New Resource Implementation &
Market Modeling
Resource Interconnection Fair
February 24, 2016
© Copyright 2016 California ISO
Page 2
Topics
• Discuss the New Resource Implementation (NRI) process.
– Structure and timeline for any resource required to or electing to
participate in the CAISO commercial market.
– Review requirements to incorporate projects into the ISO energy
market (Full Network Model)
– Including all expansions, like increasing MW outputs after study
processes are complete, or changing fuel mixes.
• Review requirements for Qualifying Facilities (QFs) and
conversions with expiring agreements.
© Copyright 2016 California ISO
Page 3
Interconnection Process Map
• The New Resource Implementation (NRI) process ensures that all
ISO requirements are completed:
– For initial synchronization, or
– To declare that a resource for commercial operation
– QF and other types of conversions
• Resources seeking wholesale market participation, but not required
to complete the ISO interconnection process, will start with NRI
processes. Examples could include:
– Distribution-connected resources,
– QF and other types of conversions
You are here
© Copyright 2016 California ISO
Page 4
Modeling and Contracts Implementation Group
MPAI
EDAS NRI
ERMMCI
FNM
Energy ManagementOperations Outage Planning Outage Coordination
Operational Readiness
Congestion RightsTransmission PlanningMeter Data Acquisition VER Forecasting
Queue Management Regulatory Contract Management
EDAS:
Energy Data Acquisition Systems
ERM:
Energy Resource Management
FNM:
Full Network Model
MPAI:
Market Participant Asset Implementation
NRI:
New Resource Implementation
© Copyright 2016 California ISO
Page 5
Function of the Bucket and File naming System
• Buckets represent a group of required submittals
– Buckets represent NRI checklist items that must be accepted
(not merely received) by the respective bucket due date
– Buckets dates are derived by working backward from the sync,
QF completion, or conversion date
– Email reminders are sent if a bucket deliverables have not been
accepted
• File Naming (of email attachments)
– Filenames are specifically designed for automated identification
– Ensure files are routed to the appropriate business unit for
reviews and acceptabnce
– Automatically “checks off” the bucket item when accepted.
© Copyright 2016 California ISO
Page 6
Tips for success: NRI document submission
• Review the NRI Guide and Checklist
• Start the NRI process early and submit documents before
bucket dates
• Include your CAISO Project number (e.g. 16GEN1234)
• One project per email
– Multiple attachments per email per project are okay
• Email sender must be listed on the Project Details Form
• Follow the file naming convention in the NRI Guide
• Please read the email responses from NRI
• We are here to help - ask questions!
© Copyright 2016 California ISO
Page 7
Live, learn, and love your buckets.
Accurate documents submitted
well ahead of bucket deadline:
Inaccurate documents
submitted at the last minute
without reviewing requirements
in advance of submission:
© Copyright 2016 California ISO
Page 8
Buckets timeline and recent process changes
• NRI deliverables are collected in 6 buckets
• As of Feb. 24, 2016, the number of buckets shrank, however:
– More deliverables are associated with Bucket 1, and
– Bucket 1 now collects what used to be collected in Buckets 1 & 2
© Copyright 2016 California ISO
Page 9
Getting Started
• First step of the NRI process:
– Submit a Project Details Form no less than 7 months in advance
of your estimated initial sync, QF, or conversion date
• Your project will be assigned a NRI project number
– Example: “16GEN1234”
• Use the Project Details Form to update:
– Project Description
– Initial Sync, QF, or conversion date
– Email addresses (to designate recipient of project progress
reports and to allow an authorized user to submit documentation
to NRI)
© Copyright 2016 California ISO
Page 10
Bucket 1: Full Network Model Preparation
• Deliverables are required to:
– Create a Market Resource ID
• Essential for participation in the ISO market;
– Satisfy requirements for Direct Telemetry (if applicable).
• Bucket 1 items include:
– Copy of executed two-party Interconnection Agreement
– Issued For Construction (IFC), single-line, & three-line drawings
– Communication Block Diagram,
– Network Application information,
– Other itesm (See NRI checklist and guide for complete listing)
• For wind projects only:
– Submit Site Information document and Topographical map
© Copyright 2016 California ISO
Page 11
Bucket 2: Regulatory Contracts, Forecasting
Information and Model Testing
• Initiate the applicable ISO Regulatory Contracts
– The type of contracts required for a project depends on the
project type (New resource, QF, Dynamic, etc.).
– Email [email protected] for questions about
specific contract types.
• Submit the initial Generator Resource Data Template (GRDT)
– Resource characteristics recorded in the GRDT are necessary
for preliminary modeling of the resource.
• Meter Configuration Worksheet
– For Initial set up the meter(s) in the meter polling system
• For solar projects only
– Submit Site Information document and Topographical map
© Copyright 2016 California ISO
Page 12
Bucket 3: Market Preparation
• Bucket 3 Deliverables:
– Regulatory contracts fully executed
– Final GRDT submitted
– The Interconnection Customer (IC) submits a copy of the SC
Selection Letter
– The SC signs the SC Acceptance Letter, routes to the IC, and the
IC submits
• A resource cannot synchronize or participate in the ISO markets
without an SC association.
© Copyright 2016 California ISO
Page 13
Bucket 3: Market Preparation (cont.)
• Bucket 3 Deliverables (cont):
– Control & Protection documentation
• If directly connected to CAISO transmission (projects with an
ISO Queue Number)
– Final Meter and Remote Intelligent Gateway (RIG) requirements:
• Pre-testing confirmed,
• Schedule end-to-end test with CAISO
• Submit signed security agreement(s)
© Copyright 2016 California ISO
Page 14
Bucket 4: Trial Operations Approval, or a Resource
Requesting Sync, QF Transition or Conversion
For New Construction For QF or Conversions
Buckets 1-3 are completed Buckets 1-3 are completed
Testing Completed Testing completed
Must provide connected utility approval letter IC and SC coordinate transition of settlement data
WebOMS Outage for test energy
Send NRI Request to Sync Email with subject line in
specific format: e.g. 14GEN1234 Request for Initial
Synchronization
Send NRI Request to Sync email with subject line in
specific format: e.g. Request for QF Conversion for
(Project Name) 14GEN1234
Telemetry error free for 72 hours
Final Metering Documents & Meter Data Validation
Certificate of Compliance issued by ISO
Still to do: Complete Buckets 5 and 6 Hurray! You’re Done with NRI…
© Copyright 2016 California ISO
Page 15
Bucket 5: Trial Operations (After Sync & Before COD)
• During Trial Operations:
– SCs must follow Operating Procedure 5320
– Metering and telemetry data are monitored to ensure data quality
meets CAISO standards
• 72 uninterrupted hours of error-free telemetry required
• Final metering documents are reviewed and accepted, and
validation is completed.
– Then, a Certificate of Compliance will be issued.
• Trial Operations biggest show stoppers:
– Final metering documentation issues
– MET station problems
© Copyright 2016 California ISO
Page 16
Bucket 6: Commercial Operation Date (COD) or
Commercial Operation for Markets (COM)
Commercial Operations Date (COD) Commercial Operation for Markets (COM)
IC: Request COD IC: Request COM
IC: Sends email to NRI requesting COD. Email
subject line in specific format. e.g. COD Request
Approval for [Project Name] 14GEN12
IC: Sends email to NRI requesting COM and
accompanies request with COM implementation plan.
Email subject line in specific format. e.g. COM
Request Approval for [Project Name] 14GEN1234
SC: follow Operating Procedure 5320 SC: follow Operating Procedure 5320
ISO: 72 hours monitoring of metering and telemetry
data ensure data quality meets CAISO standards.
ISO: 72 hours monitoring of metering and telemetry
data ensure data quality meets CAISO standards.
ISO: Internal business units confirm that the market,
operational readiness, real-time and the UDC or PTO
is ready.
ISO: Internal business units confirm that the market,
operational readiness, real-time and the UDC or PTO
is ready.
NRI: sends an email to the IC that provides a
declaration date for the commercial operations date.
NRI: will send an email to the IC that provides a
declaration date for the first commercial operations
for market.
Process for declaring commercial operation after Trial
Operations is complete:
© Copyright 2016 California ISO
Page 17
Bucket 6: Commercial Operation Date (COD) or
Commercial Operation for Markets (COM)
Commercial Operations Date (COD) Commercial Operation for Markets (COM)
No equivalent action for COD IC Actions, for each declaration:
1. Attach and email a COM declaration letter before
9am for same day declaration, or for a later date,
but no sooner than the date stated in the ISO
email.
2. If changed, attach an updated COM plan to the
same email.
No equivalent action for COD SC: Updates WebOMS outage by following Operating
Procedure 5320.
No equivalent action for COD NRI: sends an email confirming the increase.
No equivalent action for CODThis process is repeated until you’ve reached the full
COD amount.
© Copyright 2016 California ISO
Page 18
Bucket 6: Commercial Operation Date (COD) and
Commercial Operation for Markets (COM)
Commercial Operations Date (COD) Commercial Operation for Markets (COM)
NRI: No futher action required NRI: No futher action required
IC Action: Attach and email a COD declaration letter
before 9am for same day declaration, but no sooner
than the date stated in the email above.
IC Action: Attach and email a COD declaration letter
before 9am for same day declaration, but no sooner
than the date stated in the email above.
NRI: sends an email confirming the declaration NRI: sends an email confirming the declaration
Hurray you’re done with NRI!!!! Hurray you’re done with NRI!!!!
© Copyright 2016 California ISO
Page 19
Recent or upcoming changes to the NRI Process
• Revisions to Bucket System filing dates (effective Feb 24,
2016. See earlier slide)
• Meter Site Verification Sheet (MSVS)
• RIMS5 POC and User Provisioning
• RIMS5 user interface (late summer 2016)
• Project Details Form (Version 9)
• Updated NRI Guide, Checklist and Website
© Copyright 2016 California ISO
Page 20
• New Resource Implementation webpage: http://www.caiso.com/participate/Pages/NewResourceImplementation/Default.aspx
• NRI Checklist: http://www.caiso.com/Documents/NewResourceImplementationChecklist.xls
• NRI Guide: http://www.caiso.com/Documents/NewResourceImplementationGuide.doc
• Project Details Form: http://www.caiso.com/participate/Pages/NewResourceImplementation/Default.aspx
Resources – NRI Checklist and Guide
© Copyright 2016 California ISO
Page 21
Thank you!
If you have any further questions regarding the NRI process,
please send them to [email protected]