project.  From Village Road products will be transported to local customers via Burrup Road and the Karratha‐Dampier Highway.  Truck  loading  will  use  a  system  consisting  of  front  loaders, bucket elevators and silos in combination with a truck weighing system. Approximately 25  trucks will operate per day  for bulk, bagged and solution products.   BNPL will have  in place a parking area  for use by  transporters on the Site, as well as offices (3 staff), workshop (3 mechanics) and a parking/truck wash (with all runoff water to be directed to  the  clean  and/or  contaminated  surface  water  ponds).  The area is foreseen to be adequate for parking of a fleet of about 20 road trains. 

Accommodation Facility 

Work  force  employed  during  construction  will  be accommodated  in  either  existing  or  new  camps  in Karratha  or Dampier, depending on availability. No accommodation will be in place on the Burrup Peninsula as a result of this project. 

Page 19: Nitrat de Amonio

 

37 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Permanent  housing  for  operational  workforce  will  be  built  or acquired  in  the  Karratha  region  (for  about  60  Karratha  based persons in total). 

Sewage 

Sanitary waste will be  collected by authorised personnel using trucks  and  transported  to  an  off‐site  treatment  plant.  The amount  of  sanitary  waste  is  estimated  to  be  a  maximum 0.2 m3/person/day. During  the  construction  an  average  of  400 persons will  be  on  site with  a  peak  of  650  persons. When  the TANPF  is  in  normal  operation  a  total  of  60  persons  will  be employed  (including  shift  personnel).  Sanitary  waste  storage, collection  and  disposal  will  be  organised  sufficiently  for  the number  of  personnel  on‐site  in  accordance  with  all  relevant legislative requirements, including those of the WA Department of Health (DoH).  

Lighting 

The  provision  and  use  of  artificial  lighting  are  required  for safety and operational  reasons as  the TANPF will operate on a 24 hour, seven days a week basis. Artificial sources of light will be  used  during  the  construction  and  operations  phases  of  the TANPF as follows: 

• Lighting to enable 24‐hour a day activities at the TANPF. 

• Lighting  within  the  construction  site,  should  night‐time works be required. 

 The  permanent  lighting  system  for  the  TANPF  will  be determined  in  the  detailed  design  phase  for  the  TANPF. Permanent  artificial  lighting  will  be  reduced  to  the  least practicable level for the safe conduct of operations, with design considerations including: 

• Need for the light; 

• Timing  requirement  for  the  light,  such  as  timers  to extinguish lights; 

• Shielding  to  limit  light  spill  to  within  the  Site  (where possible); 

• Light  positioning,  such  as  reducing  height  and  using screening; 

• Orientation  of  lights  away  from  Hearson  Cove  (where possible); and 

• Reducing wattages. 

5.7 Project Life Cycle 

5.7.1 Construction 

Construction of  the TANPF will  take  approximately  30 months with  the workforce  level  likely  to  vary  over  the  entire  period. During peak periods, approximately 650 persons will be on site while  the  mean  construction  workforce  is  expected  to  be approximately  400  persons.  These  numbers  include  all categories  of  construction  workforce  personnel.    Construction activities  will  be  conducted  during  normal  project  working hours with the potential for some out of hours activities. 

Site Preparation and Earth Works 

The  proposed  site  preparation  works  for  TANPF  will  include (but not necessarily be limited to): 

• Removing vegetation within the designated area; 

• Preparing  the  plant  footprint  including  laydown  and stockpile areas; 

• Dewatering and trenching (as required); 

• Establishing water facilities – including construction potable water and wastewater treatment plant; 

• Site drainage; 

• Establishing perimeter fencing; and, 

• Road and access tracks for construction. 

Civil Works 

The proposed civil works for TANPF will include: 

• Excavation  for  foundations  and  other  civil  works  (eg. footings); 

• Controlled blasting (if required); 

• Laying  of  concrete  pad/footings  –  including  curing  of  the concrete (water requirement); 

• Equipment Storage/construction laydown; and 

• Preparation of ammonia pipeline and utilities from BFPL.  Should blasting be required,  this will be controlled,  low impact blasting,  so  as  to  manage  potential  risks  associated  with  the adjacent BFPL facility,  located immediately to the west.   Due to the sensitivity to vibrations of the heavy rotating machinery, for example compressors and turbines, operating at the BFPL plant, blasting  must  be  performed  in  a  very  controlled  manner  to avoid  tripping  of  the  ammonia  plant.    Therefore,  the  use  of explosives will be avoided or  limited to the absolute minimum, and  if  used  blasting  will  be  carried  out  in  a  very  controlled manner.    Controlled  blasting  is  normally  performed  with  a number  of  low  intensity  charges,  which  are  initiated  in  a sequence. 

Page 20: Nitrat de Amonio

 

38 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Plant Installation 

The  proposed  activities  associated  with  plant  installation  for TANPF will include: 

• Transport  of  construction  materials  on  and  off‐site  (via Karratha‐Dampier Rd, Burrup Rd and Village Rd) – including cranes; 

• Operation of cranes; 

• Grinding and welding; 

• Insulation and painting; 

• Non‐destructive testing (incorporating x‐ray tests of welds); 

• Joining cooling water lines (resins, glass fibre); and 

• Landing of prefabricated Components.  The landing of components for the plant can be undertaken via the  Dampier  Public  Wharf  or  Mermaid  Marine’s  Wharf.  The Dampier  Public  Wharf  currently  has  a  maximum  capacity  of 300 T.  Alternatively  Mermaid  Marine’s  Wharf  has  a  larger capacity  of  2,000 T  which  is  well  within  the  capability  of accepting all necessary components for the TANPF. Use of either of  the  facilities  for  the  landing  of  plant  components  will  be negotiated  under  a  commercial  agreement  between  BNPL  and Mermaid Marine or the Dampier Port Authority. 

General 

Proposed general  activities associated with  the  construction of the TANPF will include: 

• Workers  commuting  to  site  (using  buses  to  transport  all personnel to and from the Site); 

• Use  of  existing  roads,  power,  water,  sewage  and  waste disposal facilities. 

• Preparation of on‐site worker facilities (crib rooms etc.); 

• Vehicle movements for construction and installation of plant equipment; 

• Off‐site  construction  workforce  camp  (in  Karratha  or Dampier); 

• Fuel storage; and 

• Refuelling of vehicles and machinery. 

5.7.2 Emissions, Discharges and Waste during Construction 

Atmospheric Emissions 

Construction  activities  associated  with  earthworks  and vehicular movement are likely to result in a temporary increase in  atmospheric  emissions  across  the  Site.  Emissions will  result from  the  use  of  heavy  machinery  and  plant  equipment,  the running of generators and increased use of vehicles required for construction workforce transport. 

Dust  emissions  are  expected  to  be  greatest  during  the construction  phase  and  are  likely  to  vary  depending  on  the construction  activity  and  the  prevailing  wind  conditions. Earthworks  for  the  TANPF,  area  for  surface  water  ponds,  and trenching  and  filling  are  all  likely  to  result  in  increased  dust levels.  Construction  will  also  see  an  increase  in  vehicle movements  over  unpaved  roads  and  access  tracks  within  the Site, which will add to dust creation during construction. 

Solid Non­Hazardous Waste 

Solid non‐hazardous waste shall mainly be composed of general refuse such as building rubbish (including metal, plaster board etc.) and packaging material. All wastes will be segregated and disposed of accordingly depending on the types of waste.  

Liquid Waste 

No  significant  amounts  of  liquid  waste  are  expected  during construction  apart  from  potential  water  resulting  from dewatering which is expected to be very limited (if required). 

5.7.3 Commissioning 

Commissioning  is  scheduled  to  take  six  months  and  will  start three months prior to mechanical completion of the TANPF. To assist  the  contractor  (who  will  have  overall  responsibility  for commissioning)  with  commissioning,  suppliers  of  the  main equipment  will  be  invited  to  have  an  involvement  in commissioning of the TANPF. Also, all plant operators will take part in the commissioning phase as a form of advance training.   

Leak Testing 

Leak testing utilising air or water is likely to be performed on all elements  required  to  be  leak‐free  in  the  TANPF  process  units.  Any  contaminated  materials  will  be  sent  offsite  to  licensed contractors for treatment and disposal. 

Pressure Testing  

Pressure testing shall be performed on all elements required to be  pressure  certified  or  expected  to  operate  in  pressurised conditions  in  the  TANPF.    Testing  of  elements  that  require certification  shall  follow  the  relevant  procedure  according  to applicable regulations and codes. 

Commissioning of TANPF 

Commissioning shall involve the testing of all systems within the TANPF  independently  or  in  a  given  combination  including control  systems,  electrical  and  all  process  units.  Process  units shall  either  be  tested  with  water  or  with  the  actual  fluid  for operation.  

Page 21: Nitrat de Amonio

 

39 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

All units may require cleaning prior  to actual  testing. All waste developed from cleaning process will be collected and disposed off appropriately in accordance with relevant legislation and the waste management plan within the CEMP. 

5.7.4 Emissions, Discharges and Waste during Commissioning 

Atmospheric Emissions 

During blowing out of the nitric acid plant (cleaning with air) air with  small  amounts  of  dust  and  sand  will  be  emitted  to atmosphere.  More generally, all pipe work  is  likely  to be blown clean by air before being leak or pressure tested.   Although some sections may require cleaning with solvents that can  evaporate,  it  is  not  foreseen  that  significant  amounts  of solvents shall be used. 

Solid Waste 

During  commissioning  a  number  of  systems  may  be  operated outside normal operating conditions that may result in the need to  replace  consumable  parts  of  the  systems  more  frequently than during nominal operation. For example  the oil unit of  the turbo  set  in  the  NA  plant  will  be  cleaned  by  circulating  oil through  the  oil  filter.  The  cartridges  of  the  oil  filter  will  be changed when  these  filters  are  spent. The  spent  cartridges  are non hazardous wastes and will be disposed of appropriately  in accordance with relevant legislation and the waste management plan within the CEMP. 

Liquid Waste 

Some flow lines within the TANPF will be cleaned with water or water  with  chemicals.  For  example,  the  process  gas  cooler system of the NA plant will be boiled out with water and some chemicals.   In most cases the spent water will be sent accordingly to either the  contaminated or  clean  surface water  ponds.  If  spent water contains  a  significant  amount  of  special  compounds  (oil  for example)  it shall be treated as special waste,  the procedure for which  shall  be  clearly  stated  in  the  waste  management  plan prior to commissioning.   The water used for leak testing and/or pressure testing will also be sent to either the contaminated or clean surface water ponds. Any  contaminated  materials  will  be  sent  offsite  to  licensed contractors for treatment and disposal as required.  Some  machinery  may  require  exceptional  oil  purging  during commissioning.    The  resulting  liquid  waste  shall  be  treated accordingly.  Procedure  shall  be  clearly  stated  in  the  waste management plan prior to commissioning. 

Sanitary wastewater shall be collected by truck for treatment as described in Section 5.6.9. 

5.7.5 Operations 

Although  it  is  likely  to  operate  for  a  much  longer  period,  the TANPF will be designed for a minimum lifetime of 20 years.   It will have an annual uptime of 90% minus the provision of any downtime due to market reasons or other reasons that are not related to plant operations. An inter‐stage NA storage tank will allow  the  NA  plant  and  the  AN  solution  and  TAN  plants  to operate independently for up to two days. This is deemed to be adequate  in  terms  of  time,  for  plant maintenance  (e.g.  catalyst change  in  NA  plant,  necessary  cleaning  in  the  TAN  plant  etc.). When the NA plant is shutdown, the necessary steam and power to maintain the AN/TAN production will be provided by BFPL.   The  operation  will  require  60  full  time  (direct)  personnel. Certain  positions  will  be  outsourced  (eg.  in  bagging, maintenance, transport) and are not included in this figure.  

Production (Operations) Phase 

In  the  normal  production  phase  all  units  in  the  TANPF  will operate at a steady rate that is close to the nominal production rate or at  least within the minimum safe operating parameters as per the design. This will be: 

• 760 MTPD for the NA plant;  

• 965 MTPD for the AN solution plant; and 

• 915 MTPD for the TAN prilling plant.  Truck  loading  and  bagging  of  TAN  will  be  operated  to  match production levels.  Normal  operation  may  also  include  normal  maintenance  on systems, which include redundancy (for example pumps 1 out of 2).  

Start Up, Shut Down, Upset Conditions 

Scheduled  shutdowns  may  result  from  the  need  for  extra‐ordinary  repairing,  market  situation  (no  demand),  routine maintenance  or  a  combination  of  factors.  Typically,  scheduled shutdowns  shall  follow  a  given  and  safe  procedure  so  as  to minimise  the  amount  of  unrecoverable  product  within  the system,  as  well  as  minimise  the  creation  of  higher  emission levels  associated  with  shutdown  procedures  (see  Table 5.10, Table 5.11 and Table 5.12).  Unscheduled  shutdowns,  though  rare,  may  result  from  the malfunction of any given critical system within the units of  the TANPF. Malfunction is  identified as either the physical  inability of the system to perform the required task or unsafe operation.  In  either  case  the  relevant  units  shut  down  automatically according to a predetermined safe sequence.  

Page 22: Nitrat de Amonio

 

40 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Upset  conditions  may  result  from  some  perturbation  to  the system that prevents the TANPF from stabilising in nominal and steady  conditions.  Upset  conditions  may  require  special attention  and  additional  personnel  (such  as  laboratory personnel) so that steady operation can be reached again.    Start  ups  will  always  follow  a  given  procedure  and  sequence that  are  designed  to  bring  the  TANPF  to  nominal  operation status  within  a  given  timeframe,  in  a  safe  manner  and  with minimised emissions and impacts on the environment.    All  shutdown,  upset  and  start‐up  conditions  will  be  carefully monitored  by  BNPL  staff  trained  in  accordance  with  strict operating  procedures  set  out  in  TOPS  and  the  Operations Environmental Management Plan (OEMP). 

Workforce and Hours of Operation 

The TANPF will operate 24 hours per day, seven days a week.  It is  anticipated  that  the  on‐site  workforce  will  comprise  60 people, inclusive of six to eight administration staff who will be present  during  standard  daytime  working  hours.    There  will typically be two shifts, with shifts to nominally be between 7 am to 7 pm and 7 pm to 7 am. This start‐finish timing, along with all staff  being  bussed  in  and  out  of  the  TANPF  will  help  avoid potential  cumulative  impacts on  traffic on  the  congested  roads around Karratha and Dampier at peak times.   

Routine Maintenance 

Every  year  the  TANPF  will  be  stopped  for  preventive maintenance  for  approximately  one  week.  Additionally,  every half year the NA plant will be stopped for a change of the Pt/Rh catalyst.  Lighter  maintenance  work  may  also  be  performed  during scheduled or unscheduled stops of shorter time (for example air filter changes, cleaning of dryer drums etc.). 

Transport of TAN 

See Section 5.6.5. 

5.7.6 Emissions, Discharges and Waste during Operation 

The TANPF will be designed to meet statutory requirements for all emissions as a minimum. A wastewater treatment facility will be  operating  on  site  to  treat  all  wastewater  produced  by  the TANPF.  Contaminated  wastewater  will  be  evaporated  in  a contaminated  surface  water  pond,  with  sludge  removed  by licensed contractors  (as discussed above). Clean water shall be exported  back  to  the  Water  Corporation  via  a  pipeline  in accordance with approved Ministerial and licence conditions for release  of  water  to  the  Water  Corporation  return  line  (as discussed above). 

Atmospheric Emissions 

For  the NA  plant,  Nitrous  Oxide  (N2O)  and Oxides  of  Nitrogen (NOx)  will  be  continuously  emitted  to  the  atmosphere.  The former will be controlled via gas mixing and distribution to the catalytic  gauzes,  proper  raw  material  filtering,  with  further abatement by  catalytic decomposition  in  the  reactor, while  the latter will  be  controlled via  a high pressure  absorption design, use of  chilled water  in  the  tower and abatement of  the  tail gas from the catalytic reactor.   N2O  emissions  will  be  less  that  100 ppm while  NOx  emissions will  be  below  75 ppm.  In  addition  to  continuous  emissions, fugitive  emissions  of  NOx  are  also  expected  to  occur  during filling of nitric acid storage tanks and plant shutdown (venting). Fugitive emissions of NOx during filling are expected to be very low,  and  will  produce  a  maximum  of  approximately  0.04 g/s (1.5 kg/day)  of  NOx.    Tanks  will  only  breathe  NOx  during daytime, with  zero  emissions  at  night.  These  emission  sources have  been  included  in  the  dispersion model,  conservatively  as venting 0.04 g/s for all hours of the day for each tank vent.  For the AN plant continuous emissions will be emitted from one single  stack  into which a common scrubber will  exhaust all  air used  from  the  plant.  The  use  of  BAT  shall  be  reflected  in  the exhaust  air  quality  (<30 mg/Nm3  particulate  and  <50 mg/Nm3 ammonia as per EFMA Best Available Techniques 2000). 

Solid Waste 

Any spills of organic additives or coating agent from the off spec treatment unit that is expected to contain significant amounts of TAN shall be recovered and treated as special waste. The waste management  plan  (to  be  completed  prior  to  operation  and included  in  the  OEMP)  shall  describe  procedures  for management of hazardous waste in detail.  More generally  speaking, other  liquid or  solid wastes  that may result in a mixture of TAN and organic compounds shall always be treated as special waste.  For the NA plant catalysts will be collected and returned to the catalyst  manufacturer.  Spent  filter  elements  (air  etc.)  will  be collected as solid non‐hazardous, if deemed non‐hazardous.   More  generally  speaking,  normal  operation,  routine maintenance  and  replacement  of  consumables  such  as  filter elements,  pump  seals,  gaskets  etc.  will  generate  solid  non‐hazardous waste.  There will also be solid salts resulting from the operation of the contaminated surface water pond. These salts shall be collected and disposed as per legislative requirements.   Procedures  for  management  of  non‐hazardous  waste  will  be clearly  documented  in  the  waste  management  plan  (to  be incorporated into the OEMP). 

Page 23: Nitrat de Amonio

 

41 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

Liquid Waste 

The only liquid waste sources resulting from the TANPF process during normal operation are:  

• Oil residue and sludge from the heat exchangers and storage tanks will be recovered and treated as special waste. 

• Sea water blow down of 350 m3/h shall be exported back to the  Water  Corporation  in  compliance  with  the  Water Corporation’s approved Ministerial conditions for release of water to King Bay. 

• Water  collected  in  the  clean  surface  water  pond  shall  be controlled  for  pollution  and  once  water  is  deemed  of acceptable  quality,  it  shall  be  transferred  to  the  Water Corporation for further treatment.  

• Spent  oil  from machinery  shall  normally  be  sent  out  to  be treated as non‐hazardous waste. 

• Blow  down  and  draining  of  equipment  and  miscellaneous washings  that  may  contain  nitrogen  will  be  sent  to  the contaminated surface water pond.  

• Liquid  waste  from  the  laboratory  may  contain  special chemicals  that shall be  treated as special waste  (hazardous or  non‐hazardous  depending  on  the  exact  nature  of  the chemicals). 

• Sanitary  wastewaters  shall  be  collected  by  truck  for treatment, as detailed in Section 5.6.9. 

5.7.7 Decommissioning 

Decommissioning activities will involve the recovery of catalyst (platinum)  from  the  heat  exchangers  and  vessels  in  the  NA plant. The decommissioning phase will  last approximately  four to  six months with  an  average manning  level  of  20  personnel. Upon  decommissioning,  the  TANPF  is  not  considered  likely  to have  any  significant  hazardous  wastes  or  contaminated  lands. All  left  over wastes  and  contaminated material will  be  cleaned and  removed  in  accordance  with  relevant  legislation  and  a Decommissioning  Environmental Management  Plan  (DEMP)  to be developed prior to decommissioning.   Where  appropriate,  potential  impacts  from  decommissioning have  been  discussed  in  Section 8.  Specific  abandoning  and decommissioning  requirements  will  be  formulated  and discussed  with  the  relevant  state  and  federal  regulatory authorities  at  the  time  of  decommissioning.  Decommissioning, including the DEMP, will be conducted in line with the standards of the day. 

Removal of Plant Equipment 

Plant  equipment  and  piping  will  be  dismantled  and  removed and the metal recycled. 

Rehabilitation of Site 

The  Site will  be  brought  back  to  a  level  of  an  industrial  zoned area.  Prior  to  decommissioning,  a  Decommissioning  and  Final Rehabilitation Plan will be developed.   This will specify control measures which will be used to guide the management of water resources,  landforms,  revegetation  and  infrastructure  and support  facilities  during  decommissioning.    If  a  contamination issue  is  identified  before  or  during  the  closure  of  the  TANPF, specific closure actions will be included in the plan. In addition, equipment,  buildings  and  other  facilities  will  be  removed. Surface  water  ponds  will  be  emptied  and  cleaned  (with  any contaminated  waste  to  be  appropriately  removed  by  an approved  waste  contractor).  Interconnections  (piping)  to  the BFPL site will be removed. 

5.7.8 Emissions, Discharges and Waste during Decommissioning 

Atmospheric Emissions 

Some  dust  may  be  generated  during  decommissioning  due  to removal of concrete constructions and levelling of the ground.  

Solid Waste 

Potential  solid  waste  materials  that  may  be  created  during decommissioning of the TANPF are (but not limited to): 

• Insulation;  

• Cabling (copper will be recovered);  

• Piping (to be recycled); 

• Equipment (to be recycled); 

• Concrete; 

• Asphalt; 

• Rubber (belt conveyors); 

• Gaskets; 

• Prill tower skirts (fabric); and 

• Glass from windows.  Some  instruments  may  contain  radioactive  substances  and spent catalysts and other accumulated substances and these will be  handled  in  accordance with  relevant  legislation  and BNPL’s waste management plan incorporated in the DEMP. 

Liquid Waste 

Potential  solid  non‐hazardous  waste  materials  that  may  be created  during  decommissioning  of  the  TANPF  are  (but  not limited to): 

• Oil (from turbo set); and 

• Sludge (from cleaning). 

Page 24: Nitrat de Amonio

 

42 ‐   B U R R U P   N I T R A T E S   P T Y   L T D   ‐  Technical Ammonium Nitrate Production Facility Public Environmental Review – January 2010 

                    

This page intentionally blank