New Brunswick Transmission & Market Issues NPCC Annual Meeting Halifax - Sept 18, 2003 Bill Marshall Director - Strategic Planning New Brunswick Power Corporation
17

New Brunswick Transmission & Market Issues

Feb 19, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: New Brunswick Transmission & Market Issues

New Brunswick Transmission & Market Issues

NPCC Annual MeetingHalifax - Sept 18, 2003

Bill MarshallDirector - Strategic PlanningNew Brunswick Power Corporation

Page 2: New Brunswick Transmission & Market Issues

Ø Market Implementation Update

Ø Resource Adequacy Concerns

Ø Maritime Market Issues

Ø International Power Line

Ø August 14 Operation

Presentation Summary

Page 3: New Brunswick Transmission & Market Issues

Ø NB Power restructuring legislationØ Separate corporations (Transco,Disco,Genco,Nucco)

Ø New ISO

Ø Wholesale & Large Industry Market opening

Ø Legislation passed but not proclaimed

Ø Original target April 1, 2003 but now set at ??????

Ø ProForma equivalent tariff Ø Sept 30, 2003

Market Implementation Update

Page 4: New Brunswick Transmission & Market Issues

Ø Maritime area will be deficient in capacity

Ø Projected by 2007

Ø Load growth continues Ø Natural gas penetration less than expected

Ø Actual growth masked by past years weather

Ø Reality was revealed last winter

Resource Adequacy Concerns

Page 5: New Brunswick Transmission & Market Issues

Winter Peak - 8:00 AM, Feb 17, 2003

Area Load 5365 MWExports 165 MWImports 30 MWNet load 5500 MWResources 6300 MW

3030

130

NM

NMNew

BrunswickPEI

NovaScotia

Maine

Québec

NewHampshire

165

45

10

Page 6: New Brunswick Transmission & Market Issues

Ø Coleson Cove and Pt Lepreau projectsØ Quality energy but no new capacity

Ø Natural gas outlook is poorØ Both availability and price

Ø Area needs new resources - From where?Ø Generation?Ø Imports?Ø Transmission?Ø Market interaction?

Resource Adequacy Concerns

Page 7: New Brunswick Transmission & Market Issues

Maritimes Market Issues

NM

NMNew

BrunswickPEI

NovaScotia

Maine

Québec

NewHampshire

Limited Transmission Access

No open access

LMP

PancakedMEPCO Tariff

Tariff Issues

No Spot Market

Page 8: New Brunswick Transmission & Market Issues

Ø Improved HQ tariffØ Detailed cost allocation study in Oct 2003Ø New application expected this year ???

Ø Improved ISO-NE tariffØ New application expected in Oct 2003Ø Improved scheduling ??Ø Remove pancaking of MEPCO & Phase II ??Ø Resolve marginal loss issue ??

External Regulatory Solutions

Page 9: New Brunswick Transmission & Market Issues

International Power Line Project

NewBrunswick

Maine

Keswick

Pt. Lepreau

Orrington

Existing Tie

Maine Yankee

Proposed 2nd Tie

Page 10: New Brunswick Transmission & Market Issues

Ø Improved market access to / from New EnglandØ 300MW export and 400MW import

Ø Improved reliability for Maritimes and MaineØ Parallel interconnectionØ Capacity benefits

Ø Increased efficiency in New Brunswick / MaineØ Loss savingsØ Improved LMP pricing

IPL Project Benefits

Page 11: New Brunswick Transmission & Market Issues

Ø NEB approval in CanadaØ Start construction by Dec 2006Ø Conditional on US project

Ø Continuing toward US approvals– Cooperation from Bangor Hydro (Emera)

Ø Finalizing the business case– Acceptable tariff required– Meetings with various stakeholders

IPL Project Status

Page 12: New Brunswick Transmission & Market Issues

Ø NE and Maritimes areas survived - How?Ø Good luck? Or Good management?

Ø Or Protection systems that worked

Ø Prior operation in MaritimesØ 3000 MW load (1600MW in NB)

Ø 500 MW export to NE

Ø 300MW export to Quebec

Aug 14, 2003 - Avoiding the Blackout

Page 13: New Brunswick Transmission & Market Issues

Ø The disturbanceØ 1500MW generation surge from NY to NE/Maritimes

– about 7-8% of total load

Ø Major frequency increase

Ø NE-NB tie reversed - 300MW import to Maritimes

– 800MW swing on 3000MW load - 25% of load

Ø NE/Maritimes separated from NY

Ø What happened in Maritimes?

Aug 14, 2003 - Avoiding the Blackout

Page 14: New Brunswick Transmission & Market Issues
Page 15: New Brunswick Transmission & Market Issues

Ø Maritime protection systems operated wellØ Automatic generation rejection - 400MW

Ø Increased HVDC export to Quebec - 100MW

Ø Governors responded - 200MW

– Pt Lepreau contributed 140MW

Ø Maritime Imbalance contribution Ø About 45% of the need (700 out of 1500MW)

Ø From 15% of the system (3000 out of 20,000MW)

Aug 14, 2003 - Avoiding the Blackout

Page 16: New Brunswick Transmission & Market Issues

Ø Maritime Area perspectiveØ Single 345kV line to Eastern Interconnection

Ø Experience “islanding” once every two years

Ø Maritime Area approach Ø Need protection systems in place and operational

ØRegular modeling and design preparation

ØRegular governor and relay systems testing

Aug 14, 2003 - Avoiding the Blackout

Page 17: New Brunswick Transmission & Market Issues

Questions?