1 NITIN CORPORATION 402, 4 th Floor, Bezzola Commercial Complex, Sion Trombay Road, Chembur, Mumbai 400071, India. WEB :www.corponit.com E MAIL : [email protected] [email protected] FAX : +91 - 22 - 25235386 PH (O) : +91 - 22 - 25234478/67973677 THE FOLLOWING GAS FIRED POWER BARGE IS AVAILABLE FOR SALE WITH US WITH IMMEDIATE DELIVERY: 2
18

NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

Apr 14, 2018

Download

Documents

phungdieu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

1

NITIN CORPORATION

402, 4th

Floor,

Bezzola Commercial Complex,

Sion – Trombay Road,

Chembur,

Mumbai – 400071,

India.

WEB :www.corponit.com E – MAIL : [email protected]

[email protected]

FAX : +91 - 22 - 25235386

PH (O) : +91 - 22 - 25234478/67973677

THE FOLLOWING GAS FIRED POWER BARGE IS AVAILABLE FOR SALE WITH US WITH IMMEDIATE DELIVERY: 2

Page 2: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

2

Description of 220 MW Barge Mounted CCPP

Page 3: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

3

1. The Barge mounted Combined Cycle power plant having net power output of 220 MW.

2. Fuel used will be Natural Gas. Required amount of Natural gas is 1 mmscmd approximately.

3. The total fresh water requirement is approx. 1000 cu. m per day.

4. The gas turbines, OTSG’s, steam turbine and their auxiliaries are all mounted on a single floating

barge.

5. Compact Barge of size 106 M x 55 M x 6 M having a total draft of 6 M with minimum onshore

facilities required. Minimum draft 3 M is required.

6. The barge mounted combined cycle power plant (CCPP) has:

4 nos. 50.8 MW- LM6000 PC Sprint aero derivative gas turbines

4 nos. Once Through Steam Generators.

1 no 53 MW rated output steam turbine and generator. 7. Minimum onshore facilities with following major systems:

Switchyard for Power Evacuation, 415V MCC for DM Plant etc.

Fuel treatment and forwarding

Water Treatment Plant and DM plant

Fire Fighting System.

Page 4: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

4

Advantages o

Minimum land requirement of about 20 acres for offshore facilities. Foundation is not required for main plant hence reduced construction time.

Black start facility for plant start up is available.

Main plant systems supplied by reputed OEM’s like GE and ABB.

OTSG has dry running capability up to 560 Deg C which is suitable to operate in a simple-cycle mode.

Once Through Steam Generator is quick to adjust during sudden fluctuation in load.

Page 5: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

5

GAS TURBINE

Make – GE

Model: LM 6000 PC Sprint

Capacity: 50.8 MW

Installed on Barge

Gas turbine Generator is open air-cooled, synchronous type and totally enclosed

5 Stage Low Pressure Compressor – Compression ratio is 2.4:1, 14 Stage High Pressure

Compressor – Compression ratio is 12.5:1

STEAM TURBINE

Make-ABB

Installed on Barge

Capacity: 53.58 MW

40 Stage Dual Pressure Condensing type Steam Turbine

2 Pole Generator with air cooling for Stator & Rotor winding

Page 6: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

6

ONCE THROUGH STEAM GENERATOR

Make – IST, Canada

Dual Pressure OTSG installed at the exhaust of the Gas Turbine

Steam parameters : Pressure/Temperature

HP Steam : 56 Bar / 419oC

LP Steam : 4.7 Bar / 240oC

Dry Running Capability as the tubes are made of Inco alloy

CHILLERS

Used for Cooling the Gas turbine intake air for increasing the Gas turbine output

Chiller Capacity : 1210 TR

Refrigerant used is HFC134a

COMPRESSED AIR SYSTEM

3 X100% Screw Type Air Compressors with 2 x100% desiccant type dryers

Capacity : 12.7 Nm3/min and 8.64 bar g discharge pressure

Page 7: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

7

Plant Electrical system (Barge Mounted) Power is generated at 11 KV and Evacuated at 220 KV

2 Nos. of Step-up transformer 11KV /220KV ( 1 each for 2 Gas turbines) and 1 Step-up transformer for Steam turbine

2 Nos. of Unit Auxiliary transformers for stepping down from 11KV to 6.6 KV for running Plant auxiliaries

4 Nos. of Step-down transformers called Auxiliary Transformers for stepping down the 6.6KV to 415V

Other Plant Facilities Demineralization Plant: Demineralization plant (DM plant) produces de-mineralized water for

generating steam in OTSG.

Cooling Water System: Cooling Water System suitable for river/sea water which can be connected to Closed Circuit Cooling Water system onshore if required.

Fire Protection and Fire Detection System The plant fire protection system will consist of the following:

Water Hydrant system (Consisting of six fire water pumps out of which 2 are diesel engine driven

and 1 Barge mounted emergency Fire pump (diesel driven)) - High Velocity Water Spray System (HVWS) System - Carbon Dioxide Flooding System - Portable Fire extinguishers (Water type, Foam type, CO2 gas type, Dry Chemical Powder type

extinguishers). - Fire detection and alarm system.

Page 8: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

8

Barge Mounted Power Plant

Curves

Note:

• These are typical curves for Barge Mounted Power Plant before conversion to sprint version. • These Curves are for liquid fuel firing.

Page 9: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

9

Correction Parameter for Ambient Pressure

Page 10: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

10

GT Heat Rate Correction Factor vs. Ambient Temperature, Humidity

Page 11: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

11

GT Power Correction Factor vs. Ambient Temperature, Humidity

Page 12: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

12

Barge Mounted Power Plant

Photographs

Page 13: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

13

Barge moored at its location

Page 14: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

14

Barge -Ready to be towed to the mooring location

Page 15: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

15

Barge Plant Loaded on to Mother Vessel

Page 16: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These

16

Barge Being Tugged to Mooring Location by Tugs

after Unloading from Mother Vessel

Page 17: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These
Page 18: NITIN CORPORATION th - corponit.com€¦ · Black start facility for plant start up is available. ... 40 Stage Dual Pressure Condensing type Steam Turbine ... Curves Note: • These