THE UNIVERSITY of TEXAS SYSTEM OFFICE of FACILITIES PLANNING and CONSTRUCTION Nine Universities, Six Health Institutions, Unlimited Possibilities. 302-642 Naveen Jindal School of Management, Phase II The University of Texas at Dallas Executive Summary Report Project Description $25 million addition to the School of Management building, including classrooms, a trading lab, staff & faculty offices, computer labs, and other instructional space. The ground floor level includes a programmed space for a future Jason's Deli. The new design includes a central courtyard facing north and elevated bridge connections to the existing School of Management building. Careful management of project buy-out and contingency resulted in build-out of all previously scheduled shell space and complete building occupancy by the end users. Project Information Project Status: Active Project Delivery Method: Construction Manager at Risk CIP Project Type: New Gross and Assignable Square Feet: GSF: 107,445 ASF: 69,497 "44 Initiative: Project: Yes Phase and Estimated % Complete: Warranty - 75% OFPC RPM, SPM, PM, RCM, IM: Salcher, Lund, Head, Yauger, Connolly Architecture Firm: SHW Group Construction Firm: The Beck Group Project Budget Construction Services: $ 23,426,207 at $ 218 / GSF Total Project Cost: $ 27,500,000 at $ 256 / GSF Project Funding Permanent University Fund Bonds $ 5,000,000 Revenue Financing System Bonds $ 20,000,000 Unexpended Plant Fund $ 2,500,000 Project Schedule BOR/Chancellor DD Approval 11/14/2012 Issue NTP - Construction 05/31/2013 Achieve Substantial Completion 08/04/2014 Achieve Operational Occupancy 08/25/2014 Project Remarks 1.) Substantial Completion Acceptance achieved on August 4, 2014 - 6 weeks early. 2.) Landscaping, irrigation and site paving acheived on August 27, 2014. 3.) Alternates for 2nd Level Bridge and 4th Level shell space build out - SCA on 10/6/2014. 4.) Final Completion acceptance acheived on October 30, 2014. 5.) Final Audit report received in April 2015 - contractor negotiation completed 6.) Final Change Order executed on April 16, 2015. 7.) Final Contractor Pau Application #18 submitted in April 2015. Board Approvals BOR DD Approval: 11/14/12. THECB Approval: 12/12/12. Updated By Vince Yauger - RCM / PM II on 05/08/2015 Report Date: 05/26/2015
1

Nine Universities, Six Health Institutions, Unlimited Possibilities. 302-642 Naveen ... · 2015. 5. 26. · 1.) Substantial Completion Acceptance achieved on August 4, 2014 - 6 weeks

Sep 17, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Nine Universities, Six Health Institutions, Unlimited Possibilities. 302-642 Naveen ... · 2015. 5. 26. · 1.) Substantial Completion Acceptance achieved on August 4, 2014 - 6 weeks

THE UNIVERSITY of TEXAS SYSTEM OFFICE of FACILITIES PLANNING and CONSTRUCTIONNine Universities, Six Health Institutions, Unlimited Possibilities.

302-642 Naveen Jindal School of Management, Phase IIThe University of Texas at Dallas Executive Summary ReportProject Description

$25 million addition to the School of Management building, including classrooms, a trading lab, staff & faculty offices, computer labs, and other instructional space. The ground floor level includes a programmed space for a future Jason's Deli. The new design includes a central courtyard facing north and elevated bridge connections to theexisting School of Management building. Careful management of project buy-out and contingency resulted in build-out of all previously scheduled shell space and complete building occupancy by the end users.

Project InformationProject Status: Active

Project Delivery Method: Construction Manager at Risk

CIP Project Type: New

Gross and Assignable Square Feet: GSF: 107,445 ASF: 69,497

"44 Initiative: Project: Yes

Phase and Estimated % Complete: Warranty - 75%

OFPC RPM, SPM, PM, RCM, IM: Salcher, Lund, Head, Yauger, Connolly

Architecture Firm: SHW Group

Construction Firm: The Beck Group

Project BudgetConstruction Services: $ 23,426,207 at $ 218 / GSF

Total Project Cost: $ 27,500,000 at $ 256 / GSF

Project FundingPermanent University Fund Bonds $ 5,000,000

Revenue Financing System Bonds $ 20,000,000

Unexpended Plant Fund $ 2,500,000

Project ScheduleBOR/Chancellor DD Approval 11/14/2012

Issue NTP - Construction 05/31/2013

Achieve Substantial Completion 08/04/2014

Achieve Operational Occupancy 08/25/2014

Project Remarks1.) Substantial Completion Acceptance achieved on August 4, 2014 - 6 weeks early.2.) Landscaping, irrigation and site paving acheived on August 27, 2014.3.) Alternates for 2nd Level Bridge and 4th Level shell space build out - SCA on 10/6/2014.4.) Final Completion acceptance acheived on October 30, 2014.5.) Final Audit report received in April 2015 - contractor negotiation completed6.) Final Change Order executed on April 16, 2015.7.) Final Contractor Pau Application #18 submitted in April 2015.

Board ApprovalsBOR DD Approval: 11/14/12.THECB Approval: 12/12/12.

Updated By Vince Yauger - RCM / PM II on 05/08/2015 Report Date: 05/26/2015