Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress RONALD O’ROURKE, SPECIALIST IN NAVAL AFFAIRS The DDG-51 program was initiated in the late 1970s. The DDG-51 is a multi- mission destroyer with an emphasis on air defense (which the Navy refers to as anti-air warfare, or AAW) and blue-water (mid-ocean) operations. DDG-51s, like the Navy’s 22 Ticonderoga- (CG-47) class cruisers, are equipped with the Aegis combat system, an integrated ship com- bat system named for the mythological shield that defended Zeus. CG-47s and DDG-51s consequently are often referred to as Aegis cruisers and Aegis destroyers, respectively, or collectively as Aegis ships. The Aegis system has been updated several times over the years. Existing DDG-51s (and also some CG-47s) are being modified to receive an additional capability for ballistic missile defense (BMD) operations. The first DDG-51 was procured in FY85. A total of 72 have been procured through FY15, including 62 in FY85-FY05 and 10 in FY10-16. During the period FY06-FY09, the Navy procured three Zumwalt- (DDG-1000) class destroyers (see discussion below) rather than DDG- 51s. The first DDG-51 entered service in 1991, and a total of 62 were in service as of the end of FY14. DDG-51s are built by General Dynamics Bath Iron Works (GD/ BIW) of Bath, Maine, and Ingalls Ship- building of Pascagoula, Miss., a division of Huntington Ingalls Industries (HII). The DDG-51 design has been modi- fied over time. The first 28 DDG-51s (i.e., DDGs 51 through 78) are called Flight I/II DDG-51s. Subsequent ships in the class (i.e., DDGs 79 and higher) are referred to as Flight IIA DDG-51s. The Flight IIA de- sign, first procured in FY94, implemented a significant design change that included, among other things, the addition of a he- licopter hangar. The Flight IIA design has a full load displacement of about 9,500 tons, which is similar to that of the CG-47. The Navy is implementing a pro- gram for modernizing all DDG-51s (and CG-47s) so as to maintain their mission and cost effectiveness out to the end of their projected service lives. Older CRS reports provide additional historical and background information on the DDG-51 program. Procurement of First Flight III DDG-51 Planned for FY16 The Navy wants to begin procur- ing a new version of the DDG-51 design, called the Flight III design, starting with the second of the two ships scheduled for procurement in FY16. The Flight III design Naval Readiness On March 26, Vice Chief of Naval Operations Admiral Michelle Howard testified to the House Armed Services Committee’s Subcommittee on Readiness about the Navy’s 21st-century readiness posture. Chairman Wittman, Ranking Member Bordallo and distinguished members of the House Armed Services Readiness Subcommit- tee, I appreciate the opportunity to testify on the current state of Navy readiness and the resources necessary to provide a ready Navy in the future as described in our fiscal year 2016 budget request. As we meet, the Navy and our sister services have entered a third year of fiscal uncertainty. In addition, new threats to our nation’s interests are emerging, and old tensions are surfacing. Today, it is my honor to represent all our active and reserve sailors, particularly the 41,000 sailors who are under way on ships and submarines or deployed in expeditionary roles overseas today. ey are standing the watch and are ready to meet today’s security challenges. American citizens can take great pride in the daily contribu- tions of their sons and daughters who serve in Navy units around the world. We are where it matters, when it matters, ensuring the security that underpins the global economy and respond- ing to crises. Last August, the George H.W. Bush carrier strike group, already forward present in the North Arabian Sea, quickly relocated to the North Arabian Gulf. Flying 20 to 30 combat sorties per day, this Navy-Marine Corps strike fighter team was the only coalition strike option to project power against the Islamic State of Iraq and the Levant (ISIL) from the skies over Iraq and Syria for 54 days. Similarly, USS Truxton (DDG-103) arrived in the Black Sea to establish U.S. presence and reassure allies a week after Russia invaded Crimea. In the Java Sea, USS Fort Worth (LCS-3), a littoral combat ship, and USS Sampson (DDG-102), a destroyer, were among the first to support the Indonesian-led search effort for Air Asia Flight 8501. is forward CONTINUED ON PAGE 11 ➥ CONTINUED ON PAGE 21 ➥ APRIL 07, 2015 WWW.NPEO-KMI.COM A PUBLICATION WWW.NPEO-KMI.COM 07 APR 2015 Plus: • USS MARYLAND UNDOCKS • LASER EYE PROTECTION Including: DEFENSE INNOVATIONS
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for CongressRonald o’RouRke, SpecialiSt in naval affaiRS
The DDG-51 program was initiated in
the late 1970s. The DDG-51 is a multi-
mission destroyer with an emphasis on
air defense (which the Navy refers to as
anti-air warfare, or AAW) and blue-water
(mid-ocean) operations. DDG-51s, like
the Navy’s 22 Ticonderoga- (CG-47) class
cruisers, are equipped with the Aegis
combat system, an integrated ship com-
bat system named for the mythological
shield that defended Zeus. CG-47s and
DDG-51s consequently are often referred
to as Aegis cruisers and Aegis destroyers,
respectively, or collectively as Aegis ships.
The Aegis system has been updated
several times over the years. Existing
DDG-51s (and also some CG-47s) are
being modified to receive an additional
capability for ballistic missile defense
(BMD) operations.
The first DDG-51 was procured in
FY85. A total of 72 have been procured
through FY15, including 62 in FY85-FY05
and 10 in FY10-16. During the period
FY06-FY09, the Navy procured three
Zumwalt- (DDG-1000) class destroyers
(see discussion below) rather than DDG-
51s. The first DDG-51 entered service in
1991, and a total of 62 were in service as
of the end of FY14. DDG-51s are built by
General Dynamics Bath Iron Works (GD/
BIW) of Bath, Maine, and Ingalls Ship-
building of Pascagoula, Miss., a division
of Huntington Ingalls Industries (HII).
The DDG-51 design has been modi-
fied over time. The first 28 DDG-51s (i.e.,
DDGs 51 through 78) are called Flight I/II
DDG-51s. Subsequent ships in the class
(i.e., DDGs 79 and higher) are referred to
as Flight IIA DDG-51s. The Flight IIA de-
sign, first procured in FY94, implemented
a significant design change that included,
among other things, the addition of a he-
licopter hangar. The Flight IIA design has
a full load displacement of about 9,500
tons, which is similar to that of the CG-47.
The Navy is implementing a pro-
gram for modernizing all DDG-51s (and
CG-47s) so as to maintain their mission
and cost effectiveness out to the end of
their projected service lives. Older CRS
reports provide additional historical and
background information on the DDG-51
program.
procurement of first flight iii ddG-51 planned for fY16
The Navy wants to begin procur-
ing a new version of the DDG-51 design,
called the Flight III design, starting with
the second of the two ships scheduled for
procurement in FY16. The Flight III design
Naval ReadinessOn March 26, Vice Chief of Naval Operations
Admiral Michelle Howard testified to the House Armed Services Committee’s Subcommittee on Readiness about the Navy’s 21st-century readiness posture.
Chairman Wittman, Ranking Member Bordallo and distinguished members of the House Armed Services Readiness Subcommit-tee, I appreciate the opportunity to testify on the current state of Navy readiness and the resources necessary to provide a ready Navy in the future as described in our fiscal year 2016 budget request. As we meet, the Navy and our sister services have entered a third year of fiscal uncertainty. In addition, new threats to our nation’s interests are emerging, and old tensions are surfacing. Today, it is my honor to represent all our active and reserve sailors, particularly the 41,000 sailors who are under way on ships and submarines or deployed in expeditionary roles overseas today. They are standing the watch and are ready to meet today’s security challenges. American citizens can take great pride in the daily contribu-tions of their sons and daughters who serve in Navy units around the world. We are where it matters, when it matters, ensuring the security that underpins the global economy and respond-ing to crises.
Last August, the George H.W. Bush carrier strike group, already forward present in the North Arabian Sea, quickly relocated to the North Arabian Gulf. Flying 20 to 30 combat sorties per day, this Navy-Marine Corps strike fighter team was the only coalition strike option to project power against the Islamic State of Iraq and the Levant (ISIL) from the skies over Iraq and Syria for 54 days. Similarly, USS Truxton (DDG-103) arrived in the Black Sea to establish U.S. presence and reassure allies a week after Russia invaded Crimea. In the Java Sea, USS Fort Worth (LCS-3), a littoral combat ship, and USS Sampson (DDG-102), a destroyer, were among the first to support the Indonesian-led search effort for Air Asia Flight 8501. This forward
DDG 51 Class DestroyerThe U.S. Navy has awarded funding for the construction of DDG 122,
the fiscal year 2015 Arleigh Burke-class destroyer under contract at General Dynamics Bath Iron Works, a business unit of General Dynamics. This $610.4 million contract modification fully funds this ship and was awarded in 2013 as part of a multiship competition for DDG 51 class destroyers. The total value of the five-ship contract is approximately $3.4 billion.
Fred Harris, president of Bath Iron Works, said, “This announcement al-lows us to continue efforts associated with planning and construction of DDG 122. We appreciate the leadership of Senators Collins and King and the strong support of our entire delegation in matters of national defense. We are grateful for their recognition of the contributions made by the people of BIW to the U.S. Navy’s important shipbuilding programs.”
There are currently three DDG 51 destroyers in production at Bath Iron Works, Rafael Peralta (DDG 115), Thomas Hudner (DDG 116) and Daniel Inouye (DDG 118). The shipyard began fabrication on DDG 115 in November 2011, and delivery to the Navy is scheduled for 2016. Fabrication
on DDG 116 began in November 2012, and that ship is scheduled to be delivered to the Navy in 2017. Fabrication has just begun on DDG 118, the first ship of the 2013 multiship award.
Bath Iron Works is also building the three ships in the planned three-vessel Zumwalt-class of destroyers, Zumwalt (DDG 1000), Michael Monsoor (DDG 1001) and Lyndon Johnson (DDG 1002).
The Arleigh Burke-class destroyer is a multimission combatant that offers defense against a wide range of threats, including ballistic missiles. It operates in support of carrier battle groups, surface action groups, amphibious groups and replenishment groups, providing a complete array of anti-submarine (ASW), anti-air (AAW) and anti-surface (ASUW) capabilities. Designed for survivabil-ity, the ships incorporate all-steel construction and have gas turbine propulsion. The combination of the ships’ AEGIS combat system, the Vertical Launching System, an advanced ASW system, two embarked SH-60 helicopters, advanced anti-aircraft missiles and Tomahawk anti-ship and land-attack missiles make the Arleigh Burke class the most powerful surface combatant ever put to sea.
MH-60S Seahawk Test Aircraft ContractElbit Systems of America, LLC, a subsidiary
of Elbit Systems Ltd., was awarded a contract from Science Applications International Cor-poration to install, integrate and support flight evaluations of the Elbit Color Helmet Display and Tracking System (CHDTS) on MH-60S Se-ahawk test aircraft for the U.S. Navy. The contract value, which is in an amount that is not material to Elbit Systems, will be performed over a year.
The program is part of the U.S. Navy’s MH-60 Sierra’s Improved Targeting System
for the Seahawks’ Armed Helicopter Weapon Kits. The CHDTS will provide the pilots with both night and day capability to see color flight instrument symbols on their helmet-mounted display (HMD) modules. Additionally, the line-of-sight tracking system enables the pilots to interact with the flight navigation system, improves pilot and copilot situational aware-ness, and can also be used to control pilot or copilot slewable sensor systems. The system also presents a continuously calculated weapon
impact symbol for the pilot display, thus increasing system accuracy in the employment of installed weapon systems.
“We are pleased to provide U.S. naval avia-tors the CHDTS for their aircraft,” commented Raanan Horowitz, president and CEO of Elbit Systems of America. “The CHDTS will provide pilots with improved situational awareness through enhanced optics and symbology dis-played directly on their HMDs, allowing them to keep their eyes up and out.”
APRIl 07, 2015 | 3WWW.NPEO-kMI.COM
Experts Discuss Maritime Power, International SecurityMaritime security leaders gath-
ered at U.S. Naval War College (NWC) in Newport, R.I., March 25-26, to focus global military attention on seapower during the EMC Chair Symposium, “Mari-time Power and International Security.”
Experts from the military, academia, national security, cor-porate interests, United Nations, government and nongovernmen-tal organizations took part in the two-day event, which focused on power projection, deterrence, humanitarian assistance, special operations and security and strategies.
“NWC is home to Navy thought, and Naval War College should be leading the Navy and the nation on maritime issues,” said Derek Reveron, EMC chair, professor in national security affairs and organizer of the annual event. “This conference gives us the opportunity to do that.”
The symposium was timed to coincide with the March 13 release of a new maritime strategy by the U.S. sea services titled, “A Coop-erative Strategy for 21st Century Seapower: Forward, Engaged, Ready.”
The new maritime security, released by the U.S. Navy, Marine Corps and Coast Guard, outlines maritime priorities in support of the national interest. It replaces a similar 2007 document and accounts for changes in the global security environment, new strate-gic guidance and a changed fiscal environment.
One of the areas highlighted at the symposium, humanitar-ian assistance and disaster relief, is already being explored by experts from NWC and Harvard University.
The two schools currently ex-change faculty to discuss this topic and bring two different perspec-tives to the subject.
“As the number of humanitar-ian disasters expands (some due to natural disasters, others to conflict), we can expect that increased civil-military engagement will be required to meet the life-saving needs of affected populations,” said Vincenzo Bollettino, executive director of the Harvard Humanitarian Initiative, who was a member of the Humani-tarian Assistance and Disaster Relief panel at the symposium.
“It is imperative that we begin more systematic study of
civil-military engagement, both to help guide normative discussions about civil-military interaction as well as to inform conversations related to the efficiency of the response,” he added.
Both military and civilian groups are needed to assist when large disasters happen, according to Bollettino.
“Today’s humanitarian emergencies, particularly complex emergencies that entail aspects of natural disasters and conflict, require that both military and hu-manitarian actors better train for and participate in conversations about civil-military engagement,” he said. “These conversations should be taking place in multiple fora (military, academic, humani-tarian) and in various countries.”
Another aspect of maritime power was discussed in the power projection session, where a panelist focused on the changing nature of the challenges faced by the country.
“I think the biggest challenge facing the U.S. military is to adjust to the rise of small, smart and cheap weapons systems,” said T.X. Hammes, distinguished research fellow at National
Defense University, Washington, D.C., and panelist at the sym-posium. “Poor nations and even small groups will have access to precision, long-range weapons in significant numbers. Thus our base areas, supply convoys, fuel dumps, ammo dumps, and air and sea ports will be subject to attack. We have to figure out how to deal with this type of threat.”
The symposium touches on many aspects of maritime power in just a few days. Reveron says that addressing all of these issues in a short time is not intended to solve the problems, but to serve as a platform for the experts to think about the issues that will eventu-ally lead to answers.
“This event will help me and my colleagues think through these important issues and serves as an incubator for ideas,” said Reveron.
Reveron also said one of his aims is to encourage attendees to write about maritime issues after the event and hope they incorpo-rate some of the discussion points into their own writings.
By Daniel Kuester, U.S. Naval War College Public Affairs
Ingalls Shipbuilding Awarded $604.3 million Contract to Build DDG 121
Huntington Ingalls Industries’ Ingalls Shipbuilding division has
received a $604.3 million contract modification to fund construction of
the Arleigh Burke-class (DDG 51) Aegis guided missile destroyer DDG
121 for the U.S. Navy. The ship is the third of five DDG 51 destroyers
the company was awarded in June 2013.
“The DDG 51 program has been the backbone of Ingalls
Shipbuilding for the past three decades,” said DDG 51 Program
Manager George Nungesser. “We now have a hot production line
in the shipyard where we can maintain our highly skilled shipbuild-
ing crews in the same working areas for each ship. This will allow
increased learning and provide the most efficient way to reduce cost
and schedule while building quality ships for the U.S. Navy. We have
a lot of experience and talent throughout our program, and with the
facilities to build ships simultaneously, we will continue to improve as
each ship is launched.”
The five-ship contract, part of a multiyear procurement in the DDG
51 program, allows Ingalls to build ships more efficiently by buying bulk
material and moving the skilled workforce from ship to ship. With the
contract, Ingalls will be building DDGs over the next decade.
Ingalls has delivered 28 Arleigh Burke-class destroyers to the Navy.
Destroyers currently under construction at Ingalls are John Finn (DDG
113), ralph Johnson (DDG 114), Paul Ignatius (DDG 117) and delbert
d. Black (DDG 119).
Arleigh Burke-class destroyers are highly capable, multimission
ships that can conduct a variety of operations, from peacetime pres-
ence and crisis management to sea control and power projection, all in
support of the U.S. military strategy. DDGs are capable of simultane-
ously fighting air, surface and subsurface threats. The ship contains
a myriad of offensive and defensive weapons designed to support
maritime defense needs well into the 21st century.
WWW.NPEO-kMI.COM4 | APRIl 07, 2015
USS Peleliu Decommissioned After 34 Years of ServiceHundreds of current and
former crew members, 10 previ-ous commanding officers and their family members crowded onto the flight deck of the amphibious assault ship USS Peleliu (LHA 5) to bid farewell to the “Iron Nickel” during the ship’s decommissioning ceremony at Naval Base San Diego, March 31.
Tears wet the eyes of many of the former sailors and Ma-rines in attendance as the flag was hauled down, the watch was secured, and the crew of one of the most famous ships in the U.S. Navy’s Pacific Fleet ceremoniously disem-barked the vessel for the final time.
Peleliu was named after the September 15 to November 27, 1944 Battle of Peleliu, in which 1,256 Marines gave their lives to take the island, which was being held by the Imperial Japanese Army.
Rear Admiral Marcus A. Hitchcock, the current director of Fleet and Joint Training at U.S. Fleet Forces Command, was the ship’s 18th command-
ing officer from March 2008 to September 2009 and served as the guest speaker for the ceremony.
Hitchcock talked not only about his time as commanding officer, but also about how he read many books and studied up on the ship’s namesake when he received orders to become the ship’s commanding officer. In addition, he spoke about howhe was fortunate enough to host a ship’s tour in the summer of 2009 for Marine veterans from the actual Battle of Peleliu.
“These marines had seen and done extraordinary things on a remote island called Peleliu. Like millions of their generation, they were commit-ted to keeping America free,” said Hitchcock. “They came to represent grit and determina-tion. It was fighting men like these for which this warship is named.”
Hitchcock also thanked all the plankowners and former crew members in attendance for their service to the ship over the past 34 years.
“From that first deployment onward, USS Peleliu and her crew demonstrated time and again that she always achieved the mission, to perfection, with style and in ways that had never been seen before,” said Hitch-cock. “Except on rare occasions, USS Peleliu never did it alone. She always had a teammate by her side—the U.S. Marine Corps.”
To close his remarks, Hitch-cock led the audience in three cheers to mark the grit and determination of all the sailors and marines who served on board Peleliu during her years of service.
Captain Paul C. Spedero, Peleliu’s last commanding of-ficer, read the decommissioning orders and gave the order to disembark the ship.
“From deputy chief of naval operations to commanding offi-cer, USS Peleliu, subject, decom-missioning of USS Peleliu,” read Spedero. “On 31 March, 2015, decommission USS Peleliu and transfer to the inactive reserve.
Executive officer, disembark the crew.”
During 34 years of service, Peleliu was homeported in both Long Beach and San Diego on the California coast as thou-sands of sailors and Marines called the ship home. Capable of launching a coordinated air and sea attack from one platform, Peleliu conducted 17 deployments, 178,051 flight operations, served 57,983 personnel and steamed approximately 1,011,946 nautical miles since being commissioned May 3, 1980 in Pascagoula, Miss.
After the decommissioning process is complete, Peleliu will be towed from San Diego to Hawaii to join the Navy’s reserve fleet. There, the last-of-its-class amphibious assault ship will take its place alongside its sister ship and first in class, the ex-USS Tarawa (LHA 1).
By Senior Chief Mass Com-munication Specialist (SW/AW) Donnie W. Ryan
Rear Admiral Marcus A. Hitchcock, director of fleet and joint training for U.S. Fleet Forces Command, offers three cheers during the decommissioning ceremony for the amphibious assault ship USS Peleliu (LHA 5) at Naval Base San Diego. Peleliu is being decommissioned after more than 34 years of service. After the decommissioning process is complete, Peleliu will be towed from San Diego to Pearl Harbor, Hawaii, to join the reserve fleet. (U.S. Navy photo by Mass Communication Specialist 2nd Class Antonio P. Turretto Ramos)
APRIl 07, 2015 | 5WWW.NPEO-kMI.COM
Littoral Combat Ships Contract ModificationU.S. Navy has issued a Lockheed Martin-led
industry team a contract modification for one fully funded 2015 littoral combat ship (LCS) valued at $362 million, along with $79 million in advanced procurement funding for a second ship. The balance of the second ship will be funded by December 31, 2015.
The advanced procurement dollars approved by Congress provides the funding required to maintain the cost and schedule of the final block buy option. The award also includes a priced op-tion for one additional fiscal year 2016 ship.
“We are proud to continue this partner-ship with the Navy in building the advanced Freedom-variant littoral combat ship, and we thank the Navy for maintaining the cost and schedule for the block buy,” said Joe North, vice president of Littoral Ship Systems at Lockheed Martin Mission Systems and
Training. “Thousands of people across the country contribute to this important program and will continue to do so as we transition to the new frigate upgrade in the coming years.”
The award comes as USS Freedom conducted a successful deployment to southeast Asia in 2013 and is currently operating out of her homeport in San Diego, Calif., while USS Fort Worth is deployed until 2016. USS Fort Worth is serving in the U.S. 7th Fleet to strengthen international relationships, visit more ports, engage in multire-gional naval exercises and further LCS capabilities using both manned and unmanned assets.
The contract modification is for construc-tion of LCS 21 and LCS 23, the 11th and 12th Freedom-variant ships. The first ship on this 2010 contract, the Milwaukee (LCS 5), was christened and launched in 2013, and is slated to be delivered to the Navy this summer. Detroit
(LCS 7) was launched in 2014. Little Rock (LCS 9) and Sioux City (LCS 11) are in construction, with LCS 9 christening and launch planned for this summer. Wichita (LCS 13) had its keel laid in February 2015. Billings (LCS 15), as well as Indianapolis (LCS 17) and to be named LCS 19, are in the construction phase.
Marinette Marine Corporation, a Fincantieri company, is building the ships in Marinette, Wis., with naval architect Gibbs & Cox of Arlington, Va., providing engineering support. Fincantieri has invested more than $100 million in the Marinette facility on upgrades that have increased efficiency and minimized energy consumption, an expansion that will allow for construction of more than two ships at a time, and process improve-ments that will speed up production.
Nearly 900 suppliers across 43 states are con-tributing to the Freedom-class LCS program.
National Cutter Boat Pooling ProgramIn the present state, each major Coast Guard cutter is permanently
assigned a set of cutter boats. While the parent cutter is in port or in programmed depot maintenance, the assigned cutter boat(s) remain idle, and not utilized for operational service. A strategy to improve readiness and lower life cycle costs is to centrally store and maintain the cutter boats.
As such, the U.S. Coast Guard Surface Forces Logistics Center (SFLC), Small Boat Product Line (SBPL), is seeking qualified sources to establish a National Cutter Boat Pooling (NCBP) Program for the over-the-horizon cutter boats (CB-OTH) MKII, MKIIIs and OTH IV cutter boats and trailers. Performance will include the transportation, storage, maintenance, repair and technical support services for a
rotatable pool of up to 125 boats and trailers deployed on cutters throughout the United States.
The SFLC SBPL mission is to develop and execute various altera-tion and technical support programs to upgrade and maintain in a more cost-effective and timely manner the material readiness of vari-ous boat hull, mechanical and electrical and electronic systems in order to meet major cutters operational needs. This contract is to provide the full spectrum of technical support encompassing all phases of the NCBP process. This contract will be under the administrative control of SFLC SBPL.
Primary point of contact: Kelly A. Wyatt [email protected], 410-582-4720
WWW.NPEO-kMI.COM6 | APRIl 07, 2015
CNo Stresses Versatility of Independence-Class lCS
Chief of Naval Operations (CNO) Admiral Jonathan Greenert and Rep-
resentative Jeff Miller (R-Fla.) stressed the versatility of the Independence-
class littoral combat ships (lCS) April 1 at a press conference on board
Naval Air Station (NAS) Pensacola.
After touring the USS Independence (lCS 2) with the congressman, the
CNO highlighted the value of the lCS’s ability to be repackaged for multiple
missions.
“The thing that is of value about the lCS is that she has great volume,
high speed, and is modular,” said Greenert. “What that means is you can
change out packages to perform different missions.”
“Currently, the Independence is configured for mine countermeasures
operations, but she can be reconfigured for other missions including mari-
time security or anti-submarine warfare. These packages could be forward
deployed around the world in hot spots, where in a matter of a few days, the
ship could be changed as necessary to meet the demand.”
The ship has been testing its new anti-mine warfare technology in the
Gulf of Mexico since February 20, and will be docking between sorties at
NAS Pensacola throughout its training operation.
Greenert praised the experience of the crew testing the new lCS, saying
it allows the Navy to be more efficient with crew management.
“These sailors on board the ship are more senior than the average
sailor,” he said. “They’ve been in the Navy for four to six years. This enables
us to keep the crew to half of what it would normally be on a conventional
ship.”
The CNO also addressed the pace of construction for these new ships.
“In the future, I expect to see continued construction of the lCS
platform. We took a pause and decided we need 52 of these ships,” said
Greenert. “The secretary of defense asked us to take a look at this and see if
we could make these more survivable and more lethal. We’ve done that and
we are all guns ahead.”
Miller was thanked by the CNO for his work in Congress in aiding mili-
tary personnel and veterans. The representative likewise thanked the CNO
for letting him visit the ship.
“It’s been an outstanding tour of a great new capability that we have in
the United States Navy,” said Miller. “I appreciate not only seeing this great
vessel, but being able to talk to the men and women of the USS Indepen-
dence.”
Laser Eye ProtectionThe purpose of laser eye protection (LEP) is to reduce
the possibility of damage to the eye from a variety of laser threats. Threats to aircrew come from both unintentional friendly and unfriendly sources. Aircraft and pilot lasing incidents are increasing, with the majority of the incidents occurring at night during aircraft takeoff and landing. The Navy has been tasked to design, produce and deploy a mul-tiple wavelength spectacle to address the needs of fixed- and rotary-wing aircrew in fixed multiple wavelength laser threat environments.
Specific threat wavelengths and optical density (OD) requirements are contained in the classified and only persons with a “need-to-know” will be authorized access.
The lens shall be tested to demonstrate the wearer is protected throughout the entire safety zone as defined in ANSI Z136.7. Optical density shall be verified at each threat wavelength or wavelength range using laser sources of the appropriate wavelength. Laser source shall have a bandwidth no greater than 1nm. OD shall be verified throughout the entire specified wavelength protection bands where lasers were not used, using a measurement system of appropriate wavelength range and dynamic range for the OD being measured. Optical density and angular testing shall be performed to test the full protection of the safety zone, up to the frame edge when it falls within the safety zone projected angle.
13:00 Future of Naval Unmanned Systems and Integration OPNAV N2/N6
13:30 Networking Break
14:00 Future of Naval Aviation Requirements OPNAV N98
14:30 Marine Aviation Requirements APW-72 (TBD)
WWW.NPEO-kMI.COM8 | APRIl 07, 2015
Light Weight Wide Aperture Array and Wide Aperture Array Software Development and Engineering Services
Program Executive Office Submarines (PMS401) has issued a statement of work defining the efforts required for the program management, engineering, software develop-ment, logistics, configuration management, software integration test and evaluation, and Information Assurance (IA), of the Light Weight Wide Aperture Array (LWWAA) and Wide Ap-erture Array (WAA) systems. This effort includes exploring existing and new approaches to sensor processing and developing new or augment-ing existing capabilities as required to meet the acoustic processing needs for the Navy. The efforts defined herein are applicable to SSN688I, SSN21 and SSN 774 class submarines.
The successful contractor shall develop, test, and deliver a common operational LWWAA and WAA software to meet all requirements specified in the “AN/BQQ-10(V) LWWAA and WAA
In-Board Processing Specification” (PMS401-LWWAA/WAA Spec-01). The delivery and acceptance of the common LWWAA and WAA Software will be contingent on success-ful completion of qualification and acceptance testing.
The contractor is required to deliver the common LWWAA and WAA Software for TI-18 and TI-20 as GFE to acoustic rapid commercial-off-the-shelf insertion (A-RCI) system integrator for system integration and shipboard installation. There are also other industry partners whom provide engineering services and support of the A-RCI sonar system. The contractor shall work in a collaborative environment with a consortium of Navy, Navy laboratories, academia, A-RCI prime system integrator, ownership monitoring ship developer, common acoustic cabinet developer, and other
industry partners to ensure continued success of the program. The contractor shall identify his approach to be used to support the “Open Source Initiative/Open Systems Architecture” to enable third-party applications and allow for the efficient integration of improvements with the submarine acoustic systems. The contractor shall leverage past experience involved in similar ef-forts and indicate the approach that will be used in delivering this effort.
Based on the rapid development cycle for A-RCI builds, it is highly encouraged that the contractor maintains a constant presence at the A-RCI system integration facility to support all integration efforts, fleet support is-sues, and common LWWAA and WAA system development.
Primary Point of Contact: Danielle C. Tyler [email protected], 202-781-0828
enterprise Air Surveillance RadarThe Enterprise Air Surveillance Radar
Norfolk Naval Shipyard undocks uSS marylandOn February 21, Norfolk Naval Shipyard (NNSY) successfully
undocked USS Maryland (SSBN 738).
SSBN 738 is now pier-side to finish its engineered refueling over-
haul, a complex, major shipyard availability at the submarine’s mid-
life point that enables the submarine to operate for its entire design
service life. Maryland has been at NNSY since December 2012.
According to Project Superintendent John Darlington, “The Mary-
land is in the end game now. We have less than 10 percent produc-
tion work remaining. The majority of the end game will involve testing
the systems that have been overhauled and upgraded.”
Some of the major jobs during the availability include ship sys-
tems overhaul, specifically the replacement of distilling plants with
a reverse osmosis unit; replacement of the service turbine genera-
tor rotor with a low-sensitivity rotor; installation of an upgraded 500
kilowatt motor generator; and local area network upgrades.
Undocking was achieved despite high winds challenging crane
service, unusually cold weather preventing the normal process of
washing down the dry dock, and several inches of snowfall. When it
became apparent the effort might fall short of maintaining the planned
undocking date, volunteers pitched in from around the shipyard to
assist.
“The team has shown great perseverance and refused to give
up,” said John Darlington. “It took the entire shipyard to help us get
through the snow event, and we have proven that when everyone
works together we can be successful. This is a proud project team
and we will continue to work together to give the shipyard more
successes in the future.”
According to Darlington, there are many challenges, not the least
of which is the number of people to be managed. “Due to the mag-
nitude of the effort and the span in time from pre-planning through
completion, the efforts of thousands of people are required. At the
peak we had greater than 1,000 personnel working the Maryland
each day. To date, over 5,821 different personnel have directly sup-
ported the Maryland’s availability. These availabilities are very chal-
lenging for the ship and the shipyard.”
In addition to the small amount of production work to still be
accomplished on the boat, system testing and certification and
ship’s force training will be conducted, culminating in sea trials
later this year.
WWW.NPEO-kMI.COM10 | APRIl 07, 2015
is to feature a new and more capable radar called the Air and Missile
Defense Radar (AMDR). The version of the AMDR to be carried by the
Flight III DDG-51 is smaller and less powerful than the version that was
envisaged for a cruiser called the CG(X) that the Navy at one point was
planning to procure, but subsequently canceled. The Flight III DDG-
51’s AMDR is to have a diameter of 14 feet, while the AMDR envis-
aged for the CG(X) would have had a substantially larger diameter.
Multiyear procurement (MYp) in fY13-fY17
As part of its action on the Navy’s FY13 budget, Congress
granted the Navy authority to use a multiyear procurement (MYP)
contract for DDG-51s to be procured FY13-FY17. The Navy awarded
the contract on June 3, 2013. The Navy plans to use an engineer-
ing change proposal (ECP) to shift from the Flight IIA design to the
Flight III design during this MYP contract. If the Flight III design is not
ready to support the procurement of the first Flight III ship in FY16,
the Navy can delay issuing the ECP and shift the start of Flight III
procurement to FY17.
ddG-1000 pRoGRaM
The DDG-1000 program was initiated in the early 1990s. The DDG-
1000 is a multimission destroyer with an emphasis on naval surface fire
support (NSFS) and operations in littoral (i.e., near-shore) waters. The
DDG-1000 is intended to replace, in a technologically more modern
form, the large-caliber naval gun fire capability that the Navy lost when
it retired its Iowa-class battleships in the early 1990s, to improve the
Navy’s general capabilities for operating in defended littoral waters, and
to introduce several new technologies that would be available for use
on future Navy ships. The DDG-1000 was also intended to serve as the
basis for the Navy’s now-canceled CG(X) cruiser.
The DDG-1000 is to have a reduced-size crew of 142 sailors (com-
pared to roughly 300 on the Navy’s Aegis destroyers and cruisers) so
as to reduce its operating and support (O&S) costs. The ship incorpo-
rates a significant number of new technologies, including an integrated
electric-drive propulsion system and automation technologies enabling
its reduced-sized crew.
With an estimated full load displacement of 15,482 tons, the DDG-
1000 design is roughly 63 percent larger than the Navy’s current 9,500-
ton Aegis cruisers and destroyers, and larger than any Navy destroyer or
cruiser since the nuclear-powered cruiser long Beach (CGN-9), which
was procured in FY57.
The first two DDG-1000s were procured in FY07 and split-funded
(i.e., funded with two-year incremental funding) in FY07-FY08; the
Navy’s FY16 budget submission estimates their combined procurement
cost at $8,797.9 million. The third DDG-1000 was procured in FY09
and split-funded in FY09-FY10; the Navy’s FY16 budget submission
estimates its procurement cost at $3,490.8 million.
As shown in Table 1 below, the estimated combined procurement
cost for all three DDG-1000s, as reflected in the Navy’s annual budget
submission, has grown by $3,311.6 million, or 36.9 percent, since
the FY09 budget (i.e., the budget for the fiscal year in which the third
DDG-1000 was procured).
Table 1. Change in Estimated Combined Procurement Cost of DDG-1000, DDG-1001, and DDG-2002 (In millions, rounded to nearest tenth, as shown in annual Navy budget submissions)
Estimated combined
procurement cost (millions of dollars)
Change from prior
year’s budget submission
Cumulative change from
FY2009 budget submission
FY09 budget 8,977.1 — —
FY10 budget 9,372.5
+395.4 (+4.4%)
+395.4 (+4.4%)
FY11 budget 9,993.3
+620.8 (+6.6%)
+1,016.2 (+11.3%)
FY12 budget 11,308.8
+1,315.5 (+13.2%)
+2,331.7 (+26.0%)
FY13 budget 11,470.1
+161.3 (+1.4%)
+2,493.0 (+27.8%)
FY14 budget 11,618.4
+148.3 (+1.3%)
+2,641.3 (+29.4%)
FY15 budget 12,069.4
+451.0 (+3.9%)
+3,092.3 (+34.4%)
FY16 budget 12,288.7
+219.3 (+1.8%)
+3,311.6 (+36.9%)
Some of the cost growth in the earlier years in the table was caused
by the truncation of the DDG-1000 program from seven ships to three,
which caused some class-wide procurement-rated costs that had been
allocated to the fourth through seventh ships to be reallocated to the
three remaining ships.
The Navy states that the cost growth shown in the later years of the
table reflects, among other things, a series of incremental, year-by-year
movements away from an earlier Navy cost estimate for the program, and
toward a higher estimate developed by Cost Assessment and Program
Evaluation (CAPE) office within the Office of the Secretary of Defense
(OSD). As one consequence of a Nunn-McCurdy cost breach experi-
enced by the DDG-1000 program in 2010 (see “2010 Nunn-McCurdy
Breach, Program Restructuring, and Milestone Recertification” in Appen-
dix A), the Navy was directed to fund the DDG-1000 program to CAPE’s
higher cost estimate for the period FY11-FY15, and to the Navy’s cost
estimate for FY16 and beyond. The Navy states that it has been imple-
menting this directive in a year-by-year fashion with each budget submis-
sion since 2010, moving incrementally closer each year to CAPE’s higher
estimate. The Navy stated in 2014 that even with the cost growth shown
in the table, the DDG-1000 program as of the FY15 budget submission
was still about 3 percent below the program’s rebaselined starting point
for calculating any new Nunn-McCurdy cost breach on the program.
All three ships in the DDG-1000 program are to be built at GD/BIW,
with some portions of each ship being built by Ingalls Shipbuilding for
delivery to GD/BIW. Raytheon is the prime contractor for the DDG-
1000’s combat system (its collection of sensors, computers, related
software, displays, and weapon launchers). The Navy awarded GD/BIW
the contract for the construction of the second and third DDG-1000s on
September 15, 2011.
Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress
➥ continued fRoM paGe 1
APRIl 07, 2015 | 11WWW.NPEO-kMI.COM
SuRface coMbatant conStRuction induStRial baSe
All cruisers, destroyers and frigates procured since FY85 have been
built at General Dynamics’ Bath Iron Works (GD/BIW) shipyard of Bath,
Maine, and Ingalls Shipbuilding of Pascagoula, MS, a division of Hunting-
ton Ingalls Industries (HII). Both yards have long histories of building larger
surface combatants. Construction of Navy surface combatants in recent
years has accounted for virtually all of GD/BIW’s ship-construction work
and for a significant share of Ingalls’ ship-construction work. (Ingalls also
builds amphibious ships for the Navy.) Navy surface combatants are over-
hauled, repaired and modernized at GD/BIW, Ingalls, other private-sector
U.S. shipyards, and government-operated naval shipyards (NSYs).
lockheed Martin and Raytheon are generally considered the two
leading Navy surface combatant radar makers and combat system in-
tegrators. Northrop Grumman is a third potential maker of Navy surface
combatant radars. lockheed is the lead contractor for the DDG-51
combat system (the Aegis system), while Raytheon is the lead contrac-
tor for the DDG-1000 combat system, the core of which is called the To-
tal Ship Computing Environment Infrastructure (TSCE-I). lockheed has
a share of the DDG-1000 combat system, and Raytheon has a share
of the DDG-51 combat system. lockheed, Raytheon, and Northrop
competed to be the maker of the AMDR to be carried by the Flight III
DDG-51. On October 10, 2013, the Navy announced that it had selected
Raytheon to be the maker of the AMDR.
The surface combatant construction industrial base also includes
hundreds of additional firms that supply materials and components. The
financial health of Navy shipbuilding supplier firms has been a matter
of concern in recent years, particularly since some of them are the sole
sources for what they make for Navy surface combatants.
fY16 fundinG RequeSt
The Navy estimates the combined procurement cost of the two
DDG-51s requested for procurement in FY16 at $3,522.7 million. A
comparison with the cost of the two DDG-51s procured in FY15 sug-
gests that, within the estimated combined cost of $3,522.7 million for
the two FY16 DDG-51s, the Flight III DDG-51 might account for, very
roughly, $2 billion, while the other DDG-51 might account for, very
roughly, $1.5 billion. The potential difference of, very roughly, $500
million in cost between the two ships includes one-time design and
change-order costs for modifying the DDG-51 design to the Flight III
configuration, additional costs for the AMDR radar and associated
electrical power and cooling equipment, and some loss of shipyard
production learning curve benefits due to the change in the ship’s
design.
The two DDG-51s requested for procurement in FY16 have received
a total of $373.0 million in prior-year advance procurement (AP) funding.
The Navy’s proposed FY16 budget requests the remaining $3,149.7
million needed to complete the ships’ estimated combined procurement
cost. The Navy’s proposed FY16 budget also requests $75.0 million in
so-called cost-to- complete procurement funding to replace funding for
DDG-51s procured in FY10-FY12 that was canceled by March 1, 2013,
sequester. The Navy’s proposed FY16 budget also requests $433.4
million in procurement funding to complete construction of Zumwalt-
(DDG-1000) class destroyers procured in prior years, and $241.8 million
in research and development funding for development work on the
AMDR. The funding request for the AMDR is contained in Program
Element (PE) 0604522N (“Advanced Missile Defense Radar [AMDR] Sys-
tem”), which is line 118 in the Navy’s FY16 research and development
account.
issues for congress
fliGht iii ddG-51: ReadineSS of deSiGn foR pRocuReMent in fY16
One issue for Congress concerns the readiness of the Flight III de-
sign for procurement in FY16. As noted earlier, the Navy plans to shift to
procurement of the Flight III design with the second of the two DDG-51s
requested for procurement in FY16.
The Navy argues that the Flight III design will be ready for procure-
ment in FY16. If it is judged that the design is not ready, the Navy’s plan
allows for procurement of the first Flight III DDG-51 to be shifted to
FY17 or a later year.
At a February 25, 2015 hearing on Department of the Navy acquisi-
tion programs before the Seapower and Projection Forces subcom-
mittee of House Armed Services Committee, Department of the Navy
officials testified that
In October 2013, the Navy awarded the contract for devel-
opment of the AMDR, with options for up to nine low rate initial
production (lRIP) units. The AMDR radar suite will be capable of
providing simultaneous surveillance and engagement support for
long range BMD and area defense. The program continues to dem-
onstrate maturity in the design development as shown in successful
completion of the AMDR hardware critical design review (CDR) in
December 2014 and is on track for the system CDR in April 2015.
Engineering Change Proposal (ECP) detail design efforts for the
DDG Flight III design will continue in FY16, ultimately leading to over
90 percent detail design completion prior to construction on the first
Flight III ship.
In a February 2015 report to Congress on the status of the Flight III
design, the Navy stated that
with respect to systems and equipment levels of maturity for
Flight III, the AMDR is the only new development technology. The
AMDR has successfully completed Milestone B, a full system Pre-
liminary Design Review, a hardware Critical Design Review, and will
deliver its first full ship set of production equipment by early FY20.
The remaining equipment required to provide power and cooling to
the AMDR are all based on currently existing equipment and there-
fore induce low technical risk to the program. Given the tremendous
capability improvement AMDR provides to defeat emerging air and
ballistic missile threats over current radars, the low to moderate
technical risk associated with implementing this radar on an FY16
DDG 51 justifies execution of the ECP during the FY13-17 multiyear
procurement contract....
All major equipment development is on track to support DDG 51
Class implementation of the AMDR in FY16....
The Flight III program is supported by appropriate design execu-
tion, Systems Engineering Technical Reviews, and stakeholder rela-
tionships consistent with meeting requirements and overall pro-gram
schedule. Major supporting component developments for AMDR-S
[AMDR S band], PCMs [power conversion modules], and SSGTGs
[ship service gas turbine generators] are well underway by the as-
sociated Participating Resource Managers (PARMs) with schedules
and milestones that support the overall Flight III delivery targets.
Detail design was started in FY14 with the Program Office delivering
WWW.NPEO-kMI.COM12 | APRIl 07, 2015
Government Furnished Information (GFI) to the shipyard services to
support continued Flight III development. Continued development of
GFI will support detail design fidelity leading to successful Preliminary
Design Review (PDR), Critical Design Review (CDR), and Production
ity (to cool equipment), and ability to accept increases in the ship’s
WWW.NPEO-kMI.COM14 | APRIl 07, 2015
vertical center of gravity. Navy ship classes are typically designed so
that the first ships in the class will be built with a certain amount of
growth margin. Over time, some or all of the growth margin in a ship
class may be used up by backfitting additional or newer systems
onto existing ships in the class, or by building later ships in the
class to a modified design that includes additional or newer
systems.
Modifying the DDG-51 design over time has used up some of
the design’s growth margin. The Flight III DDG-51 would in some
respects have less of a growth margin than what the Navy would aim
to include in a new destroyer design of about the same size. A Janu-
ary 18, 2013, press report stated, “In making decisions about the
[Flight III] ship’s power, cooling, weight and other margins, [DDG-51
program manager Captain Mark] Vandroff said [in a presentation at
a conference on January 15, 2013, that] the Navy wanted to ensure
that there was room to grow in the future, to allow for modernization
as well as capability upgrades when new weapons such as the elec-
tromagnetic railgun enter the fleet. Allowing for growth was balanced
with cost, and Vandroff said he thought the program did a great job
of coming up with an affordable solution to a leap-ahead capability
for the fleet.” In his presentation, Vandroff showed a slide comparing
the growth margins of the Flight III design to those of Flight IIA DDG-
51s procured or scheduled to be procured in FY10-FY14.
CRS-13
Figure 2. Navy Briefing Slide on DDG-51 Growth Margins Flight III DDG-51 Design Compared to Flight IIA DDG-51s
DISTRIBUTION STATEMENT A:Approved for public release, distribution is unlimited.
FY10 Flt IIA – FY16* Flt IIIService Life Allowance Comparison
0%
5%
10%
15%
20%
25%
FY10
FY12
FY13
FY14
FY16
Cooling SLA - Connected Loads
0%
5%
10%
15%
20%
25%
30%
35%
FY10
FY12
FY13
FY14
FY16
Electric Power SLA
0.000.100.200.300.400.500.600.700.800.901.00
FY10
FY12
FY13
FY14
FY16
KG SLA (ft)
0%
2%
4%
6%
8%
10%
12%
FY10
FY12
FY13
FY14
FY16
Weight SLA
FY16 Flt III with change to 3x4MW GTGS & 4160 VAC
Current
Baseline
450 VAC
450 VAC
450 VAC
4160 VAC
FY16 Flt III with change to 5x300T HES-C AC Units
Current
Baseline
5x300T ACs
5x200T AC
s
5x200T AC
s
5x200T AC
s
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
Notes: 1. - * Second ship in FY16 is designated as the DDG 51 Flight III2. - FY10 values are calculated, out year values are projections based on Not to Exceed Design Budget Estimates
AMD
R-S ∆
SPQ-9B
∆
AMD
R-S ∆
SPQ-9B
∆
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
15
Current
Baseline Current
Baseline
Source: Presentation of Captain Mark Vandroff to Surface Navy Association, January 15-17, 2013; a copy of the slides was provided to CRS by the Navy Office of Legislative Affairs on January 28, 2013.
Note: SLA means service life allowance (i.e., growth margin).
CRS-13
Figure 2. Navy Briefing Slide on DDG-51 Growth Margins Flight III DDG-51 Design Compared to Flight IIA DDG-51s
DISTRIBUTION STATEMENT A:Approved for public release, distribution is unlimited.
FY10 Flt IIA – FY16* Flt IIIService Life Allowance Comparison
0%
5%
10%
15%
20%
25%
FY10
FY12
FY13
FY14
FY16
Cooling SLA - Connected Loads
0%
5%
10%
15%
20%
25%
30%
35%
FY10
FY12
FY13
FY14
FY16
Electric Power SLA
0.000.100.200.300.400.500.600.700.800.901.00
FY10
FY12
FY13
FY14
FY16
KG SLA (ft)
0%
2%
4%
6%
8%
10%
12%
FY10
FY12
FY13
FY14
FY16
Weight SLA
FY16 Flt III with change to 3x4MW GTGS & 4160 VAC
Current
Baseline
450 VAC
450 VAC
450 VAC
4160 VAC
FY16 Flt III with change to 5x300T HES-C AC Units
Current
Baseline
5x300T ACs
5x200T AC
s
5x200T AC
s
5x200T AC
s
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
Notes: 1. - * Second ship in FY16 is designated as the DDG 51 Flight III2. - FY10 values are calculated, out year values are projections based on Not to Exceed Design Budget Estimates
AMD
R-S ∆
SPQ-9B
∆
AMD
R-S ∆
SPQ-9B
∆
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
15
Current
Baseline Current
Baseline
Source: Presentation of Captain Mark Vandroff to Surface Navy Association, January 15-17, 2013; a copy of the slides was provided to CRS by the Navy Office of Legislative Affairs on January 28, 2013.
Note: SLA means service life allowance (i.e., growth margin).
notes:
1 - * Second ship in Fy16 is designated as the ddG 51 Flight III
2 - Fy10 values are calculated, out year values are projections based on not to Exceed
design Budget Estimates
CRS-13
Figure 2. Navy Briefing Slide on DDG-51 Growth Margins Flight III DDG-51 Design Compared to Flight IIA DDG-51s
DISTRIBUTION STATEMENT A:Approved for public release, distribution is unlimited.
FY10 Flt IIA – FY16* Flt IIIService Life Allowance Comparison
0%
5%
10%
15%
20%
25%
FY10
FY12
FY13
FY14
FY16
Cooling SLA - Connected Loads
0%
5%
10%
15%
20%
25%
30%
35%
FY10
FY12
FY13
FY14
FY16
Electric Power SLA
0.000.100.200.300.400.500.600.700.800.901.00
FY10
FY12
FY13
FY14
FY16
KG SLA (ft)
0%
2%
4%
6%
8%
10%
12%
FY10
FY12
FY13
FY14
FY16
Weight SLA
FY16 Flt III with change to 3x4MW GTGS & 4160 VAC
Current
Baseline
450 VAC
450 VAC
450 VAC
4160 VAC
FY16 Flt III with change to 5x300T HES-C AC Units
Current
Baseline
5x300T ACs
5x200T AC
s
5x200T AC
s
5x200T AC
s
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
Notes: 1. - * Second ship in FY16 is designated as the DDG 51 Flight III2. - FY10 values are calculated, out year values are projections based on Not to Exceed Design Budget Estimates
AMD
R-S ∆
SPQ-9B
∆
AMD
R-S ∆
SPQ-9B
∆
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
15C
urrent Baseline C
urrent Baseline
Source: Presentation of Captain Mark Vandroff to Surface Navy Association, January 15-17, 2013; a copy of the slides was provided to CRS by the Navy Office of Legislative Affairs on January 28, 2013.
Note: SLA means service life allowance (i.e., growth margin).
CRS-13
Figure 2. Navy Briefing Slide on DDG-51 Growth Margins Flight III DDG-51 Design Compared to Flight IIA DDG-51s
DISTRIBUTION STATEMENT A:Approved for public release, distribution is unlimited.
FY10 Flt IIA – FY16* Flt IIIService Life Allowance Comparison
0%
5%
10%
15%
20%
25%FY10
FY12
FY13
FY14
FY16
Cooling SLA - Connected Loads
0%
5%
10%
15%
20%
25%
30%
35%
FY10
FY12
FY13
FY14
FY16
Electric Power SLA
0.000.100.200.300.400.500.600.700.800.901.00
FY10
FY12
FY13
FY14
FY16
KG SLA (ft)
0%
2%
4%
6%
8%
10%
12%
FY10
FY12
FY13
FY14
FY16
Weight SLA
FY16 Flt III with change to 3x4MW GTGS & 4160 VAC
Current
Baseline
450 VAC
450 VAC
450 VAC
4160 VACFY16 Flt III with change to 5x300T HES-C AC Units
Current
Baseline
5x300T ACs
5x200T AC
s
5x200T AC
s
5x200T AC
s
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
Notes: 1. - * Second ship in FY16 is designated as the DDG 51 Flight III2. - FY10 values are calculated, out year values are projections based on Not to Exceed Design Budget Estimates
AMD
R-S ∆
SPQ-9B
∆
AMD
R-S ∆
SPQ-9B
∆
FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S
15
Current
Baseline Current
Baseline
Source: Presentation of Captain Mark Vandroff to Surface Navy Association, January 15-17, 2013; a copy of the slides was provided to CRS by the Navy Office of Legislative Affairs on January 28, 2013.
Note: SLA means service life allowance (i.e., growth margin).
A June 7, 2013 blog post stated:
The Navy is confident it has enough space, power and cooling
onboard the hull of its planned new line of destroyers to accom-
modate the planned high-powered Air and Missile Defense Radar
(AMDR), Captain Mark Vandroff, Naval Sea Systems Command
program manager for the DDG-51 shipbuilding program, told USNI
News in an interview on Thursday.
However, the Arleigh Burke-class destroyer (DDG-51) Flight III
would be limited in the amount of additional weapons the ship could
accommodate—including electromagnetic railguns and high-energy
lasers—without removing other capabilities.
“Depending on how heavy that railgun is, could you fit it on
a DDG? My answer is what on that DDG are you willing to live
without right now?” Vandroff said.
“You wouldn’t have the space and weight to put on some-
thing very large without something relatively sizable coming off.”
Supporters of the Navy’s proposal to procure Flight III DDG-51s
could argue that the ship’s growth margin would be comparable to
that of recently procured Flight IIA DDG-51s, and would be ad-
equate because the increase in capability achieved with the Flight
III configuration reduces the likelihood that the ship will need much
subsequent modification to retain its mission effectiveness over its
projected service life. They could also argue that, given technology
Flight III DDG-51 Design Compared to Flight IIA DDG-51s
FY10 Flt IIA- FY16 Flt III Service Life Allowance Comparison
APRIl 07, 2015 | 15WWW.NPEO-kMI.COM
advances, new systems added to the ship years from now might
require no more (and possibly less) space, weight, electrical power
or cooling capacity than the older systems they replace.
Skeptics could argue that there are uncertainties involved in pro-
jecting what types of capabilities ships might need to have to remain
mission effective over a 35- or 40-year life, and that building expensive
new warships with relatively modest growth margins consequently
would be imprudent. The Flight III DDG-51’s growth margin, they
could argue, could make it more likely that the ships would need to
be removed from service well before the end of their projected service
lives due to an inability to accept modifications needed to preserve
their mission effectiveness. Skeptics could argue that it might not be
possible to fit the Flight III DDG-51 in the future with a high-power (200
kW to 300 kW) solid-state laser (SSl), because the ship would not
have enough available electrical power or cooling capacity to support
such a weapon. Skeptics could argue that high-power SSls could
be critical to the Navy’s ability years from now to affordably counter
large numbers of enemy anti-ship cruise missiles (ASCMs) and anti-
ship ballistic missiles (ASBMs) that might be fielded by a wealthy and
determined adversary. Skeptics could argue that procuring Flight III
DDG-51s could delay the point at which high-power SSls could be
introduced into the cruiser-destroyer force, and reduce for many years
the portion of the cruiser-destroyer force that could ultimately be back-
fitted with high-power SSls. This, skeptics could argue, might result in
an approach to AAW and BMD on cruisers and destroyers that might
ultimately be unaffordable for the Navy to sustain in a competition
against a wealthy and determined adversary.
flight iii ddG-51: issues Raised in January 2015 dot&e Report
Another issue for Congress concerns issues raised in a January
2015 report from DoD’s Director of Operational Test and Evaluation
(DOT&E)—DOT&E’s annual report for FY14. Regarding the Flight III
DDG-51 program, the report stated:
Executive Summary
• On March 6, 2014, the deputy secretary of defense
(DEPSECDEF) issued a Resource Management Decision
memorandum directing the Navy to develop a plan to conduct
at-sea testing of the self-defense capability of the DDG 51 Flight
III Destroyer with the Air and Missile Defense Radar (AMDR) and
Aegis Combat System. The plan was to be approved by DOT&E
and then adequately funded by the Navy. However, the Navy has
not provided any plan to DOT&E or planned funding to facilitate
the testing.
• On April 23, 2014, DOT&E issued a memorandum to USD(AT&l)
[Under Secretary of Defense for Acquisition, Technoogy, and
logistics—DoD’s acquisition executive] stating the intention to
not approve any operational test plan for an Early Operational
Assessment (EOA) of the AMDR due to non-availability of the
required AMDR hardware and software.
• On September 10, 2014, DOT&E issued a classified memorandum
to USD(AT&l) with a review of the Navy Program Executive
Office for Integrated Warfare Systems Design of Experiments
study. The study attempted to provide a technical justification to
show the test program did not require using a Self-Defense Test
Ship (SDTS) to adequately assess the self- defense capability of
the DDG 51 Flight III Class Destroyers. DOT&E found the study
presented a number of flawed rationales, contradicted itself, and
failed to make a cogent argument for why an SDTS is not needed
for operational testing....
Activity
• On March 6, 2014, DEPSECDEF issued a Resource Management
Decision memorandum directing the Navy to develop a plan
to conduct at-sea testing of the self-defense capability of the
DDG 51 Flight III Destroyer with the AMDR and Aegis Combat
System. The plan was to be approved by DOT&E and then
adequately funded by the Navy. To date, the Navy has not
provided any plan to DOT&E or funding in response to this
direction.
• On April 23, 2014, DOT&E issued a memorandum to USD (AT&l)
stating the operational test plan for an EOA of the AMDR could
not be approved because the required AMDR hardware and
software were not available as planned, per the 2010 DOT&E-
and Navy- approved Test and Evaluation Strategy, and as
briefed to the deputy assistant secretary of defense (strategic
and tactical systems) in 2012. A prototype AMDR array, coupled
to an upgraded radar controller using basic software for radar
control and simple search and track functionality, was expected
to be available. The lack of this hardware and software would
have limited the EOA to a “table-top” review of program
documentation, program plans, and available design data, which
would, in DOT&E’s view, not have been a worthwhile use of
resources.
• On September 10, 2014, DOT&E issued a classified
memorandum to USD(AT&l) that provided a review of the
Navy Program Executive Office for Integrated Warfare Systems
Design of Experiments study. The study attempted to provide a
technical justification to show the test program did not require
using an SDTS to adequately assess the self-defense capability
of the DDG 51 Flight III Class Destroyers. DOT&E found the
study presented a number of flawed rationales, contradicted
itself, and failed to make a cogent argument for why an SDTS is
not needed for operational testing.
Assessment
• DOT&E’s assessment continues to be that the operational test
programs for the AMDR, Aegis Modernization and DDG 51
Flight III Destroyer programs are not adequate to fully assess
their self-defense capabilities in addition to being inadequate to
test the following Navy-approved AMDR and DDG 51 Flight III
requirements.
• The AMDR Capability Development Document describes AMDR’s
IAMD mission, which requires AMDR to support simultaneous
defense against multiple ballistic missile threats and multiple
advanced anti-ship cruise missile (ASCM) threats. The Capability
Development Document also includes an AMDR minimum track
range key Performance Parameter.
• The DDG 51 Flight III Destroyer has a survivability requirement
directly tied to meeting a self-defense requirement threshold
WWW.NPEO-kMI.COM16 | APRIl 07, 2015
against ASCMs described in the Navy’s Surface Ship Theater
Air and Missile Defense Assessment document of July 2008. It
clearly states that area defense will not defeat all the threats,
thereby demonstrating that area air defense will not completely
attrite all ASCM raids and that individual ships must be capable
of defeating ASCM leakers in the self-defense zone.
• Use of manned ships for operational testing with threat
representative ASCM surrogates in the close-in, self-defense
battlespace is not possible due to Navy safety restrictions
because targets and debris from intercepts pose an unacceptable
risk to personnel at ranges where some of the engagements
will take place. The November 2013 mishap on the USS
Chancellorsville (CG 62) involving an ASCM surrogate target
resulted in even more stringent safety constraints.
• In addition to stand-off ranges (on the order of 1.5 to 5 nautical
miles for subsonic and supersonic surrogates, respectively),
safety restrictions require that ASCM targets not be flown
directly at a manned ship, but at some cross-range offset, which
unacceptably degrades the operational realism of the test.
• Similar range safety restrictions will preclude manned ship
testing of eight of the nine ASCM scenarios contained in
the Navy-approved requirements document for the Aegis
Modernization Advanced Capability Build 16 Combat System
upgrade as well as testing of the AMDR minimum track range
requirement against supersonic, sea-skimming ASCM threat-
representative surrogates at the land-based AMDR Pacific
Missile Range Facility test site.
• To overcome these safety restrictions for the lHA-6, littoral
Combat Ship (lCS), DDG1000, lPD-17, lSD-41/49, and CVN-
78 ship classes, the Navy developed an Air Warfare/Ship Self
Defense Enterprise modeling and simulation (M&S) test bed
that uses live testing in the close-in battlespace with targets
flying realistic threat profiles and manned ship testing for other
battlespace regions and softkill capabilities to validate and
accredit the M&S test bed. The same needs to be done for
the DDG 51 Flight III Destroyer with its AMDR. Side-by-side
comparison between credible live fire test results and M&S test
results form the basis for the M&S accreditation. Without an
SDTS with AMDR and an Aegis Combat System, there will not be
a way to gather all of the operationally realistic live fire test data
needed for comparison to accredit the M&S.
• The Navy needs to improve its Aegis Weapon System (AWS)
models that are currently provided by lockheed Martin’s Multi-
Target Effectiveness Determined under Simulation by Aegis
(MEDUSA) M&S tool.
• MEDUSA encompasses several components of the AWS
including the SPY-1 radar, Command and Decision, and Weapon
Control System. MEDUSA models AWS performance down to
the system specification and the Navy considers it a high-fidelity
simulation of AWS.
• However, it is not a tactical code model, so its fidelity is
ultimately limited to how closely the specification corresponds to
the Aegis tactical code (i.e., the specification is how the system
is supposed to work while the tactical code is how the system
actually works). This adds to the need for realistic live fire shots
to support validation efforts.
• Earlier test events highlight the limitations of specification
models like MEDUSA. During Aegis Advanced Capability Build
08 testing in 2011, five AWS software errors were found during
live fire events and tracking exercises. Three software errors
contributed to a failed SM-2 engagement, one to a failed ESSM
engagement, and one to several failed simulated engagements
during tracking exercises. Since these problems involved
software coding errors, it is unlikely that a specification model
like MEDUSA (which assumes no software errors in tactical
code) would account for such problems and hence it would
overestimate the combat system’s capability.
• By comparison, the Air Warfare/Ship Self Defense Enterprise M&S
test bed used for assessing USS San Antonio’s (lPD-17) self-
defense capabilities used re-hosted Ship Self-Defense System
Mk 2 tactical code.
• Since Aegis employs ESSM in the close-in, self-defense
battlespace, understandingESSM’s performance is critical to
understanding the self-defense capabilities of the DDG 51 Flight
III Destroyer.
• Past DOT&E annual reports have stated that the ESSM’s
operational effectiveness has not been determined. The Navy
has not taken action to adequately test the ESSM’s operational
effectiveness.
• Specifically, because safety limitations preclude ESSM firing in
the close-in self-defense battlespace, there are very little test
data available concerning ESSM’s performance, as installed on
Aegis ships, against supersonic ASCM surrogates.
• Any data available regarding ESSM’s performance against
supersonic ASCM surrogates are from a Ship Self-Defense
System-based combat system configuration, using a completely
different guidance mode or one that is supported by a different
radar suite.
• The cost of building and operating an Aegis SDTS is small
when compared to the total cost of the AMDR development/
procurement and the eventual cost of the 22 (plus) DDG 51
Flight III ships that are planned for acquisition ($55-plus billion).
Even smaller is the cost of the SDTS compared to the cost of the
ships that the DDG 51 Flight III Destroyer is expected to protect (ap-
proximately $450 Billion in new ship construction over the next 30
years).
• If DDG 51 Flight III Destroyers are unable to defend themselves,
these other ships are placed at substantial risk.
• Moreover, the SDTS is not a one-time investment for only
the AMDR/DDG 51 Flight III IOT&E [Initial Operational Test &
Evaluation], as it would be available for other testing that cannot
be conducted with manned ships (e.g., the ESSM Block 2) and as
the combat system capabilities are improved.
Recommendations
• Status of Previous Recommendations. There are three previous
recommendations that remain valid. The Navy should:
1. Program and fund an SDTS equipped with the AMDR and
DDG 51 Flight III Aegis Combat System in time for the DDG
51 Flight III Destroyer IOT&E.
2. Modify the AMDR, Aegis Modernization and DDG 51 Flight
III Test and Evaluation Master Plans to include a phase of
APRIl 07, 2015 | 17WWW.NPEO-kMI.COM
IOT&E using an SDTS equipped with the AMDR and DDG 51
Flight III Combat System.
3. Modify the AMDR, Aegis Modernization, and DDG 51 Flight
III Test and Evaluation Master Plans to include a credible
M&S effort that will enable a full assessment of the AMDR
and DDG 51 Flight III Combat System’s self-defense capa-
bilities.
• FY14 Recommendation.
1. The Navy should comply with the DEPSECDEF direction
to develop and fund a plan, to be approved by DOT&E,
to conduct at-sea testing of the self-defense of the DDG
51 Flight III Destroyer with the AMDR and Aegis Combat
System.
flight iii ddG-51: adequacy of aaW and bMd capability
Another issue for Congress is whether the Flight III DDG-51 will
have sufficient AAW and BMD capability to adequately perform future
AAW and BMD missions. The Flight III DDG-51 would have more
AAW and BMD capability than the current DDG-51 design, but less
AAW and BMD capability than was envisioned for the CG(X) cruiser,
in large part because the Flight III DDG-51 would be equipped with a
14-foot-diameter version of the AMDR that would have more sensi-
tivity than the SPY-1 radar on Flight IIA DDG-51s, but less sensitivity
than the substantially larger version of the AMDR that was envisioned
for the CG(X). The CG(X) also may have had more missile-launch
tubes than the Flight III DDG-51.
The Navy argues that while the version of the AMDR on the
Flight III DDG-51 will have less sensitivity than the larger version
of the AMDR envisioned for the CG(X), the version of the AMDR on
the Flight III DDG-51 will provide sufficient AAW and BMD capabil-
ity to address future air and missile threats. A March 2014 GAO
report assessing selected DoD acquisition programs stated:
The X-band portion of AMDR will be comprised of an
upgraded version of an existing rotating radar (SPQ-9B),
instead of the new design initially planned. The new radar will
instead be developed as a separate program at a later date
and integrated with the thirteenth AMDR unit. According to
the Navy, the upgraded SPQ-9B radar fits better within the
Flight III’s sea frame and expected power and cooling avail-
ability. Program officials state that the SPQ-9B radar will have
capabilities equal to the new design for current anti-air warfare
threats, it will not perform as well against future threats.
The Navy plans to install a 14-foot variant of AMDR on
Flight III DDG 51s starting in 2019. According to draft AMDR
documents, a 14-foot radar is needed to meet threshold re-
quirements, but an over 20-foot radar is required to fully meet
the Navy’s desired integrated air and missile defense needs.
However, the shipyards and the Navy have determined that a
14-foot active radar is the largest that can be accommodated
within the existing DDG 51deckhouse. Navy officials stated
that AMDR is being developed as a scalable design but a new
ship would be required to host a larger version of AMDR.
lack of Roadmap for accomplishing three things in cruiser-destroyer force
Another issue for Congress concerns the lack of an announced
Navy roadmap for accomplishing three things in the cruiser-destroyer
force:
• restoring ship growth margins;
• introducing large numbers of ships with integrated electric
drive systems or other technologies that could provide ample
electrical power for supporting future electrically powered
weapons (such as high-power, solid-state lasers); and
• introducing technologies (such as those for substantially
reducing ship crew size) for substantially reducing ship
operating and support (O&S) costs. (The potential
importance of high-power, solid-state lasers is discussed
in the previous section on the Flight III DDG-51’s growth
margin.)
The Navy’s pre-2008 plan to procure DDG-1000 destroyers and
then CG(X) cruisers based on the DDG-1000 hull design represented
the Navy’s roadmap at the time for restoring growth margins, and for
introducing into the cruiser-destroyer force significant numbers of
ships with integrated electric drive systems and technologies for sub-
stantially reducing ship crew sizes. The ending of the DDG-1000 and
CG(X) programs in favor of continued procurement of DDG-51s leaves
the Navy without an announced roadmap to do these things, because
the Flight III DDG-51 will not feature a fully restored growth margin,
will not be equipped with an integrated electric drive system or other
technologies that could provide ample electrical power for supporting
future electrically powered weapons, and will not incorporate features
for substantially reducing ship crew size or for otherwise reducing ship
O&S costs substantially below that of Flight IIA DDG-51s.
options for congressIn general, options for Congress concerning destroyer acquisition
include the following:
• approving, rejecting or modifying the Navy’s procurement,
advance procurement, and research and development funding
requests for destroyers and their associated systems (such as the
AMDR);
• establishing conditions for the obligation and expenditure of
funding for destroyers and their associated systems; and
• holding hearings, directing reports, and otherwise requesting
information from DoD on destroyers and their associated
systems.
In addition to these general options, below are some additional acqui-
sition options relating to destroyers that Congress may wish to consider.
adjunct Radar ShipThe Navy canceled the CG(X) cruiser program in favor of
developing and procuring Flight III DDG-51s reportedly in part on
WWW.NPEO-kMI.COM18 | APRIl 07, 2015
the grounds that the Flight III destroyer would use data from off-
board sensors to augment data collected by its AMDR. If those
off-board sensors turn out to be less capable than the Navy as-
sumed when it decided to cancel the CG(X) in favor of the Flight
III DDG-51, the Navy may need to seek other means for aug-
menting the data collected by the Flight III DDG-51’s AMDR.
One option for doing this would be to procure an adjunct
radar ship—a non-combat ship equipped with a large radar
that would be considerably more powerful than the Flight III
DDG-51’s AMDR. The presence in the fleet of a ship equipped
with such a radar could significantly improve the fleet’s AAW
and BMD capabilities. The ship might be broadly similar to (but
perhaps less complex and less expensive than) the new Cobra
Judy Replacement missile range instrumentation ship (rendering
shown below), which is equipped with two large and powerful ra-
dars, and which has an estimated total acquisition cost of about
$1.7 billion. One to a few such adjunct radar ships might be
procured, depending on the number of theaters to be covered,
requirements for maintaining forward deployments of such ships,
and their homeporting arrangements. The ships would have little
or no self-defense capability and would need to be protected in
threat situations by other Navy ships.
flight iii ddG-51 with increased capabilities
Another option would be to design the Flight III DDG-51 to
have greater capabilities than what the Navy is currently envision-
ing. Doing this might well require the DDG-51 hull to be length-
ened—something that the Navy is not envisioning for the Flight III
design. Navy and industry studies on the DDG-51 hull design that
were performed years ago suggested that the hull has the poten-
tial for being lengthened by as much as 55 feet to accommodate
additional systems. Building the Flight III DDG-51 to a lengthened
configuration could make room for additional power-generation
and cooling equipment, additional vertical launch system (VlS)
missile tubes, and larger growth margins. It might also permit a
redesign of the deckhouse to support a larger and more capable
version of the AMDR than the 14-foot diameter version currently
planned for the Flight III DDG-51. Building the Flight III DDG-51
to a lengthened configuration would increase its development
cost and its unit procurement cost. The increase in unit procure-
ment cost could reduce the number of Flight III DDG-51s that the
Navy could afford to procure without reducing funding for other
programs.
ddG-1000 variant with aMdR
Another option would be to design and procure a version of the
DDG-1000 destroyer that is equipped with the AMDR and capable
of BMD operations. Such a ship might be more capable in some re-
gards than the Flight III DDG-51, but it might also be more expensive
to develop and procure. An AMDR-equipped, BMD-capable version
of the DDG-1000 could be pursued as either a replacement for the
Flight III DDG-51 or a successor to the Flight III DDG-51 (after some
number of Flight III DDG-51s were procured). A new estimate of the
cost to develop and procure an AMDR-equipped, BMD-capable
version of the DDG-1000 might differ from the estimate in the Navy’s
2009 destroyer hull/radar study (the study that led to the Navy’s de-
cision to stop DDG-1000 procurement and resume DDG-51 procure-
ment) due to the availability of updated cost information for building
the current DDG-1000 design.
new-design destroyerAnother option would be to design and procure a new-design
destroyer that is intermediate in size between the DDG-51 and DDG-
1000 designs, equipped with the AMDR, and capable of BMD opera-
tions. This option could be pursued as either a replacement for the
Flight III DDG-51 or a successor to the Flight III DDG-51 (after some
number of Flight III DDG-51s were procured). Such a ship might be
designed with the following characteristics:
• either the same version of the AMDR that is envisioned for the
Flight III DDG-51, or a version that is larger (but not as large as the
one envisioned for the CG[X]);
• enough electrical power and cooling capacity to permit the ship to
be backfitted in the future with a high-power SSl;
• more growth margin than on the Flight III DDG-51;
• producibility features for reducing construction cost per ton that
are more extensive than those on the DDG-51 design;
• automation features permitting a crew that is smaller than what
can be achieved on a Flight III DDG-51, so as to reduce ship O&S
costs;
• physical open-architecture features that are more extensive than
those on the Flight III DDG-51, so as to reduce modernization-
related life cycle ownership costs;
• no technologies not already on, or being developed for, other Navy
ships, with the possible exception of technologies that would
enable an integrated electric drive system that is more compact
than the one used on the DDG-1000; and
• DDG-51-like characteristics in other areas, such as survivability,
maximum speed, cruising range and weapons payload.
Such a ship might have a full load displacement of roughly
11,000 to 12,000 tons, compared to about 10,000 tons for the Flight
III DDG-51, 15,000 or more tons for an AAW/BMD version of the
DDG-1000, and perhaps 15,000 to 23,000 tons for a CG(X).
A March 18, 2013 press report states that
A recommended reevaluation of the next flights of lCSs [lit-
toral Combat Ships]... is only part of a classified memo, “Vision
for the 2025 Surface Fleet,” submitted late last year by the head
of Naval Surface Forces, Vice Admiral Tom Copeman, to Chief of
APRIl 07, 2015 | 19WWW.NPEO-kMI.COM
Naval Operations Admiral Jon Greenert....
Copeman, according to several sources familiar with the
document, also recommended against building the DDG 51
Flight III destroyers, a modification of the Arleigh Burke class
to be fitted with the new Air Missile Defense Radar (AMDR)
under development to replace the SPY-1 radars used in Aegis
warships. The AMDR, designed with higher power and fidel-
ity to handle the complex ballistic-missile defense mission,
will require significantly more electrical power than the current
system. And, while the AMDR apparently will fit into the DDG 51
hull, margins for future growth are severely limited.
Instead, sources said Copeman recommends creating a
new, large surface combatant fitted with AMDR and designed
with the power, weight and space to field “top-end energy
weapons” like the electromagnetic rail gun under development
by the Navy.
The new ship could also be developed into a replacement
for today’s Ticonderoga-class missile cruisers in the air defense
mission of protecting deployed aircraft carriers—a mission
Copeman says needs to be preserved. All flattops have a “shot-
gun” cruiser that accompanies them throughout a deployment,
but the missile ships are aging and, by 2025, only four will
remain in service to protect the fleet’s 11 carriers.
The Navy prefers cruisers over destroyers for the role
because of the bigger ships’ extra missile fire control channels,
their more senior commanders and a better ability to tow the
carrier should it be disabled.
While recommending against the Flight III, Copeman would
continue building the existing
DDG 51 Flight IIA variant until a new design is available.
An April 9, 2014 press report states:
The U.S. Navy is in the very early stages of developing a
new destroyer—called the Future Surface Combatant—which
will replace the existing Arleigh Burke-class destroyers and
enter service by the early 2030s, Navy leaders told Military.com.
Navy officials said it is much too early to speculate on hull
design or shape for the new ship but lasers, on-board power-
weapons, sensors and electronics are all expected to figure
prominently in the development of the vessel.
The Future Surface Combatant will succeed and serve
alongside the Navy’s current Flight III DDG 51 Arleigh Burke-
class destroyer program slated to being construction in 2016.
Overall, the Secretary of the Navy’s long-range shipbuilding
plan calls for construction of 22 Flight III DDGs, Navy officials
said.
There are a handful of early emerging requirements regard-
ing what admirals want for the ship, Rear Adm. Tom Rowden,
director of surface warfare, told Military.com in an interview.
“I could not even draw a picture for you,” said Rowden, who
went on to explain that greater automation and integrated elec-
trical power are part of the calculus of early discussions.
He emphasized that the new ship will leverage successful
next-generation technologies already underway in other plat-
forms such as the DDG 1000 destroyer, littoral Combat Ship
and Ford-class aircraft carriers.
The Future Surface Combatant may draw from the DDG
1000’s high-tech electric drive system that propels the ship
while generating 58 megawatts of on-board electrical power.
On-board power will be in high demand as lasers and directed
energy weapons become more prominent, Rowden said.
“We are moving all ahead with respect to the development
of lasers as a weapon in the future. You can take the power that
is generated on the ship and convert that into a fire control so-
lution without having to shoot a missile that may cost a million
to ten million,” Rowden explained....
The largest aspect of emphasis for the nascent Future
Surface Combatant program is something Rowden called
modularity, a term referring to a technological ability to rap-
idly and effectively make adjustments as needed.
The new ship design will emphasize flexibility to ensure the
platform keeps pace with fast- moving technological change
and threats, he said....
“The modules that we install in the ship may have no
bearing or resemblance to what needs to be there when we
decommission the ship. The weapons and sensors will be
different. We have to think about how to move through the
design, manufacture and subsequent upgrades in the most
cost-effective and affordable fashion. We need to design that
into the ship,” he said.
legislative activity for fY16
fY16 fundinG RequeSt
The Navy estimates the combined procurement cost of the two
DDG-51s requested for procurement in FY16 at $3,522.7 million.
A comparison with the cost of the two DDG-51s procured in FY15
suggests that, within the estimated combined cost of $3,522.7
million for the two FY16 DDG-51s, the Flight III DDG-51 might ac-
count for, very roughly, $2 billion, while the other DDG-51 might
account for, very roughly, $1.5 billion. The potential difference of,
very roughly, $500 million in cost between the two ships includes
one-time design and change-order costs for modifying the DDG-51
design to the Flight III configuration, additional costs for the AMDR
radar and associated electrical power and cooling equipment, and
some loss of shipyard production learning curve benefits due to the
change in the ship’s design.
The two DDG-51s requested for procurement in FY16 have
received a total of $373.0 million in prior-year advance procure-
ment (AP) funding. The Navy’s proposed FY16 budget requests the
remaining $3,149.7 million needed to complete the ships’ estimated
combined procurement cost. The Navy’s proposed FY16 budget also
requests $75.0 million in so-called cost-to- complete procurement
funding to replace funding for DDG-51s procured in FY10-FY12 that
was canceled by March 1, 2013, sequester. The Navy’s proposed
FY16 budget also requests $433.4 million in procurement funding to
complete construction of Zumwalt- (DDG-1000) class destroyers pro-
cured in prior years, and $241.8 million in research and development
funding for development work on the AMDR. The funding request for
the AMDR is contained in Program Element (PE) 0604522N (“Ad-
vanced Missile Defense Radar [AMDR] System”), which is line 118 in
the Navy’s FY16 research and development account.
WWW.NPEO-kMI.COM20 | APRIl 07, 2015
presence is possible because Navy planning and budget decisions continue to be guided by the three tenets the chief of naval operations (CNO) established when he first took office: Warfighting First, Operate Forward and Be Ready. Each of these tenets helps drive a strong focus on readi-ness—both now and in the future.
Actions of Congress helped stabilize readi-ness by supporting increases over sequestered funding levels through the Bipartisan Budget Act of 2013, and the subsequent authorization and appropriations acts for FY14 and this year. Nonetheless, we have not yet recovered from the readiness impact of over a decade of combat operations, exacerbated by the imposition of a lengthy continuing resolution and followed by budget sequestration in FY13, just as we were beginning to reset the force. These circum-stances created maintenance backlogs that have prevented us from getting ships back to the fleet on time and aircraft back on the flight line. We continue our efforts to rebuild the workforce in our public depots—both shipyards and aviation readiness centers—and reduce the number of lost operational days, but it will take years to dig out of a readiness hole.
The FY16 Navy budget submission is designed to continue our readiness recovery, restoring our required contingency operations capacity by 2018-2020 while continuing to pro-vide a sustainable forward presence. PB-16 is the minimum funding required to execute the na-tion’s defense strategy, though we still carry risks in two important mission areas, notably when confronted with a technologically advanced adversary or when forced to deny the objective of an opportunistic aggressor in a second region while already engaged in a major contingency. As the CNO stated in his recent testimony to the full committee, risk in our ability to deter and defeat aggression and project power despite anti-access/area-denial challenges mean “longer timelines to win, more ships and aircraft out of action in battle, more sailors, Marines and mer-chant mariners killed, and less credibility to deter adversaries and assure allies in the future.” That level of risk arises from capacity and readiness challenges as well as slower delivery of critical capabilities to the fleet, particularly in air and missile defense and overall ordnance capacity.
My testimony today will focus on the current readiness of the Navy, and our plan, sup-ported by our FY16 budget submission, to meet
the challenges to delivering future readiness. If we return to a sequestered budget in FY16, we will not be able to execute the defense strategy as it is conveyed in the 2014 Quadrennial Defense Review and a revision will be required.
Current Navy Operations and Readiness
Employing a combination of forward-deployed naval force ships homeported overseas and rotationally deploying units from CONUS, our Navy sustains a global presence of about 100 ships and submarines. Their combat power and other capabilities include the contributions of embarked carrier air wings or other aviation units, Marine expeditionary units or elements of a special purpose Marine air/ground task force, Coast Guard detachments and special opera-tions units, among others. These capabilities are further enhanced by land-based or expeditionary Navy forces in theater. With additional ships training in home waters, approximately half the battle force is underway or deployed on any given day.
Every hour of every day around the globe we are executing missions. The sun never sets on the U.S. Navy. Ballistic missile submarines sustain the most survivable leg of our nation’s nuclear triad. Carrier strike groups (CSGs), amphibi-ous ready groups (ARGs) and attack submarines (SSNs) conduct named operations in support of the combatant commanders (COCOMs) or exercise with other nations to build the partnerships essential to the stability of the global system. Ballistic missile defense-capable cruisers and destroyers protect U.S. and allied sea and shore-based assets. Our units operate with other nations through exercises or through execut-ing theater security cooperation plans; activities essential to the stability of the global system. As an example, last month, USS Fort Worth (LCS-3) practiced the Code for Unplanned Encounters at Sea with the Chinese Navy, enhancing the professional 4 maritime relationship between the U.S. Seventh Fleet and the People’s Liberation Army-Navy. Our crews and platforms are trained and certified to execute their core capabilities across the spectrum of military operations and are ready to be re-tasked as required to meet the next challenge. This was the case in August 2014 when the George H.W. Bush CSG relocated from the Arabian Sea to the North Arabian Gulf and was on station, ready for combat operations, in less than 30 hours. The Navy is fundamentally
multimission and rapidly adjusts to meet new challenges that might require U.S. presence and power projection forces.
Navy will continue to sustain the readiness of our deployed forces under our FY16 budget submission, but it will require several years to fully recover the capability to rapidly respond to COCOM requirements for a major contin-gency. In addition to our forces that are globally deployed today, combined requirements include: three extra CSGs and three ARGs to deploy within 30 days to respond to a major crisis. However, on average, we have only been able to keep one CSG and one ARG in this readiness posture, one-third of the requirement. Assuming the best case of an on-time, sufficient and stable budget with no major contingencies, we should be able to recover from accumulated backlogs by 2018 for CSGs and 2020 for ARGs—five-plus years after the first round of sequestration.
Recovery of readiness also requires a com-mitment to protect the time required to properly maintain and modernize our capital-intensive force and to conduct full-spectrum training. Our updated force generation model—the Optimized Fleet Response Plan (OFRP)—is designed to meet this commitment as well as better align all elements that support readiness development. Achieving full readiness entails the restoration of required capacity to our public shipyards and aviation depots—primarily through hiring and workforce development. In addition to aviation depots backlogs, we must also overcome the chal-lenges of extending the service life of our legacy F/A-18 Hornet aircraft to 10,000 hours. Under-lying our plan is the need to operate the battle force at a sustainable level over the long term. With this plan, we recover our material readiness, keep faith with our sailors and their families by providing more predictability in the operations schedule, and control the pace of deployments.
Meeting Our Readiness Challenges
The Navy FY16 budget request continues to fully support the readiness of our deployed forces. The budget request sustains our credible and sur-vivable sea-based strategic deterrent and with con-tinued overseas contingency operations (OCO) funding meets the adjudicated requirements of the FY16 Global Force Management Allocation Plan (GFMAP). This includes at least two CSGs and two ARGs, operating forward, fully mission-capable and certified for deployment. We continue
Naval Readiness➥ continued fRoM paGe 1
APRIl 07, 2015 | 21WWW.NPEO-kMI.COM
to employ innovative approaches, including the use of new platforms like the joint high-speed vessel and the mobile landing platform, to ensure the Navy/Marine Corps team continues to meet the security requirements of our nation, while providing the opportunity to reset and sustain the material condition of the force. Greater use of capable auxiliaries helps relieve pressure on our overstretched amphibious fleet.
Generating the Force
Navy readiness is at its lowest point in many years. Budget reductions forced cuts to afloat and ashore operations, generated ship and aircraft maintenance backlogs, and compelled us to ex-tend unit deployments. Since 2013, many ships have been on deployment for eight to 10 months or longer, exacting a cost on the resiliency of our people, sustainability of our equipment, and service life of our ships.
Navy has managed force generation using the Fleet Response Plan (FRP) since it was adopted in 2003 and fully implemented in 2007. This cyclic process was designed to support readiness by synchronizing periodic deep maintenance and modernization with the fleet training required to achieve GFMAP forward presence objectives and provide contingency response capacity. However, the continued employment of our contingency response units to generate increased presence over the past decade has not only increased main-tenance requirements, it has also limited their availability to complete required maintenance and training. As with previous testimony of the last few years, this practice is unsustainable.
In 2013 and 2014, for example, naval forces provided 6 percent and 5 percent more forward presence, respectively, than allocated due to emer-gent operations and unanticipated contingencies. This unbudgeted employment amounted to great-er than 2,200 days in theater over that approved on the global force management plan in 2013 and greater than 1,800 days in theater over in 2014. We should operate the fleet at sustainable presence levels in order for the Navy to meet requirements, while still maintaining material readiness, giving ships time to modernize, and allowing them to reach their expected service lives.
This year, Navy began implementation of the Optimized Fleet Response Plan (OFRP) to address these challenges. Designed to stabilize maintenance schedules and provide sufficient time to maintain and train the force while continuing to meet operational commitments, OFRP aligns supporting processes and resources to improve overall readiness. Furthermore, it provides a more stable and predictable schedule for our sailors and
their families. We will continue OFRP implemen-tation across the FYDP.
Ship Operations
The baseline Ship Operations request for FY16 provides an average of 45 underway steam-ing days per quarter for deployed ships and 20 days non-deployed, and would support the highest priority presence requirements of the combatant commanders to include global presence for two CSGs, two ARGs and an acceptable number of deployed submarines. With OCO, ship operations are funded at 58 steaming days deployed/24 days non-deployed. The requested funding will meet the full adjudicated FY16 GFMAP ship presence requirement, support higher operational tempo for deployed forces and provide full operating funding for individual ship-level maintenance and training.
Air Operations (Flying Hour Program)
The Flying Hour Program funds opera-tions, intermediate and unit-level maintenance, and training for ten Navy carrier air wings, three Marine Corps air wings, fleet air support aircraft, training squadrons, reserve forces and various enabling activities. The FY16 baseline program provides funding to build required levels of readi-ness for deployment and sustain the readiness of units that are deployed. Navy and Marine Corps aviation forces are intended to achieve an average T-2.5/T-2.0 USN/USMC training readiness requirement with the exception of non-deployed
F/A-18 (A-D) squadrons. Because of shortfalls in available aircraft due to depot throughput issues, these squadrons are funded at the maximum ex-ecutable level while non-deployed, resulting in an overall readiness average of T-2.8/2.4. All squad-rons deploy meeting the T-2.0 readiness require-ment and OCO provides for additional deployed operating tempo above baseline funding.
Spares
The replenishment of existing, “off the shelf” spares used in ship and aircraft maintenance is funded through the Ship Operations and Flying Hour Programs. With OCO, those programs are fully funded in PB16. The provision of initial and outfitting spares for new platforms, systems and modifications is funded through the spares accounts. Traditionally, these accounts have been funded below the requirement due to limited funding or past execution issues. Due to the ulti-mate impact on readiness, PB16 sustains execut-able funding levels to reduce cross-decking and cannibalization of parts driven by large backlogs. This is complemented by Navy-wide efforts to improve execution of these accounts, which have shown considerable success in aviation spares over the last two years, and continues to be a focus area.
Readiness Investments Required to Sustain the Force: Ship and Aircraft Maintenance
The Navy maintenance budget requests are built upon proven sustainment models. They
WWW.NPEO-kMI.COM22 | APRIl 07, 2015
are focused on continuing our ongoing invest-ment to improve material readiness of our surface combatants, and support the integration of new capabilities into naval aviation.
The FY16 baseline budget request funds 80 percent of the ship maintenance requirement across the force, addressing both depot and inter-mediate level maintenance for carriers, submarines and surface ships. OCO funding provides the remaining 20 percent of the full baseline require-ment to continue reduction of the backlog of life cycle maintenance in our surface ships after years of high operational tempo and deferred maintenance. This year, the additional OCO for maintenance reset ($557 million) includes fund-ing for aircraft carriers as well to address increased wear and tear outside of the propulsion plant as a result of high operational demands. Since much of this work can only be accomplished in drydock, maintenance reset must continue across the FYDP.
To address the increased workload in our public shipyards and improve on-time delivery of ships and submarines back to the fleet, the FY16 budget grows the shipyard workforce, reaching a high of 33,500 personnel in FY17, with additional investment in workforce training and develop-ment. One attack submarine (SSN) availability is moved to the private sector in FY16 with plans for two additional SSN availabilities in the private sector in FY17 to mitigate total workload. The FY16 budget includes $89.5 million in MILCON projects and $142M in restoration and modern-ization projects for naval shipyards in FY16, for a total capital investment of 8.7 percent in these important facilities.
The Fleet Readiness Centers (FRCs), Navy’s aviation depots, have been challenged to recover full productivity after hiring freezes, furlough, and overtime restrictions in FY13. They face a growing workload, particularly for the additional service life extension of our legacy F/A-18 Hornets. FRCs are aggressively hiring with a goal of reaching full capacity by the end of this year. The hiring of additional engineering support to address new repairs required to reach 10,000 hours of service life, reallocation of some of the workforce, and contracting for private sector support have all been undertaken to complete existing work-in-process at the FRCs, particularly for legacy Hornets. Field teams have been increased to improve flight line maintenance and understanding of the material condition of airframes coming to the depots. As new repairs and parts are identified and approved, kits are developed to ensure long-lead parts are readily available.
As a result of these challenges, the Aviation Depot Maintenance program is funded to an executable level of 77 percent in baseline, 83
percent with OCO for new work to be inducted in FY16. This funding level supports a total of 564 airframes and 1,834 engines/engine modules to be repaired.
Navy Expeditionary Combat Forces
Navy expeditionary combat forces support ongoing combat operations and enduring combatant commander requirements by deploy-ing maritime security, construction, explosive ordnance disposal, logistics and intelligence units to execute missions across the full spectrum of naval, joint and combined operations. In FY16, baseline funding is improved significantly over 10 prior years, providing 80% of the enduring requirement, with OCO supporting an additional 15% of the requirement.
Readiness Investments Required to Sustain the Force: Shore Infrastructure
The Navy’s shore infrastructure, both in the United States and overseas, provides essential support to our fleet. In addition to supporting op-erational and combat readiness, it is also a critical element in the quality of life and quality of work for our sailors, Navy civilians and their families. As we have done for several years, we continue to take risk in the long-term viability of our shore infrastructure to sustain fleet readiness under the current funding level. However, in FY16 our facilities sustainment is improved to 84 percent of the OSD Facilities Sustainment Model versus 70 percent this year. When restoring and moderniz-ing our infrastructure, we intend to prioritize life/safety issues and efficiency improvements to exist-ing infrastructure and focus on repairing only the
key components of our mission critical facilities. Less critical projects will remain deferred. Overall, the Department of the Navy will exceed the mandated capital investment of 6 percent across all shipyards and depots described in 10 USC 2476 with a 7.4 percent total investment in FY16. With the support provided by the Congress, Navy is on track to exceed the minimum investment in FY15 as well.
Looking Ahead
As we look to the future, the Navy will con-tinue to be globally deployed to provide a credible and survivable strategic deterrent and to support the mission requirements of the regional combat-ant commanders. Global operations continue to assume an increasingly maritime focus, and our Navy will sustain its forward presence, warfighting focus, and readiness preparations to continue op-erating where it matters, when it matters. We see no future reduction of these requirements and we have focused the FY16 Navy budget submission to address the challenges to achieving the necessary readiness to execute our missions. Any funding be-low this submission requires a revision of America’s defense strategy. Sequestration would outright damage the national security of this country.
In closing, we should recall that our sailors are the most important element of the future readiness of the Navy. Fortunately, they are the highest quality, most diverse force in our his-tory and continue to make us the finest Navy in the world. As the CNO says, “They are our asymmetric advantage.” On behalf of all our sailors (active and reserve), civilians and their families, let me reiterate our appreciation for the continued support of the members of the com-mittee.
APRIl 07, 2015 | 23WWW.NPEO-kMI.COM
ContraCt awarDs
The Navy is awarding indefinite-
delivery/indefinite-quantity, multiple-
award contracts to 464 contractors that
will provide for their competition for
service requirements solicited by Naval
Sea Systems Command, Naval Air
Systems Command, Space and Naval
Warfare Systems Command, Naval
Supply Systems Command, Military
Sealift Command, Naval Facilities
Command, Strategic Systems Programs,
Office of Naval Research and the Marine
Corps. The 22 functional service areas
within the scope of the contracts include:
1) research and development support; 2)
engineering system engineering and
process engineering support; 3)
modeling, simulation, stimulation and
analysis support; 4) prototyping,
pre-production, model-making and fabric
support; 5) system design documenta-
tion and technical data support; 6)
software engineering, development,
programming and network support; 7)
reliability, maintainability and availability
support; 8) human factors, performance
and usability engineering support; 9)
system safety engineering support; 10)
configuration management support; 11)
quality assurance support; 12) informa-
tion system development, information
assurance and information technology
support; 13) ship inactivation and
disposal support; 14) interoperability, test
and evaluation, trials support; 15)
measurement facilities, range and
instrumentation support; 16) acquisition
logistics support; 17) supply and
provisioning support; 18) training
support; 19) in-service engineering, fleet
introduction, installation and checkout
support; 20) program support; 21)
functional and administrative support;
and 22) public affairs and multimedia
support. These contracts are in addition
to the existing 2,420 contracts previously
awarded under the SeaPort Enhanced
(SeaPort-e) acquisition program for
services procurements. The government
estimates a maximum of $5,300,000,000
of services will be procured per year via
orders issued under the SeaPort-e
multiple award contracts. The award of
these contracts is a result of the
SeaPort-e Rolling Admissions solicita-
tion. The SeaPort-e acquisition is
comprised of seven regional zones in
which task orders will be competed
based upon the principal place of
performance. These awards contain
provisions to set aside requirements for
small businesses, service-disabled
veteran-owned small businesses, 8a
business development program and
historically underutilized business zone
small businesses. Under these multiple
award contracts, each contractor will be
provided a fair opportunity to compete
for individual task orders solicited within
their zone or zones of performance. The
awards will have four-year periods of
performance. These contracts were
competitively procured via the Navy
Electronic Commerce Online website,
with 612 offers received and 464
contracts awarded. Contract funds will
be obligated at the time of task order
award and, multiple funding types with
varying expiration dates may be used,
consistent with the purpose for which the
funds were appropriated. The Naval
Surface Warfare Center, Dahlgren
Division, Dahlgren, Va., is the contracting
activity (N00178-15-D-8053 -- N00178-
15-D-8516). The list of contractors
involved are: 11th Hour Search llC
doing business as 11 Hour Service,
Springfield, Va.; 2rbConsulting Inc.,
kirkland, Wash.; 3T Federal Solutions
llC, Austin, Texas; 838 Inc., Folsom,
Calif.; Abacus Technology Corp., Chevy
Chase, Md.; Acadia Cyber Solutions
llC, Rockville, Md.; AccessAgility llC
doing business as AccessAgility,
Bethesda, Md.; ActioNet Inc., Vienna,
Va.; Adsys Controls Inc., Irvine, Calif.;
Advance Digital Systems Inc. doing
business as ADS, Fairfax, Va.; Advanced
Technologies and laboratories Interna-
tional Inc., Gaithersburg, Md.; AEEC, llC
doing business as American Consultants,
Reston, Va.; Aerosol Monitoring &
Analysis, Hanover, Md.; Aerospace
Engineering & Support Inc. doing
business as AES, Ogden, Utah; AG
GRACE Inc., Frederick, Md.; Agile
Communications Inc., Thousand Oaks,
Calif.; Airport Properties Inc. doing
business as AP IT Solutions, California,
Md.; Alaris Companies, Petaluma, Calif.;
All Native Inc., Winnebago, Neb.; AllCom
Global Services Inc., lake Saint louis,
Mo.; Alliant keystone Consulting Partners
llC, Houston, Texas; Altus Technical
Solutions llC doing business as Altus
Technology Solutions, Severn, Md.;
AMEC Foster Wheeler Environment &
Infrastructure Inc., Blue Bell, Pa.;
Anglicoelectric llC, North Charleston,
S.C.; ANR Consulting Group Inc.,
Addison, Texas; Applied Information
Sciences Inc., Reston, Va.; Applied
Intellect, Wexford, Pa.; Applied Tech-
niques Corp. doing business as ATC,
Silverdale, Wash.; Appsential llC,
Bethesda, Md.; Aptima Inc., Woburn,
Mass.; Archimedes Global Inc., Wesley
Chapel, Fla.; Ardmore Consulting Group
Inc., Atlanta, Ga.; ARGO Systems llC,
Hanover, Md.; Arrow Solutions Group
Inc., Billings, Mont.; Arrowpoint Corp.,
Alexandria, Va.; Artel llC, Herndon, Va.;
ASJ IT Services llC, Chesapeake, Va.;
Assured Consulting Solutions llC,
Fairfax, Va.; Atlas Group ltd., Fairfax, Va.;
Atlas Technologies Inc., North Charles-
ton, S.C.; Audavi Corp., San Jose, Calif.;
Automation Technologies Inc. doing
business as ATI, Columbia, Md.; Avatar
Partners Inc, Huntington Beach, Calif.;
Avening Management and Technical
Services llC doing business as
AveningTech, la Plata, Md.; AVUM Inc.,
Agoura, Calif.; Bacik Group llC, Pelham,
Ala.; Banda Group International llC,
Chandler, Ariz.; Banneker Industries Inc.,
North Smithfield, R.I.; Barquin and
Associates Inc. doing business as
Barquin International, Washington, D.C.;
Bart & Associates Inc. doing business as
B&A, Mclean, Va.; BB&E Inc., Northville,
Mich.; BCF Solutions Inc., Arlington, Va.;
Beat llC doing business as Business
Enabled Acquisition & Technology, San
Antonio, Texas; Bennett Aerospace Inc.,
Cary, N.C.; Biscotti, Giacomo doing
business as ATCSI, Chesapeake, Va.;
Biswas Information Technology Solutions
Inc. doing business as BITS, Herndon,
2APrIl
WWW.NPEO-kMI.COM24 | APRIl 07, 2015
Compiled by KMI Media Group staff
Va.; Black knight Technology Inc.,
Fredericksburg, Va.; Black Tree Group
llC doing business as Black Tree Group,
Tampa, Fla.; Brace Management Group
Inc., Upper Marlboro, Md.; Brockwell
Technologies Inc., Huntsville, Ala.;
Buchanan & Edwards Inc., Arlington, Va.;
Burns & McDonnell Engineering Co. Inc.,
kansas City, Mo.; Business Management
Associates Inc. , Alexandria, Va.; By light
Professional Services Inc., Arlington, Va.;
C² Technologies Inc., Vienna, Va.; C4
Planning Solutions llC, Blythe, Ga.;
Canterbury Resources Inc., Alexandria,
Va.; Canvas Inc., Huntsville, Ala.; Capital
Strategies llC, leesburg, Va.; CB&I
Federal Services llC, Baton Rouge, la.;
Celerity Government Solutions llC doing
business as Xcelerate Solutions, Mclean,
Va.; Centech Group Inc., Falls Church,
Va.; Centeva llC, South Jordan, Utah;
Certified Technical Experts Inc. doing
business as CTE, Montgomery, Ala.;
Chakrabarti Management Consultancy
Inc. doing business as CMCI, Fairfax, Va.;
Chenault-Herbert, Johnnie Maria doing
business as MCH Consulting Services,
Suffolk, Va.; Chenega Support Services
llC, San Antonio, Texas; Cherokee
Energy Management & Construction Inc.,
Virginia Beach, Va.; Cherokee Information
Services Inc. doing business as CIS,
Alexandria, Va.; Chimera Enterprises
International Inc., Edgewood, Md.; Chitra
Productions llC, Virginia Beach, Va.;
Chugach Information Technology Inc.,
Anchorage, Alaska; Clarus Group llC,
Overland Park, kan.; Clason Point
Partners Inc., Yonkers, N.Y.; Cline-Morin
Associates, Huntsville, Ala.; Command
Post Technologies Inc., Suffolk, Va.;
Companion Data Services llC,
Columbia, S.C.; Competitive Innovations
llC doing business as CI, Arlington, Va.;
Computek Inc. doing business as
Tidewater Naval Architects, Portsmouth,
Va.; Computing Technologies Inc.,
Fairfax, Va.; Control Point Corp., Goleta,
Calif.; Conviso Inc., luray, Va.; CorDel
Information Security Services llC doing
business as CorDel, Sunnyvale, Calif.;
Cornerstone Defense, Ellicott City, Md.;
Corp of Mercer University, The doing
business as Mercer Engrg Res Ctr,
Warner Robins, Ga.; Cosmic Software
Technology Inc., Princeton, N.J.; Cowan
& Associates Inc., Arlington, Va.; Creative
Information Technology Inc., Falls
Church, Va.; Creek Technologies Co.
doing business as Creek Tech, Beaver-
creek, Ohio; Crescent Allied Solutions
Inc., Irvine, Calif.; CRI Advantage Inc.,
Boise, Idaho; Crisis Response Co. llC,
Roanoke, Texas; Critical-Path-Solutions
Inc., Moorpark, Calif.; Cubic Applications
Inc., San Diego, Calif.; D9Tech Resources
llC, Virginia Beach, Va.; Dane llC,
Chantilly, Va.; Darkblade Systems Corp.,
Stafford, Va.; Data Intelligence llC,
Marlton, N.J.; Data Matrix Solutions Inc.,
Herndon, Va.; linda M. Davies doing
business as Comprehensive Professional
and Proposal Services (CP2S), Freder-
icksburg, Va.; Dayton T. Brown Inc.,
Bohemia, N.Y.; Defense Acquisition &
logistics Solutions llC doing business
as DAlS, Norfolk, Va.; Defense Venture
Holdings llC doing business as DVH,
Virginia Beach, Va.; DefTec Corp. doing
business as DefTec, Huntsville, Ala.;
Delex Systems Inc., Herndon, Va.;
DeVilliers Technology Solutions llC
doing business as DeVil-Tech, Stafford,
Va.; DeVine Consulting Inc., Fremont,
Calif.; Dial & Associates llC, California,
Md.; DigiFlight Inc., Columbia, Md.;
Digital Cloak llC, Stafford, Va.; Disk
Enterprise Solutions Inc., lexington Park,
Md.; Dnutch Associates Inc., Methuen,
Mass.; Dominion Energy Management
Inc., Ashland, Va.; Donnelly & Moore Inc.,
New City, N.Y.; DWBH llC doing
business as DWBH, Mclean, Va.;
Dynamic Animation Systems Inc. doing
business as DAS, Fairfax, Va.; Dynamic
Aviation Group Inc., Bridgewater, Va.; E.
k. Fox & Associates ltd., Fairfax, Va.;
E.M. Norton Enterprises Inc. doing
business as EMN Defense Services, San
Diego, Calif.; E3 Federal Solutions llC,
Arlington, Va.; Eagle TG llC, New
Braunfels, Texas; Eiden Systems Corp.,
Charlottesville, Va.; Elevan llC doing
business as Elevate Systems, San
Antonio, Texas; ElEVI Associates llC,
Columbia, Md.; EliteTech Associates llC
doing business as EliteTech Associates,
San Diego, Calif.; Emerging Technology
Ventures Inc., Alamogordo, N.M.;
EmeSec Inc. doing business as
EMESEC, Reston, Va.; Emprise Corp.,
ledyard, Conn.; Endyna Inc., Mclean,
Va.; Engenuity llC, Edgewater, Md.;
Enterprise Solutions & Management,
Chula Vista, Calif.; Enterprise Systems
Management llC, leonardtown, Md.;
Envistacom llC, Atlanta, Ga.; Ernst &
Young llP, Washington, D.C.; eScience
& Technology Solutions Inc., North
Charleston, S.C.; Evoke Research and
Consulting llC, Arlington, Va.; Excella
Consulting Inc., Arlington, Va.; Excelsior
Consulting Services Inc., Westmont, Ill.;
Expression Networks llC, Mclean, Va.;
FEDITC llC doing business as Federal
Integrated Engineering Consulting,
Rockville, Md.; Fednova Inc., Alexandria,
Va.; Filius Corp., Centreville, Va.; First
Division Consulting Inc., Arlington, Va.;
Five Stones Research Corp., Browns-
boro, Ala.; Fluor Intercontinental Inc.,
Greenville, S.C.; Foresight Engineering
P.C., Reston, Va.; FreeAlliance.com llC,
Washington, D.C.; Frontier Technology
Inc., Goleta, Calif.; Full Circle Computing
Inc., Exton, Pa.; G & H International
Services Inc., Washington, D.C.; G Force
Inc., Washington, D.C.; GAMA-1
Technologies llC, Greenbelt, Md.; GAP
Solutions Inc. doing business as GAPSI,
Reston, Va.; GeminiTech llC doing
business as GeminiTech, Waipahu,
Hawaii; Gemini Technologies Inc.,
Warrington, Pa.; General Infomatics Inc.,
Mclean, Va.; Geowireless Inc., North
Charleston, S.C.; Global Data Solutions
Inc. doing business as GDS, Blooming-
ton, Ill.; Global Infotek Inc., Reston, Va.;
Global Management Systems Inc. doing
business as GMSI, Washington, D.C.;
Global Productivity Solutions llC,
Clinton Township, Mich.; Global
Research and Technology Corp.,
Camarillo, Calif.; Global Technical
Services llC, Anchorage, Alaska;
Government Tactical Solutions llC,
Potomac Falls, Va.; GPH Consulting llC,
Charleston, S.C.; Green Expert Technol-
ogy Inc., Cherry Hill, N.J.; GRT Corp.,
APRIl 07, 2015 | 25WWW.NPEO-kMI.COM
Stamford, Conn.; Guardian Moving and
Storage Co. Inc., Hunt Valley, Md.;
Guardians of Honor llC, Oxon Hill, Md.;
Guerrero Professional Services Inc. doing
business as Dr. Diesel Technologies,
Temecula, Calif.; Cignus Consulting llC,
leesburg, Va.; Halfaker and Associates
llC, Arlington, Va.; Hana Industries Inc.,
Honolulu, Hawaii; Harris IT Services
Corp., Herndon, Va.; Hawk Associates
llC, Sierra Vista, Ariz.; HazTrain Inc.,
Waldorf, Md.; Helios Remote Sensing
Systems Inc., Rome, N.Y.; Higgins,
Hermansen, Banikas llC, Reston, Va.;
High Side Technology llC, California,
Md.; HigherEchelon Inc., Arlington, Va.;
Highlight Technologies llC, Fairfax, Va.;
Horizon Industries ltd., Vienna, Va.; The
Human Geo Group, Arlington, Va.;
Hyperion Inc., Reston, Va.; IAP World-
wide Services Inc., Cape Canaveral, Fla.;
i-Mazing Solutions Inc., Virginia Beach,
Va.; Impact Makers Inc., Richmond, Va.;
Inalab Consulting Inc., Stafford, Va.;
Independent Strategic Management
Solutions Inc. doing business as
ISMSolutions, Richland, Wash.; Indig-
enous Intelligence llC doing business as
Indigenous, Glen Burnie, Md.; IndraSoft
Inc., Reston, Va.; Indtai Inc., Sterling, Va.;
Infinity Systems Engineering llC,
Colorado Springs, Colo.; Ingenicomm
Inc., Chantilly, Va.; Innovative Technical
Solutions llC, Paducah, ky.; Innovative
Technologies Inc. doing business as ITI,
Chantilly, Va.; Innovatus Technology
Consulting, San Diego, Calif.; Inode Ink
Corp., Westminster, Colo.; Inserso Corp.,
Vienna, Va.; Integrated Data Services
Inc., El Segundo, Calif.; Integrated Design
Solutions llC, Bohemia, N.Y.; Integrated
Finance and Accounting Solutions llC
doing business as IFAS, Woodbridge,
Va.; Integrated Video Solutions llC doing
business as IVS, Chesapeake, Va.;
Integrity Consulting Engineering &
Security Solutions llC, Frederick, Md.;
Intelesis Technologies Corp. doing
business as Intelesis, San Diego, Calif.;
IntellecTechs Inc., Virginia Beach, Va.;
Intepros Federal Inc., Washington, D.C.;
Intercom Federal Systems Corp.,
leesburg, Va.; Invictus Technical
Solutions llC, Roseburg, Ore.; Iron Wind
Associates llC, Ashburn, Va.; ISHPI
Information Technologies Inc. doing
business as ISHPI, Mount Pleasant, S.C.;
iSoft Solutions llC, Virginia Beach, Va.;
J. Aguinaldo Group Inc., Hollywood, Md.;
JD Ross Consulting llC, Fredericksburg,
Va.; JlGov llC, Virginia Beach, Va.;
Johnston Pierce Engineering llC, Duluth,
Ga.; JTEl Solutions llC, Fredericksburg,
Va.; kairos Inc., California, Md.; karago-
zian & Case, Glendale, Calif.; kAYA
Associates Inc., Huntsville, Ala.; kearney
& Co. P.C., Alexandria, Va.; kelley's
logistics Support Systems Inc. doing
business as klSS, Dayton, Ohio;
kENTCO Corp. doing business as
ProteQ, Reston, Va.; kerberos Interna-
tional Inc., Temple, Texas; keThink SFS,
lexington Park, Md.; key Group Inc.,
Fillmore, Calif.; key Innovations Inc.,
Orlando, Fla.; key Management Solutions
llC doing business as kMS, Colorado
Springs, Colo.; keystone Advisors llC,
South Holland, Ill.; kforce Government
Solutions Inc., Fairfax, Va.; kinetic
Multimedia Systems Inc., Fort lauder-
dale, Fla.; kM Management Group llC
doing business as kM Systems Group,
Arlington, Va.; kMEA, National City, Calif.;
knowledge Based Systems Inc., College
Station, Texas; kova Global Inc., Virginia
Beach, Va.; kSJ & Associates Inc., Falls
Church, Va.; kyzen Consulting Services
Inc. doing business as Nu Staffing
Solutions, West Palm Beach, Fla.; land
Sea Air Autonomy llC doing business as
lSA Autonomy, Westminster, Md.;
leverage Information Systems Inc. doing
business as Federal Network Services,
Woodinville, Wash.; liberty IT Solutions
llC, Reston, Va.; limelight Consulting
Services Inc., Mechanicsburg, Pa.;
lingual Information System Technologies
Inc. doing business as lG-TEk, Elkridge,
Md.; link Tech, llC doing business as
link Technologies, las Vegas, Nev.; lJT
& Associates Inc., Columbia, Md.; loyal
Source Government Services llC,
Orlando, Fla.; lRH Group llC, Stafford,
Va.; lynker Technologies llC, leesburg,
Va.; lynxnet llC, Suffolk, Va.; MDA Tech-
nologies llC doing business as MDA
Technologies, Woodbridge, Va.; Maden
Tech Consulting Inc. doing business as
Maden Technologies, Arlington, Va.;
Mainstay Information Solutions, Arlington,
Va.; Management and Administrative
Support llC, Glen Burnie, Md.; Marine
Design Dynamics Inc. doing business as
MDD, Washington, D.C.; Markesman llC
doing business as Markesman Group,
Newport News, Va.; MARRS Services
Inc., Buena Park, Calif.; Mathematical
Research Inc. doing business as MRI
Technologies, Houston, Texas; MATH-
TECH Inc., Falls Church, Va.; MDA
Information Systems llC, Gaithersburg,
Md.; Media Fusion Inc. doing business as
MFI, Huntsville, Ala.; MICRO USA Inc.,
Poway, Calif.; Microhealth llC, Vienna,
Va.; Military Personnel Services Corp.,
Falls Church, Va.; Mora Consultants, San
Diego, Calif.; MorganFranklin Consulting
llC doing business as MorganFranklin,
Mclean, Va.; Na Alii Consulting & Sales
llC doing business as Na Alii, Honolulu,
Hawaii; Nationwide IT Services Inc.,
Alexandria, Va.; Native Hawaiian Veterans
llC, Honolulu, Hawaii; Neany Inc.,
Hollywood, Md.; Nester Consulting llC
doing business as Government CIO,
Washington, D.C.; Network Security
Services llC doing business as NSS,
Vienna, Va.; Nevada System of Higher
Education doing business as Desert
Research Institute, Reno, Nev.; NextGen
Inc., Fairfax, Va.; Nextrinsic Corp.,
Southfield, Mich.; Nextstep Technology
Inc. doing business as Rightstep
Services, Morgan Hill, Calif.; n-link Corp.,
Bend, Ore.; Noovis llC, Hanover, Md.;
NorthTide Group llC, Dulles, Va.; NTT
Data Federal Services Inc., Vienna, Va.;
Oakland Consulting Group Inc., lanham,
Md.; Obera llC, Herndon, Va.; Open San
Consulting llC, Atlanta, Ga.; OPTECH
llC, Troy, Mich.; Optimal Technologies
International llC doing business as OTI,
Orlando, Fla.; Optimum Software
Solutions Inc., Tallahassee, Fla.; Organic
Motion Inc., New York, N.Y.; Oroday Inc.
doing business as Digital Consulting
Services, Newbury Park, Calif.; Osi Vision
llC, San Antonio, Texas; OTD Solutions
& Services llC, North Charleston, S.C.;
ContraCt awarDs
WWW.NPEO-kMI.COM26 | APRIl 07, 2015
O-Tech Solutions llC, Green Bay, Wis.;
PAE Applied Technologies llC, Fort
Worth, Texas; Pagnotta Engineering Inc.,
Exton, Pa.; Panaceapro Corp., Fairfax,
Va.; Paratusec llC, Warrenton, Va.; Parra
Consulting Group Inc., Middletown, Md.;
Iode Inc. doing business as I/O Test, Salt
lake City, Utah; PEMCCO Inc., Virginia
Beach, Va.; People, Technology and
Processes llC, lakeland, Fla.; Peo-
pleTec Inc. doing business as Peopletec,
Huntsville, Ala.; Performix Consulting llC
doing business as: Performix Consulting,
Mclean, Va.; Phase One Consulting
Group Inc., Alexandria, Va.; Phoenix Data
Corp., Indianapolis, Ind.; Pioneer
Technologies Inc., Fairfax, Va.; PITSC
Inc., Jacksonville, Fla.; Pl Systems llC,
Centreville, Va.; Plexus Installations Inc.
doing business as Plexus Communica-
tions Group, Baltimore, Md.; Point Rock
Solutions llC, lansdowne, Va.; Potomac
River Enterprise Solutions llC doing
business as PRES, Fredericksburg, Va.;
Pragmatics Inc., Reston, Va.; Precision
Air Inc., Manning, S.C.; Premier Inc.
doing business as Premier Analysis, Falls
Church, Va.; Prevailance Inc., Virginia
Beach, Va.; Product Data Integration
Technologies Inc. doing business as
Modulant, North Charleston, S.C.;
Productivity Apex Inc., Orlando, Fla.;
PROJECTXYZ Inc., Huntsville, Ala.;
Proofpoint Systems Inc. doing business
as Proofpoint, los Altos, Calif.; ProSidian
Consulting llC, Charlotte, N.C.; PUlAU
Corp., Orlando, Fla.; Qnexis Inc., Reston,
Va.; Quality Aero Inc. doing business as
Acquisition logistics Engrg, Worthington,
Ohio; Quantum Dynamics Inc., Mclean,
Va.; Radiation Safety & Control Services
Inc. doing business as RSCS, Stratham,
N.H.; RBR-Technologies, Annapolis,
Maryland; The Red Gate Group ltd.,
Chantilly, Va.; Red River Computer Co.
Inc., Claremont, N.H.; Reliable Systems
Solutions llC doing business as RSS
logistics, Orlando, Fla.; ReMilNet llC,
Jacksonville, Fla.; Renegade Technology
Systems Inc., Reston, Va.; The RHarvey
Group llC, Mclean, Va.; Ricardo Inc.,
Belleville, Mich.; Rigil Corp., lorton, Va.;
Riptide Software Inc., Oviedo, Fla.; RMW
Associates llC doing business as RMW
Associates, Camp Springs, Md.;
Rohmann Services Inc. doing business
as RSI, San Antonio, Texas; Rome
Research Corp. doing business as RRC,
Rome, N.Y.; RPI Group Inc., Fredericks-
burg, Va.; Ryan Consulting Group Inc.,
Indianapolis, Ind.; Saile Technologies
doing business as OnBridge Technolo-
gies, Foothill Ranch, Calif.; SAWTST llC,
Peachtree City, Ga.; Science and
Management Resources Inc. doing
business as SMR, Pensacola, Fla.;
Scientific and Commercial Systems Corp.
doing business as SCSC Quality
Assurance Services, Falls Church, Va.;
Seaward Services Inc., New Albany, Ind.;
Secure Data Inc., O Fallon, Ill.; Sehlke
Consulting llC, Arlington, Va.; Select-
Tech Services Corp., Centerville, Ohio;
Seville Staffing llC, Chicago, Ill.; Si
Global Inc., West Point, Ga.; Siena Group
llC, The doing business as A&M
Restoration Services, Cocoa Beach, Fla.;
SigmaRiver llC, Front Royal, Va.; Signet
Technologies Inc., Beltsville, Md.; Silver
Bear Technologies Inc. doing business as
SBT, Stafford, Va.; Sinergy Solutions llC,
Triangle, Va.; SJ Technologies Inc.,
Buford, Ga.; Skyward ltd., Dayton, Ohio;
SMS Data Products Group Inc. doing
business as SMS, Mclean, Va.; Social
Intelligence Corp., Santa Barbara, Calif.;
Sonawane WebDynamics Inc., Ashburn,
Va.; Southeast Safety Solutions llC
doing business as SES Solutions,
Huntsville, Ala.; SPC Business Consult-
ing, Waldorf, Md.; Special Applications
Group llC, Tampa, Fla.; Spectrum
Comm Inc., Newport News, Va.;
Spotswood Consulting doing business as
SC Wireless Solutions, Huntington
Beach, Calif.; SRR International Inc.,
loxahatchee, Fla.; Stafford Consulting
Co. Inc., Fairfax, Va.; Starry Associates
Inc., Annapolis, Md.; StellarPeak Corp.,
Mclean, Va.; Storsoft Technology Corp.,
Tampa, Fla.; Strategic Alliance Business
Group llC, Arlington, Va.; Strategic
Communications llC, louisville, ky.;
Strategic Resolution Experts Inc. doing
business as S R E, Martinsburg, W.Va.;
Strategic Resources Inc., Mclean, Va.;
Strategic Ventures Consulting Group
llC, Falls Church, Va.; Sumaria Systems
Inc., Danvers, Mass.; Sylvain Consulting
Inc. doing business as SAI, Albuquerque,
N.M.; Symtech Corp., Sarasota, Fla.;
Syneren Technologies Corp., College
Park, Md.; Synergy Business Innovation
& Solutions Inc., Arlington, Va.; Synergy
ECP llC doing business as Synergy
ECP, Columbia, Md.; Synesis7 Corp.,
Butte, Mont.; Syngineering llC,
Annandale, Va.; System Dynamics
International Inc. doing business as SDI,
Huntsville, Ala.; System Modeling Experts
llC doing business as SME, Mclean,
Va.; Systems and Proposal Engineering
Co. doing business as SPEC Innovations,
Manassas, Va.; Systems Integration/
Modeling and Simulation Inc., Tullahoma,
Tenn.; Systems Research Group Inc.
doing business as SRG, longwood, Fla.;
Systems Support Alternatives Inc. doing
business as SSA, Alexandria, Va.; Syzygy
Technologies Inc., San Diego, Calif.; T.J.
Drafting & Design Inc. doing business as
T.J., Christmas, Fla.; T3W Business
Solutions Inc., San Diego, Calif.; Tactical
Electronics & Military Supply llC, Broken
Arrow, Okla.; TATE Inc., Stafford, Va.;
Taygeta Scientific Inc., Monterey, Calif.;
TConneX Inc., Mclean, Va.; TD&S
Associates Inc. doing business as
Technology Decisions & Solutions, State
College, Pa.; TDI Technologies Inc., king
of Prussia, Pa.; TechAnax llC, Montclair,
Va.; Technologist Inc. doing business as
Technologist, Vienna, Va.; Technology
Management Co. Inc. doing business as
TMC, Albuquerque, N.M.; TechOp
Solutions International Inc. doing
business as TechOp, Stafford, Va.;
Teknologic llC, Edmonds, Wash.;
Tellenger Inc., Rockville, Md.; Teya
Services llC, Anchorage, Alaska;
Thousand Oaks Research and Develop-
ment Inc., Riverside, Calif.; TMG Inc.
doing business as The Moore Group,
Norfolk, Va.; Torres Advanced Enterprise
Solutions llC, Falls Church, Va.; Total
Technology Inc., Cherry Hill, N.J.;
Trailblazer Innovations Inc., Amherst, Va.;
Trident Proposal Management Inc. doing
business as Red Sky Production
Compiled by KMI Media Group staff
APRIl 07, 2015 | 27WWW.NPEO-kMI.COM
Services, San Diego, Calif.; Trident
Technical Solutions llC doing business
as Ardent Eagle Solutions, St. Peters-
burg, Fla.; Tridentis PllC, Washington,
D.C.; Triumph Aerospace Systems,
Newport News Inc., Newport News, Va.;
Twintron Data Systems Inc. doing
business as Twintron, Marlton, N.J.;
Tyche Consulting llC, Rockville, Md.;
UniTech SoftSolutions Inc. doing
business as Unisofts, Ashburn, Va.;
United Support Services Inc., Oceanside,
Calif.; Vectrus Systems Corp., Colorado
Springs, Colo.; Venesco llC, Chantilly,
Va.; Veratics Inc., Indian Harbour Beach,
Fla.; Veris Group llC, Vienna, Va.;
Veteran Business Solutions llC,
Arlington, Va.; Virginia Electronic Systems
Inc. doing business as Virginia Electron-
ics, Virginia Beach, Va.; Virginia Tech
Applied Research Corp. doing business
as National Capital Region, Arlington, Va.;
Virtual Computing Technology, Carlsbad,
Calif.; Vision Engineering Solutions llC,
Orlando, Fla.; Visionary Consulting
Partners llC, Fairfax, Va.; Vista Interna-
tional Operations Inc., Rock Island, Ill.;
Vistra Communications llC, Tampa, Fla.;
Visual Connections, llC doing business
as: VC, Chevy Chase, Md.; VOTA
Consulting Corp., Coronado, Calif.;
VSolvIT llC doing business as Vsolvit,
Ventura, Calif.; Wambaw Creek llC,
North Charleston, S.C.; Ward ENG
Support Services Inc., Stafford, Va.; Web
Courseworks ltd. doing business as Web
Courseworks, Madison, Wis.; Weems
Design Studio Inc., Suwanee, Ga.; Weris
Inc., Potomac Falls, Va.; WIllCOR Inc.,
College Park, Md.; Xenotran Corp.,
linthicum Heights, Md.; Xgility llC,
Dulles, Va.; Yahya Technologies llC
doing business as Y-Tech, Brandywine,
Md.; Zachary Piper Solutions llC,
Mclean, Va.; Zero Point Inc., Virginia
Beach, Va.; Zia Engineering & Environ-
mental Consultants llC, las Cruces,
N.M.; MF lightwave Inc. doing business
as Custom Cable, Tampa, Fla.; FCN Inc.,
Rockville, Md.; Marieke Consulting Inc.,
Washington, D.C.; Man-Machine
Systems Assessment Inc. doing business
as MSA, El Paso, Texas; Drayton Drayton
and lamar Inc., Evans, Ga.; Federal
Integrated Systems Corp. doing business
as Fedsync, Alexandria, Va.; Career
Management Associates of Iowa llC,
Ankeny, Iowa; Jasper Solutions Inc.,
Huntington Station, N.Y.; Ultimate
knowledge Corp., Rancho Santa
Margarita, Calif.; Zillion Technologies Inc.,
Ashburn, Va.; New Wave People Inc.,
Princeton, N.J.; R2C llC doing business
as R2C Support Services, Huntsville, Ala.;
Software Information Resource Corp.
doing business as SIRC, Washington,
D.C..
Raytheon Missile Systems, Tucson,
Ariz., is being awarded a $517,300,000
cost-plus-incentive-fee and cost-plus-
fixed-fee contract for the Evolved
Seasparrow Missile (ESSM) Block 2
engineering and manufacturing develop-
ment (EMD) requirements. This contract
will procure all necessary efforts to
design, qualify and test ESSM Block 2
and prepare the program for a suc-
cessful ‘Milestone C’ decision, currently
planned in FY18. The ESSM Block 2 is an
international cooperative effort to design,
develop, test, and procure ESSM Block
2 missiles. ESSM Block 2 provides en-
hanced ship self-defense. This contract
combines purchases for the Navy (40
percent) and the governments of Australia
(16.51 percent), Canada (13.77 percent),
Germany (6.44 percent), the Netherlands
(5 percent), Denmark (4.56 percent), Nor-
way (4.56 percent), Turkey (4.56 percent),
Spain (2.5 percent), Greece (1.5 percent),
and Portugal (.6 percent), as part of the
NATO Seasparrow Consortium. Work
will be performed in Tucson, Ariz., (67
percent); Norway (2 percent); Mckinney,
Texas (5 percent); Australia (3 percent);
the Netherlands (3 percent); Canada (3
percent); Germany (3 percent); Turkey
(2 percent); Andover, Massachusetts (2
percent); San Marco, Calif., (1 percent);
San Diego, Calif., (1 percent); San Jose,
Calif., (1 percent); Cincinnati, Ohio (1 per-
cent); Canton, N.Y., (1 percent); Greece (1
percent); Denmark (1 percent); and with 3
percent in various locations that each will
perform less than 1 percent of the effort,
and is expected to be completed by May
2019. Fiscal 2015 research, development,
test and evaluation funs and foreign Mili-
tary Sales contract funds in the amount
of $26,000,000 will be obligated at time
of award and will not expire at the end
of the current fiscal year. This contract
was not competitively procured. Full and
open competition need not be provided
for when precluded by the terms of
an international agreement or a treaty
between the U.S. and a foreign govern-
ment or international organization, or the
written directions of a foreign government
reimbursing the agency for the cost of the
acquisition of the supplies or services for
such government. The Naval Sea Sys-
tems Command, Washington, D.C., is the
contracting activity (N00024-15-C-5420).
Seemann Composites Inc., Gulfport,
Miss., is being awarded a $49,944,504
indefinite-delivery/indefinite-quantity
contract with one cost-plus-fixed-fee
line item for the design, fabrication and
testing of various structural components
for naval surface and sub-surface vessels
using a proprietary Resin Infusion Mold-
ing Process (SCRIMP). This contract will
use an advanced composite fabrication
technique to design and fabricate proto-
type components, support installation,
perform material testing, and provide test
support to the government for various
marine components and structures using
the SCRIMP fabrication process to sup-
port the fleet. The company will provide
complete and tested prototypes and
end items as deliverables via individual
completion type delivery orders. Work
will be performed in Gulfport, Miss., and
is expected to complete by April 2020.
Fiscal 2015 research, development,
test and evaluation funds in the amount
of $5,000,000 will be obligated at time
of award and will not expire at the end
of the current fiscal year. This contract
was not competitively procured as it is a
follow-on to a Small Business Innovation
Research Phase III contract. The Naval
ContraCt awarDs
WWW.NPEO-kMI.COM28 | APRIl 07, 2015
Surface Warfare Center, Carderock Divi-
sion, Ship System Engineering Station,
Philadelphia, Pa., is the contracting activ-
ity (N65540-15-D-0015).
General Dynamics Electric Boat
Corp., Groton, Conn., is being awarded
a $32,621,880 cost-plus-fixed-fee
modification to previously awarded
contract (N00024-13-C-4311) to provide
a nuclear regional maintenance depart-
ment (NRMD). Under the terms of the
contract, Electric Boat will provide NRMD
tasks in support of operational nuclear
submarines at the Naval Submarine
Support Facility, Naval Submarine Base,
New london, Conn. The contract will
also require project management, techni-
cal analysis, engineering and planning,
training, inspection and nuclear services
to accomplish intermediate-level nuclear
submarine maintenance, modernization,
and repairs in support of operational
nuclear submarines, including maintain-
ing and modernizing government-owned
facilities and equipment and providing
off-hull support of submarine mainte-
nance. Work will be performed in New
london, Conn., and is expected to be
completed by March 2015. Fiscal 2015
operations and maintenance (Navy) con-
tract funds in the amount of $29,621,880
will be obligated at time of award and
will expire at the end of the current fiscal
year. The Naval Sea Systems Command,
Washington, D.C., is the contracting
activity.
Lockheed Martin Space Systems
Co., Sunnyvale, Calif., is being awarded
a maximum $31,095,958 cost-plus-fixed-
fee, level of effort, completion contract
to provide the United kingdom (Uk) with
engineering and technical support ser-
vices and deliverable materials for the Uk
Trident II Missile System. This contract
provides for, but is not limited to, techni-
cal planning, direction, coordination, and
control to assure that Uk fleet ballistic
missile program requirements are identi-
fied and integrated to support planned
milestone schedules and emergent re-
quirements, re-entry systems Uk resident
technical support, operational support
hardware, and a Collaborative Reentry
Material Experiment deliverable. Work will
be performed in Sunnyvale, Calif., (79.49
percent); Cape Canaveral, Fla., (10.39
percent); Aldermaston, England (2.82
percent); St. Mary’s, Ga., (1.61 percent);
Colorado Springs, Colo., (1.54 percent);
82 other U.S. cities (1.54 percent); Palo
Alto, Calif., (1.42 percent); Silverdale,
Wash., (0.62 percent); Coulport, Scotland
(0.54 percent); and Borgo San Dalmazzo,
Italy (0.26 percent), with an expected
level-of-effort completion date of March
31, 2016 and deliverable items comple-
tion date of March 31, 2019. Uk contract
funds are being utilized in the amount
of $31,095,958. Contract funds will not
expire at the end of the current fiscal
year. This contract was a sole source
acquisition pursuant to 10 U.S.C. 2304(c)
(4). The Department of the Navy, Strate-
gic Systems Programs Office, D.C., is the
contracting activity (N00030-15-C-002).
Lockheed Martin, Mission Systems
and Training, Baltimore, Md., is being
awarded a $13,297,144 cost-plus-
award-fee order against previously
awarded basic ordering agreement
N00024-15-G-2303 to provide engi-
neering and management services for
advance planning and design in support
of the post-shakedown availability
for USS Milwaukee (lCS 5). Work will
be performed in Hampton, Va., (50
percent); Baltimore, Md., (45 percent);
and Marinette, Wis., (5 percent), and is
expected to be completed by March
2016. Fiscal 2015 shipbuilding and
conversion (Navy) funding in the amount
of $12,453,025 will be obligated at time
of award and will not expire at the end
of the current fiscal year. The Supervisor
of Shipbuilding, Conversion, and Repair,
Bath, Maine, is the contracting activity.
Raytheon Co., Integrated Defense
Systems, Sudbury, Mass., is being
awarded a $61,978,016 modification to
previously awarded contract N00024-
13-C-5115 to provide multiyear procure-
ment funding for two AN/SPY-1D(V)
transmitter group radar system ship
sets, select missile fire control system
(MFCS) Mk 99 equipment, and associ-
ated engineering services. This contract
modification provides fiscal 2015 fund-
ing to support Aegis Weapon System
(AWS) production requirements for DDG
121 and DDG 122. The AN/SPY-1D(V)
radar system and the MFCS Mk99 are
critical components of the AWS. Work
will be performed in Andover, Mass., (80
percent); Sudbury, Mass., (15 percent);
and Portsmouth, R.I. (5 percent), and is
expected to be completed by June 2019.
Fiscal 2015 shipbuilding and conver-
sion (Navy) funding in the amount of
$61,978,016 will be obligated at the time
of award and will not expire at the end
of the current fiscal year. The Naval Sea
Systems Command, Washington, D.C., is
the contracting activity.
General Dynamics National Steel
and Shipbuilding Co., San Diego, Calif.,
was awarded a not-to-exceed amount
$61,780,484 undefinitized contract action
to previously awarded cost-plus-award-
fee contract N00024-13-C-4404 on
March 31, 2015, for USS Makin Island
(lHD 8) fiscal 2015 phased maintenance
availability. A phased maintenance avail-
ability includes the planning and execu-
tion of depot-level maintenance, altera-
tions and modifications that will update
and improve the ship’s military and tech-
nical capabilities. Work will be performed
in San Diego, Calif., and is expected to
be completed by November 2015. Fiscal
2015 operations and maintenance (Navy)
and fiscal 2015 research, development,
test and evaluation funding in the amount
of $35,196,683 will be obligated at time
of award. Fiscal 2015 operations and
maintenance (Navy) funds in the amount
of $25,551,329 will expire at the end of
1APrIl
Compiled by KMI Media Group staff
APRIl 07, 2015 | 29WWW.NPEO-kMI.COM
the current fiscal year. The Southwest
Regional Maintenance Center, San Diego,
Calif., is the contracting activity.
Astronics Test Systems Inc., Irvine,
Calif., is being awarded a $36,402,740
firm-fixed-price, indefinite-delivery/
indefinite-quantity supply contract for the
manufacture, test and delivery of radio
frequency distribution and control sys-
tems (RFDACS) and system parts which
is a major subsystem within the common
submarine radio room installed on board
all submarine classes. The RFDACS
provides a means of routing signals and
information between the various antenna
systems and other submarine commu-
nication subsystems. Work will be per-
formed in Irvine, Calif., and is expected
to be completed by March 2020. Fiscal
2015 other procurement (Navy) funding in
the amount of $949,380 will be obligated
at time of award and will not expire at
the end of the current fiscal year. This
contract was competitively procured
via the Federal Business Opportunities
website, with two offers received. The
Naval Undersea Warfare Center, Division
Newport, Newport, R.I., is the contracting
activity (N66604-15-D-1083).
Lockheed Martin Mission Systems
& Training, Moorestown, N.J., is being
awarded a $22,995,000 modification to
previously awarded contract N00024-
11-C-5106 for Aegis Weapon System
and Aegis Combat System combat
systems engineering, in-country sup-
port services, and staging support to
fulfill Aegis Foreign Military Sales (FMS)
lifetime support requirements for the
Japan Maritime Self Defense Force, the
Republic of korea Navy, and the Spanish
Armada under the FMS Program. Work
will be performed in Moorestown, N.J.,
(95.15 percent); kumi, South korea (1.5
percent); Chinhae, South korea (1.4 per-
cent); kongsburg, Norway (0.86 percent);
Tokyo, Japan (0.5 percent); Sasebo,
Japan (0.23 percent); Maizuru, Japan
(0.14 percent); San Fernando, Spain (0.12
percent), and Yokohama, Japan (0.1 per-
cent), and is expected to be completed
by September 2015. FMS funding in the
amount of $17,690,000 will be obligated
at time of award and will not expire at the
end of the current fiscal year. The Naval
Sea Systems Command, Washington,
D.C., is the contracting activity.
SFS Global LLC, Susanville, Calif.,
was awarded a $10,130,183 firm-fixed-
price contract on March 31, 2015, to
support Marine Corps vehicle main-
tenance services at Production Plant
Barstow, Barstow, Calif. This contract
contains options, which if exercised, will
bring the contract value to $24,325,457.
Work will be performed at Marine Corps
logistics Base, Barstow, Calif., and work
is expected to be completed September
2015. If the options are exercised, the
work will continue through June 2016.
Navy working capital funds in the amount
of $10,130,183 will be obligated at the
time of award and the funds will not
expire at the end of the current fiscal
year. This was a sole-source 8(a) tribal
procurement. The Marine Corps logistics
Command, Albany, Ga., is the contract-
ing activity (M67004-15-C-0009).
BAE Systems Information and Elec-
tronic Systems Integration Inc., Green-
lawn, N.Y., is being awarded an $8,455,805
modification to a previously issued firm-
fixed-price, indefinite-delivery/indefinite-
quantity contract (N00019-14-D-0004) to
exercise an option for the procurement of
22 AN/UPX-41 (C) digital interrogators for
the Navy (14) and the government of Japan
(8), and 57 Mode 5 identification friend or
foe field change kits for the Navy (45) and
the government of Japan (12). Work will
be performed in Greenlawn, N.Y., and is
expected to be completed in December
2016. No funds are being obligated at
time of award. Funds will be obligated
against individual delivery orders as they
are issued. This modification combines
purchases for the Navy ($5,808,440; 68.7
percent) and the government of Japan
($2,647,365; 31.3 percent) under the for-
eign military sales program. The Naval Air
Systems Command, Patuxent River, Md.,
is the contracting activity.
Lockheed Martin Corp., Baltimore,
Md., is being awarded an $8,291,108
cost-plus-fixed-fee delivery order under
a previously awarded contract (N00024-
12-G-4329) for the accomplishment of
planning and support efforts for littoral
combat ships (lCS) 1 and 3. The services
provided will include: management
services, engineering support, transi-
tion efforts to lCS planning yard, Total
Ship Computing Environment work up,
installation and test; materials manage-
ment, shore based trainer maintenance
and configuration management, Navy
continuous training environment, support
and maintain selected ship systems soft-
ware baselines. Work will be performed
in San Diego, Calif., (50 percent); and
Morristown, N.J., (50 percent), and is
expected to be completed by April 2016.
Fiscal 2015 operations and maintenance
(Navy) contract funds in the amount of
$6,000,000 will be obligated at time of
award and will expire at the end of the
current fiscal year. This contract was not
competitively procured. The Naval Sea
Systems Command, Washington, D.C., is
the contracting activity.
Didlake Inc., Manassas, Va., is
being awarded a $7,947,400 firm-fixed-
price, indefinite-delivery/indefinite-quan-
tity contract for annual custodial ser-
vices at Naval Air Station Oceana, Naval
Weapons Station Yorktown, and Norfolk
Naval Shipyard and their outlying clinics
in the Hampton Roads area. The work to
be performed provides for annual cus-
todial services, but is not limited to, all
management, supervision, tools, materi-
als, supplies, labor, and transportation
services necessary to perform custodial
services for office space, restrooms and
other types of rooms. The maximum
dollar value including the base period
and four option years is $40,303,053.
Work will be performed in Portsmouth,
Va., (41 percent); Virginia Beach, Va., (40
percent); Yorktown, Va., (18 percent);
and outlying clinics in the Hampton
Roads area, Va., (1 percent), and is ex-
pected to be completed by April 2020.
Fiscal 2015 operation and maintenance
ContraCt awarDs
WWW.NPEO-kMI.COM30 | APRIl 07, 2015
(Navy) contract funds in the amount of
$7,618,481 are being obligated on this
award and will expire at the end of the
current fiscal year. This contract is a
sole-source procurement awarded to a
SourceAmerica participating nonprofit
agency pursuant to the Javits-Wagner-
O’Day Act and the Federal Acquisition
Regulation Part 8. The Naval Facilities
Engineering Command, Mid-Atlantic,
Norfolk, Va., is the contracting activity
(N40085-15-D-0063).
Huntington Ingalls Inc., New-
port News, Va., is being awarded a
$7,300,000 modification to previously
awarded contract N00024-08-C-2110 for
onboard repair parts material procure-
ment to support outfitting Gerald R.
Ford (CVN 78). Work will be performed
in Newport News, Va., and is expected
to be completed by September 2015.
Fiscal 2015 shipbuilding and conversion
(Navy) contract funds in the amount of
$7,300,000 will be obligated at time of
award and will not expire at the end of
the current fiscal year. The Supervisor
of Shipbuilding, Conversion and Repair,
Newport News, Va., is the contracting
activity.
Textron Inc., New Orleans, la.,
is being awarded an $84,087,094
modification to previously awarded
contract N00024-12-C-2401 to exercise
an option for construction of landing
craft, air cushions (lCACs) 102 and 103
and their associated technical manu-
als under the Ship to Shore Connector
(SSC) program. The SSC Program is the
functional replacement for the existing
fleet of lCAC vehicles, which are near-
ing the end of their service life. The SSC
program involves air cushion vehicles
designed for a 30-year service life. The
SSC mission is to land surface assault
elements in support of operational
maneuver from the sea, at over-the-
horizon distances, while operating from
amphibious ships and mobile landing
platforms. SSC provides increased
performance to handle current and fu-
ture missions, as well as improvements
which will increase craft availability and
reduce total ownership cost. Work will
be performed in New Orleans, la., (42
percent); Indianapolis, Ind., (20 percent);
Camden, N.J., (14 percent); Norway
(7 percent); Great Britain (4 percent);
livonia, Mich., (4 percent); Huntington,
Calif., (2 percent); Eatontown, N.J., (2
percent); San Diego, Calif., (2 percent);
Chanhassen, Minn., (1 percent); Corona,
Calif., (1 percent); and Gold Beach,
Ore., (1 percent), and is expected to be
completed by September 2019. Fiscal
2015 shipbuilding and conversion (Navy)
funding in the amount of $84,087,094
is being obligated at time of award and
will not expire at the end of the current
fiscal year. The Naval Sea Systems
Command, Washington, D.C., is the
contracting activity.
Lockheed Martin Mission Systems
and Training, Moorestown, N.J., is being
awarded an $81,712,989 modifica-
tion to previously awarded contract
N00024-14-C-5114 to provide multiyear
procurement funding for Aegis Weapon
System (AWS) Mk 7 ship sets and as-
sociated special tooling and special test
equipment. The AWS represents the
core of the Aegis Combat System and
is comprised of the AN/SPY-1D(V) radar
system with the Multi-Mission Signal
Processor, Command and Decision
System Mk 2, Weapons Control System
Mk 8, Missile Fire Control System Mk
99, Operational Readiness and Test
System Mk 9, Aegis Display System
Mk 2, Aegis computer programs, Aegis
Combat Training System Mk 50, and
logistic support system. Work will be
performed in Moorestown, N.J., (85.5
percent); Clearwater, Fla., (13.1 percent);
and Akron, Ohio, (1.4 percent), and is
expected to be completed by Septem-
ber 2021. Fiscal 2015 shipbuilding and
conversion (Navy) funding in the amount
of $81,712,989 will be obligated at time
of award and will not expire at the end
of the current fiscal year. The Naval Sea
Systems Command, Washington, D.C., is
the contracting activity.
Lockheed Martin Mission Systems
and Training, Moorestown, N.J., is being
awarded a $63,808,548 modification to
previously awarded contract N00024-
09-C-5013 for Aegis Platform Systems
Engineering Agent activities and Aegis
Modernization Advanced Capability Build
engineering. Work will be performed in
Moorestown, N.J., (99 percent); Tewks-
bury, Mass., (0.6 percent); and Dahlgren,
Va., (0.4 percent), and is expected to be
completed by September 30, 2016. Fiscal
2014 and 2015 research, development,
test and evaluation; fiscal 2015 operations
and maintenance (Navy), and fiscal 2014
other procurement (Navy) funding in the
amount of $47,444,226 will be obligated
at time of award. Contract funds in the
amount of $24,245,792 will expire at the
end of the current fiscal year. The Naval
Sea Systems Command, Washington,
D.C., is the contracting activity.
Lockheed Martin Space Sys-
tems Co., Sunnyvale, Calif., is being
awarded a not-to-exceed $59,000,000
undefinitized contract action (N00030-
15-C-0015) for Trident II D-5 Naviga-
tion Subsystem Strategic Systems
Program Shipboard Integration (SSI)
Increment 4, Increment 8 Inertial and
Increment 8 Non-Inertial efforts. Work
will be performed in Mitchell Field,
N.Y., (61 percent); Oldsmar, Fla., (22
percent); Huntington Beach, Calif., (11
percent); Clearwater, Fla., (5 percent);
and Cambridge, Mass., (1 percent), and
work is expected to be completed Dec.
31, 2016. Fiscal 2015 other procure-
ment (Navy) funds in the approximate
amount of $47,063,590 and United
kingdom funding in the approximate
amount of $11,936,410 will be obligated
at time of award. No contract funds will
expire at the end of the fiscal year. This
31MArCB
Compiled by KMI Media Group staff
APRIl 07, 2015 | 31WWW.NPEO-kMI.COM
contract was a sole-source acquisition
in accordance with 10 U.S.C. 2304(c)
(1) & (4). The Navy’s Strategic Systems
Programs, Washington, D.C., is the
contracting activity.
V. Lopez Jr. & Sons General Engi-
neering Contractors Inc., Santa Maria,
Calif., is being awarded a maximum
amount $30,000,000 indefinite-delivery/
indefinite-quantity contract for painting
services at government shore-based
facilities in Guam. The work to be per-
formed provides for interior and exterior
painting requirements at various federal
and military installations on Guam. The
work includes all labor, safety controls,
transportation, materials, equipment and
supervision necessary to perform interior
and exterior painting, surface prepara-
tion on previously painted and unpainted
buildings, application of new paint,
taping and spackling work, replacement
of caulking and puttying, repair of flash-
ings and sheet-metal, repair of concrete
cracks and spalls, cutting and trimming
of trees and shrubs (obstructing perfor-
mance of work), painting of pavement
markings, and incidental related work.
Work on this contract will be performed
in Guam, and is expected to be complet-
ed by March 2020. Fiscal 2015 operation
and maintenance (Navy) contract funds
in the amount of $10,000 are obligated
on this award and will expire at the end
of the current fiscal year. This contract
was competitively procured via the Navy
Electronic Commerce Online website,
with eight proposals received. The Naval
Facilities Engineering Command, Mari-
anas, Guam, is the contracting activity
(N40192-15-D-2900).
Raytheon Co., Integrated Defense
Systems, Tewksbury, Mass., is being
awarded a $26,917,593 cost-plus-fixed-
fee design agent contract to provide
level-of-effort support for the develop-
ment environment infrastructure that
supports the complete development,
verification and support of the CVN 78
Dual Band Radar (DBR) and support of
testing to be accomplished at Wal-
lops Island Engineering Test Center
land-Based Test Site. This radar suite
is a single, integrated radar system
combining the AN/SPY-3 Multi-Function
Radar at X-Band and AN/SPY-4 Volume
Search Radar at S-Band. This radar
suite is a state of the art, high-perfor-
mance radar system with self-defense
anti-aircraft warfare mission. The design
agent contract described is intended to
provide the engineering services neces-
sary to fully mitigate numerous system
integration schedule risks that are being
tracked by the DBR program. This
contract will provide services necessary
to conduct follow on software interface
development efforts to resolve software
trouble reports discovered during land
based and at-sea testing. This contract
includes options which, if exercised,
would bring the cumulative value of
this contract to $50,821,247. Work will
be performed in Sudbury, Mass., (86
percent); Moorestown, N.J., (9 percent);
and Burlington, Mass., (5 percent),
and is expected to be completed by
December 2015. Fiscal 2015 shipbuild-
ing and conversion (Navy) and fiscal
2015 research, development, test and
evaluation funding in the amount of
$11,602,288 will be obligated at the time
of contract award and will not expire at
the end of the current fiscal year. This
contract was not competitively procured
in accordance with authority FAR 6.302-
1(a)(2)(iii)—only one responsible source
and no other supplies or services will
satisfy agency requirements. The Naval
Sea Systems Command, Washington,
D.C., is the contracting activity (N00024-
15-C-5335).
BAE Systems Southeast Shipyards
Mayport LLC, Jacksonville, Fla., is being
awarded an $18,336,160 modification to
a previously awarded multiship, multi-
option cost-plus-award-fee and cost-
plus-incentive-fee contract (N40024-
10-C-4406) to provide ship repairs, hull,
machinery, electrical, electronics, ship
alterations and piping for USS Philippine
Sea (CG 58). This modification is for the
selected restricted availability of USS
Philippine Sea to include hull, machinery,
electrical, electronics, ship alterations
and piping alteration and repair work. The
primary focus of this repair package is to
accomplish structural repairs and habit-
ability upgrades. Work will be performed
in Jacksonville, Fla., and is expected to
be completed by August 2015. Fis-
cal 2015 operations and maintenance
(Navy) and fiscal 2015 other procurement
(Navy) contract funds in the amount of
$18,336,160 will be obligated at time of
award and will expire at the end of the
current fiscal year. The Southeast Re-
gional Maintenance Center, Jacksonville,
Fla., is the contracting activity.
GFP-Yates, a joint venture, Uni-
versal City, Texas, is being awarded
$15,693,100 for firm-fixed-price task
order 0002 under a previously awarded
multiple award construction contract
(N69450-13-D-1763) for renovation and
repairs of Building 1, Chief of Naval Air
Training Headquarters at Naval Air Sta-
tion Corpus Christi, Texas. The work to
be performed provides for renovation
of an existing 1940s multi-story, wood
frame structure. The project will demol-
ish one wing; the remaining three wings
require extensive renovation, including
upgrades to the exterior envelope and
structure, a full interior renovation with
reconfiguration of spaces, and replace-
ment of all building mechanical, electrical
and fire protection systems. Support
projects include related utilities infra-
structure and civil site improvements.
Work will be performed in Corpus Christi,
Texas, and is expected to be completed
by May 2017. Fiscal 2015 operation
and maintenance (Navy) contract funds
in the amount of $15,693,100 are being
obligated on this award and will expire at
the end of the current fiscal year. Three
proposals were received for this task
order. The Naval Facilities Engineering
Command, Southeast, Jacksonville, Fla.,
is the contracting activity.
Sundt Construction Inc., Tempe,
Ariz., is being awarded $13,449,500 for
firm-fixed-price task order 0003 under a
ContraCt awarDs
WWW.NPEO-kMI.COM32 | APRIl 07, 2015
previously awarded multiple award con-
struction contract (N62473-10-D-5408)
to design and construct a new engine
dynamometer facility at Marine Corps
logistics Base Barstow, Calif. The new
high-bay single-story facility will house
engine dynamometers to be supplied
by the government, as well as ancillary
equipment and systems to support the
dynamometer test process. The facility
shall be designed with acoustical mitiga-
tion measures to protect the safety of
the workers and those in the immediate
vicinity of the facility. The task order
also contains an option item and a
planned modification, which if exercised
would increase cumulative task order
value to $13,949,500. The work will be
performed in Barstow, California, and is
expected to be completed by October
2016. Fiscal 2015 military construction
(Navy) contract funds in the amount of
$13,449,500 are being obligated on this
award and will not expire at the end of
current fiscal year. Seven proposals
were received for this task order. The
Naval Facilities Engineering Command,
Southwest, San Diego, Calif., is the
contracting activity.
Lockheed Martin Mission Systems
and Training, Moorestown, N.J., is being
awarded an $11,705,637 not-to-exceed
modification to previously awarded firm-
fixed-price contract (N00024-14-C-5114)
for the procurement of Aegis Ashore
Removable Equipment Units (REUs),
accomplishment of the required physical
modifications to the Production Test Cen-
ter (PTC) to accommodate the installation
of REUs and skid accessories, as well as
planning efforts in advance of system-
level testing for the Aegis Ashore Missile
Defense System (AAMDS) Host Nation #2
equipment set. The AAMDS is comprised
of a land-based version of the Aegis
weapon system, which serves as the core
of the AAMDS. Work will be performed in
Moorestown, N.J., and is expected to be
completed by August 2017. Fiscal 2015
Defense-wide procurement funding in the
amount of $3,334,745 will be obligated
at the time of award and will not expire
at the end of the current fiscal year. The
Naval Sea Systems Command, Washing-
ton, D.C., is the contracting activity.
MECTS Services Joint Venture,
New Town, N.D., is being awarded a
$10,932,036 modification to a previously
awarded cost-plus-fixed-fee contract
(N68335-13-C-0292) for additional
logistic services and spare/repair parts in
support of the Persistent Ground Surveil-
lance System. Work will be performed in
Fairfax, Va., (59 percent); Afghanistan (24
percent); Yuma, Ariz., (7 percent); China
lake, Calif., (5 percent); and Point Mugu,
Calif., (5 percent), and is expected to be
completed in September 2015. Fiscal
2015 operations and maintenance (Army)
funds in the amount of $1,150,000 are
being obligated on this award, all of
which will expire at the end of the current
fiscal year. The Naval Air Warfare Center
Aircraft Division, lakehurst, N.J., is the
contracting activity.
Electronic Metrology Laboratory
LLC, Franklin, Tenn., is being awarded
a $9,757,376 modification under a
previously awarded firm-fixed-price,
indefinite-delivery/indefinite-quantity
contract to exercise option one for base
operations support services at Naval Air
Station Whiting Field and outlying fields.
The work to be performed provides for all
management, supervision, labor, equip-
ment, materials, supplies and tools nec-
essary to perform facilities management,
facilities investment, facility maintenance
services (non-family housing), pest con-
trol, utility plant and distribution system
operations and maintenance (chiller,
electrical, gas, wastewater, steam and
water), managed safety services, and
base support vehicles and equipment.
The total contract amount after exercise
of this option will be $19,460,652. Work
will be performed in Milton, Fla., (80
percent); and Outlying Fields (20 percent),
and is expected to be completed by
March 2016. Fiscal 2015 operation and
maintenance (Navy); fiscal 2015 Navy
working capital funds; fiscal 2015 Navy
family housing, and fiscal 2015 Defense
health program funds contract funds in
the amount of $7,755,360 are being obli-
gated on this award and will expire at the
end of the current fiscal year. The Naval
Facilities Engineering Command, South-
east, Jacksonville, Fla., is the contracting
activity (N69450-14-D-8000).
Leebcor Services LLC, Williamsburg,
Va., is being awarded $8,188,374 for
firm-fixed-price task order 0003 under
a previously awarded multiple award con-
struction contract (N69450-14-D-1277)
for the repair of the Trident Refit Facility
Refit Wharf 2 located at Naval Subma-
rine Base, kings Bay, Ga. The work to
be performed provides for repairs that
include basic concrete restoration of
concrete piles, pile caps, edge beams
and mooring foundation and hardware.
Cathodic protection will be built into the
concrete structure to maintain the integ-
rity of the repair. ladders will be replaced
and a catwalk will be repaired. Fender
pile sacrificial anodes, fender wraps
and bonding systems will be repaired.
Work will be performed in kings Bay,
Ga., and is expected to be completed
by August 2016. Fiscal 2015 operation
and maintenance (Navy) contract funds
in the amount of $8,188,374 are being
obligated on this award and will expire at
the end of the current fiscal year. Three
proposals were received for this task
order. The Naval Facilities Engineering
Command, Southeast, Jacksonville, Fla.,
is the contracting activity.
Raytheon Co., Integrated Defense
Systems, Tewksbury, Mass., is being
awarded a $7,800,000 modification to
previously awarded contract N00024-
10-C-5126 to purchase DDG 1000
provisional item orders spares. Work will
be performed in Portsmouth, R.I., and is
expected to be completed by September
2016. Fiscal 2014 shipbuilding and con-
version (Navy) funding in the amount of
$7,800,000 will be obligated at the time
of award and will not expire at the end
of the current fiscal year. The Naval Sea
Systems Command, Washington, D.C., is
the contracting activity.
Compiled by KMI Media Group staff
APRIl 07, 2015 | 33WWW.NPEO-kMI.COM
Whiting Turner Contracting Co.,
Inc., Baltimore, Md., is being awarded
a $38,490,000 firm-fixed-price contract
for mechanical and electrical system
improvements and repairs at Walter Reed
National Military Medical Center. Work
will be performed in Bethesda, Md., and
is expected to be completed by February
2017. Fiscal 2014 military construction
(Defense) contract funds in the amount
of $38,490,000 are being obligated on
this award and will not expire at the end
of the current fiscal year. This contract
was competitively procured via the Navy
Electronic Commerce Online website,
with three proposals received. The Naval
Facilities Engineering Command, Wash-
ington, D.C., is the contracting activity
(N40080-15-C-0156).
Piedmont Natural Gas Co. Inc.,
Charlotte, N.C., is being awarded a
$27,543,774 firm-fixed-price contract
for construction efforts to implement
a steam decentralization utility energy
services project at Marine Corps Base,
Camp lejeune. The work to be per-
formed provides for installation of new
energy efficient space and domestic
water-heating systems, and the removal
of existing steam equipment and dis-
tribution infrastructure at Hadnot Point
and French Creek, Courthouse Bay, and
Marine Corps Air Station New River.
This implementation will allow the U.S.
government to effectively improve the
efficiency, maintenance and reliability of
systems located in the aforementioned
facilities and reduce its energy consump-
tion resulting in utility cost avoidance and
compliance with mandatory laws and
statutes to reduce energy consumption.
Work will be performed in Jacksonville,
N.C., and is expected to be completed
by April 2017. The exact amount of the
contract will be determined by financing
at the time of award, but is estimated
to be approximately $37,898,833. No
funds will be obligated with this award.
The contract was procured under the
authority of Title 10 U.S. Code Section
2304(c)(5), statute expressly autho-
rizes or requires that the acquisition be
made through another agency or from
a specific source, as implemented by
Federal Acquisition Regulation 6.302-5.
The Energy Independence and Security
Act of 2007 authorizes agencies to use
appropriations, private financing, or a
combination to comply with its require-
ments for utility energy service contracts
for evaluations and project implementa-
tion. For this project, the Marine Corps
has agreed to pay for the costs of
services and construction from project
financing which will be obtained by
Piedmont Natural Gas Company Inc. The
Naval Facilities Engineering Command,
Mid-Atlantic, Norfolk, Va., is the contract-
ing activity (N40085-15-C-7701).
Marvin Engineering Co., Inc.,
Inglewood, Calif., is being awarded
$24,990,472 for firm-fixed-price delivery
order 0013 against a previously issued
basic ordering agreement (N00019-
11-G-0009) for the procurement of 648
lAU-127 guided missile launchers for
the Navy (608), and the government
of Australia (40), to enable the F/A-18
aircraft to carry and launch AIM-120 and
AIM-9X missiles. Work will be performed
in Inglewood, Calif., and is expected to
be completed in October 2018. Fiscal
2013 aircraft procurement (Navy) funds
and foreign military sales funds in the
amount of $24,990,472 will be obligated
at time of award, of which $23,436,232
will expire at the end of the fiscal year.
This modification combines purchase for
the Navy ($23,436,232; 93.8 percent) and
the government of Australia ($1,554,240;
6.2 percent). The Naval Air Systems
Command, Patuxent River, Md., is the
contracting activity.
The Boeing Co., Seattle, Wash., is
being awarded a $21,065,841 modi-
fication to a previously awarded cost
reimbursement type contract (N00019-
04-C-3146) for system development and
testing to resolve open trouble reports on
the existing P-8A Poseidon Test aircraft.
Work will be performed in Huntington
Beach, Calif., (51 percent); Seattle, Wash.
(47 percent); and Patuxent River, Md., (2
percent), and is expected to be complet-
ed in March 2017. Fiscal 2015 research,
development, test and evaluation (Navy)
funds in the amount of $19,970,000 will
be obligated at time of award, none of
which will expire at the end of the current
year. The Naval Air Systems Command,
Patuxent River, Md., is the contracting
activity.
Logos Technologies Inc., Fairfax,
Va., is being awarded an $18,615,621
cost-plus-fixed-fee contract to provide
operations, maintenance, and logistics
services in support of kestrel Wide
Area Surveillance systems and sensors
deployed on Persistent Ground Surveil-
lance Systems and Persistent Threat
Detection Systems aerostats in support
of the North Atlantic Treaty Organization
Resolute Support mission for the Army.
Work will be performed in Fairfax, Va., (55
percent); Afghanistan (30 percent); Yuma,
Ariz., (5 percent); Raleigh, N.C., (5 per-
cent); and Pt. Mugu, Calif., (5 percent),
and is expected to be completed in De-
cember 2015. Fiscal 2015 operations and
maintenance (Army) funds in the amount
of $3,240,741 are being obligated at
time of award, all of which will expire at
the end of the current fiscal year. This
contract was not competitively procured
pursuant to 10 U.S.C. 2304(c)(1). The
Naval Air Warfare Center Aircraft Division,
lakehurst, N.J., is the contracting activity
(N68335-15-C-0144).
Northrop Grumman Systems Corp.,
linthicum Heights, Md., is being awarded
$15,292,388 for modification P00149
under a previously awarded cost-plus-
fixed-fee contract (M67854-07-C-2072)
in support of Ground/Air Task-Oriented
Radar (G/ATOR) program managed
by Program Executive Officer land
Systems, Quantico, Va. This modification
incorporates a change order to imple-
ment Phase II of the computer program
reliability improvement plan within the
framework of the low rate initial produc-
tion contract. Work will be performed
in linthicum Heights, Md., (82 percent);
and Syracuse, N.Y., (18 percent), and
30MArCB
ContraCt awarDs
WWW.NPEO-kMI.COM34 | APRIl 07, 2015
is expected to be completed by Dec.
31, 2016. Research, development, test
and evaluation funds in the amount
of $4,410,000 will be obligated at the
time of award. No contracts funds will
expire the end of the current fiscal year.
This modification is awarded against a
sole-source contract in accordance with
10 U.S.C. 2304(c)(1). The Marine Corps
Systems Command, Quantico, Va., is the
contracting activity.
BAE Systems Technology Solu-
tions & Services Inc., Rockville, Md., is
being awarded a $14,709,312 cost-plus-
fixed-fee contract for program and proj-
ect management and systems logistics
and engineering support of the Naval
Air Warfare Center Aircraft Division’s
air traffic control and landing system.
These efforts will include system certi-
fication; technical assistance; systems
test, evaluation and analysis; software
and hardware development, installation
and maintenance; test data acquisi-
tion, reduction and analysis; configura-
tion management; training support;
equipment manufacturing, refurbishing,
overhaul, and repair; and quality control.
Work will be performed in St. Inigoes,
Md., (49 percent); Patuxent River, Md.,
(49 percent); Norfolk, Va., (1 percent);
and San Diego, Calif., (1 percent), and
is expected to be completed in March
2016. Fiscal 2015 Navy working capital
funds in the amount of $1,250,000 are
being obligated at time of award, none
of which will expire at the end of the
current fiscal year. This contract was
not competitively procured pursuant
to FAR 6.302-1. The Naval Air Warfare
Center Aircraft Division, Patuxent River,
Md., is the contracting activity (N00421-
15-C-0012).
Joint Venture of Casco Bay
Engineering-CLD Consulting Engineers
LLC, Portland, Maine, is being awarded
a maximum amount $10,000,000 firm-
fixed-price, indefinite-delivery/indefinite-
quantity, architect-engineering contract for
design and engineering services in sup-
port of utility and infrastructure projects
primarily in the Naval Facilities Engineer-
ing Command (NAVFAC) Mid-Atlantic
Public Works Department (PWD) Maine
area of responsibility (AOR). Task order
0001 is being awarded at $728,011 for
design of multiple utility system replace-
ment and upgrade projects at the Ports-
mouth Naval Shipyard, kittery, Maine.
Work for this task order is expected to be
completed by November 2015. All work
on this contract will be performed within
the NAVFAC Mid-Atlantic PWD Maine
AOR which includes Maine (70 percent);
New Hampshire (5 percent); Vermont
(5 percent); Massachusetts (5 percent);
Connecticut (5 percent); New York (5
percent); Rhode Island (4 percent) and
in the remainder of the U.S. (1 percent).
The term of the contract is not to exceed
60 months with an expected completion
date of March 2020. Fiscal 2015 Navy
working capital funds contract funds
in the amount of $728,011 are being
obligated on this award and will expire
at the end of the current fiscal year. This
contract was competitively procured via
the Navy Electronic Commerce Online
website, with eight proposals received.
The Naval Facilities Engineering Com-
mand, Mid-Atlantic, Norfolk, Va., is the
contracting activity (N40085-15-D-6102).
L-3 Communication Integrated
Systems LP, Waco, Texas, is being
awarded an $8,180,126 firm-fixed-price
contract for the procurement of three
production installation kits (A-kits), one
spare A-kit required for the installation
of the upgraded auxiliary power unit in
the E-6B aircraft, and the installation
technical data package for the A-kit.
Work will be performed in Waco, Texas,
and is expected to be completed in
March 2016. This contract was not
competitively procured pursuant to
FAR.6.302-1. Fiscal 2014 and 2015
aircraft procurement (Navy) funds in the
amount of $8,180,126 will be obligated
at time of award, none of which will
expire at the end of the current fiscal
year. The Naval Air Systems Command,
Patuxent River, Md., is the contracting
activity (N00019-15-C-0093).
Rockwell Collins Inc., Cedar Rap-
ids, Iowa, is being awarded a $7,824,175
modification to a previously awarded
firm-fixed-price contract (N00019-
13-C-0004) to upgrade the configuration
and operational properties of the EA-6B
Block I aircraft’s nuclear planning and ex-
ecution system. Work will be performed
in Richardson, Texas, and is expected to
be completed in September 2016. Fiscal
2014 aircraft procurement (Navy) funds
in the amount of $7,824,175 are being
obligated on this award, none of which
will expire at the end of the current fiscal
year. The Naval Air Systems Command,
Patuxent River, Md., is the contracting
activity.
Lockheed Martin Corp., Lockheed
Martin Aeronautics Co., Fort Worth,
Texas, is being awarded a $6,808,493
modification to a previously awarded
cost-plus-fixed-fee contract (N00019-
15-C-0031) to provide interim contrac-
tor sustainment services in support of
the F-35 lightening II low rate initial
production lot aircraft for the Air Force.
Work will be performed at luke Air Force
Base, Glendale, Ariz., and is expected to
be completed in November 2015. Fiscal
2014 aircraft procurement (Air Force)
funding in the amount of $6,808,493 will
be obligated at time of award, none of
which will expire at the end of the current
year. The Naval Air Systems Command,
Patuxent River, Md., is the contracting
activity.
Bell Helicopter Textron Inc., Fort
Worth, Texas, has been awarded a
maximum $7,098,324 firm-fixed-price
contract for gearbox assembly spare
parts in support of the H-1 helicopter.
This contract was a sole-source. This is a
54-base contract with no option periods.
location of performance is Texas with
a September 30, 2019, performance
completion date. Using military service
is Navy. Type of appropriation is fiscal
2015 Navy working capital funds. The
contracting activity is the Defense logis-
tics Agency Aviation, Philadelphia, Pa.
(W58RGZ12G0001-THGQ).
Compiled by KMI Media Group staff
APRIl 07, 2015 | 35WWW.NPEO-kMI.COM
leading-edge technologies and innovations from around the world.
navy air/Sea looks at what the industrial complex—both friendly and
threat—are developing.
aerial Recovery of Small and Micro air vehiclesBrigham Young University
country of origin: united States
language: english
Due to recent directives from the Department of Defense, there is
great pressure to develop the technology behind unmanned aerial ve-
hicles (UAVs). UAVs are remotely piloted or autonomous aircraft that can
carry cameras, sensors, communications equipment or other payloads.
UAVs have proven their usefulness in military applications in recent
years. large UAVs have become an integral part of the U.S. arsenal.
large UAVs have executed surveillance and tactical missions in virtually
every part of the world. For example, unmanned aircraft systems (UAS)
have become an essential tool for warfighters. While high-altitude, long-
endurance UAS like the Predator and Global Hawk provide persistent
intelligence, surveillance and reconnaissance (ISR) capabilities, they are
a scarce resource that cannot be given specific data-gathering tasks
by individual troops. At the other end of the spectrum are backpack-
able small and micro air vehicles (MAVs), with wingspans less than 48
inches, which theoretically can be carried by every warfighter.
One drawback of MAVs is the recovery of the MAV after it has
completed its mission. Although the relatively low cost of MAVs may
suggest that they may be expendable (and thereby removing the need
for recovery), MAVs still contain critical and often classified technology
that needs to be kept out of enemy hands. Thus, innovative recovery
techniques are critical to ubiquitous use of MAV technology.
This concept relates generally to unmanned aerial vehicles, and
more specifically, to the aerial recovery of small and micro unmanned
aerial vehicles.
4 drawings
flight of Warplane GroupPetrenko L.P.
country of origin: ukraine
language: Russian
This invention relates to aircraft engineering. Proposed method com-
prises takeoff and flight of the main warplane and takeoff of the plane with
computer control and fire set. Said main warplane tail is equipped with the
first pawl for transmission there through the info messages and second
pawl to replenish smaller computer-control plane with hydrocarbons.
After takeoff of the main warplane, first pawl is turned and after ap-
proach of smaller plane it is pre-coupled with said main warplane to make
the info communication channel. Thereafter, second pawl is turned at sec-
ond main warplane to connect it with the second receiver pawl of second
pawl of smaller plane.
In the combat area, data is transmitted via data communication chan-
nel to smaller plane computer system to uncouple smaller plane from the
main warplane.
4 drawings
detecting Weather conditions including fog using vehicle onboard Sensors Google Inc.
country of origin: united States
language: english
Autonomous vehicles use various computing systems to aid in the
transport of passengers from one location to another. Some autono-
mous vehicles may require an initial input or continuous input from
an operator, such as a pilot, driver or passenger. Other autonomous
systems, for example autopilot systems, may be used when the system
has been engaged, which permits the operator to switch from a manual
mode (where the operator exercises a high degree of control over the
movement of the vehicle) to an autonomous mode (where the vehicle
essentially drives itself) to modes that lie somewhere in between.
Such vehicles are typically equipped with various types of sen-
sors in order to detect objects in the surroundings. For example, an
autonomous vehicle may include lasers, sonar, radar, cameras and other
devices which scan and record data from surroundings of the vehicle.
Sensor data from one or more of these devices may be used to detect
objects and their respective characteristics (position, shape, head-
ing, speed, etc.). This detection and identification is useful for the safe
operation of autonomous vehicle.
This design describes methods and systems for detecting weather
conditions including fog using vehicle onboard sensors are provided.
An example method includes receiving laser data collected from scans
of an environment of a vehicle, and associating, by a computing device,
laser data points of with one or more objects in the environment. The
Defense innovations
WWW.NPEO-kMI.COM36 | APRIl 07, 2015
Compiled by KMI Media Group staff
method also includes comparing laser data points that are unassoci-
ated with the one or more objects in the environment with stored laser
data points representative of a pattern due to fog, and based on the
comparison, identifying by the computing device an indication that a
weather condition of the environment of the vehicle includes fog.
8 drawings
launching facilityOAO Zavod im. V.A. Degtjareva
country of origin: Russia
language: Russian
This concept describes the launching facility for anti-aircraft missiles
including base, rack and frame with guides. The guides have a possibil-
ity of independent guidance from each other as to an angle of elevation
(meaning each launcher tube can be elevated separately). Installed on
the guides are remotely controlled devices of depression of a limit stop
retaining the missile. The guides are charged with target-missiles in
launching containers. Missiles are electrically connected to connectors
of the launching facility.
According to the designers, the effect of this concept is to enlarge
the technical capabilities of the launching facility and improving quality.