Consultancy Services as Independent Engineer during Operation & Maintenance of 4-lane divided carriageway facility of Tambaram – Tindivanam Section of NH-45 (Km 28/000 to 121/000), Tindivanam to Ulundurpet Section of NH- 45 (VI-A) (Km 121/0 to 192/25in the State of Tamil Nadu under BOT basis (Package 2A) Independent Engineer L.N. MALVIYA INFRA PROJECTS PVT LTD Executive Summary MONTHLY PROGRESS REPORT FOR THE MONTH OF: MARCH, 2017
23
Embed
nhai.org.innhai.org.in/spw/IEReport/MPR - March - 17 (tt).docx · Web viewAll project facilities like wayside amenities, truck lay byes including attending repairs to illumination,
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Consultancy Services as Independent Engineer during Operation & Maintenance of 4-lane divided carriageway facility of Tambaram – Tindivanam Section of NH-45 (Km
28/000 to 121/000), Tindivanam to Ulundurpet Section of NH-45 (VI-A) (Km 121/0 to 192/25in the State of Tamil Nadu under BOT basis (Package 2A)
Independent Engineer L.N. MALVIYA INFRA PROJECTS PVT LTD
Executive Summary
MONTHLY PROGRESS REPORT
FOR THE MONTH OF: MARCH, 2017
1.1 Summary of Current Month’s Progress: Nil
Maintenance activities like cleaning of carriage way, cleaning of drains, removal of garbage, repairing of sign boards, repairing or replacement of damaged metallic crash barriers, pedestrian guard rails, kerb, etc are in progress.
Accident victims have been rescued through ERP (Emergency Response Protocol), intimating to the nearest police and ambulances and in coordination with hospitals.
All project facilities like wayside amenities, truck lay byes including attending repairs to illumination, landscaping, water supply, drainage, waste disposal system, litterbins, and toilets have been maintained properly.
Round the clock patrolling is being done for surveillance of the ROW in respect of the Project / Project Facilities.
Maintenance of illuminations Toll plazas, Truck lay byes, Rest rooms, Bus shelters, Major junctions is in progress.
Maintenance of bus bays, truck lay byes, rest rooms, toll plazas, toll plaza buildings, etc is in progress.
Replacing of dead / missing plants, watering, manuring, etc. in progress for median / avenue plantation.
Repair to the damaged portions of lined drains is in progress.
Cleaning of vents of culverts and bridges is in progress.
Encroachments are being removed periodically at service roads and ROW areas.
Cleaning of lined drains and toe drains are in progress.
Guard post fixing and painting is in progress in high embankment.
Rectification of earthen shoulder is in progress.
Trimming median plants in median is in progress.
Replacement of damaged pedestrian grills is in progress.
Cutting and trimming of grass and weeds in the median and ROW is in progress.
Replacing of missed / damaged cluster boards, sign boards, etc. is in progress.
Numbering and replacing of missed / damaged HM / KM stones are in progress.
Milling of damaged BC surface is in progress.
Inlaying of BC over the milled surface is in progress.
Current Issues & Recommended Actions by IE:
1.2 Critical Issues & Action Log
1.2.1 Pending Issues & Action Log
SNoIssue
DescriptionType
Ongoing/ New
Issue/ Resolved
ConcernedAuthority
Chainage(s) affected due to the issue
Length affected
(km)Action(s) taken till now Action(s) suggested by the IE
Expected date/ Actual Date for resolving issue
1
2
3
1.3.1 Salient Features of Project
Project Name Strengthening of existing 4 lanes from Ch. 28.000 to Ch. 67.000 & Widening to 4 lanes from Ch. 67.000 to Ch. 121.000 of NH – 45 in the State of Tamil Nadu, BOT (ANNUITY) PROJECT
NH No. (New/ Old) NH-45
Scheme/ Phase
Mode of the Execution (BOT Toll/ BOT Annuity/ EPC/ HAM/ Item Rate/ Others)
BOT Annuity
No. of Lanes/ Configuration 6
Length of the Project (in Km) 93.00
Total Project Cost (in Cr)
No. of Bypasses (Name of Town, Length)
No. of Major Bridges (Number and Location) Minor – 15 Nos. , Major – 2 Nos
No. of Toll Plazas (Number and Location) 12 laned at Km 52/800 , 10 laned at Km 103/250
No. of Fly Overs (Number and Location) 56/1 & 61/1