New Nuclear Deployment Virgil C. Summer Nuclear Station

Page 2: New Nuclear Deployment Virgil C. Summer Nuclear Station

Activities at the Site

2

• Worlds largest derrick

(crane) in use

• Training on simulators

• Completed CV lower bowl

• Welding U2 CV rings

• Switchyard – energized

• Receiving CA-20

submodules

• Erecting cooling towers

• Assembling condensers

• Poured >30,000 cu yds

NSR concrete per unit

• Poured U2 turbine bldg

basemat

• Placing U3 mud mat

• Unit 2 FNC complete

Page 3: New Nuclear Deployment Virgil C. Summer Nuclear Station

Construction 2012 Milestones

3

• Second Quarter

– Set CR-10

– Module welding continues

– Install unit 3 water proof membrane

• Third & Fourth Quarter

– Set Unit 2 Lower containment Vessel head

– Set CA-20

– Pour unit 3 basemat

Page 4: New Nuclear Deployment Virgil C. Summer Nuclear Station

Other NND Stuff

• Received NPDES permit

• Ops initial Accreditation by NANT

• CB&I acquires Shaw

• Toshiba now 87% owner of Westinghouse

• Westinghouse new CEO Danny Roderick

• Initial licensed operator class started

• Duke still involved with Santee on ownership

Page 5: New Nuclear Deployment Virgil C. Summer Nuclear Station

Forming- No Concrete placed March 2012

Dental Concrete April 2012

Vapor Barrier

Mud mat

| Unit 2 Nuclear Island

Mud mat July 2012

Rebar Cage February 2013

SCANA | Investor Presentation | 5

Page 6: New Nuclear Deployment Virgil C. Summer Nuclear Station

Unit 2 NI Basemat South End 2/9/2013 6

Page 7: New Nuclear Deployment Virgil C. Summer Nuclear Station

Unit 2 NI Shield Building 12/7/12 7

Page 8: New Nuclear Deployment Virgil C. Summer Nuclear Station

Unit 2 NI Basemat North End 2/9/13 8

Page 9: New Nuclear Deployment Virgil C. Summer Nuclear Station

9

Start of FNC Pour

Page 10: New Nuclear Deployment Virgil C. Summer Nuclear Station

10

The Whole 9 Yards

Concrete Pumper

Page 11: New Nuclear Deployment Virgil C. Summer Nuclear Station

11

CV Area

Page 12: New Nuclear Deployment Virgil C. Summer Nuclear Station

12

Poured for 50+ Consecutive Hours

Page 13: New Nuclear Deployment Virgil C. Summer Nuclear Station

13

Turbine Building

Nearing End of FNC Pour

Page 14: New Nuclear Deployment Virgil C. Summer Nuclear Station

Unit 3 Nuclear Island 1/31/2013 14

Page 15: New Nuclear Deployment Virgil C. Summer Nuclear Station

NI Basemat Issue

• One sump & two elevator sumps require additional 6” rebar

• Adds little concrete to 6800 cubic foot basemat.

• < 1% of 32,000 sq ft surface affected

CV

Aux Bldg

Page 16: New Nuclear Deployment Virgil C. Summer Nuclear Station

16

| Sanmen Unit 1 in China

Fourth Quarter 2012 | Earnings Conference Call | 16 © 2013 Sanmen Nuclear Power Company Ltd.

Containment Vessel

Page 17: New Nuclear Deployment Virgil C. Summer Nuclear Station

Top Head Ring 3

Ring 2 Ring 1 Bottom head

| Containment Vessel

17

Page 18: New Nuclear Deployment Virgil C. Summer Nuclear Station

| Unit 2 Containment Vessel Fabrication

18

Page 19: New Nuclear Deployment Virgil C. Summer Nuclear Station

Unit 2 Turbine Island 1/31/2013 19

Page 20: New Nuclear Deployment Virgil C. Summer Nuclear Station

| Cooling Towers

20 SCANA | Investor Presentation |

2A Mechanical Draft Cooling Tower

Page 21: New Nuclear Deployment Virgil C. Summer Nuclear Station

Cooling Tower 2A 2/9/13 21

Page 22: New Nuclear Deployment Virgil C. Summer Nuclear Station

Unit 2 Condenser 1/31/13 22

Page 23: New Nuclear Deployment Virgil C. Summer Nuclear Station

| Limited Scope Simulator

23

Page 24: New Nuclear Deployment Virgil C. Summer Nuclear Station

V.C. Summer 2 & 3 Equipment Fabrication

U2 Integrated Head Package Fit-up Integrated Head Package Lift Rig

24 Premier Technologies; Blackfoot, Idaho

Page 25: New Nuclear Deployment Virgil C. Summer Nuclear Station

Doosan Manufacturing Update

25

Unit 2 RV-Ready to Ship

Hydro test Complete for Unit 2A SG Upper internal welding of Final Vessel for Unit 2B SG

Page 26: New Nuclear Deployment Virgil C. Summer Nuclear Station

Mangiarotti Manufacturing Update

26

CMT – Unit 3 Upper Pedals ACC – Unit 2 – Tanks 1 & 2

CMT – Unit 2 Tanks 1 & 2 ACC – Unit 3 - Tank 2 – Shell to Lower Crown

Page 27: New Nuclear Deployment Virgil C. Summer Nuclear Station

Generator Rotor

Low Pressure “B” Turbine –

Prep for Blade Assembly

Low Pressure “A” Turbine

27

| Toshiba, Keihin - Japan

Page 28: New Nuclear Deployment Virgil C. Summer Nuclear Station

$1.514 $2.025

$1.261 $0.968 $0.935

$-

$1

$2

$3

$4

$5

$6

$7

$8

Order No. 2009-104(A)

Order No. 2010-12

Order No. 2011-345

Order No. 2012-884

Projected @ 12/31/12

Capital Cost, 2007 Dollars Escalation AFUDC

$6.313

$6.875

| New Nuclear Projected Cost (in billions)

$5.787 $5.698 $5.755

28

Note: Reflects new nuclear projected costs as filed February 2013 in BLRA Quarterly Report

$600M Lower