Page 1: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

Today’s topics 1.  Milton Keynes – Planned and Modern

2.  MK Broadband Delivery Programme

3.  Challenges Ahead

Navin Sankersingh Broadband Delivery Programme

Milton Keynes Council

15 Nov 2011

Page 2: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

Milton Keynes – Planned and Modern •  Birth of MK (1967)

•  The Blue print – Grids, Roundabouts and Open Space (1970s, 80s, 90s)

•  Modern Telecommunication Infrastructure (1970s)

•  More Growth – 1750 homes per year and 1.5 jobs created per home (2000s - today)

“…telecommunications meant that the old idea of a city as a concentric cluster was out of date and

that cities which enabled people to travel around them readily would be the thing of the future achieving "community without propinquity" for residents…”

Melvin M Webber US Architect commenting on Milton Keynes

Page 3: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

Milton Keynes – Modern and Digital •  Digital Infrastructure Strategy (2010)

•  BT’s Fibre to the Premises trial (2010)

•  BDUK and MK Broadband Survey (2011)

•  Corporate Priority (2011)

•  Broadband Stakeholder Group (2011)…and more to do!

The MK Vision: “To make Milton Keynes a truly Smart City with world class communications, scalable infrastructure and technology all of which underpins strong economic growth, healthy lifestyles and inclusion at all

levels.” Cllr David Hopkins

Portfolio Holder for Broadband, MKC

Digital Strategic Visions UK leadership

Ubiquitous coverage

Competitive market

Future-proof infrastructure

High take-up of digital services

Page 4: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

MK Broadband Delivery Programme •  Delivering projects and initiatives •  Member’s and public expectations

•  Not prescriptive…Reactive and bespoke

•  Documentation, Benefits, Risks and Issues…and a Comms Plan!

•  Broadband Matrix (Programme Tool?)

Page 5: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

MK Broadband Matrix – The Visibility ACCESS 2009 2011 2013 2015 2017

Standard Broadband <50% 70% 90% 100% 100%

Next Generation Broadband <10% 65% 75% 90% 97%

Mobile Broadband <10% 50% 75% 100% 100%

TAKE UP Standard Broadband <35% 50% 70% 85% 95%

Next Generation Broadband <5% 10% 25% 60% 80%

Mobile Broadband <5% 10% 40% 75% 85%

Jeremy Hunt and BDUK National and Local

targets

FttP trial - >11,000 premises FttC – c. 50,000 premises

OfCom ranked MK 194th out of 200 for having 29.7% of premises with

speeds below 2Mbps

Data is not a true reflection of what exists

Page 6: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

MK Broadband Matrix – The Reality ACCESS 2009 2011 2013 2015 2017

Standard Broadband <50% 70% 90% 100% 100%

Next Generation Broadband <10% 65% 75% 90% 97%

Mobile Broadband <10% 50% 75% 100% 100%

TAKE UP Standard Broadband <35% 50% 70% 85% 95%

Next Generation Broadband <5% 10% 25% 60% 80%

Mobile Broadband <5% 10% 40% 75% 85%

Setting the baseline • Validity of data • Technology mix

Setting future targets • Setting realistic targets • What are the costs and benefits for moving targets

Data is not a true reflection of what exists

We All Like Maps!!!

Page 7: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

MK Broadband Matrix – The Benefits ACCESS 2009 2011 2013 2015 2017

Standard Broadband <50% 70% 90% 100% 100%

Next Generation Broadband <10% 65% 75% 90% 97%

Mobile Broadband <10% 50% 75% 100% 100%

TAKE UP Standard Broadband <35% 50% 70% 85% 95%

Next Generation Broadband <5% 10% 25% 60% 80%

Mobile Broadband <5% 10% 40% 75% 85%

Data is not a true reflection of what exists

Direct Council Savings • Less publication/consultations • E-Procurement • Video conferencing • Work space reduction

Tangible Benefits • Direct Investment • Smart Homes/Tech • Job creation (IT-Tech)

Intangible Benefits • GVA • Crime reduction • Health • Well being • Education • …. • ….

Page 8: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

MK Broadband Matrix – The Costs ACCESS 2009 2011 2013 2015 2017

Standard Broadband <50% 70% 90% 100% 100%

Next Generation Broadband <10% 65% 75% 90% 97%

Mobile Broadband <10% 50% 75% 100% 100%

TAKE UP Standard Broadband <35% 50% 70% 85% 95%

Next Generation Broadband <5% 10% 25% 60% 80%

Mobile Broadband <5% 10% 40% 75% 85%

Data is not a true reflection of what exists

Access to Infrastructure • Direct funding • Technical/Staff resources • Consultancy

Take Up • Demand Stimulation • Demand registration • Broadband Surveys • Campaigning and awareness

Would the Benefits exceed the Costs? How much will it cost to move xx% to yy%...and what value of benefits can be derived from that move.

Page 9: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

Challenges Ahead •  Programme Development

–  Governance –  Visibility –  Cost Benefit analysis and

Value for Money

•  Strategic Fit –  Other services –  Private Public Partnerships

•  Communications, communications, Communications

–  Public awareness –  Visibility

Page 10: NextGen 2011 Workshop Navin Sankersingh MILTON KEYNES

Milton Keynes Broadband Story

Thank you…

…and enjoy the rest of Next Gen 11

Navin Sankersingh Broadband Delivery Programme

Milton Keynes Council