Naperville Woman’s Club Landmark Remodeling Project Summer of 2015
28

Naperville Woman’s Club Landmark Remodeling Project

Apr 12, 2017

Download

Real Estate

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Naperville Woman’s Club Landmark Remodeling Project

Naperville Woman’s ClubLandmark Remodeling Project

Summer of 2015

Page 2: Naperville Woman’s Club Landmark Remodeling Project

Professional Expertise

March 11, 2015

Sequoia General Contracting Corp.

Terry Oppermann, AIA

Neville Structural Engineering

Page 3: Naperville Woman’s Club Landmark Remodeling Project

Packing

June 9, 2015

Page 4: Naperville Woman’s Club Landmark Remodeling Project

Demolition

June 19, 2015

Page 5: Naperville Woman’s Club Landmark Remodeling Project

Demolition

June 19, 2015

Page 6: Naperville Woman’s Club Landmark Remodeling Project

Groundbreaking

June 25, 2015

Page 7: Naperville Woman’s Club Landmark Remodeling Project

Groundbreaking

June 25, 2015

Mayor Steve Chirico explains the importance of making the NWC Landmark accessible to the community.

Page 8: Naperville Woman’s Club Landmark Remodeling Project

Groundbreaking

June 25, 2015

Page 9: Naperville Woman’s Club Landmark Remodeling Project

Preparation for a Ramp

June 29 and 30, 2015

Page 10: Naperville Woman’s Club Landmark Remodeling Project

Excavation

July 6, 2015

Note the trenchis flooded

Page 11: Naperville Woman’s Club Landmark Remodeling Project

Concrete Forms

July 10, 2015

Page 12: Naperville Woman’s Club Landmark Remodeling Project

Ramp Takes Shape

July 12, 2015

Page 13: Naperville Woman’s Club Landmark Remodeling Project

Framing

July 13, 2015

Page 14: Naperville Woman’s Club Landmark Remodeling Project

Starting to look like an entrance

July 15, 2015

Page 15: Naperville Woman’s Club Landmark Remodeling Project

Sidewalk and stairs added

July 17, 2015

Page 16: Naperville Woman’s Club Landmark Remodeling Project

Pipes and evac from kitchen brought up to code

July 21, 2015

Page 17: Naperville Woman’s Club Landmark Remodeling Project

Plumbing passes inspection, electrical panel, not as easy.

July 22, 2015

Page 18: Naperville Woman’s Club Landmark Remodeling Project

Original subfloor

July 29, 2015

Page 19: Naperville Woman’s Club Landmark Remodeling Project

Drywall

August 3, 2015

Page 20: Naperville Woman’s Club Landmark Remodeling Project

New entry and railing.

August 12, 2015

Page 21: Naperville Woman’s Club Landmark Remodeling Project

Old entry closed, new ceiling arch, electric panel up to code

August 13, 2015

Page 22: Naperville Woman’s Club Landmark Remodeling Project

Tile

August 15 & 16, 2015

Page 23: Naperville Woman’s Club Landmark Remodeling Project

Cabinets

August 17-20, 2015

Page 24: Naperville Woman’s Club Landmark Remodeling Project

Fixturesinside andoutside

August 19, 2015

Page 25: Naperville Woman’s Club Landmark Remodeling Project

Accessories

August 20, 2015

Page 26: Naperville Woman’s Club Landmark Remodeling Project

Exterior light and TYVEK®

August 21, 2015

Page 27: Naperville Woman’s Club Landmark Remodeling Project

Backsplash, extra tile, varnished cabinets, balanced arches

August 26, 2015

Page 28: Naperville Woman’s Club Landmark Remodeling Project

Final inspection

August 31, 2015