-
Churn Creek Bottom Flood Risk Reduction Reconnaissance Study
Shasta County
Prepared for:
Western Shasta Resource Conservation District 6270 Parallel
Road
Anderson, CA 96007
Prepared by:
Pacific Hydrologic Incorporated 1062 Market Street
Redding, CA 96001
Norman S. Braithwaite
March 7, 2019
-
Churn Creek Bottom Flood Risk Reduction Reconnaissance Study
Introduction: The reach of Churn Creek from the mouth to Churn
Creek Road (between South Bonnyview Road and Rancho Road), locally
known as Churn Creek Bottom, is subject to flooding on a relatively
frequent basis. The Western Shasta Resource Conservation District
(RCD) has assisted flood prone property owners to reduce flood risk
by removing invasive vegetation in and adjacent to the Churn Creek
channel thus increasing the flood carrying capacity of the channel.
Although this project has reduced flood risk to some degree, the
level of flood risk is still high and the RCD believes additional
projects including further vegetation management and physical
modifications may be of benefit in reducing flood risk to an
acceptable level. Figure 1 identifies the study area on the current
effective FEMA Flood Insurance Rate Map (FIRM). This study has been
funded by the FEMA Cooperating Technical Partners (CTP) Program,
contract EMF-2017-CA-00009. Above Churn Creek Bottom, Churn Creek
drains a basin of 33.4-square miles ranging in elevation from
approximately 460-feet at the upper end of Churn Creek Bottom to
over 2000-feet on hills adjacent to Shasta Lake. Mean annual
precipitation in the basin is reported to be 48-inches by the USGS.
Land use in the basin consists mostly of urban development in the
City of Redding and Shasta Lake City with some rural residential
and undeveloped lands outside of the cities and on steep ground in
the headwaters. City of Redding design standards have prevented
development during the past 25-years from increasing the peak flow
in Churn Creek, a standard more stringent than the “rule of
reasonableness” establishing the standard of care for development
in California. Vegetation in undeveloped areas consists primarily
of chaparral. Many flood studies have been conducted within the
Churn Creek basin in support of specific developments and for
planning purposes. Two of these studies, the FEMA Flood Insurance
Study (FIS) and the City of Redding City-Wide Master Storm Drain
Study, address the entire basin and are of significance to the
current study. Within Churn Creek Bottom, Churn Creek has a well
defined meandering channel that is generally choked with non-native
vegetation except where vegetation is being managed. A vegetation
management program has been established for the Churn Creek channel
from a point approximately ½-mile downstream of the middle Churn
Creek Road crossing (near Green Acres Drive) to the north Churn
Creek Road crossing (off South Bonnyview) after several flood
events inundated farm land and structures in the vicinity of Green
Acres Drive. Downstream of Meadowview Drive, the 100-year flood
peak flow is generally contained within the active, vegetation
choked channel. This reach of channel has incised since
construction of Shasta Dam due to water surface elevations in the
Sacramento River being maintained at artificially low elevations
during times of high flow in Churn Creek. Knowledge of channel
changes since the survey supporting the FEMA FIS including upstream
propagation of incision and potential sedimentation (aggradation)
in the upper reaches of Churn Creek within Churn Creek Bottom are
of interest and have been addressed in this study. Since the
ultimate goal of this project is to reduce flood risk and revise
the published FEMA FIS and FIRM, this study has been prepared
consistent with FEMA requirements for map revisions. The
1
-
FEMA process generally consists of obtaining the original FEMA
backwater model data set (current effective backwater model),
rerunning the model data set in the current version of the original
model program (duplicate effective backwater model) including
recalibration to match the published FEMA 100-year flood (base
flood) profile if necessary, and updating data to represent current
conditions (corrected or current condition backwater model). The
current effective FEMA FIS and FIRM were developed based upon a US
Army Corps of Engineers’ HEC-RAS linear steady state backwater
model. A two dimensional (2D) dynamic backwater model is required
for this study. Therefore, as part of this study, a linear steady
state duplicate effective backwater model was prepared before
converting to a dynamic 2D model and rerunning to produce a dynamic
2D duplicate effective backwater model. Subsequent to preparation
of the duplicate effective backwater models and prior to evaluation
of alternatives, data in the dynamic 2D duplicate effective
backwater model data was modified to represent the current
condition. After completion of the current condition 2D backwater
model, candidate flood risk reduction alternatives identified below
were developed and in some cases evaluated using the dynamic 2D
backwater model. These alternatives are described in greater detail
later in this report.
Extend vegetation management downstream to the mouth of Churn
Creek Develop off-channel detention at a location upstream of Churn
Creek Bottom Construct a flood relief channel conveying Churn Creek
flood flow to the Sacramento
River Construct a flood relief channel paralleling Churn Creek
Construct a channel conveyance improvement (widen Churn Creek
channel)
Other candidate alternatives including removal of a berm
encroaching within the 100-year floodplain upstream of Knighton
Road and construction of set back levees have not been evaluated in
this analysis. Based on the results of the vegetation management
alternative, no significant reduction in flood risk is believed to
be associated with removal of the berm. The set back levee
alternative was eliminated due to high costs associated with
procurement of easements through private property and the fact that
this alternative will increase flood risk downstream of the levees.
Flood Hydrologic Analysis: Flooding in Churn Creek Bottom occurs as
a result of large storm events, primarily cloudburst or nested
cloudburst events now referred to as stationary convergence events,
over the Churn Creek drainage basin. Developed in support of the
City-Wide Master Storm Drain Study of 1993, the City of Redding
maintains a rainfall-runoff model on the Corps of Engineers’ HEC-1
platform that is up to date and sufficient for evaluation of
existing conditions in Churn Creek Bottom. A cursory review of
flood hydrology in Churn Creek indicates that the FEMA FIS has
relied upon the City of Redding rainfall-runoff model and that
rainfall-runoff model results are consistent with the 100-year
flood peak flow estimate by the USGS Streamstats web application
(regional methodology) when considering the presence of urban
development within the basin. All backwater model runs therefore
relied on the FEMA published peak flows with the unsteady duplicate
effective backwater models employing hypothetical partial flood
hydrographs consisting of flow ramping up to the published FEMA
100-year flood flows over a period of 20-hours followed by constant
flow at the published FEMA values over a period of 10-hours thus
simulating steady state peak flow. Flood peak flows relied upon by
FEMA for the Churn Creek FIS do not account for
2
-
loss of flow from the channel due to overflow leaving the Churn
Creek basin over Interstate 5 or for attenuation of peak flow by
storage of flood water in the floodplain. The upstream boundary
conditions for the current condition model runs consisted of
100-year flood hydrographs from the City of Redding rainfall-runoff
model scaled to have the peak flows match the published FEMA
100-year flood flows. Loss of flood water from the basin and
storage of flood water within the overbank floodplains are
accounted for by the 2D backwater model. As such the peak flow in
the Churn Creek channel is attenuated in the downstream direction
by the 2D model. Simulated steady state and dynamic flood
hydrographs for the upstream model boundary conditions are shown on
Figures 2 and 3. The flood frequency relationship for Churn Creek
at the upstream backwater model boundary (COR rainfall-runoff model
“C1898” above Linden Drain) is identified in Figure 4. Duplicate
Effective Backwater Models: Two duplicate effective backwater
models were prepared for this study, one being a linear steady
state backwater model (Duplicate Corrected) and the other being a
linear dynamic backwater model (Duplicate Unsteady) in preparation
of adding 2D domains representing shallow overbank flood flow.
Unfortunately, simply re-running the current effective backwater
model data set did not produce a flood profile meeting the FEMA
standard for a duplicate effective backwater model (Duplicate
Received). The reasons for substantial differences in 100-year
flood profiles may be due to changes in HEC-RAS computational
routines or more likely, the actual data set relied upon for
preparation of the FIS was not submitted and saved by FEMA.
Substantial differences in flood profiles were found at and
upstream of bridges. Reasonable modifications of the Current
Effective data set were therefore employed as necessary to produce
the linear steady state Duplicate Corrected backwater model.
Changes to the original data set included the following:
Meadowview Bridge – Convert computation method from pressure
& weir to energy Change pier widths from 4.0-feet to
4.2-feet
Middle Bridge – Convert computation method from pressure &
weir to energy X-sec 25968 – Define ineffective area in left
overbank X-sec 25968 – Define ineffective area in left overbank
X-sec 25984 – Revise encroachment limits
A comparison of the Current Effective, Duplicate Received, and
Duplicate Corrected flood profiles is presented on Figures 5 and 6.
In preparation of converting the model to employ overbank flow
computations within two dimensional (2D) domains, a dynamic
duplicate effective (Duplicate Unsteady) backwater model was
prepared by employing the following steps:
Add horizontal coordinates for cross-section points to produce a
georeferenced duplicate backwater model (Duplicate Georeferenced).
Locations of georeferenced cross-sections are shown on Figure
7.
3
-
Replace steady state flow data with flow hydrographs and run the
model in dynamic mode (Duplicate Unsteady)
A comparison of the Current Effective and Duplicate Unsteady
flood profiles is presented in Figure 8. Some further adjustment of
the duplicate unsteady model will be required prior to any FEMA map
revision due to differences in water surface elevations exceeding
0.5-feet at one location. Channel Morphology: As a result of
controlled flows in the Sacramento River during times of local
flooding, the Churn Creek channel has incised from the mouth to
near Meadowview Drive. According to residents in the vicinity of
Green Acres Drive, sediment accumulation was observed in the
channel prior to implementation of the vegetation management
program. Given these recognized and potentially continuing
processes, a backwater model run was prepared to identify the
significance of continuing geomorphic processes. This model run was
developed by replacing channel data in a copy of the Duplicate
Georeferenced model employing the FEMA data set (2004±) with new
field surveyed channel data collected at the FEMA cross-section
locations. No other data from the Duplicate Georeferenced model was
modified so as not to contaminate the ability of the Morphology
Check model results. Both model runs were linear steady state runs.
Data and results of the Morphology Check model were compared to the
duplicate effective model run to determine the magnitude and
significance of changes to the channel since the FEMA survey. A
comparison of flood profiles from the Morphology Check and
Duplicate Georeferenced backwater models is presented in Figure 9.
Comparisons of channel geometry at cross-sections selected to have
a spacing of approximately 5000-feet are shown on Figures 10
through 15. If the geometry of Churn Creek has experienced
substantial changes since the FEMA survey, the trend would be
reflected by an increase or decrease in the 100-year flood profile
over a number of cross-sections. Both the flood profiles and the
selected cross-sections tend to support an argument that the
channel has not experienced significant geomorphic changes since
the FEMA cross-section survey. Any sediment which may have
accumulated in the reach of Churn Creek near Green Acres Drive
prior to implementing the vegetation management program has since
been conveyed downstream. Current Condition Backwater Model: After
completion of the duplicate effective models and morphology check,
two current condition backwater models were prepared by adding 2D
domains east and west of the Churn Creek channel, revising top of
bank stations, revising channel roughness coefficients, adding the
Knighton Road bridge (not in FEMA current effective model), and
adding internal and external boundary conditions to the 2D domains
(Current 2D). Top of bank stations were moved to reflect the active
portion of the Churn Creek channel rather than the flood channel.
Adjacent to the 2D flow domains, overbank areas were defined as
ineffective flow areas on the linear domain cross-sections to
prevent the backwater model from double accounting for flow in the
overbank areas. Channel roughness coefficients employed in the
current condition backwater model were based on field observations
of factors contributing to overall channel roughness and ranged
from 0.035 to 0.050. Roughness coefficients within the 2D domains
were based on 2011 National Land Cover Database (2011 NCLD) using
roughness coefficients suggested in the HEC-RAS v5 2D Modeling
User’s Manual. External boundary conditions were established
between Interstate 5 (I-5) and the Sacramento River
4
-
at two locations where overflow in the west 2D domain overflow
during the most probable 100-year flood will to overtop I-5. The
normal depth method with a hydraulic slope of 0.005 was used for
all external boundary conditions. Internal boundary conditions were
defined for the crowns of Smith Road, Knighton Road, and Churn
Creek Road north and south of Green Acres Road. The internal
boundary conditions were included to prevent the backwater model
from indicating flow past these road prisms unless the water
surface elevation exceeds the crown elevation. Flow over the road
prisms was computed using normal 2D computations rather than weir
equations. The Knighton Road bridge was modeled by adding a copy of
Cross-section 15593 to the model at a location 400-feet downstream
of Cross-section 15593 and adding the bridge geometry data from
as-built drawings between the two cross-sections. Unsteady flow
contraction and expansion coefficients were set to 0.1 and 0.3
respectively except in the vicinity of bridges where the unsteady
flow roughness coefficients of 0.3 and 0.5 respectively were
employed. The first current condition backwater model was run using
the simulated steady state hydrograph (Current Condition) and the
second was run using full flood hydrographs from the City of
Redding rainfall-runoff model1 (COR 100-year). A comparison of the
current condition backwater model profiles to the current effective
profile is shown on Figure 16. Differences between the current
condition flood profile and the current effective flood profile
represent differences in data between the two models including
roughness coefficients reflecting channel vegetation, the Knighton
Road bridge, and most significantly ground data representing the
overbank floodplains. Figure 17 identifies a significant floodplain
elevation difference between the FEMA current effective model and
the LiDAR terrain data used in the 2D models at cross-section
28903. Similar differences exist at other cross-sections. The COR
100-year profile is below the current condition flood profile due
to the limited volume of water represented in the COR flood peak as
opposed to an effectively unlimited volume of water available in
the simulated steady state flood hydrograph. Peak flow for both
dynamic 2D model runs is attenuated by overflow leaving the Churn
Creek basin over I-5 and by storage of flood water in the
floodplain. A comparison of peak flows along Churn Creek for the
current effective, current condition, and COR 100-year model runs
is presented in Figure 18. Dips in the peak flow followed by
increases in a downstream direction represent flow leaving the
channel as overflow then re-entering the channel. The overall
decrease in peak flow of the dynamic models represents flow lost
from the Churn Creek basin and flood water stored (delayed) in the
floodplains. The maximum extents of inundation for the two current
condition runs are presented in Figures 19 and 20. The current
condition backwater models indicate incipient overflow in the
vicinity of Green Acres Drive at a flow of approximately 7000-cfs,
a flood estimated to have a statistical recurrence of approximately
10-years.
1 The lateral inflow hydrograph was scaled such that the
magnitude of lateral inflow at the time of peak flow in Churn Creek
matched the FEMA steady state inflow.
5
-
Vegetation Management: Management of vegetation is a commonly
considered first tier approach for reducing flood risk. A
vegetation management program has been established for the Churn
Creek channel from a location approximately ½-mile downstream of
the middle Churn Creek Road crossing of Churn Creek (near Green
Acres Drive) to the upper Churn Creek Road crossing of Churn Creek
(near South Bonnyview Road). This vegetation management program has
reduced flood risk in the vicinity of Green Acres Drive but the
area remains subject to inundation on a relatively frequent basis.
From downstream of the reach for which vegetation is being managed
to the mouth of Churn Creek, however, the channel is presently
choked with vegetation. A backwater model run representing
extension of the vegetation management program to the mouth of
Churn Creek was prepared (CC2D – Vegetation) by reducing Manning’s
roughness coefficients in the channel to 0.033 from a range of
0.045 to 0.060 in order to determine the potential flood risk
benefit of extending the program to the mouth of Churn Creek. A
comparison of the 100-year flood profile for the extended
vegetation management program to the current condition 100-year
flood profile is shown on Figure 21. The comparison indicates a
substantial potential flood risk benefit downstream of the current
vegetation management reach but no significant potential flood risk
benefit along the current vegetation management reach. Upstream
Off-channel Regional Detention: Off-channel regional detention
consists of a detention basin separated from the Churn Creek
channel by a side channel weir and having a small downstream
outlet. The weir elevation is set such that flood water only enters
the detention basin when flow in the channel exceeds a design
threshold. The small downstream outlet drains keeps the detention
basin from ponding water prior to the flood (local runoff) and to
drain the detention basin after the flood. This type of detention
basin will truncate the flood peaks exceeding the design threshold
and is therefore much more efficient than conventional on channel
detention facilities. The size of the detention basin is determined
from the available hydraulic head between the upstream design
threshold water surface elevation and the downstream low flow
(1-year flood ±) water surface elevation and from the volume of
flood water in excess of the design threshold during the flood
peak. The length of the side channel weir is determined by the peak
flow to be diverted and the difference in water surface elevation
between the threshold flood profile and the maximum water surface
profile. Off-channel detention facilities can be designed as
multiple use facilities hence they can accommodate parks, community
gardens, environmental mitigations, and other uses that are not
sensitive to inundation. This study took the approach of
determining the volume of detention available in the area of low
intensity land use between the Churn Creek channel and Kids Kingdom
Park then estimating how much this volume may attenuate the Churn
Creek flood peak. The available hydraulic head was determined to be
approximately 11 feet between cross-sections 39790 and 38790 near
the up and downstream ends of the candidate detention basin area.
Without substantially encroaching in the area required by Churn
Creek to convey flood flows, the surface area available for the
detention basin was estimated to be approximately 15 acres. The
useable volume of an off-channel detention facility at this
location is therefore approximately 190 acre feet. This volume is
sufficient to truncate the 100-year flood hydrograph upstream of
Churn Creek Bottom from
6
-
12,700-cfs to 11,000-cfs. The length of the side channel weir is
estimated to be 1750-feet based on a need to divert 1700-cfs and an
elevation difference of 0.45-feet between the maximum water surface
profile and the 11000-cfs water surface profile. The low intensity
land use area on the opposite side of the Churn Creek channel
downstream of the site adjacent to Kids Kingdom Park has a similar
potential for attenuation of the flood peak. If developing both
sites as off-channel regional detention, the combined volume
available will be approximately 350 acre feet sufficient to
attenuate the 100-year flood hydrograph upstream of Churn Creek
Bottom from 12,600-cfs to 10,300-cfs. Figures 22 through 24
identify the areas available for potential off-channel regional
detention, the available hydraulic head, and the City of Redding
Churn Creek 100-year flood hydrograph with potential attenuation
identified. The estimated potential benefit of the off-channel
regional detention options at cross-section 32960 located
downstream of the upper Churn Creek Road crossing of Churn Creek
(near South Bonnyview) is identified on Figure 25 (includes local
lateral inflow). Flood Bypass to Sacramento River: At their closest
point upstream of Green Acres Drive, the Churn Creek channel is
within 1600-feet of the Sacramento River channel. Diversion of flow
from Churn Creek in excess of the incipient overflow near Green
Acres Drive (approximately 7000-cfs) to the Sacramento River can be
an effective approach to reduce flood risk in Churn Creek. The
added flow to the Sacramento River will not increase flood risk
along the Sacramento River because flow in the Sacramento River is
reduced at times of high flow in the tributaries entering the river
below Shasta Dam. Diversion of the Churn Creek flood peak to the
Sacramento River will require construction of a side channel weir
entrance structure, 2100-feet of channel or culvert including
crossings at the ACID canal and I-5, and some type of outlet
structure or erosion protection. The entrance structure will
require approximately 250-feet of side channel weir with a top
elevation approximately 3.5-feet below the 100-year flood profile
and taper to the channel or culvert entrance width. The alignment
considered for this analysis is identified on Figure 26. If an open
channel is to be considered for the bypass, the channel will
consist of two segments, one of approximately 700-feet from the
Churn Creek channel through I-5 with a slope of 0.013 and the other
of 1400-feet from the west side of I-5 to the Sacramento River with
a slope of 0.0017. The upper segment will consist of a
non-prismatic section having a 250-foot wide by 3.5-foot deep side
channel weir entrance transitioning to a 70-foot wide by 5-foot
deep downstream section. The narrow end of the upper segment will
be under Interstate-5. The lower segment will consist of an 80-foot
wide by 5-foot deep prismatic channel. Flow in the open channel
will be supercritical for the entire length with velocities
reaching 18-feet per second in the narrow portion of the upper
segment and averaging 13-feet per second in the lower segment.
Freeboard has not been included in the channel depths reported
above. If a culvert structure is to be considered for the bypass,
an entrance structure consisting of a side channel weir having a
top elevation approximately 3.5-feet below the 100-year flood
profile and a length of approximately 250-feet will be required.
The entrance structure will taper to the width and depth of the
culvert entrance at a distance approximately 100-feet downstream of
the side channel weir. The culverts should have a hydraulically
efficient entrance, be placed under the ACID canal (or pipe), and
have a uniform slope to the Sacramento River. The slope of
7
-
culverts having this configuration will be approximately 0.002
and velocities will range from 6- to 10-feet per second. The
average hydraulic slope will be approximately 0.005. Three 6’ x 20’
barrels or fourteen 6’ diameter pipes will be required to convey
the 5000-cfs flood peak between Churn Creek and the Sacramento
River. Flow in the box culverts will be supercritical. Flood Relief
Channel Parallel to Churn Creek: Unlike a flood relief channel from
Churn Creek to the Sacramento River, a flood relief channel
parallel to Churn Creek must be designed prismatic with a slope
equal to the slope of the floodplain. The alignment of the
candidate flood relief channel considered for this analysis is
shown on Figure 27. Based on Manning’s Equation, the width of the
upper segment (solid line) of channel sufficient to convey the
5000-cfs difference between the 100-year peak flow in the Churn
Creek channel and the incipient overtopping flow are identified for
a variety of depths and boundary materials in Table 4.
Table 4: Churn Creek to Churn Creek Flood Relief Channel
Geometry, Prismatic Channel
Segment Slope Manning’s n Depth1 (feet) Width (feet) Segment 1,
concrete, 4' deep 0.0019 0.011 4 89.1Segment 1, concrete, 5' deep
0.0019 0.011 5 63.9Segment 1, concrete, 6' deep 0.0019 0.011 6
49.4Segment 1, earth, clean, 4' 0.0019 0.028 4 219.3Segment 1,
earth, clean, 5' 0.0019 0.028 5 153.9Segment 1, earth, clean, 6'
0.0019 0.028 6 116.2Segment 1, earth, reeds, 4' 0.0019 0.04 4
311.1Segment 1, earth, reeds, 5' 0.0019 0.04 5 217.2Segment 1,
earth, reeds, 6' 0.0019 0.04 6 163.0
Notes: 1) Freeboard not included. The length of the upper
segment of channel is approximately 5800-feet. The lower segments,
if needed, will require similar dimensions as the upper segment.
The lengths of lower segments are approximately 1250-feet for the
middle segment and 1400-feet for the lower segment (dashed lines).
The side channel weirs at the upstream end of each segment will
have the same dimensional requirements as for the diversion from
Churn Creek to the Sacramento River. There may also be requirements
at the downstream ends of the flood relief channels to prevent
stranding of fish as flood water subsides. Channel Conveyance
Improvement: Channel conveyance improvements consist of widening
the channel to accommodate greater flow thus reducing the frequency
and magnitude of overflow. Geomorphic considerations dictate that
the conveyance improvement not deepen the channel and environmental
considerations dictate that the widening be above the water surface
elevation of some threshold flow. The edge of perennial vegetation
should be considered a lower limit of the elevation of a conveyance
improvement. Vegetation in any reach of channel having a channel
conveyance improvement will need to be managed in order for the
conveyance improvement to remain
8
-
efficient. This study has evaluated the potential requirements
and flood risk benefit of a channel conveyance improvement by
adjusting the channel width in a copy of the Current Condition CC2D
COR 100-year hydrograph model data set. The width of the channel
was increased by various factors between top of bank stations using
the adjust stations option in the HEC-RAS cross-section editor. A
factor of 1.5 or 50% increase in the width of the Churn Creek
channel was found to substantially reduce overflow in the vicinity
of Green Acres Drive. Channel widths were adjusted from just
downstream of Knighton Road (Cross-section 15273) to a point
downstream of the upper Churn Creek Road crossing of Churn Creek
(Cross-section 32154). Plots of changes in the geometry of selected
cross-sections are presented in Figures 28 and 29. Table 5
identifies the changes in channel area associated with the
increased channel width. An actual channel conveyance improvement
project (constructed widening as opposed to an assumption of a
wider channel) will require similar increases in area in order to
have similar benefits. A comparison of the 100-year flood profile
with the conveyance improvement compared to the Current Condition
CC2D COR hydrograph 100-year flood profile is presented on Figure
30. The maximum extent of inundation for the channel conveyance
improvement run is presented in Figure 30.
Table 5: Conveyance Improvement, Increases in Channel Areas
Cross-section Area (sq ft) Cross-section Area (sq ft)
32154 327 25894 568 31138 572 25563 490 30189 359 24129 318
28903 369 22273 468 28345 383 19481 533 26626 490 18480 451 26004
378 18250 481 25968 359 15593 851 25924 536 15273 845
Summary of Results: Changes to the Churn Creek channel since
publication of the current effective FEMA FIS and FIRM have not
been great enough to affect a significant change to flood risk in
Churn Creek Bottom. Evaluation of flood risk for current conditions
considering dynamic flow and loss of flood water from the basin
using a 2D modeling platform indicates flood risk in the lower
reaches of Churn Creek within Churn Creek Bottom to be as
represented by the FEMA FIS and FIRM but indicates flood risk in
the vicinity of Green Acres Drive to be greater than represented by
the FEMA FIS and FIRM. The higher flood risk for current conditions
is due to mischaracterization of floodplain ground elevations as
being lower than actual in the backwater model relied upon by FEMA
for the current effective FIS and FIRM. Of the flood risk reduction
alternatives investigated, only diversion of peak flows in Churn
Creek directly to the Sacramento River is likely to be capable of
addressing flood risk concerns in the vicinity of Green Acres Drive
on its own. Other alternatives may be used in combinations
9
-
to achieve the same goal. Descriptions of the potential flood
risk benefit of each alternative along with additional
considerations for each alternative are described below. Vegetation
Management: Extension of the vegetation management program for the
Churn Creek channel down to the mouth of Churn Creek was found to
provide no direct flood risk benefit in the vicinity of Green Acres
Drive. However, implementation of this alternative may be necessary
to prevent any increase in flood risk from near Knighton Road to
the mouth of Churn Creek associated with implementation of other
alternatives including the Churn Creek to Churn Creek flood relief
channel and the channel conveyance improvement. Both of these
alternatives will increase the peak flow in Churn Creek at their
downstream end by eliminating flood water from leaving the basin
over I-5 and by reducing storage of flood water on the floodplain.
If a vegetation management program is to be relied upon for
reduction in flood risk recognized by FEMA, the program must be
administered or overseen by a public agency and the land subject to
management must be in a vegetation management easement. Upstream
Off-Channel Detention: Although off-channel regional detention is
efficient, the area necessary for a detention basin volume
sufficient to address the flood risk concerns in the vicinity of
Green Acres Drive is not available. A reasonable assumption of the
maximum area available to implement an off-channel regional
detention basin is only sufficient to reduce peak flows in Churn
Creek to approximately 10,000-cfs. Incipient overtopping in the
vicinity of Green Acres Drive occurs when flow in the Churn Creek
channel exceeds approximately 7000-cfs. The reduction in Churn
Creek peak flow associated with implementing off-channel detention
results in a reduction in flood water leaving the basin over I-5
and a reduction in east overbank flow circumventing the Green Acres
Drive area rather than reducing peak flows near Green Acres Drive.
Off-channel detention may be used to reduce the size of flood
relief channels or channel conveyance improvements. If off-channel
detention is to be considered, the facility must be under the
ownership and jurisdiction of a local agency. Design and knowledge
of the actual flood risk benefit of off-channel detention
facilities will require preparation of a backwater model with extra
attention to detail in the vicinity of the proposed facility. The
potential benefits of off-channel detention reported here are only
rough estimates. Flood Relief Channel to Sacramento River: By
design, a flood relief channel conveying Churn Creek flows in
excess of the incipient overtopping flow of approximately 7000-cfs
near Green Acres Drive will be capable of addressing the flood risk
concerns in the vicinity of Green Acres Drive without requiring
other candidate alternatives. The reduction in flood risk will
extend downstream to the mouth of Churn Creek. In addition to the
physical requirements of a diversion channel, challenges with this
alternative include environmental concerns along both channels,
crossings of the ACID canal and I-5, and property ownership. A
reduced capacity flood relief channel may be used in conjunction
with other alternatives to address the flood risk concerns in the
vicinity of Green Acres Drive. Flood Relief Channel Parallel to
Churn Creek: Also by design, a flood relief channel conveying Churn
Creek flows in excess of the incipient overtopping flow around the
vicinity of Green Acres Drive can be capable of addressing the
flood risk concerns in the vicinity of Green Acres Drive. In
addition to eliminating overflow in the vicinity of Green Acres
Drive, the water surface elevations upstream in Churn Creek will be
reduced enough to prevent flood flow from
10
-
leaving the basin over I-5 and to prevent overflow in the east
floodplain. Consequently, the incidental flood risk benefit
associated with loss of flow from the Churn Creek basin over I-5
and storage of flood water in the floodplain under current
conditions will be eliminated resulting in higher 100-year peak
flows in the Churn Creek channel downstream of the parallel flood
relief channel project. Residential structures near Meadowview
Drive that are in the 100-year floodplain and already subject to
relatively frequent flooding will be at higher risk of flood damage
if implementing the parallel flood relief channel project without
mitigating the increased downstream flood risk. The vegetation
management alternative might be sufficient to mitigate increased
downstream flood risk associated with implementing the parallel
flood relief alternative. Channel Conveyance Improvement:
Construction of a channel conveyance improvement consisting of
widening the channel above an environmental threshold elevation can
provide a significant reduction of overflow in the vicinity of
Green Acres Drive but may not entirely eliminate overflow due to
environmental and practical considerations. The potential flood
risk benefit of a channel conveyance improvement was estimated by
increasing the existing channel width and hence channel area by
50%. Considering the environmental requirement of staying above a
threshold elevation such as may be defined by the edge of perennial
vegetation, the actual width of a conveyance improvement
representing a 50% increase in total channel area will be
approximately equal to the existing channel width (100% increase in
channel width). At this increase in width, it may be prudent to
construct the conveyance improvement on both sides of the active
channel. The existing middle Churn Creek Road bridge over Churn
Creek (near Green Acres Drive) will have to be replaced with an
appropriately longer bridge. Combined with other alternatives the
conveyance improvement alternative may be sufficient to address the
flood risk concerns near Green Acres Drive. Like the parallel flood
relief channel alternative, the channel conveyance improvement
alternative will prevent flood water from leaving the basin over
I-5 and will prevent overflow in the east floodplain thus
increasing peak flow in the Churn Creek channel downstream of the
project. The increased flood risk associated with the increased
peak flow downstream might be mitigated by implementing the
vegetation management alternative. Conclusions: A combination of
flood risk reduction alternatives may be the best approach to
address the flood risk concerns in the vicinity of Green Acres
Drive. Physical details identified by this analysis for the
alternatives may be used for preliminary cost estimates necessary
to further refine definition of candidate projects to meet the
project objectives. Recommendations: Results of this analysis may
be used to develop preliminary cost estimates of alternatives and
combinations of alternatives however confident knowledge of the
potential flood risk benefits and design details of the
alternatives and combinations of alternatives will require
additional backwater model runs representing the specific
projects.
11
-
12
With regard to any future FEMA map revision, the linear
backwater model runs prepared for this study are substantially
sufficient to meet the FEMA requirements for a map revision. Prior
to relying on the dynamic backwater model runs, the following will
need to be addressed:
1. FEMA should be consulted regarding changing the modeling
platform and flood hydrologic analysis.
2. Lateral inflow hydrographs need to be revised. The backwater
model relied upon for the current effective FEMA FIS and FIRM
included only one lateral inflow representing all contributing flow
downstream of the upstream boundary condition. This was preserved
for all linear model runs used in this study and was replaced with
only two lateral inflow hydrographs for the dynamic (City of
Redding hydrographs) model runs.
3. FEMA should be consulted regarding redefinition of the
designated floodway. At present, although theoretically possible,
computation of a designated floodway cannot always be accomplished
using a 2D backwater model.
The concept of a bypass conveying flood flow in Churn Creek to
the Sacramento River has been considered for many years. More
recently, the possibility of commercial development of the parcel
located between I-5 and the Sacramento River has been discussed.
Development of the parcel without regard to flood risk concerns
along Churn Creek will likely eliminate any opportunity to develop
what may be the most cost effective approach to reducing flood risk
along Churn Creek to an acceptable level. Negotiation with
potential developers of the property may be prudent to preserve
opportunity to reduce flood losses or possibly to develop the
Sacramento River bypass option.
-
Figure 1: FEMA FIS
-
Figure 2: Churn Creek Flood Hydrographs at Backwater Model
Boundary upstream of Churn Creek Bottom
-
Figure 3: Lateral Inflow Hydrographs at Linden Drain upstream of
Churn Creek Bottom
-
Figure 4: Churn Creek Flood Frequency Relationship at Backwater
Model Boundary upstream of Churn Creek Bottom
-
Figure 5: Comparison of Duplicate Received and Duplicate
Corrected 100-year Flood Profiles to Current Effective (Rev Encr)
Flood Profile
-
Figure 6: Detail of 100-year Flood Profiles identified in Figure
5
-
Figure 7: Locations of Georeferenced Cross-sections
-
Figure 8: Comparison of Duplicate Unsteady 100-year Flood
Profile with Current Effective (Rev Encr) Flood Profile
-
Figure 9: Comparison of Morphology Check 100-year Flood Profile
with Duplicate Georeferenced 100-year Flood Profile
-
Figure 10: Cross-section 4294 Morphology Check
Figure 11: Cross-section 10605 Morphology Check
-
Figure 12: Cross-section 14582 Morphology Check
Figure 13: Cross-section 19481 Morphology Check
-
Figure 14: Cross-section 24129 Morphology Check
Figure 15: Cross-section 30189 Morphology Check
-
Figure 16: Comparison of Current Condition 2D Simulated Steady
State and CC2D COR Hydrograph Backwater Model 100-year Flood
Profiles to Current Effective (Rev Encr) Flood Profile
-
Figure 17: Comparison of FEMA Cross-section 28903 to LiDAR
Terrain
-
Figure 18: Comparison of Current 2D Simulated Steady State and
CC2D COR Hydrograph 100-year Flood Peak Flows in Churn Creek
Channel to FEMA Current Effective 100-year Flood Peak
-
Figure 19: Area of Inundation Estimated for Current Condition
Simulated Steady State 100-year Flood
-
Figure 20: Area of Inundation Estimated for CC2D COR Hydrograph
100-year Flood
-
Figure 21: Comparison of Vegetation Management (CC2D – Veg)
100-year Flood Profile to Current Condition Simulated Steady State
Flood Profile (Both profiles computed using simulated steady state
hydrograph)
-
Figure 22: Candidate Detention Basin Locations
-
Figure 23: Approximate Hydraulic Head Available for Upper
Candidate Detention Basin Site
-
Figure 24: Approximate Potential Flood Peak Attenuation at
Candidate Detention Basin Sites
-
Figure 25: Estimated Benefit of Off Channel Regional Detention
Options at Cross-section 32960
-
Figure 26: Alignment Considered for Churn Creek to Sacramento
River Flood Relief Channel
-
Figure 27: Alignment Considered for Flood Relief Channel
Parallel to Churn Creek
-
Figure 28: Simulated Channel Conveyance Improvement,
Cross-section 18250
Figure 29: Simulated Channel Conveyance Improvement,
Cross-section 26626
-
Figure 30: Comparison of Channel Conveyance Improvement 100-year
flood profile with Current Condition CC2D COR 100-year flood
profile
-
Figure 31: Area of Inundation Estimated for Channel Conveyance
Improvement