Top Banner

of 13

Network Models CPM U9

Jun 04, 2018

Download

Documents

min_feelings
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/13/2019 Network Models CPM U9

    1/13

    Network Models CPM/PERT1. Introduction:

    # Network Models are the control technique of

    the project.

    # PERT and CPM are the network models usedfor planning, scheduling and control of the

    project.

    # PERT and CPM were originally developed in1958/59 to meet the needs of Age of Massive

    Engineering where traditional method like

    Gantt Charts were inapplicable.

  • 8/13/2019 Network Models CPM U9

    2/13

    2. Historical Background of PERT/CPM

    # PERT was created as a means to plan and

    accelerate the development of Polaris

    Ballistic Missiles.

    # The special Project office of US Navy had

    introduced PERT to plan the missile

    development as quickly as possible.

  • 8/13/2019 Network Models CPM U9

    3/13

    2. Historical Background contd

    # PERT as a planning, scheduling andcontrol technique came into existence to

    answer the following questions:

    a) What research had to be done to accomplishthe missile development and how should it

    be planned?

    b) How long would the research take place?

    c) What stages of the development and testing

    would be necessary for the missiles

    completion?

  • 8/13/2019 Network Models CPM U9

    4/13

    2. Historical Background contd

    d) How fast could the country do it?e) In summary, when could the United States

    expect to have an operational Polaris

    missile?3. Planning, Scheduling and control:

    # Planning involves listing of tasks or jobs to

    be performed; materials, equipments andmanpower requirements are analyzed and

    estimate of costs and duration for different

    jobs are made.

  • 8/13/2019 Network Models CPM U9

    5/13

    3. Planning, Scheduling and control contd..

    # Scheduling is the laying out of the actual jobs

    of the project in time order in which they

    have to be performed.

    # Control is the managerial function, which

    reviews the the difference between theschedule and actual performance.

  • 8/13/2019 Network Models CPM U9

    6/13

    4. Basic concept of PERT and CPM

    a) Events: It is starting or ending point for agroup of activities. The circles

    represent Events.

    b) Activity: It is the work required to proceedfrom one event or point to in time

    to another. Arrows represent

    activities.c) Predecessors: It is an activity which is

    required to finish to start

    next.

  • 8/13/2019 Network Models CPM U9

    7/13

    4. Basic concept of PERT and CPM contd..d) Successor: It is an activity, which can

    `be started only after thecompletion of previous

    activity.

    e) Dummy Activity: It is an activity whichdoes not consume

    time or resources.

    f. Critical Path: It is the longest path or

    sequence of connected

    activities. Its length

    determines the duration of

    the project.

  • 8/13/2019 Network Models CPM U9

    8/13

    5. Steps in PERT:

    a) Identification of different activitiesincluding dummy activities needed to

    complete the project.

    b) Identification of the sequence of the activitiesimplementation through diagram:

    1

    2

    3

    4

    6

    5

  • 8/13/2019 Network Models CPM U9

    9/13

    5. Steps in PERT contd

    c) Finalize the time requirement toaccomplish each activity. Generally two

    time estimate ( EST and LST) is

    prepared.

    d) Connect all activities in sequential order to

    form a network

  • 8/13/2019 Network Models CPM U9

    10/13

    6. PERT provides answer to the following:a) Finish time of the project

    b) Start and finish time of each individual

    activity of the project.

    c) Activities that needed to be done first before

    starting others.d) Possibilities of shifting resources from non-

    critical activities to critical activities.

    e) Activities that need concentration ofmanagement effort at one time.

    f) Uncertainty reduction in a project

  • 8/13/2019 Network Models CPM U9

    11/13

    7. PERT Conventions:

    a) Two events connectedby one activity1 2

    b) Activity A must be

    completed to start B. 21 3A B

    c) Activity A must be

    completed before tostart B and C.

    1 2

    3

    4

    A

    B

    C

    A

  • 8/13/2019 Network Models CPM U9

    12/13

    4. PERT Convintion contd

    d) Activity C can not

    be started until both A

    and B are completed

    1

    2

    3 4A

    B

    C

    e) C and D can not be

    started until both Aand B are completed.

    1

    2

    3

    4

    5

    A

    B

    C

    D

  • 8/13/2019 Network Models CPM U9

    13/13

    PERT Convention Contd

    Activities A and B must

    be completed before to

    start C. Only B must be

    completed before to

    start D.

    1

    2

    3

    4

    5

    6

    A

    B

    C

    D

    E