NEXUS Capabilities and Experience Deepwater, Shallow Water and Topsides This document presents an overview of Nexus Deepwater Engineering Inc., its capabilities, experience and global offices that are providing world class engineering services in the area of Subsea and Topsides Production Systems 2013 Created by Nexus Global Marketing Team Nexus Deepwater Engineering Inc., 1/17/2013
19
Embed
NEXUS Capabilities and Experience - · PDF fileNEXUS Capabilities and Experience ... Chevron Agbami was West Africa ... ASME pressure vessel codes by releasing a new Shell DEP
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
NEXUS Capabilities
and Experience Deepwater, Shallow Water and Topsides
This document presents an overview of Nexus Deepwater Engineering Inc., its
capabilities, experience and global offices that are providing world class
engineering services in the area of Subsea and Topsides Production Systems
The company has been expanding its portfolio by providing Project Management and
Project Engineering expertise…
SUBSEA
SURF
• Umbilical
• Riser
• Flowlines
CONTROL
SYSTEM
SUBSEA
HARDWARE
MARINE
TERMINALSTOPSIDE
STRUCTURES
FRONT END
ENGINEERING
7 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
4 NEXUS EXPERTISE - PROJECTS
PROJECT
NAME/LOCATI
ON
CLIENT PROJECT HIGHLIGHTS STATUS
Kanowit KAKG-A
pre-
commissioning,
commissioning
and start-up
PCSB/PETRA/
JPK
Provision of Hook-up and Commissioning work for KASS
Project at KAKG-A Platform. Nexus was involved in writing
the topside subsea production control system pre-commission,
commissioning and black-start up procedures. Furthermore,
Nexus was selected to lead the platform teams in the pre-
commissioning phase.
●Safety Instrumented System integration between MCS and
Subsea ESD/PSD
●Master Control Station powering and start-up
●Electrical Power Unit power-up and start-up
●Chemical Injection Unit start-up and commissioning
●Hydraulic Power Unit start-up and testing
●Topside Umbilical Termination Unit (TUTU) testing
Ongoing
Kanowit KAKG-A
pre-
commissioning,
commissioning
and start-up
PCSB/PETRA/
JPK
Nexus was selected by PETRONAS and PETRA to provide a
hydraulic flushing unit that is being used on the platform for
flushing control lines to maintain NAS Class 6 level
cleanliness
Ongoing
Structural Design
and SACS analysis
Project
AXON/
AmerCable
(USA)
Detail Structural design based on a workable structural
configuration in place with the telescopic crane as part of the
cage. The incorporation of the crane shall be up to the top
pedestal. The design of structural support for the cage system
will be included (structural integrity of the cantilever deck will
not be considered as part of the design scope).
Ongoing
Pressure Vessel
Engineering
Design Review
Project
Shell (USA)/
Metarock
Nexus was selected by Shell to provide its Professional
Engineering Licensing in evaluating the design of eighteen
(18) pressure vessels. A comprehensive calculation package
was created and Stamped for each vessel. ASME VII was used
as a criterion for comparison.
Completed
2012
8 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
Subsea Training PCSB/JPK
Nexus was selected by PETRONAS (PCSB) to provide
training on:
●Level 2, Subsea Front End Engineering (FEED) training
●Level 2, Subsea Umbilical and Subsea Distribution System
training
Nexus created presentation material, animations, workshop,
assessment exam and trainer's manual for each module
Ongoing
Patricia Water
Injection System Murphy
JP Kenny Malaysia was awarded the Patricia and Serendah
Pipeline and Subsea Pre-FEED study for a Water Injection
System. Based on Patricia Gas Production draw-down by
2013, Murphy wanted a feasibility study that would
introduce two Water Injection Wells that would allow for
increased production. Processed water is pumped from 13km
to the Water Injectors; whereas, the control system is located
1km away on the Patricia Platform. Nexus provided:
● The subsea control system (MCS, EPU, TUTA, Umbilical,
SUTA and Flying Leads) ranges from simple direct
hydraulics to complex MUX systems.
● Developed a conceptual study report that examined an
array of field architectures, using proven technologies.
● A Cost Analysis was provided as part of the study to
ensure that CAPEX and OPEX are optimized.
COMPLETED
2011
9 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
Subsea Control
System Pre-
commissioning
Woodside
(AUS)
JP Kenny Malaysia was requested by Woodside Australia to
provide pre-commissioning Subsea Control System Test
Leadership at Keppel Shipyard Singapore. Nexus was
contracted to play a lead role in representing Woodside to
successfully pre-commission the MCS, EPU, HPU and ESD
system; including testing of Control System Lines on the
OKHA FPSO. An extensive testing program was reviewed,
with daily readiness reviews, interfacing with SBM and
implementation of control system.
COMPLETED
2011
Liwan Umbilical
System CNOOC
Technip Malaysia was contracted by COOEC to perform the
conceptual and detailed engineering for the Liwan 3-1, Block
29/26 Field Development. Technip contracted NEXUS to
develop a feasibility study of Umbilical, Umbilical
Installation and possible utilization of Subsea System SSIV.
ISO13628-5 was used as a bench mark to provide a
customized report.
COMPLETED
2010
PROD Tool Testing BP
JP Kenny Malaysia was requested by BP United Kingdom to
provide technical expertise to support its new Seismic Tool
Technology for the Shendiz Caspian Project (AzSPU). Nexus
was screened and selected by BP to oversee the qualification
of its new PROD technology in Brisbane Australia.
Extensive seismic testing and drilling tool functionalities
were tested to ensure product integrity and reliability.
COMPLETED
2010
SSIV Control System
Design (TGT)
Petro
Vietnam
JP Kenny Malaysia was contracted by Petro Vietnam to
provide pipelines and subsea control system FEED / detailed
design engineering. TGT Field Development required
expertise that would guide TGT, Hong Long JOC and Petro
Vietnam with a subsea controls solution. NEXUS team
started out by creating an Interface Management Tool to
identify technical and contractual gaps. Then the team set out
through a series of studies, detailed reports, data sheets and
vendor product reviews to provide a topside-to-subsea SSIV
control system that was located on the Bumi Armada FPSO.
COMPLETED
2010
10 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
Gumusut-Kakap Shell
Gumusut-Kakap is a deepwater field located in Sarawak
Malaysian waters. JP Kenny Malaysia was awarded the
SIFOE contract by Shell Malaysia to put an umbrella team
that will pull in global expertise to successfully deliver the
project. NEXUS was one of the global experts selected and
seconded to Shell. The scope of work was related to Subsea
Control System, Manifold System and IWOCS/CWOR
systems in a lead role. Well over 100 documents were
reviewed and approved:
● FAT and EFAT Testing of IWOCS HMI was conducted in
Norway Kongsberg
● EFAT testing of IWOCS and CWOR System including the
EDP / LRP breakaway system were tested and approved
(Johor Bahru Malaysia)
●Production, WI and GI Manifold testing; including control
system testing was conducted and approved in Lumut
Malaysia
● HAZOP and HAZID's for IWOCS and Control Systems
were conducted in Shell's KL Deepwater Office
COMPLETED
2010
Festoon System BP
A new Festoon design was required by BP in the Gulf of
Mexico that would meet the stringent standards - harsh
Arctic environment. Nexus provided the design verification
package, including a detailed design study that enabled EMI
to successfully quality, manufacture, test and operate a
Festoon System on the Parker Drilling Rig.
COMPLETED
2008
11 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
Hydraulic Power
Unit Development Chevron
Agbami was West Africa (Nigeria) deepwater project. A total
of four (4) Test Hydraulic Power Units (THPU) were
designed, manufactured and tested in Houston Texas. The
HPU manufacturer experienced some challenges when DNV
discovered that some of the tubing "markings" were hard to
verify. Nexus conducted an onsite investigation and provided
its P.E.Stampings on a calculation package. This design
verification document would serve to ensure that tubing
pressure integrity was per the 1:4 burst ratio.
COMPLETED
2006
Pressure Vessel
Standardization Shell
Shell Geological Group in Houston Texas implemented
ASME pressure vessel codes by releasing a new Shell DEP
standard. Pressure Vessels at Shell facilities for Soil Sampling
were closely examined and a complete design verification
package with detailed calculations was provided; with P.E.
Stampings. The package was approved by Shell Netherlands
and was regarded a bench mark document.
COMPLETED
2005
5 PROJECT PROFILES
PETRONAS
Project: KANOWIT
Client: PETRA
Location: Kumang Cluster (Shallow Water)
Scope:
Pre-commissioning, Commissioning and Start-
up
Duration 8 Months (Ongoing)
Project Value USD 1/2 Million
Phases 1 2 3 4 5
Conceptual Pre-FEED FEED Execute Commissioning
Scope of Work and Services
12 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
This project engaged our team in developing detailed procedures for pre-commissioning, commissioning and start-up of the KASS 1 and KASS 2 subsea wells for the Kanowit Project. The Subsea Production Control pre-commissioning involved the SIS, MCS, EPU, HPU, TUTU and CIU; including a post umbilical Hook-up procedure. Our team has been on the KAKG platform leading this project.
13 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
AXON
Project: Platform Festoon Cage System
Client: AXON
Location: TLP (GoM)
Scope: Detail Design
Duration 8 weeks
Project Value USD 125,000
Phases 1 2 3 4 5
Conceptual Pre-FEED FEED
Detail
Design Operate
Scope of Work and Services
Detail Structural design based on a workable structural configuration. Design and Analysis of Festoon System structure on TLP using SACS. The structure has been designed for dynamic loading resulting from land transportation, vessel transportation (using Noble Denton Criteria) and platform dynamics.
14 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
MURPHY OIL
Project: SERENDAH, PATRICIA, SOUTH ACIS (SPSA)
Client: Murphy Sarawak Oil Co Ltd (MURPHY)
Location: Blocks SK309 and SK311
Scope: Conceptual & Pre-FEED Design Study for Subsea Water Injection System
Duration 4 months
Project Value RM 1,200,000
Phases 1 2 3 4 5
Conceptual Pre-FEED FEED Execute Operate
Scope of Work and Services
The scope of this preliminary design report is evaluate an array of subsea tie-back configurations for two (2) water injection Trees located within a 1km radius of PT-SA (Patricia Platform). The subsea control system (SCS) is to be located on the PT-SA platform, providing the required subsea electro-hydraulic controls. Moreover, 6-inch flow-line(s) approximately 13km long, shall supply treated water from WP-PA to the two PT-IA water injection wells. The following key drivers provide the net value (NV) in terms of CAPEX and OPEX: 1. Subsea Christmas Hardware 2. Subsea Control System. 3. Flow Lines. 4. Testing. 5. Installation, Hook-up and Commissioning.
15 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
SHELL F29
Project: F14 / F29
Client: Shell Sabah Oil, Malaysia
Location: F14 and F29 Fields
Scope: Conceptual & Pre-FEED Subsea Production Control System
Duration Ongoing
Project Value RM 900,000
Phases 1 2 3 4 5
Conceptual Pre-FEED FEED Execute Operate
Scope of Work and Services
The scope of work was to develop conceptual/pre-FEED studies that would set the pace for developing a Subsea Production Control System for successfully operating F29 Well. The following conceptual studies were carried out: 1. Field Layout and Architecture 2. Subsea Control System Philosophy (MCS, EPU, HPU, TUTA) 3. Subsea Start-up and Shutdown Philosophy 4. Umbilical and Flying Lead Installation Scope of Work (Umbilical, SUTA) 5. Subsea Interface Management 6. Subsea Operability and HAZOP 7. Topsides to Subsea Interfacing
16 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
WOODSIDE
Project: CWLH Project
Client: Woodside Australia
Location: Cossack Wanaea Lambert Hermes Fields
Scope: Pre-commissioning of Subsea Production Control System
Duration 8-Weeks
Project Value RM 475,000
Phases 1 2 3 4 5
Conceptual
Pre-
FEED FEED Execute Commissioning
Scope of Work and Services
Subsea Production Control System pre-commissioning was carried out. The MCS, EPU, HPU, TUTA and ESD system were integrated to function along with the OKHA FPSO Distributed Control System (DCS) and IPS. An extensive testing program was implemented, with daily readiness reviews, continuous interfacing with SBM and rectification of all onsite hardware operational issues.
17 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
COOEC
Project: LIWAN 3-1
Client: COOEC
Location: Block 29/26
Scope: FEED Study
Duration 8-Weeks
Project Value RM 120,000
Phases 1 2 3 4 5
Conceptual Pre-FEED FEED Execute Operate
Scope of Work and Services
This was a FEED study for the Liwan 3-1, Block 29/26 Shallow Field Development. Studies were conducted to understand the impact of SSIV and Subsea Umbilical System suitable for the life of the project.
18 CONTROLLED COPY - 2013
Powered by People, Steered by Safety TM
SHELL
Project: GUMUSUT-KAKAP
Client: Shell Malaysia
Location: Deepwater Field
Scope: Execute Phase: SCS, IWOCS, Manifolds
Duration 2.5yrs
Project Value
USD
1,000,000
Phases 1 2 3 4 5
Conceptual Pre-FEED FEED Execute Operate
Scope of Work and Services
This was a challenging project that required training of Local Content, overview of various Subsea Vendors, Interface Management with Shell Malaysia and Shell USA to ensure that the FMC IWOCS, CWOR and Manifold Systems were manufactured and tested to Shell DEP's. A brand new HMI design was implemented for the IWOCS system that was extensively tested in Norway. The HPU was built in Stavanger Norway and the system tested in Johor Bahru. The manifolds were manufactured in Lumut Malaysia. All testing programs were lead by our team.