2 © M+W Group M+W U.S., Inc. NFX Delay Analysis Report Critical Status: >25D Delay Overall duration affected Caution Status: >5D Delay <25D Delay Controlled Status: On Schedule LE Controll LE On Sc
5

NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM Scheduling Consultants Yellow 2 Reason for Deviation (Caution) Delays in Trestle Piping

Mar 05, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM Scheduling Consultants Yellow 2 Reason for Deviation (Caution) Delays in Trestle Piping

2 © M+W GroupM+W U.S., Inc.

NFX Delay Analysis Report

Critical Status:• >25D Delay

• Overall duration affected

Caution Status:• >5D Delay

• <25D Delay

Controlled Status:• On ScheduleSAMPLESAMPLESAMPLEControlled Status:SAMPLEControlled Status:SAMPLE•SAMPLE• On ScheduleSAMPLEOn Schedule

Page 2: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM Scheduling Consultants Yellow 2 Reason for Deviation (Caution) Delays in Trestle Piping

3 © M+W GroupM+W U.S., Inc.

Mechanical Trestle Piping

SAMPLESAMPLE

Page 3: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM Scheduling Consultants Yellow 2 Reason for Deviation (Caution) Delays in Trestle Piping

4 © M+W GroupM+W U.S., Inc.

P6 Summary – Pipe Trestle Delay Impact

SAMPLE

Page 4: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM Scheduling Consultants Yellow 2 Reason for Deviation (Caution) Delays in Trestle Piping

5 © M+W GroupM+W U.S., Inc.

P6 Summary – Pipe Trestle Delay Impact

SAMPLESAMPLE

Page 5: NFX Schedule Delay Analysis 21DEC11.ppt [Read-Only] · Waffle Slab Schedule SAMPLE. HSE CPM Scheduling Consultants Yellow 2 Reason for Deviation (Caution) Delays in Trestle Piping

6 © M+W GroupM+W U.S., Inc.

Waffle Slab Schedule

SAMPLE