report to The World Bank Robert Vernstrom consulting economist Bangkok, Thailand 662 2520186 fax 662 2532176 vernstrom@stanfordalumni.org Nam Theun 2 Hydro Power Project Regional Economic Least-Cost Analysis Draft Final Report June 2004 The findings, interpretations and conclusions contained in this report are those of the author and do not represent the views of the IBRD/IDA or of the Executive Directors of IBRD/IDA, the Electricity Generating Authority of Thailand (EGAT), or the Nam Theun 2 Power Company Limited (NTPC).
105
Embed
Nam Theun 2 Hydro Power Project Regional Economic …siteresources.worldbank.org/INTLAOPRD/491761-1094074854903/... · Least-Cost Analysis Draft Final Report ... NT2 Nam Theun 2 hydro
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
The findings, interpretations and conclusions contained in this report are those of the author and do not represent the views of the IBRD/IDA or of the Executive Directors of IBRD/IDA, the Electricity Generating Authority of Thailand (EGAT), or the Nam Theun 2 Power Company Limited (NTPC).
The author wishes to thank the Electricity Generating Authority ofThailand (EGAT), M.L. Chanaphun Kridakorn (recently retired DeputyGovernor) and Mr. Narongsak Vichetpan, Deputy Governor for Policy andPlanning, for the extensive support of their experienced professional team.In particular, we wish to thank the System Planning Division for their ableassistance. Special thanks are due to Mr. Sahust Pratuknukul (now Headof the Energy Economics Division), Ms. Petchara Rompruek (Head ofPower Development Planning), and their staff (including ManopTanglakmongkol, Nimit Sujiratanavimol, Thanawadee Deetae, andYoothapong Tancharoen, among others), without whose support theStudy would not have been possible. Countless hours were spent indiscussing and refining assumptions used in the Study, and many additionalhours were expended to complete the generation expansion planningscenarios discussed in this report.
The demand forecasting sections of this report were prepared with theexpert assistance of Dr. Tienchai Chongpeerapien, President of Businessand Economic Research Associates (BERA), a Bangkok consultant withmany years of experience working on load forecasting issues for the Thaipower sector.
Special thanks are due to Mr. Mark Segal, Mr. Darayes Mehta, and Mr.Robert Mertz, World Bank supervisors and advisors to the project, fortheir professional guidance and tireless support.
TABLE OF CONTENTS
Executive Summary i
1 Introduction 7
1.1 Background 71.2 Study Objective 81.3 Organization of the Report 9
2 System Demand Assumptions 10
2.1 Overview of the Forecasting Methodology 102.2 Comparison of Forecast Results 172.3 Load Forecast Adopted for this Study 21
3 System Supply Assumptions 23
3.1 Installed and Planned System Capacity 233.2 Thermal Expansion Candidates 263.3 Fuel Price Projections 273.4 Thermal Candidate Plant Screening Analysis 293.5 NT2 – The Alternative Expansion Candidate 29
4 Methodology for the Study 33
4.1 The Least Cost Planning Methodology 334.1.1 The PROSCREEN II Model 334.1.2 How PROSCREEN is Applied in this Study 344.2 Cost-Risk Analysis Modeling Framework 35
5 Economic Evaluation 39
5.1 Economic Planning Assumptions 395.1.1 Basic Economic Assumptions 395.1.2 System Characteristics 405.1.3 NT2 Planning Assumptions for the Economic Analysis 415.2 Base Case Results 435.3 Cost-Risk Analysis 445.4 Sensitivity Analysis 485.4.1 Delay in Commercial Operation 485.4.2 Changes in the Forecasts of Key Variables 49
6 Conclusion 55
A1 Terms of Reference 57
A2 Thailand Demand Forecast 65
A3 Fuel Price Assumptions 71
A4 Detailed Plant Data (Existing System) 79
A5 How PROSCREEN Works 85
A6 Economic Base Case with NT2 – Detail 89
TABLES AND FIGURES
Table S-1. Economic Cost-Risk Analysis Results v
Table 1. Current Forecast Methods by Company and Class 12
Table 2. National GDP Growth Assumptions 13
Table 3. Integrated National Electricity Conservation Program 16
Table 4. National Conservation Program – Alternative View 17
Table 5. Historical Energy Requirements Forecasts (GWh) 18
Table 6. Historical Peak Demand Forecasts (MW) 19
Table 7. Implied Income Elasticity of Energy Requirements Forecasts 20
Table 8. Historical Forecast Accuracy 1/ 20
Table 9. Recommended Load Forecast for this Study 22
Table 10. Installed and Purchased Capacity (as of March 2003) 24
Table 11. Committed Plant Additions (after March 2003) 25
Table 12. Schedule of Retirements (FY2003-14) 26
Table 13. Candidate Power Plants for the Study (2003 Prices) 27
Table 14. Base Case Fuel Price Forecasts 28
Table 15. Screening Analysis of EGAT Candidate Plants 30
Table 16. The Cost-Risk Framework 36
Table 17. Capital Costs of NT2 (constant US$2003, 10% discount rate) 42
Table 18. Base Case “with NT2” 44
Table 19. Base Case “without NT2” 45
Table 20. Economic Cost Risk Analysis Results 47
Table 21. Sensitivity of Base Case to Delay of Commercial Operation 49
Table 22. Sensitivity of Results to the Load Forecast 50
Table 23. Sensitivity of Results to the Price of Natural Gas 51
Table 24. Sensitivity to Changes in NT2 Capital Cost 52
Table 25. Economic Cost-Risk Sensitivity Test 54
Table A2-1. EGAT Total Generation Requirement Forecast 66
Table A2-2. EGAT Total Sales Forecast 67
Table A2-3. MEA Purchases and Sales Forecast by Customer Class 68
Table A2-4. PEA Purchases and Sales Forecast by Customer Class 69
Table A4-1. Existing Installed Generating Capacity (as of Sep-03) 80
Table A4-2. Existing Hydro Power Plant Data 81
Table A4-3. Existing and Committed Small Power Producers (as of Sep-03) 82
Table A4-4. Schedule of Planned Plant Retirements 83
Table A6-1. Demand and Supply Balance – Economic Base Case with NT2 90
Table A6-2. System Costs by Plant Group – Economic Base Case with NT2 92
Table A6-3. Fuel Use by Type – Economic Base Case with NT2 94
Table A6-4. Fuel Type by Individual Plant – Economic Base Case with NT2 96
LIST OF ACRONYMS
AAGR average annual growth rateBOI Board of InvestmentBTU British Thermal Unit (standard measure of fuel heat content)CCGT combined cycle gas turbineCIDA Canadian International Development AgencyCOD commercial operation dateDAEDE Department of Alternative Energy Development and Efficiency (formerly
DEDP)DEDP Department of Economic Development and Promotion (now DAEDE)E&P exploration and productionEDP exploration, development, productionEGAT Electricity Generating Authority of ThailandEIA Energy Information Administration (U.S. Department of Energy)EPPO Energy Policy and Planning Office (formerly NEPO)ESI electricity supply industryGDP gross domestic productGHG greenhouse gasGMS Greater Mekong Sub-regionGOL Government of the Lao People’s Democratic RepublicGOT Government of the Kingdom of ThailandGPA gas purchase agreementGRP gross regional productGT gas turbineGWh gigawatt hour (one million kWh)HFO heavy fuel oilIBRD International Bank for Reconstruction and Development (official name
for the World Bank)IMF International Monetary FundIPP independent power producerkWh kilowatt hourLER low economic recovery (Sep-98 forecast scenario)LFCR levelized fixed charge rateLOLP loss of load probabilityMEA Metropolitan Electricity AuthorityMER medium economic recovery (Sep-98 forecast scenario)MM millionMOU memorandum of understandingMUV United Nations index of the unit value of manufactured exportsMW megawatt (one thousand kW)MWh megawatt hour (one thousand kWh)NEPO National Energy Policy Office (now EPPO)NESDB National Economic and Social Development Board
NPL non-performing loanNPV net present valueNSO National Statistics OfficeNT2 Nam Theun 2 hydro power projectNTPC Nam Theun Power CompanyPCF Prototype Carbon Fund administered by the World BankPDP power development program of EGATPE primary energy (required purchases from NT2, 6 a.m. to 10 p.m.)PEA Provincial Electricity AuthorityPPA power purchase agreementPTT Petroleum Authority of ThailandPV present valueRER rapid economic recovery (Sep-98 forecast scenario)RM reserve marginR/P reserves to production ratioSCF standard cubic foot (approximately 1000 Btu)SE1 secondary energy 1 (required purchases from NT2, 10 p.m. to 6 a.m.)SE2 secondary energy 2 (optional purchases from NT2, 10 p.m. to 6 a.m.)SPP small power producerTDRI Thailand Development Research InstituteTHB Thai Baht; in this study, US$1.00 = 42 THBTLFS Thailand Load Forecast Sub-committeeWACC weighted average cost of capitalWB World BankWCD World Commission on Dams
Executive Summary i
EXECUTIVE SUMMARY
S-1 Background and ObjectivesNam Theun 2 (NT2) is a planned hydroelectric project of a thousand megawatts inthe Lao PDR to be developed by a private company (NTPC). The Government ofLaos (GOL) is a 25 percent shareholder in NTPC. Upon anticipated commencementof commercial operation in 2009 (FY2010), NTPC will sell fixed amounts of power atpre-negotiated prices to the Electricity Generating Authority of Thailand (EGAT).
A World Bank Partial Risk Guarantee to NTPC is under consideration. This study isa component of the Bank’s on-going due diligence process. The work is a complementto an earlier study, the Thailand Power Scenario Study (TPSS),1 developed incooperation with the Electricity Authority of Thailand (EGAT), utilizing EGAT’s least-cost planning tools. That analysis was conducted from a commercial perspective.Further, the study assessed NT2 from the perspective of Thailand rather than theregion as a whole.
The World Bank carried out a detailed review of the TPSS, and concluded that theBank's evaluation policies also required an economic analysis assessing the project froma regional perspective. Therefore, the review also highlighted the need for astructured “cost-risk” analysis (see Section S-2 below). The current study reports thefindings of the analysis conducted to achieve these expanded objectives.
Chapter 2 presents the demand forecast of the regional power system which hasbeen adopted for the current study. Chapter 3 presents detailed background on theexisting power supply system, and on candidate plants for future system expansion.
S-2 Study Objective and MethodologyThe study outcome is to be determined by means of a results profile known as the“Cost-Risk Framework”. This profile – explained in detail in Chapter 4 – provides forcalculating the probability-weighted present value (PV) costs of either implementingor not implementing NT2 for commercial operation in FY2010, given the interplay ofseveral major uncertain factors – project cost, long-term demand for electricity, andlong-term economic value of natural gas as well as the suggested probabilities ofoccurrence for Base Case, Low and High estimates of these variables. The differencebetween the probability weighted PV cost of implementing the project in FY2010versus not implementing it at all is the decision criteria for this analysis. A lower netpresent value (NPV) “with NT2” would indicate that the project is an efficienteconomic investment for the regional power market.
1 Robert Vernstrom, Thailand Power Scenario Study, Bangkok, March 2003. The World Bank financedand supervised the study.
Executive Summary i i
The specific steps undertaken to complete the cost-risk analysis are summarized in thefollowing paragraphs:
Determine Base Case, Low, and High real economic values for the three keyuncertainties expected to have the most significant potential impact on theeconomic decision to develop NT2 – (i) project cost, (ii) growth rate ofelectricity demand, and (iii) the economic value of natural gas.
Define a probability of occurrence for each state (Base Case, Low, andHigh) of each variable.
Run the PROSCREEN expansion planning model under Economic BaseCase assumptions with NT2 as a candidate competing for a place in the least-cost expansion plan from its earliest expected commercial operation date ofFY2010. This initial analysis added NT2 to the system in October 2009,i.e., it specified that the least-cost expansion plan included NT2commencing operation in October 2009. This date was therefore fixed forall subsequent "with NT2" model runs to conform to the logic of thedecision matrix (the decision being whether to develop NT2 for commercialoperation in October 2009 or not to do so).
Run the PROSCREEN generation expansion planning model with NT2commencing commercial operation in FY2010 for all combinations of theabove-defined uncertainties. The PROSCREEN “objective function” (i.e.,basis for comparison of results) is the present value of future investmentand operating costs over the Study Period.
Re-run each of the defined scenarios without NT2 so that demand must beserved from alternative resources.
Calculate the probability-weighted present value of costs for the “withNT2” and “without NT2” scenario groups.
Subtract the probability-weighted result “with NT2” from the result“without NT2” to determine the Study outcome.
To complete the Cost-Risk Framework, a total of 18 scenario runs are required, 9with NT2 and 9 without NT2. These scenarios are formed from combinations of twoplanning variables – power demand and natural gas price. Three cases – Base, Low,and High – are used for each of these variables. The 9 scenarios run with NT2 wereexpanded to 27 scenarios for the economic assessment by combining manually thethree cases for the construction cost of NT2 with the results of the other scenarios.
The Base Case analysis is characterized as follows:
The Base Case load forecast is Thailand’s official Base Case of August 2002(see Chapter 2), augmented by a Lao PDR domestic load of 75 MW and300 GWh.
Executive Summary i i i
The reliability criterion is a reserve margin of 15 percent.
The existing system corresponds to the summary in Table 10.
All “committed plants” as identified in Table 11 are presumed to commencecommercial operation according to schedule.
The schedule for plant retirements follows the assumptions detailed in Table12.
NT2 (995 MW) is added to the system in FY2010 (October 2009) in the“with NT2” scenarios.
All other plants – including plants proposed for reconditioning and allgeneric expansion options (see Table 13) – are modeled as candidateswhich must compete for a place in the least cost economic plan.
Generation of existing plants and selected candidates is dispatched byPROSCREEN according to the following rules:
All non-thermal generation – notably domestic hydro plants and Laoimports – is dispatched first. With the exception of EGAT’s ownhydro capacity, each of these resources is modeled as a separatetransaction, defined from contractual purchase price and operatingconstraints.
NT2 energy is dispatched in two parts according to the monthlyvariation reported in Chapter 3, one to provide peak-period energyand a second to provide off-peak energy.
All thermal generation – the majority of the entire system – is subjectto economic dispatch, and run only when it is lowest cost.Exceptions are small power producers (SPPs), which are assumedbased on EGAT experience to run at an average 80 percent capacityfactor.
S-3 Results of the Economic AssessmentThe Base Case economic analysis tells us that NT2 should be included in the region’sleast cost generation expansion plan. The accumulated present value of real resource
Executive Summary i v
savings to the region over the entire Study Period (FY2003-14 and beyond2) totalsUS$277 million at 2003 prices.3
The project outcome is determined by a cost-risk analysis, designed to determinewhether the same decision is justified given the high probability that future events willdiverge from Base Case assumptions.
The key decision variables for this study are defined in the study TOR (see AppendixA1). They are:
Capital cost of NT2. The World Bank has specified a cost range of +30percent (High capital cost) and –30 percent (Low capital cost); thesevalues are reported in Table 17.
Regional demand forecast. The World Bank has specified a very wide range inorder to reflect the Bank's long-term experience with demand forecastperformance;4 the regional High and Low demand forecasts are summarizedin Table 9.
Natural gas price forecast. The World Bank commissioned a separatelyprepared forecast of natural gas prices taking into account region-specificpricing conventions with indexation factors based on its own worldpetroleum product price projections, with particular emphasis on the priceof natural gas since gas is the most competitive alternative fuel. The BaseCase projections are presented in Table 14; High and Low scenarios arereported in Appendix A3.
The TOR has further specified the probability of occurrence for each of the Base,High and Low case assumptions regarding demand, natural gas value and project cost.Each “expected” (i.e., Base Case) assumption value has a probability of 50 percent inthe cost-risk matrix, with the High and Low assumption values assigned a probabilityof 25 percent each.
The results of the cost-risk analysis are summarized in Table S-1. The analysisconcludes that the probability-weighted accumulated present value of real resourcesavings to the region as a result of the development of NT2 is US$269 million (i.e. veryclose to the Base Case present value of US$277 derived without incorporating
2 The Study Period includes both the planning period (FY2003-14) and an "end effects" analysis whichutilizes sophisticated programming techniques to analyze differences between alternatives (e.g., due todifferent lives and operating characteristics) beyond the planning period. Without an end-effectsanalysis, results may be biased against commissioning capital-intensive units near the end of theplanning period.
3 It should be noted that the costs and benefits being evaluated in this report are confined to thepower sector; when other studies dealing with environmental and social costs are completed they willbe combined with the results of this report to produce an overall economic statement on theproject’s economic efficiency. The US$ 277 million represents a ‘savings” since the least-cost planwithout NT2 would come at greater total cost.
4 This experience also reflects extreme and unexpected events, such as the Asian economic crisis of1997, but that is not the primary consideration for the wide range adopted.
Executive Summary v
probabilistic outcomes for key variables). In present value terms, these savings areequivalent to US$0.012 for each kWh sold from the NT2 project.
Table S-1. Economic Cost-Risk Analysis Results
A. Present Values WITH NT2:Savings by
Case Probability Case Probability Case Probability Case Present Value Probability Scenarioh 0.25 h 0.25 h 0.25 hhh 61,720 0.01563 193 h 0.25 h 0.25 m 0.50 hhm 55,621 0.03125 125 h 0.25 h 0.25 l 0.25 hhl 51,490 0.01563 63 h 0.25 m 0.50 h 0.25 hmh 48,568 0.03125 177 h 0.25 m 0.50 m 0.50 hmm 43,855 0.06250 103 h 0.25 m 0.50 l 0.25 hml 40,684 0.03125 52 h 0.25 l 0.25 h 0.25 hlh 36,631 0.01563 139 h 0.25 l 0.25 m 0.50 hlm 33,184 0.03125 23 h 0.25 l 0.25 l 0.25 hll 30,821 0.01563 (63) m 0.50 h 0.25 h 0.25 mhh 61,546 0.03125 367 m 0.50 h 0.25 m 0.50 mhm 55,447 0.06250 299 m 0.50 h 0.25 l 0.25 mhl 51,316 0.03125 237 m 0.50 m 0.50 h 0.25 mmh 48,385 0.06250 360 m 0.50 m 0.50 m 0.50 mmm 43,681 0.12500 277 m 0.50 m 0.50 l 0.25 mml 40,510 0.06250 226 m 0.50 l 0.25 h 0.25 mlh 36,457 0.03125 313 m 0.50 l 0.25 m 0.50 mlm 33,010 0.06250 197 m 0.50 l 0.25 l 0.25 mll 30,647 0.03125 111 l 0.25 h 0.25 h 0.25 lhh 61,371 0.01563 542 l 0.25 h 0.25 m 0.50 lhm 55,272 0.03125 474 l 0.25 h 0.25 l 0.25 lhl 51,141 0.01563 412 l 0.25 m 0.50 h 0.25 lmh 48,210 0.03125 535 l 0.25 m 0.50 m 0.50 lmm 43,506 0.06250 452 l 0.25 m 0.50 l 0.25 lml 40,335 0.03125 401 l 0.25 l 0.25 h 0.25 llh 36,282 0.01563 488 l 0.25 l 0.25 m 0.50 llm 32,835 0.03125 372 l 0.25 l 0.25 l 0.25 lll 30,472 0.01563 286
A. Probability-weighted Present Value WITH NT2 44,337 1.00000
B. Present Values WITHOUT NT2:
Case Probability Case Probability Case Present Value Probabilityh 0.25 h 0.25 hh 61,913 0.06250 h 0.25 m 0.50 hm 55,746 0.12500 h 0.25 l 0.25 hl 51,553 0.06250 m 0.50 h 0.25 mh 48,745 0.12500 m 0.50 m 0.50 mm 43,958 0.25000 m 0.50 l 0.25 ml 40,736 0.12500 l 0.25 h 0.25 lh 36,770 0.06250 l 0.25 m 0.50 lm 33,207 0.12500 l 0.25 l 0.25 ll 30,758 0.06250
B. Probability-weighted Present Value WITHOUT NT2 44,606 1.00000
Probability-weighted PV Savings (Cost) WITH NT2 269 (Result A minus Result B; 2003 USD million)
POWER DEMAND GAS PRICE
CONSTRUCTION COST POWER DEMAND GAS PRICE SCENARIO RESULTS (2003 USD million)
SCENARIO RESULTS (2003 USD million)
I n t roduc t ion 7
1 INTRODUCTION
1.1 Background
Nam Theun 2 (NT2) is a planned hydroelectric project of a thousand megawatts5 inthe Lao PDR to be developed by a private company (NTPC). The Government ofLaos (GOL) is a 25 percent shareholder in NTPC. Upon anticipated commencementof commercial operation in 2009 (FY2010), NTPC will sell fixed amounts of power atpre-negotiated prices to the Electricity Generating Authority of Thailand (EGAT).While NT2 will be operated and maintained by NTPC, the facility will be under thefull dispatch control of EGAT.
The World Bank has supported the GOL in the development of the NT2 Project. Infact, a World Bank Partial Risk Guarantee to NTPC is under consideration.
This study is a component of the Bank’s on-going due diligence process. The work isa complement to an earlier study, the Thailand Power Scenario Study (TPSS),6
developed in cooperation with the Electricity Authority of Thailand (EGAT), utilizingEGAT’s least-cost planning tools. That analysis was conducted from a commercialperspective. Further, the study assessed NT2 from the perspective of Thailand ratherthan the region as a whole.
The World Bank carried out a detailed review of the TPSS, and concluded thatadditional work was needed to satisfy the Bank's operational guidelines on theeconomic evaluation of electric power projects. These guidelines stipulate that,
…for every investment project, Bank staff conducts economic analysis to determinewhether the project creates more net benefits to the economy than other mutuallyexclusive options for the use of the resources in question.
…all flows are measured in terms of opportunity costs and benefits, using 'shadowprices,' and after adjustments for inflation...
5 To avoid possible confusion, we wish to clarify the “exact” capacity of NT2. The developer (NTPC)identifies the capacity as 995 MW (plus 75 MW dedicated to Lao domestic consumption), the rating ofthe installed turbines. EGAT, however, designates the plant as 920 MW, the estimated minimummonthly delivery. The difference between the two numbers is (i) transmission losses to the purchase-point at the Thai border, and (ii) what one EGAT official calls a “margin of security” for the sake ofsystem reliability, so that EGAT can be certain of this minimum level of delivery. The contract permitsEGAT to request more than 100 percent of this capacity with permission from NTPC. For purposesof this study, which adopts a regional perspective, NT2 is defined as a 995 MW plant (i.e., 920 MWdelivered to Thailand plus 75 MW Lao domestic load). The contract is priced and largely defined interms of GWh, hence the MW accounting definition is not important for purposes of this analysis.
6 Robert Vernstrom, Thailand Power Scenario Study, Bangkok, March 2003. The World Bank financedand supervised the study.
I n t roduc t ion 8
…the Bank finances only those supply facilities and demand-management measures thathelp meet economically efficient demand at the least economic cost.
Unless the economic analysis is fully consistent with Bank policy, the review concluded,there could be lingering uncertainty as to whether the methodology adopted for theTPSS truly reflects the economic results that would occur using the Bank's ownevaluation policies and assessing the project from a regional perspective. Therefore,the review also highlighted the need for a structured “cost-risk” analysis whichconsiders alternative outlooks on demand, natural gas prices and NT2 constructioncosts, as well as pointing out some other analytical matters that warrant further work.
The current study reports the findings of the analysis conducted to achieve theseexpanded objectives. Briefly, the study includes a thorough comparison of the realresource cost to the regional7 economy of power sector development “with” and“without” NT2. Results incorporate a probabilistic “cost-risk” assessment of thiscomparison over a range of project uncertainties, including capital costs, future gasprices, and Thai load growth.
The Terms of Reference presented in Appendix A1 detail the Bank's requirements forthe analysis.
1.2 Study Objective
The study outcome is to be determined by means of a results profile known as the“Cost-Risk Framework”. This profile – explained in detail in Chapter 4 – provides forcalculating the probability-weighted present value (PV) costs of either implementingor not implementing NT2 for commercial operation in FY2010, given the interplay ofseveral major uncertain factors – project cost, long-term demand for electricity, andlong-term economic value of natural gas as well as the suggested probabilities ofoccurrence for Base Case, Low and High estimates of these variables. The differencebetween the probability weighted PV cost of implementing the project in FY2010versus not implementing it at all is the decision criteria for this analysis. A lower netpresent value (NPV) “with NT2” would indicate that the project is an acceptableeconomic investment for the regional power market.
It should be noted that the power sector costs and benefits being evaluated in thisreport include only environmental and social costs which the project sponsor iscommitted to finance, but does not include any other potential environmental costsand benefits. When other studies dealing with these factors are completed they willbe combined with the results of this report to produce an overall economic statementon the project’s economic efficiency.
7 Throughout this study, the word “regional” refers Lao PDR and Thailand.
I n t roduc t ion 9
1.3 Organization of the Report
This study is above all a careful review of anticipated electricity demand and supply inthe region, and of the role of NT2 in meeting future requirements.
The next two chapters present the basic demand and supply assumptions adoptedfor the analysis. Chapter 2 reports on the methods used to forecast the powermarket, and an analysis of results. Chapter 3 summarizes the existing supply system,as well as the cost of candidate plants which could provide future supply.
Chapter 4 presents the methodological approach for the study.
Chapter 5 presents the economic least-cost analysis and results. The chapter beginswith the Base Case evaluation of the project, and then continues with a systematic,probabilistic “cost-risk” assessment of the role of NT2 in light of a broad range offuture planning uncertainties.
Chapter 6 presents a summary of results, and the conclusion of the study.
System Demand Assumptions 1 0
2 SYSTEM DEMAND ASSUMPTIONS
Load forecasting in Thailand is a collaborative effort of the major stakeholders. TheThailand Load Forecast Sub-committee (TLFS)8 considers all methodological issues,and reviews the work of participating agencies before integrating results into anational load forecast.
The methodologies applied in forecasting have been developed and refined for over adecade, originally with international consulting assistance funded by CIDA, theCanadian development agency. In fact, methods are continuously evolving, as theTLFS strives to refine its techniques with each succeeding forecast. The most recentload forecast of the TLFS available for the current analysis was issued in August 2002;it has been used in this report.
Section 2.1 presents an overview of the forecasting methodology. Section 2.2 is areview of historical forecasting performance. Finally, Section 2.3 recommends BaseCase, High and Low demand forecasts for use in this study.
2.1 Overview of the Forecasting Methodology
The national load forecast employs at least five distinct methodologies, with theappropriate technique varying by
distribution company (MEA in greater Bangkok, and PEA in the rest of thecountry)
customer class (i.e., residential, small and large business, industrial, etc.), and
forecast horizon (i.e., short-term or long-term).
Four methods are used for energy forecasting. Two of these methods might bedescribed as “bottom up” in that they depend on detailed knowledge of end-users,while two others might be characterized as “top down,” since they depend onmacroeconomic trends. There is also an independent method for forecasting peakdemand. These methods are briefly summarized in the following paragraphs.
End-Use Model. Consumption for residential customers throughoutThailand is derived from comprehensive surveys of dwelling types byincome, and appliance utilization in each. Forecasts depend on growth in
8 The committee is comprised of representatives from EPPO (formerly NEPO), EGAT, MEA, PEA,DAEDE (formerly DEDP), NESDB, the National Statistics Office (NSO), the Federation of ThaiIndustries, the Thailand Chamber of Commerce, the Association of Thai Power Generators, and theThailand Development and Research Institute (TDRI).
System Demand Assumptions 1 1
number of households, appliance saturation, and expected applianceefficiency improvement.
Floor Space Model. Short-term (less than 5 years) consumption forlarge business (commercial customers > 30 kW) in the MEA service territoryis forecast based on available data on floor space by type of building. Dataon building stock is adjusted for factors such as demolition, constructiondeferral, occupancy rate, etc. Total consumption is then calculated fromsurvey data on energy use within each type of building. Again, factors areapplied to incorporate efficiency improvement into the forecast.
Energy Intensity Model. Gross domestic product (GDP) is carefullydisaggregated by region and by business sector so that energy consumptionrelationships by sector can be evaluated. Total consumption is derivedbased on historical consumption per unit of gross regional product (GRP),and the forecast growth in GRP by sector. The energy intensity model isused where “first hand” sources (e.g., Board of Expansion data, and surveysof available floor space) are unavailable, especially for longer-termforecasting.
Econometric Regression. When class consumption patterns are notattributed to clearly identifiable relationships (e.g., appliance usage, floorspace, sector energy intensity), econometric regression is used to define therelationship. The method is particularly applied to small business, and toother classes in which users have widely diverse consumptioncharacteristics.
Peak Demand Model. The TLFS has developed substantial loadresearch data by customer group over recent years through extensivesurveys, and applies this information to project demand from energyforecasts developed using the foregoing methods. The number of customerswithin each class is forecast based on regression analysis, and daily loadcurves derived from the load research data are used to forecast coincidentand non-coincident peak for each customer group. Peak losses are alsoforecast via regression equations for each customer class.
Table 1 summarizes the methods currently applied to each customer class.
Economic Growth (Income) Considerations in the Forecast
Growth in electricity demand is highly correlated to medium and long-term economicgrowth prospects (especially economic growth per consuming unit, e.g. per householdor per unit of industrial output). Each of the methods used by the TLFS considerincome, either directly or indirectly. For example, the end-use model forecasts end-use consumption by the stock of dwellings classed by income type. Similarly, the floorspace model directly measures economic expansion among large businesses. Theenergy intensity model relates energy requirements to anticipated growth in valueadded by business sector. Economic regression analysis typically incorporates an
System Demand Assumptions 1 2
income term (e.g., gross regional product by business sector) into its forecastequations.
Table 1. Current Forecast Methods by Company and Class
Customer Class MEA PEA
Residential End-Use model Same approach, by region
Industry Short-term: First-hand sources(e.g., BOI, applications forservice, targeted surveys)Long-term: Energy intensitymodel (energy intensity per unitof value added)
Same approach, by region
Large Business(>30 kW)
Short-term: Floor Space modelLong-term: Energy intensitymodel by business sector
Energy intensity model bybusiness sector by region
Small Business Econometric regression Same approach, by region
Other Classes Econometric regression Same approach
Peak Demand Daily load curves by customergroup applied to regression-derived customer forecasts byclass. System coincident peakderived from coincident peak ofeach class.
Same approach
Notes: (1) All methods incorporate adjustments for efficiency improvement over time; e.g. end-usemodels assume progressive improvement in efficiency of household appliances, and energyintensity models assume increasing energy efficiency per unit of value added.(2) EGAT direct customers are forecast by individual firm survey.
Thus, the economic forecasts driving Thailand’s national load forecast are a crucialfactor in their accuracy. The Government of Thailand (GOT), through its NationalEconomic and Social Development Board (NESDB), forecasts anticipated nationalGDP, but typically only for five years (i.e., the next national plan). For long-termtrends, the TLFS has relied on the Thailand Development and Research Institute(TDRI) to project economic growth and to disaggregate the national GDP forecast byregion and by business sector. TDRI was hired to develop these trends for theSeptember 1998 forecast, and is revising economic projections which will be applied infuture load forecasts. TDRI applies a very complex model to develop these results.9
9 TDRI uses a “computable general equilibrium model (CGE)” for making macroeconomic projections.This is the same type of model that NESDB uses to prepare official economic forecasts for the five-yearnational plans. The model is very large and requires considerable time to readjust and calibrate a newforecast series. The most time-consuming part of the projection process, however, is to allocate the15-year macroeconomic forecast into MEA and PEA regions and the corresponding customer sub-groups specified by TLFS. For this task, TDRI needs to conduct detailed surveys in order to establishbaseline information for each regional forecast. The TLFS requires long tem economic projections
System Demand Assumptions 1 3
Sep-97 Sep-01Year Actual IMF/GOT RER MER LER NESDB
Annual GDP Forecast Error (%, for full-year forecasts after 1997) 2/1998 14.3%1999 1.3% -1.8% -3.6% -4.8%2000 2.2% 1.1% -0.6% -1.8%2001 4.7% 4.3% 2.6% 1.5%
1/ RER - rapid economic recovery, MER - medium economic recovery, LER - low economic recovery 2/ Differernce between actual and forecast GDP growth rates.
Sep-98 Forecasts Assumptions 1/
Table 2. National GDP Growth Assumptions
National economic projections applied for recent load forecasts are compared inTable 2.
The August 2002 load forecast adopted the Sep-98 (MER) economic outlook for theperiod following NESDB’s near-term prediction (i.e., 2006-11). The TLFS noted thatthe 4.7% average annual GDP growth under MER for the Ninth Plan (2001-06) wasvery close to the NESDB’s projection of 4.6% for the same period. Furthermore, theTLFS believed that the average long term annual growth rate of 4.7% assumed in theSep-98 (MER) was still a reasonable estimate. Therefore, the committee decided to
broken down at this high level of detail in order to run its end-use load forecast model. As a result,the process is very time consuming and costly.
While we have no reason to doubt the methodology employed by TDRI, or the accuracy of its results,the approach has the disadvantage that a new demand forecast cannot be easily produced in responseto alternative views of economic growth. Given the difficulty that all economists have experienced inforecasting national (and international) economic growth in recent years, this slow response timecould be disadvantageous.
System Demand Assumptions 1 4
adopt the NESDB short-term and MER long-term economic outlooks for the Aug-02load forecast.10
Recent economic growth trends – and medium-term forecasts – are more optimisticthan the foregoing assumptions reflect. Actual 2003 growth will be approximately 6percent; the GOV is projecting 2004 growth of about 8 percent. The World Bank iscautiously optimistic, expecting 6 percent growth in 2004, but expressing severalconcerns regarding the sustainability of high growth in the medium-term.
Specifically, the Bank notes that private consumption has been the chief driver ofrecent expansion, and that private investment's contribution to growth has been lessthan in previous economic recoveries and remains lower than many other countries inthe region. Corporate access to credit has been constrained by a cautious bankingsector and slow structural reforms. Export growth has been relatively strong,however, an appreciating exchange rate and capacity constraints could restrain thisgrowth. Further, the rate of non-performing loans (NPLs) has not declined and re-entry NPLs have increased. Progress in banking and capital market reform, and in legalreform, has been limited. In summary, World Bank economists argue that Thailand willneed to improve its competitiveness and productivity in order to convert the currentrecovery into sustained high growth over the medium-term.11
Price Considerations in the Forecast
The load forecasting methodologies do not explicitly consider price as an independentvariable in forecasting demand. However, the impacts of historical price changes arecaptured in the forecasts. For example, surveys for the end-use forecasts reflect pricechanges through adjustments in appliance usage and saturation. Floor space modelscapture changes in energy use per unit of floor space which may have occurred inpart due to changes in electricity price.
Thus price is indirectly reflected in current forecasting methodologies.
Energy Conservation in the Forecast
In addition to incorporating adjustments for energy efficiency improvement in eachclass load forecast, the August 2002 Base Case is further adjusted downward toreflect the impact of a group of on-going electric energy conservation programs beingundertaken by various GOT agencies, including EPPO (formerly NEPO), DAEDE(formerly DEDP), and EGAT.
Table 3 summarizes the complete package of conservation activities; this packagerepresents the official plan of the GOT adopted by the Cabinet. The final lines of thetable show the conservation program included in the Aug-02 Base Case forecast. 10 While it is beyond the scope of the current study to produce a new load forecast, it should benoted that recent economic performance of Thailand has exceeded forecasts, and analysts aregenerally optimistic regarding medium-term economic growth prospects.
11 The views expressed in these paragraphs are based on Consultant discussions with macroeconomistsat the World Bank office in Bangkok, and opinions presented in that office's Economic Monitorpublished in October 2003.
System Demand Assumptions 1 5
(The forecast excludes 2,516 GWh of conservation savings achieved by FY2002;TLFS has assumed that this conservation is already reflected in base year consumptiondata.)
In fact, the TLFS has been very concerned about the effect of energy efficiencyimprovement on future electricity demand, and established a special working group tomake a detailed assessment of the various conservation-related programs. Thefindings of that group indicated that official estimates were probably too high, for thefollowing reasons:
Only about 15% of the planned electricity demand reduction in the next 10years is expected to come from mandatory programs where the set targetsare reasonable. The remaining 85% reduction in electricity demand isanticipated to come from numerous voluntary programs. The success ofthese programs will depend on their implementation procedures andconsumer willingness to participate. These factors are not yet clearlydefined.
Several programs have missed implementation deadlines, and many areexpected to face further delay. Other programs (e.g., switching streetlighting off late at night) have faced opposition from highway safetyengineers, and may not be implemented.
After considerable debate, the TLFS decided to reduce the amount of conservedelectricity by nearly 30% in the year 2011 for the Aug-02 load forecast. (An evengreater cut was considered, but it was decided to give the programs an opportunityto achieve targeted progress. A more critical evaluation will be incorporated intosubsequent load forecasts.) The forecast incorporates a total conservation savings of982 MW by 2011.
1/ Energy Policy and Planning Office (formerly NEPO).2/ Department of Alternative Energy Development and Efficiency (formerly DEDP).3/ Minimum efficiency standards for household appliances.4/ Aug-02 forecast excluded 2,516 GWh assumed to have already been realized in the forecast base year (FY 2002).5/ Estimate based on system load factor; a conservative assumption since some programs target load shifting and peak reduction.
ProgramPlanned Conservation Savings (GWh)
Table 3. Integrated National Electricity Conservation Program
The conservation program outlined in Table 3 is part of a 10-year master plandeveloped by responsible GOT agencies, which emphasized technical/economicpotential rather than financial/legal constraints.12
Table 4 presents an informal “order of magnitude” alternative view of conservationpotential based on the Consultant’s discussions with conservation planners. Thisalternative scenario is presented for discussion purposes only, intended to crudelyquantify the widely held opinion that the program in Table 3 may be unduly optimisticwith regard to potential savings. The alternative view in Table 4 suggests that onlyhalf of the conservation assumed in the Aug-02 forecast may be achieved by 2011,and perhaps three-quarters of that target by 2016. In other words, the load forecastcurrently used by EGAT almost certainly assumes greater conservation than theelectricity sector will actually achieve over the forecast period.13
12 Most of the funding for energy conservation will come from the “ENCON Fund’, which is financedthrough a targeted tax on petroleum products of THB 0.40 per liter.
13 Unlike some of the other programs, EGAT’s own DSM Program has been proceeding according toplan. The program is funded directly by EGAT (vs. the ENCON Fund), and conservation savings areprojected to exceed the level forecast in the consolidated national conservation plan (Table 3). InTable 4, we have adopted EGAT’s forecast of DSM savings through FY2006, and have conservativelyassumed no increases thereafter.
System Demand Assumptions 1 7
Table 4. National Conservation Program – Alternative View
EPPO is currently developing a more realistic program guided on funding and otherlimitations. As of the publication of this study, a conservation action plan is not yetfinalized. Significantly, however, EPPO reports Cabinet-level approval for a majorreduction in national energy consumption, expressed as a target energy elasticity of1.0 versus the current level of 1.3 or more (see Section 2.2). Although this is aworthwhile objective, it is perhaps premature to presume the schedule for meeting ofthis goal, given that no action plan is in place, and no performance record exists fromwhich to define a realistic pace for achieving the target.
It is important to put these conservation savings in perspective. The total savings aresignificant – on the order of 1,000 MW by 2011 (Table 3) or 2016 (Table 4).However, these capacity and associated energy savings represent less than one-year’snational demand growth (even when assuming a low demand forecast); hence, theydo not obviate the need for continued expansion of the generating system.
2.2 Comparison of Forecast Results
The TLFS has prepared a total of 12 national load forecasts since 1993. Tables 5 and6 summarize the Energy Requirements and Peak Demand projections from many ofthese forecasts, excluding those prepared immediately before and after the onslaughtof the Asian economic crisis in July 1997. The crisis, with its profound impact on theThai economy, including electricity consumption, rendered earlier forecasts irrelevantfor future planning.14 Even the first “post-crisis” forecast (September 1997) provednaively optimistic in its outlook for economic recovery. (Thai forecasters, likeeconomists everywhere, simply did not foresee the depth and duration of the crisis.)It can be observed that the forecasts in the tables are progressively lower.
14 The highest forecast (April 1996) projected peak demand in fiscal year 2002 to be over 40 percent(7,000 MW) above the recorded peak of 16,681 MW. That same forecast also projected demand in2011 to exceed 42,000 MW, 45% more than the August 2002 forecast.
1/ Informal Consultant estimate based on discussions with participants.2/ Assuming slower start-up (1-2 year delay), slower growth (original program or scaled back program spread over 10 years), but continuing growth after 2011.3/ Excludes 2,058 GWh assumed to have already been realized in the forecast base year (FY 2002).4/ Estimate based on system load factor; a conservative assumption since some programs target load shifting and peak reduction.
ProgramPlanned Conservation Savings (GWh) 1/, 2/
System Demand Assumptions 1 8
Table 5. Historical Energy Requirements Forecasts (GWh)
The forecast of September 1998 was much more successful at incorporating thepotential implications of the crisis on electricity consumption. It included threescenarios based on anticipated speed of economic recovery – rapid (RER), medium(MER), and low (LER). Two subsequent forecasts (February 2001 and August 2002)have refined these results in response to revised economic growth scenarios from theGovernment of Thailand (NESDB), and incorporated conservation program planning.
The dramatic changes in near-term expectations regarding national electricityrequirements are obvious in Tables 5 and 6. But it is equally interesting to observefrom the tables that expected average annual growth rates for medium to long-termprojections show little variation. For the period 2001-06, the annual rate of growthin demand is between 5.9 and 6.5 percent in five of the eight forecasts. Two others –the Sep-98 RER (“rapid economic recovery”) and LER (“low economic recovery”) –were intended as High and Low scenarios to bracket a medium (“MER”) forecast. Forthe period 2006-11, five forecasts project average annual generation growth between5.7 and 6.3 percent.
Fiscal Actual Jun-93 Dec-94 Oct-95 Feb-01 Aug-02Year GWh RER MER LER Base Base
This similarity of result is surprising, given that each forecast started from a differentbase and with different macroeconomic expectations (the associated national GDPforecast, as reported in Table 2). Table 7 shows the simple income (GDP) elasticity ofdemand implied by each energy requirements forecast.15
These elasticities have typically ranged from 1.30 to 1.40, with many individual yearelasticities falling outside this narrow band.16 Considering that income elasticity wasnot a basis for energy forecasting of many consumer categories, the implied elasticitiesare surprisingly stable across these recent forecasts.17 Interestingly, however, thehighest of these forecasts (Sep-98 RER) had lower-than-average income elasticities,and the lowest forecast (Sep-98 LER) has somewhat higher-than-average incomeelasticities, in later forecast years. This confirms that income elasticities were not thebasis for these forecasts.
15 Clearly, a far more meaningful elasticity measure would be income per consuming unit by customerclass (e.g., electricity consumption growth per consuming unit of industrial value added per companyor per commercial establishment). We have used a far less detailed approach, since our objective isonly to confirm to reasonableness of the Base Case forecast.
16 The TLFS has independently estimated income (GDP) elasticity of demand. We understand thatthese unpublished investigations estimated an average income elasticity of about 1.4.
17 The actual experience reported in Table 7 for the period 1995-2001 tells a somewhat differentstory; electricity demand appears to have been far more stable than the performance of the incomevariables, causing remarkable variance of the implied elasticity from year to year.
Fiscal Actual Jun-93 Dec-94 Oct-95 Feb-01 Aug-02Year MW RER MER LER Base Base
Table 7. Implied Income Elasticity of Energy Requirements Forecasts
Table 8 summarizes forecast performance in terms of accuracy for each year afterpublication, excluding the “crisis years.” With few exceptions, demand and energyforecasts have been accurate to within a couple of percent in their early years.(Perhaps the error observed in the October 1995 energy forecast was an earlywarning of the pending crisis.) This performance suggests that the short-termforecasting models employed by the TLFS have performed well. In the longer term,the dramatic distortions of the 1997 Asian economic crisis make it difficult to assessthe accuracy of Thailand’s forecasting models under a period of more stable marketconditions.
Table 8. Historical Forecast Accuracy 1 /
Years Jun-93 Dec-94 Oct-95 Feb-01Forecast RER MER LER Base
1/ Energy forecasts adopted Sep-98 (MER) economic growth forecast after 2006.n/m - not meaningful
Sep-98 Forecasts Assumptions
System Demand Assumptions 2 1
2.3 Load Forecast Adopted for this Study
The August 2002 Base Case load forecast18 is the planning basis for EGAT’s PDP2003, and is used for the current study. It is a technically and methodologically soundbasis for future system planning.
Due to the unique regional perspective of the present study, there are differencesbetween the Base Case forecast used in this report and the August 2002 loadforecast. Specifically, the Base Case forecast includes Lao domestic load which isassumed to grow enough to utilize its allocated share of total NT2 project output.Thus, starting in FY2010, the August 2002 forecast is increased by 300 GWh of netgeneration and 75 MW of peak demand.19
Low and High demand forecasts, as requested by the World Bank, reflect a wide bandof future loads. Based on the Bank's extensive experience with long-term loadforecast accuracy around the world, the Bank specified the Low and High Casedemand forecasts to be symmetrically keyed off the Base Case forecast using thefollowing equations, reflecting the percentage gap between these forecasts that theBank considers appropriate by year 10 of the forecast period:
(1+grL)^10 = 0.75*(1+grB)^10 [for the low case]
(1+grH)^10 = 1.25*(1+grB)^10 [for the high case]
where “grB” means Base Case growth rate of demand, “grL” means Low Casegrowth rate of demand and “grH” means High Case growth rate of demand.
Thus, the Low Case forecast is set to a growth rate at which the capacity and energyrequirements in FY2012 are 75 percent of the Base Case requirements. Symmetrically,the High Case load forecast in FY2012 is 125 percent of the Base Case requirement.The constant annual growth rates implied by these results are applied to all forecastyears.
Table 9 summarizes all three forecast scenarios adopted for this study. The averageannual growth rates of these scenarios range from a Low of about 3.4 percent to aHigh of nearly 9 percent. This wide band subsumes the range of futures that havebeen projected in the recent past: (i) the GOT's very optimistic economic growthand energy conservation targets, (ii) the World Bank's more cautious growthperspective coupled with slower energy elasticity improvement, and (iii) the slower
18 For readers who would like to review the August 2002 forecast in greater detail, complete resultsby customer class for MEA, PEA, and direct customers of EGAT are reported in Appendix A2.
19 A necessary corollary of this assumption is that Laos’ alternative to NT2 for meeting this portion ofits demand would be import of electricity from Thailand. Further, this load increment is presumed tomirror the Thai load curve, a simplifying assumption that avoids separate modeling of the Lao system.Given planned changes to that system over coming years (including regional grid integration andpossible introduction of TOU tariffs to flatten the curve), modeling of the future Lao system would bespeculative at best.
System Demand Assumptions 2 2
growth outlook that drives the Base Case forecast. The volatility of recent economicprognostications highlights the futility of projecting long-term economic performancewith accuracy; it is reassuring to know that the current analysis incorporatesconsideration of this uncertainty.
Note that the forecasts presented in the table exclude station use in order toconform to the requirements of the model (“PROSCREEN II”) used for least-costexpansion planning. Net generation and net peak forecasts are shown; theseforecasts are on the order of 2 percent lower than the Base Case forecast reported inTables 5 and 6.
1/ All cases exclude station use; forecasts reflect net generation and net peak as utilized by the PROSCREEN model.
2/ All cases include Lao domestic load (300 GWh, 75 MW) from FY2010, theenergy and demand assumed to be fully absorbed from NT2 project output.
RECOMMENDED LOAD FORECAST (net, including Lao Load) 1/,2/Gross Energy Requirement (GWh) Peak Demand (MW)
System Supply Assumptions 2 3
3 SYSTEM SUPPLY ASSUMPTIONS
This Chapter of the report describes the existing power system and the optionsavailable for system expansion in order to provide for the demand growth identified inChapter 2.
Section 3.1 summarizes the existing power system. Section 3.2 describes candidatesfor system expansion, including their capital and operating costs. Assumed fuel pricesfor the system are presented in Section 3.3. Section 3.4 is a preliminary screeninganalysis of thermal expansion candidates that illustrates their competitive advantagesat different utilization factors. Finally, Section 3.5 discusses the non-thermalalternative for meeting future expansion requirements – NT2.
3.1 Installed and Planned System Capacity
The study adopts PDP 2003, as published by EGAT in April 2003, as the basis fordefining the existing system, committed additions and retirements. All tables andcalculations reported in this and subsequent chapters of the report assume the samebase as PDP 2003.20
Table 10 summarizes EGAT’s installed and purchased capacity as of March 2003.EGAT’s own system is dominated by thermal capacity, accounting for over half of thetotal. These units are predominantly gas-fired, although more than 2000 MW oflignite capacity are still in service. Purchased power is a major source of supply,accounting for over 40 percent of total available capacity. Although not shown in thetable, this segment, too, is predominantly gas-fired thermal. Large thermal units –whether oil, lignite, or gas-fired, including purchased power from IPPs and SPPs – havean availability factor of at least 80 percent. (Detailed data by plant is presented inAppendix A4.)
Thailand’s hydro capacity is almost entirely reservoir storage. (The exception is 136MW Pak Mun Dam.) Dependable hydro generation, exogenously estimated usinghistorical records from each site, represents the level of energy assumed to be availableby month at the 90 percent confidence level. Capacity factors are relatively low.
Lao imports represent purchases of energy from Theun Hinboun and Huay Hohydroelectric plants whose collective capacity factor is about 65 percent.
20 It should be noted, however, that there are minor discrepancies between actual and plannedinstalled capacity as of end-FY2003 due to minor delays and adjustments in scheduled plant additions(see Appendix A4).
System Supply Assumptions 2 4
Table 10. Installed and Purchased Capacity (as of March 2003)
Table 11 summarizes committed plant additions from March 2003.21 The table isdivided into four groups – EGAT plants, IPPs, SPPs, and NT2 – with a total capacityof nearly six thousand MW including NT2. The first three plants listed are underconstruction and scheduled to commence commercial operation in FY2003-04. Thesecond group (3,447 MW) includes three IPP plants whose firm contracts have facedlong delays due to multiple factors including the Asian economic slowdown andconcerted environmental opposition; these issues have been resolved and schedulesare now considered firm. The third group (197 MW) includes SPP plants (90 MWmaximum plant capacity) under contract for commissioning in the next three years.(Only plants approved by the Energy Conservation Fund as of March 2003 areincluded.)
21 The study assumes installed capacity of 25,697 MW as of September 2003, equal to September2002 installed capacity of 23,530 plus 2,167 MW added in FY2003; the FY2003 additions are dividedbetween Table 10 (1,848 MW) and Table 11 (319 MW).
1/ Excluding 3 x 75 MW at Mae Moh retired but providing cold reserve. 2/ Includes Khanom 824 MW, Rayong 1232 MW, Ratchaburi 3615 MW. 3/ Includes Independent Power 700 MW, Tri Energy 700 MW, Bowin Power 713 MW, Eastern Power 350 MW. 4/ Includes Theun Hinboun Hydro 340 MW, Houay Ho Hydro 126 MW.
Installed CapacityPlant / Fuel Type
System Supply Assumptions 2 5
Table 11. Committed Plant Additions (after March 2003)
Nam Theun 2 is also a committed plant in EGAT’s generation expansion plan,scheduled for commercial operation in FY2010. Although the plant is included in thetotals reported in Table 11, NT2 is treated as an expansion candidate for purposes ofthe economic analysis in this study.
Retirements scheduled for the period FY2003-1422 are summarized in Table 12. Wehasten to add that this retirement schedule is a drastic oversimplification, reflectingmainly the “planned life” for each plant type.23 It is EGAT policy to assume fixed unitlives for planning purposes. However, should units be performing well as theyapproach their planned retirement date, a plant-specific study is undertaken todetermine whether extending the service life would be cost-effective, given anyrequired investment for reconditioning.
22 As explained in the following chapter, FY2003-14 is the planning period for our analysis.
23 The Khanom Thermal plant is an exception, scheduled for early retirement in FY2007 when a farmore efficient gas-fired combined cycle plant is expected to be available in the South.
2. IPP Contracts 1/ 3,447 - BLCP Power - Unit 1 673 - BLCP Power - Unit 2 673 - Gulf Power 700 - Union Power Development - Unit 1 700 - Union Power Development - Unit 2 700
3. SPP Contracts 2/ 197 - Phase I Contracts 69 - Phase II Contracts (Renewables) 128
4. Nam Theun 2 Hydro 3/ 995
TOTAL 5,945
1/ Includes committed plants with planned COD after March 2003 as reported in PDP 2003 (April 2003) 2/ SPP plants approved but not in operation as of March 2003. 3/ This regional study defines NT2 as 995 MW, inclusive of the 75 MW Lao domestic load it will also serve; PDP 2003 defines the plant as 920 MW delivered to the Thai system.
2. IPP Contracts 1/ 3,447 - BLCP Power - Unit 1 673 - BLCP Power - Unit 2 673 - Gulf Power 700 - Union Power Development - Unit 1 700 - Union Power Development - Unit 2 700
4. SPP Contracts 2/ 197 - Phase I Contracts 69 - Phase II Contracts (Renewables) 128
5. Nam Theun 2 Hydro 3/ 995
TOTAL 4/ 4,950
1/ Includes committed plants with planned COD after March 2003 as reported in PDP 2003 (April 2003) 2/ SPP plants approved but not in operation as of March 2003. 3/ This regional study defines NT2 as 995 MW, inclusive of the 75 MW Lao domestic load it will also serve; PDP 2003 defines the plant as 920 MW delivered to the Thai system. 4/ Total does not include NT2.
FY2007FY2007FY2008FY2008FY2009
FY2010
FY2003-05FY2003-05
PlantEGAT Planned
Commissiong Date 1/
FY2004FY2004FY2004FY2007
System Supply Assumptions 2 6
Table 12. Schedule of Retirements (FY2003-14)
EGAT has concluded that life extension is economically justified for thermal capacityat South Bangkok (units 3 through 5), and Bang Pakong;24 these reconditioned unitsare included in PDP 2003. The current study evaluates these four retiring thermalunits as candidates for reconditioning (see Section 3.2).
3.2 Thermal Expansion Candidates
EGAT has identified a number of candidate plants for long-term system expansion.This Study has focused on four new candidate options which might be expected tomeet future capacity requirements. These are: (i) oil-fired steam thermal, (ii) coal-firedsteam thermal, (iii) gas-fired combined cycle, and (iv) gas turbines. The study alsoconsiders reconditioning of a group of large thermal units scheduled for retirementduring the study period (i.e., South Bangkok Thermal and Bang Pakong Thermal). Allof these candidates are summarized in Table 13.
The capital costs, lives, and operating cost assumptions for each candidate have beenreviewed and approved by the World Bank based on both (i) discussions regardingEGAT’s recent experience, and (ii) the Bank’s own experience with large powerprojects in other countries. In particular, the Bank wished to have the study reflectevidence of a spread of US$200/kW between the cost of gas turbine (GT) andcombined-cycle (CCGT) capacity to reflect EPC cost differences (includingdevelopment cost margins). Hence, Bank-recommended values of US$250/kW for GTcapacity and US$450/kW for CCGT capacity have been adopted.
24 Parallel investigations by EGAT have concluded that life extension is not justified for South Bangkokunits 1-2 or the combined cycle units at Bang Pakong.
3. Gas Turbine 140 - Lan Krabu various 140 depends on available gas 30+
TOTAL 2/ 2,790
1/ Under PDP 2003, these units are to be reconditioned for further service as of this date. 2/ Early retirement due to availability of lower cost generation. 3/ Total excludes Lan Krabu
3. Gas Turbine 750 - Lan Krabu various 140 30+ (depending on gas availability) - Nong Chok - 3x122 20 Oct-2015 - Surat - 2x122 15 Oct-2016
TOTAL 7,084
RetirementDate(s)
System Supply Assumptions 2 7
Table 13. Candidate Power Plants for the Study (2003 Prices)
3.3 Fuel Price Projections
Fuel price forecasts for this study have been developed in cooperation with EGATand the World Bank. In general, the Bank adopted EGAT’s assumptions for coal andlignite, but conducted an independent analysis to establish petroleum product prices.
One of the most critical determining factors for this study is the value of natural gasto be used in combined cycle gas turbines, since these are the most likely economicalternatives to NT2. The following discussion summarizes the methodology employedby the Bank in deriving natural gas prices. (Other petroleum products have beenvalued in a similar manner, appropriately adjusted to their own unique productcharacteristics and markets.) A more comprehensive discussion of the analysis ispresented in Appendix A3.
The economic value of natural gas has been calculated based on:
the cost of discovery, development and production for local supply,
border price for Myanmar supply,
removal of taxes and royalties from domestic production,
addition of the PTT marketing margin and
the estimated LRMC of gas transmission on a postage stamp basis.
Capacity Capital Cost Life Heat Rate Fixed O&M Var. O&M FOR MaintenanceType MW US$/kW 1/ years Btu/kWh $/kW-yr $/MWh 2/ % weeks
1/ Assumed expenditure profiles (%): year 0 year -1 year -2 year -3 year -4Thermal 19.0% 23.5% 34.5% 13.5% 9.5%Combined Cycle 11.1% 37.9% 34.4% 16.6%Gas Turbine 8.8% 49.6% 41.6%
2/ VOM calculated as a ratio (FOM:VOM): oil-fired (85:15), coal-fired (80:20), combined cycle (85:15), gas turbine (95:5).3/ VOM includes limestone for FGD4/ 2GT multi-shaft assumed5/ Excluding land and land rights.6/ South Bangkok and Bang Pakong thermal units are candidates for reconditioning (life extension); this option only permitted in the year immediately following retirement: SBT3 - 2010, SBT4 - 2011, SBT5 - 2013, BKT1 - 2014. Asterisk (*) indicates costs and efficiencies are included in the model's database and used in the analysis, but not identified here for reasons of confidentiality.
System Supply Assumptions 2 8
Although the World Bank does not have access to individual gas contracts, it isunderstood that the gas pricing structure, valid for the duration of the contract, isspecified in Thai Baht, incorporating an indexation formula which adjusts the priceover time according to the following factors:
the fob price of 3.5%S HFO Singapore,
a petroleum industry machinery inflation index reflecting USD inflation,
the Thai CPI reflecting Thai domestic inflation,
an exchange rate adjuster, and
a constant.
Given that our project numeraire is US dollars, the machinery index, the Thai CPIindex and the exchange rate adjuster are offsetting in future price projections (basedon purchasing power parity method of exchange rate projection). When working inUS$ prices, therefore, the only non-offsetting element of the index is the HFOadjuster, having a weight of about 30% in the total index.
In addition, PTT charges EGAT and IPPs a marketing margin of 1.75% of the salesprice, plus a postage-stamp pipeline toll.
Moving from the commercial value of natural gas to an economic value furtherrequires removal of all transfers – royalties and taxes – from the commercial price.Finally, resulting nominal economic natural gas values are converted into real values bydeflating the nominal series by the MUV index.25
Base Case economic fuel price projections adopted for this study are summarized inTable 14. High and Low scenario fuel price projections are reported in Appendix A3.
Table 14. Base Case Fuel Price Forecasts
25 The MUV index is more formally identified as the United Nations’ Index of Unit Value ofManufactured Exports from the G-5 industrial countries to developing country markets expressed inU.S. dollars.
End Effect 2.27 2.50 4.50 1.05 1.41 Average Annual Growth (%)2003-2014 -1.1% -2.7% -2.7% -1.3% -0.8%
System Supply Assumptions 2 9
3.4 Thermal Candidate Plant Screening Analysis
The Study TOR requests a preliminary screening analysis based on real economiccosts in order to confirm the expectation that natural gas-fired units are the primaryalternatives to NT2.
The analysis has been prepared for the candidate generating units summarized inTable 13, assuming the fuel price forecasts from Table 14. Each candidate has beenevaluated at constant prices, using a real economic discount rate of 10 percent.
Table 15 shows the results of this analysis. The graph in the table plots the unit costof one kWh from each source as a function of the rate of capacity utilization.26
The table shows that gas turbines are the clear thermal choice for capacity utilizationbelow 25 percent (i.e., peaking duty). Gas-fired combined cycle appears to be theclear choice for higher capacity utilization. Even at very high capacity factors, the costof combined cycle is at or below the cost of coal-fired units. Oil appears to be non-competitive at the real fuel prices adopted for the current study.
3.5 NT2 – The Alternative Expansion Candidate
Contractually, in the EGAT-NTPC power purchase agreement (PPA), NT2 is treatedas three separate transactions:
the first transaction is a firm power purchase of 4406 GWh per year(allocated to peak-period hours [6 a.m. to 10 p.m.] and according toexpected monthly generation) at the Primary Energy Tariff (“PE”) specifiedin the contract;
the second transaction is a purchase of 948 GWh annually during off-peakhours at the Secondary Energy 1 Tariff (“SE1”) specified in the contract;this transaction is treated as non-firm so that PROSCREEN does notrecord a further increment to installed capacity; and
a third transaction (not required, but at the option of EGAT) is a purchaseof an additional 282 GWh at the Secondary Energy 2 Tariff (“SE2”).
26 Because plant capacities have already been adjusted for the effect of forced outages andmaintenance, each effective kW can be used up to 100 percent of the time.
System Supply Assumptions 3 0
Table 15. Screening Analysis of EGAT Candidate Plants
Levelized Cost of GenerationCandidate Units ($/kWh)
$0.00
$0.05
$0.10
$0.15
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Percent Ulilization of Effective kW
US
$ p
er
kW
h
Oil Coal Combined Cycle Gas Turbine
System Supply Assumptions 3 1
For purposes of the current study, total planned generation is allocated by monthbased on a review of historical data (1953-99) provided by NTPC, as summarized inthe following chart:
For the economic [real resource] analysis presented in Chapter 5, Base Caseinvestment and operating costs of the NT2 project are based on real cash flow dataderived from the project sponsor’s financial model, excluding transfers and sunk costs,but including incremental sponsor development costs that reflect use of real resources
Costs for associated transmission in Thailand and Laos are also included in theanalysis. Even when these costs are not borne by the project sponsor (as is the casewith associated transmission in Thailand), these investments represent real resourcecosts required to deliver NT2 energy from the powerhouse to end-users.
PE SE1 SE2Jan 370.4 62.2 18.5 Feb 331.0 46.2 13.7 Mar 362.1 44.0 13.1 Apr 349.8 30.0 8.9 May 361.8 77.7 23.1 Jun 355.9 114.7 34.1 Jul 386.4 147.2 43.8 Aug 391.2 107.1 31.9 Sep 382.6 98.5 29.3 Oct 389.2 88.6 26.4 Nov 363.4 70.0 20.8 Dec 362.2 61.8 18.4 Total 4,406.0 948.0 282.0
NT2 GWh by Month (1953-99)
Methodology for the Study 3 3
4 METHODOLOGY FOR THE STUDY
The primary focus of the current study is an economic analysis to determine whetherthe NT2 Project has a satisfactory economic cost-risk profile in the context of theregional power market. The main distinguishing characteristics of this second stageanalysis are threefold:
all values reflect real economic resource costs (to the greatest extentfeasible);
the scope of work includes both the Thai and Laotian electricity markets;and
the risk analysis consists of an integrated multi-event probabilisticframework that produces one overall quantitative result showing whetherimplementing the NT2 project in October 200927 would be an acceptableeconomic investment for the power sector.
Section 4.1 introduces the least-cost generation expansion planning methodologyadopted for this study. Section 4.2 describes the cost-risk framework used todetermine the Study outcome.
4.1 The Least Cost Planning Methodology
4.1.1 The PROSCREEN II ModelPROSCREEN II, the least-cost generation expansion planning model currently usedby EGAT, has been adopted for use in this study.28 This model is widely used byutilities throughout the world. Specifically, three modules within the model are used:(i) the Load Forecast Adjustment (LFA) module, (ii) the Generation and Fuels (GAF)module, and (iii) the PROVIEW module. These modules:
organize the necessary load data (annual/seasonal energy and peak load andload shape) which define capacity requirements to maintain a specified levelof system reliability;
27 Sensitivity analysis evaluated alternative start-dates, and concluded that Oct-09 (i.e., the beginning ofFY2010) is the least-cost.
28 Indeed, without the full support of EGAT generation planners, this study would not have beenpossible.
Methodology for the Study 3 4
assemble the necessary data on unit operating characteristics, fuel costs, saleand purchase arrangements for evaluation of alternative generationresource plans, and calculate the production cost and reliability associatedwith these plans; and
determine the least-cost plan for meeting system demand under aprescribed set of constraints by simulating the operation of the utility todetermine the cost and reliability effects of alternative system resourceadditions.
EGAT conducts its least-cost generation expansion planning at current, financial prices,i.e., including annual inflation, and not adjusting market prices to economic prices byexcluding transfer payments (taxes, duties, and subsidies). This policy is consistentwith a gradual industry-wide trend away from traditional economic analysis as utilitiesmove toward privatization and away from government subsidies and preferentialtreatment. As noted in Chapter 1, however, this study is a regional evaluation ofexpansion options using real resource costs, and therefore cost assumptions divergefrom values currently assumed for EGAT planning.29
For the interested reader, a more complete explanation of how PROSCREEN works ispresented in Appendix A5.
4.1.2 How PROSCREEN is Applied in this StudyTo summarize, we have adopted the following assumptions for PROSCREEN least-cost expansion planning runs in the current study:
All plants defined as “committed” (Table 11) are “fixed” in the plan atnegotiated cost/timing. These units are considered as part of the system;they are not “selected” as least cost by the model.
Non-thermal resources are dispatched without regard to cost:
Hydro capacity, according to an exogenously determined level ofmonthly dependable generation;
Lao imports from Theun Hinboun and Huay Ho plants;
SPP contracts (and commitments), assuming a capacity factor of 80percent.
29 The World Bank has outlined detailed requirements in the TOR (see Appendix A1) regardingmodeling approach, and specified a large number of input assumptions. Further, the Bank recognizesthe unique perspective of a study based on real regional resource costs, and acknowledges that themethods and values used in this study for its purposes are completely without prejudice to differentones that EGAT may consider as more appropriate for its own operating context and requirements.
Methodology for the Study 3 5
With the exception of EGAT’s own hydro capacity, each of these resourcesis modeled as a separate transaction, defined from contractual purchaseprice and operating constraints.
NT2 is treated as two transactions ("PE" and "SE1"; see Section 3.5) withan October 2009 starting date (FY2010) when it is included in the analysis.
Thermal resources, including both EGAT’s existing thermal capacity andavailable IPP capacity, are economically dispatched based on cost. IPPs arenot required to run, but in general are dispatched, since they are relativelylow-cost gas-fired units.30
Implicit in this modeling approach is the reasonable assumption that the Laoalternative to NT2 for meeting that portion of its demand would be importof thermal-fired electricity from Thailand.
4.2 Cost-Risk Analysis Modeling Framework
As specified in the TOR, the study outcome is to be determined by means of theresults profile shown in Table 16 (the “Cost-Risk Framework”). This profile providesfor calculating the probability-weighted present value (PV) costs of eitherimplementing or not implementing NT2 for commercial operation in FY2010, giventhe interplay of several major uncertain factors – project cost, long-term demand forelectricity, and long-term economic value of natural gas as well as the suggestedprobabilities of occurrence for Base Case, Low and High estimates of these variables.The difference between the probability-weighted PV cost of implementing the projectin FY2010 versus not implementing it at all is the decision criteria for this analysis. Alower net present value (NPV) “with NT2” indicates that the project is an acceptableeconomic investment for the regional power market.
The specific steps undertaken to complete the cost-risk analysis are summarized in thefollowing paragraphs:
30 Thermal capacity at Krabi is dispatched without regard to cost, as transmission constraintsnecessitate its use for reliability in the South.
Methodology for the Study 3 6
Table 16. The Cost-Risk Framework
Determine Base Case, Low, and High real economic values for the three keyuncertainties – (i) project cost, (ii) growth rate of electricity demand, and(iii) the economic value of natural gas – expected to have the mostsignificant potential impact on the economic decision to develop NT2.
Define a probability of occurrence for each state (Base Case, Low, andHigh) of each variable. In fact, these probabilities are specified in theproject TOR, and shown in Table 16. It should be noted that theprobabilities were selected based on judgment – backed by World Bankstudies from other projects – about relationship between extent ofvariance and its probability of occurrence, as well as the presumption thatthe base case should have a higher probability of occurrence while High
A. Present Values WITH NT2:
Case Probability Case Probability Case Probability Case Present Value Probabilityh 0.25 h 0.25 h 0.25 hhh <Scenario PV> 0.01563 h 0.25 h 0.25 m 0.50 hhm <Scenario PV> 0.03125 h 0.25 h 0.25 l 0.25 hhl <Scenario PV> 0.01563 h 0.25 m 0.50 h 0.25 hmh <Scenario PV> 0.03125 h 0.25 m 0.50 m 0.50 hmm <Scenario PV> 0.06250 h 0.25 m 0.50 l 0.25 hml <Scenario PV> 0.03125 h 0.25 l 0.25 h 0.25 hlh <Scenario PV> 0.01563 h 0.25 l 0.25 m 0.50 hlm <Scenario PV> 0.03125 h 0.25 l 0.25 l 0.25 hll <Scenario PV> 0.01563 m 0.50 h 0.25 h 0.25 mhh <Scenario PV> 0.03125 m 0.50 h 0.25 m 0.50 mhm <Scenario PV> 0.06250 m 0.50 h 0.25 l 0.25 mhl <Scenario PV> 0.03125 m 0.50 m 0.50 h 0.25 mmh <Scenario PV> 0.06250 m 0.50 m 0.50 m 0.50 mmm <Scenario PV> 0.12500 m 0.50 m 0.50 l 0.25 mml <Scenario PV> 0.06250 m 0.50 l 0.25 h 0.25 mlh <Scenario PV> 0.03125 m 0.50 l 0.25 m 0.50 mlm <Scenario PV> 0.06250 m 0.50 l 0.25 l 0.25 mll <Scenario PV> 0.03125 l 0.25 h 0.25 h 0.25 lhh <Scenario PV> 0.01563 l 0.25 h 0.25 m 0.50 lhm <Scenario PV> 0.03125 l 0.25 h 0.25 l 0.25 lhl <Scenario PV> 0.01563 l 0.25 m 0.50 h 0.25 lmh <Scenario PV> 0.03125 l 0.25 m 0.50 m 0.50 lmm <Scenario PV> 0.06250 l 0.25 m 0.50 l 0.25 lml <Scenario PV> 0.03125 l 0.25 l 0.25 h 0.25 llh <Scenario PV> 0.01563 l 0.25 l 0.25 m 0.50 llm <Scenario PV> 0.03125 l 0.25 l 0.25 l 0.25 lll <Scenario PV> 0.01563
A. Probability-weighted Present Value WITH NT2 #VALUE! 1.00000
B. Present Values WITHOUT NT2:
Case Probability Case Probability Case Present Value Probabilityh 0.25 h 0.25 hh <Scenario PV> 0.06250 h 0.25 m 0.50 hm <Scenario PV> 0.12500 h 0.25 l 0.25 hl <Scenario PV> 0.06250 m 0.50 h 0.25 mh <Scenario PV> 0.12500 m 0.50 m 0.50 mm <Scenario PV> 0.25000 m 0.50 l 0.25 ml <Scenario PV> 0.12500 l 0.25 h 0.25 lh <Scenario PV> 0.06250 l 0.25 m 0.50 lm <Scenario PV> 0.12500 l 0.25 l 0.25 ll <Scenario PV> 0.06250
B. Probability-weighted Present Value WITHOUT NT2 #VALUE! 1.00000
Probability-weighted PV Savings (Cost) WITH NT2 #VALUE! (Result A minus Result B; 2003 USD million)
SCENARIO RESULTS (2003 USD million)
SCENARIO RESULTS (2003 USD million)POWER DEMAND GAS PRICE
CONSTRUCTION COST POWER DEMAND GAS PRICE
Methodology for the Study 3 7
and Low values should have high-enough probabilities so that they have ameasurable impact final cost-risk analysis results.
Run the PROSCREEN expansion planning model under Economic BaseCase assumptions with NT2 as a candidate competing for a place in the least-cost expansion plan from its earliest expected commercial operation date ofFY2010. This initial analysis added NT2 to the system in October 2009,i.e., it specified that the least-cost expansion plan included NT2commencing operation in October 2009. This date was therefore fixed forall subsequent "with NT2" model runs to conform to the logic of thedecision matrix (the decision being whether to develop NT2 for commercialoperation in October 2009 or not to do so).31
Run the PROSCREEN expansion planning model with NT2 commencingcommercial operation in October 2009 (FY2010) for all combinations of theabove-defined uncertainties. The PROSCREEN “objective function” (i.e.,basis for comparison of results) is the present value of future investmentand operating costs over the Study Period.
Re-run each of the defined scenarios without NT2 so that demand must beserved from alternative resources.
Calculate the probability-weighted present value of costs for the “withNT2” and “without NT2” scenario groups.
Subtract the probability-weighted result “with NT2” from the result“without NT2” to determine the Study outcome.
To complete the Cost-Risk Framework, a total of 18 scenario runs are required, 9with NT2 and 9 without NT2. These scenarios are formed from combinations of twoplanning variables – power demand and natural gas price. Three cases– Base, Low, andHigh – are used for each of these variables. The 9 scenarios run with NT2 areexpanded to 27 scenarios in the economic assessment by combining manually thethree cases for the construction cost of NT2 with the results of the other scenarios.
For each scenario, the combined probability is simply the product of the probabilitiesof each of its components. For example, the probability of the “with NT2” Base Caseor “mmm” scenario (i.e., “medium” values for each possible outcome) is equal to 0.125(0.50 x 0.50 x 0.50), and the probability of the “without NT2” Base Case ("mm"scenario) is 0.25 (0.50 x 0.50). Similarly, the probability of the “with NT2” scenarioassuming all “high” outcomes (“hhh”) is 0.015625 (0.25 x 0.25 x 0.25). When allscenarios are considered, of course, the probabilities for the "with NT2" and "withoutNT2" scenario groups each sum to 1.00.
Chapters 5 explains the specific Base Case, Low, and High values adopted for eachvariable in the economic cost-risk analysis.
31 The sensitivity of results to a delay in commercial operation date was also evaluated, as reported inChapter 5.
Methodology for the Study 3 8
Economic Evaluation 3 9
5 ECONOMIC EVALUATION
The objective of this chapter is to evaluate whether NT2 is a part of the least-costgeneration expansion plan for meeting future regional electricity needs when it isevaluated using the real economic cost of the resources required. The cost-riskanalytical framework outlined in Chapter 4 is applied to give a comprehensive,probabilistic answer to this question which systematically incorporates the range ofuncertainties – construction costs, load growth, fuel prices – assumed in this study toface the regional electricity sector in the coming years.
Section 5.1 summarizes the basic assumptions adopted for system expansion planning.Section 5.2 presents Base Case results. Section 5.3 reports the results of the cost-riskanalysis. Section 5.4 discusses the sensitivity of results to changes in specific variables.
5.1 Economic Planning Assumptions
5.1.1 Basic Economic AssumptionsThe World Bank has specified the following economic basis for the real resourceanalysis of NT2:
All costs exclude internal fiscal transfers (e.g. taxes, duties, and subsidies)
All values are expressed in constant US dollars of 2003
The discount rate is 10% real
The MUV index (a UN index of the unit value of manufactured exportsfrom G-5 industrial countries to developing country markets, expressed inUS dollars) is used as the price deflator to restate future year prices in real2003 US dollars; the MUV index averages 1.2 percent per annum through2015, and a constant rate of 1.5 percent is assumed thereafter. Thaiinflation is assumed to be a constant 2.25 percent, the rate currentlyadopted by EGAT.
An exchange rate of 42 Thai Baht per US dollar was used for planning purposes. Thestandard assumption of purchasing power parity (PPP) is adopted to estimate theexchange rate in future years based on the above-noted differential inflationassumptions.
Economic Evaluation 4 0
5.1.2 System CharacteristicsIn general, system characteristics adopted for the current analysis follow EGAT’sPower Development Plan for 2003 (PDP2003) as published in April 2003.Characteristics common to the Economic runs of PROSCREEEN, as detailed inChapter 4, are summarized below:
The Base Case load forecast is Thailand’s official Base Case of August 2002(see Chapter 3), augmented by a Lao PDR domestic load of 75 MW and300 GWh.
The reliability criterion is a reserve margin of 15 percent.
The existing system corresponds to the summary in Table 10.
All “committed plants” as identified in Table 11 are presumed to commencecommercial operation according to schedule.
The schedule for plant retirements follows the assumptions detailed in Table12.
NT2 (995 MW) is added to the system in October 2009 (FY2010) in the“with NT2” scenarios.32
All other plants – including plants proposed for reconditioning and allgeneric expansion options (see Table 13) – are modeled as candidateswhich much compete for a place in the least cost economic plan. (Notethat candidates for “reconditioning” – South Bangkok thermal (units 3-5)and Bang Pakong (unit 1) – are only permitted to enter the expansion planin the year following scheduled retirement.)
Generation of existing plants and selected candidates is dispatched byPROSCREEN according to the following rules:
All non-thermal generation – notably domestic hydro plants and Laoimports – is dispatched first, without regard to cost. With theexception of EGAT’s own hydro capacity, each of these resources ismodeled as a separate transaction, defined from contractualpurchase price and operating constraints.
NT2 energy is dispatched in two parts according to the monthlyvariation reported previously in Chapter 3, one to provide peak-period energy and a second to provide off-peak energy. Optionaloff-peak generation is not assumed.
32 Project-associated transmission works in Laos are included in the project cost. Project-associatedincremental transmission costs for Thailand do not presume any other future hydro exports fromLaos to Thailand, due to the uncertainty of these exports.
Economic Evaluation 4 1
All thermal generation – the majority of the entire system – is subjectto economic dispatch, and run only when it is lowest cost.Exceptions are small power producers (SPPs), which are assumed torun at an 80 percent capacity factor.33
. The following section discusses the NT2 cost assumptions for the economic projectassessment.
5.1.3 NT2 Planning Assumptions for the Economic AnalysisAs already noted, the Base Case economic analysis has been run in two modes – “withNT2” included in the expansion plan for commercial operation from October 2009(FY2010), and “without NT2” in the plan.34
Base Case economic investment and operating costs of the NT2 project are based onreal cash flow data derived from the project sponsor’s financial model, excludingtransfers and sunk costs, but including incremental sponsor development costs thatreflect use of real resources.35
The total capital cost of NT2 will be US$729 million, equivalent to a present value ofUS$499 million at 2003 prices. Associated transmission (including lines andsubstations, but excluding sunk costs) has a capital cost of US$135 million, equivalentto a present value of US$82 million. Table 17 summarizes the investment coststreams.
Low and High estimates of construction costs for NT2 and associated transmissionhave been specified in the TOR to be ±30% of the expected construction cost usedfor the Base Case. These costs are reported at the bottom of Table 17.
Operating costs for NT2 have likewise been derived from the project sponsor’sfinancial model. The real annual cost of O&M is estimated as US$16.28 million peryear.
Based on preliminary analysis, it is presumed that NT2 would replace gas-firedcombined cycle generation. The World Bank has requested that an environmentalbenefit – a “carbon credit” of $3 per tonne Carbon of gas substitution – should begiven to NT2 for its contribution to global greenhouse gas reduction. This valuereflects recent global carbon trading experience. The resulting annual credit of
33 This is a reasonable assumption given the high percentage of this output which is fossil fueled(predominantly by gas).
34 As discussed in Section 4.2 above, the starting date was fixed based on a PROSCREEN run in whichNT2, treated as a candidate, was added to the least cost plan in October 2009. FY2010 (Oct-09) isconsidered to be the earliest possible commercial operation date (COD); Section 5.3 reports thesensitivity of results to delayed starting dates.
35 For a commercial evaluation at market prices, negotiated PPA payments per kWh purchased wouldbe taken as the project cost rather than actual developer cash flows, since NT2 generation is beingpurchased at that agreed price.
Economic Evaluation 4 2
US$1.91 million is included in the analysis as a decrease in the annual O&M cost ofNT2.
Table 17. Capital Costs of NT2 (constant US$2003, 10% discount rate)
The TOR requests that the Consultant determine whether there is any “systematicbias” in the estimated construction costs for NT2 (i.e., whether the Base Caseestimated project cost reported here can be assumed to be the expected projectcost). There is evidence that the Base Case project cost estimate is not systematicallybiased either positively or negatively:
As with planning for any large hydropower project, NT2 developer planninghas included comprehensive activity scheduling to assure efficient projectdevelopment at least cost. Moreover, NT2 project developers have reliedon fixed-price bidding for key civil and electro-mechanical contracts. Facedwith fixed prices, contract bidders necessarily undertake an evaluation ofthe risks they are undertaking. Further, these fixed-price contracts includeboth physical and price contingencies, further protecting the developeragainst a wide range of unforeseen cost overruns.
NT2 project developers have also employed sophisticated risk models totrace the linkages from randomly selected project activity delays, and theircumulative impact on the critical path to final project completion. In otherwords, complex models have been utilized to ascertain if randomly selecteddelays might cause subsequent delays that could not be mitigated so as toachieve targeted project deadlines. The Base Case project cost estimateincludes a quantified estimate of the risk premium associated with suchunanticipated delays. Thus, there is a risk “insurance” against unexpectedcost overruns already incorporated into the Base Case cost estimatesreported in Table 17.
TotalFiscal Cost PV of Cost Cost PV of Cost PV of CostYear USD million USD million USD million USD million USD million20032004 - 1.4 1.2 2005 196.5 154.8 6.3 5.0 2006 137.9 98.8 6.1 4.4 2007 236.1 153.7 28.8 18.8 2008 118.5 70.2 69.2 41.0 2009 39.9 21.5 15.6 8.4 2010 - - 7.4 3.6
Base Case 728.9 499.0 135.0 82.4 581.4
High Case 947.6 648.7 175.5 107.1 755.8 - increase 218.7 149.7 40.5 24.7 174.4 Low Case 510.2 349.3 94.5 57.7 407.0 - decrease 218.7 149.7 40.5 24.7 174.4
NT2 Associated Transmission
Economic Evaluation 4 3
5.2 Base Case Results
Table 18 summarizes the results of the Base Case scenario “with NT2” included inthe expansion plan from FY2010. (A detailed summary of these results is presented inAppendix A6.)
A total of 17,673 MW are added to the system during the planning period. NT2, ofcourse, accounts for 995 MW of new capacity. A further 6,798 MW representcapacity that is already committed (i.e., not competing for a place in the plan). All ofthe candidates selected to meet future load are gas-fired. Recommended additionsinclude 10,500 MW of combined cycle capacity and 690 MW of gas turbine capacity.Reconditioned thermal plants account for a further 1,480 MW.
The lower panel of Table 18 shows the present value (PV) of this expansion program.The PV of total cost over the planning horizon is US$26,200 million. AfterPROSCREEN calculates the end-effects of this expansion program in order to avoidany biases which might result from a short planning horizon, the estimated total PV ofcosts over the Study Period is US$43,681 million.
Table 19 presents results of an expansion planning model run identical to the onespecified for Table 18 except that NT2 is not included. The table shows therecommended expansion plan in the absence of the 995 MW from NT2. This caserequires a total of 12,600 MW of combined cycle plant over the Planning Period, withless gas turbine plant and less reconditioning – a net increase of 940 MW.
The middle panel of Table 19 compares the PV of total costs required for each of theBase Case generation expansion plans, both “with” and “without” NT2. Assumingthat all assumptions adopted for the Base Case analysis prove correct, the estimatedPV of total costs over the Study Period is US$43,681 million when NT2 is included inthe plan, and US$43,958 million when NT2 is excluded.
The graph at the bottom of Table 19 charts the annual cumulative benefits associatedwith the decision to proceed with NT2. Each point on the “without NT2” linerepresents the annual accumulated difference in costs over the “with NT2” case. (Apositive difference indicates a real resource savings associated with developing NT2,while negative numbers would indicate a real resource cost.) The chart suggests thatthe decision to purchase NT2 power will produce a significant savings over the studyhorizon. The accumulated present value of savings to the region over the entireStudy Period totals US$277 million at 2003 prices.36
A total present value of savings of US$277 million may seem small in relation to thetotal long term investment requirements. These savings should be put in perspective.They are equivalent to 48% of the total capital investment in NT2, and represent asavings to the region of US$0.012 per kWh of NT2 sales to EGAT.
36 The US$ 277 million represents a ‘savings” since the least-cost plan without NT2 would come atgreater total cost.
Economic Evaluation 4 4
Table 18. Base Case “with NT2”
5.3 Cost-Risk Analysis
The Base Case tells us that NT2 should be included in the region’s least costgeneration expansion plan assuming that the assumptions adopted for decision-making are correct. The objective of cost-risk analysis is to determine whether thesame decision is justified given the high probability that future events will diverge fromthe Base Case assumptions.
As specified in the TOR, the study outcome is determined by means of the resultsprofile shown in Table 16 (the “Cost-Risk Framework”). This profile provides forcalculating the probability-weighted present value (PV) costs of either implementingor not implementing NT2 for commercial operation in FY2010, given the interplay ofseveral major uncertain factors – project cost, long-term demand for electricity, andlong-term economic value of natural gas as well as the suggested probabilities ofoccurrence for Base Case, Lower and Higher estimates of these variables. Thedifference between the probability weighted PV cost of implementing the project inFY2010 versus not implementing it at all is the decision criteria for this analysis. Alower net present value (NPV) “with NT2” would indicate that the project is anacceptable economic investment for the regional power market.
Notes: CC - gas-fired combined cycle, GT - gas turbine.
PRESENT VALUE OF COSTS(US$ million) With NT2 Without NT2 A. Planning Period (2003-2014) 26,200 26,304 B. End-Effects Period 17,481 17,654 C. Study Period (A + B) 43,681 43,958
PV of Savings with NT2 A. Planning Period (2003-2014) 104 B. End-Effects Period 173 C. Study Period (A + B) 277 % of total cost 0.63%
Planned Additions (excluding NT2)Committed Plant
Savings (Cost) Due to Selecting Nam Theun 2Difference in Accumulated Present Value (US$ million)
-40
0
40
80
120
160
200
240
280
2010 2015 2020 2025 2030 2035
US
$ m
illi
on
with NT2 without NT2
Economic Evaluation 4 6
The key decision variables for this study are defined in the study TOR (see AppendixA1). They are:
Capital cost of NT2. The World Bank has specified a cost range of +30percent (High capital cost) and –30 percent (Low capital cost); thesevalues are reported in Table 17.
Regional demand forecast. The World Bank has specified a very wide range inorder to reflect accumulated international experience with load forecastaccuracy over time; the regional High and Low demand forecasts aresummarized in Table 10.
Natural gas price forecast.37 The World Bank has developed its own fuel priceprojections, with particular emphasis on the price of natural gas since it isthe most competitive alternative fuel. The Base Case projections arepresented in Table 15; High and Low scenarios are reported in AppendixA3.
For each of these three key variables, the TOR specifies base case, low case and highcase assumptions, as well as the probabilities of occurrence associated with each. Basecase assumption values are assigned a 50 percent probability of occurrence, while theLow and High case assumption values are assigned probabilities of 25 percent each.
Based on these assumptions, a total of 27 possible scenarios are required to representall probable outcomes “with NT2”, and 9 possible scenarios to represent all possibleoutcomes “without NT2”.
The results of the cost-risk analysis are summarized in Table 20. They confirm thattaking all evaluated potential outcomes into account, a system expansion planfeaturing the commissioning of NT2 in October 2009 is the correct decision from aneconomic least-cost perspective. The probability-weighted PV of total savings overthe entire Study Period is estimated to be US$269 million, equivalent to US$0.012 perkWh sold from the NT2 project.
37 Since natural gas is the primary fuel alternative to NT2, this report uses the terms "natural gasprice forecast" and "fuel price forecast" interchangeably; readers should be reminded that either termrefers to the complete sets of fossil fuel forecasts (Base Case, High, and Low) presented in AppendixA3.
Economic Evaluation 4 7
Table 20. Economic Cost Risk Analysis Results
A review of the cost-risk matrix indicates that NT2 capital cost is the variable havingthe greatest impact on results. High capital costs decrease the savings by US$174million when other variables are held constant (i.e., from US$277 to US$103 million),while Low capital costs increase savings by US$175 million.
High and low demand have an uneven impact; high demand increases savings by onlyUS$22 million, but low demand reduces savings by US$80 million. Results areasymmetrical around the Base Case despite the symmetry of input assumptions;investment decisions are made by PROSCREEN at specific trigger-points that aresomewhat differently timed between low and high cases, making outcomes lesssymmetrical than the inputs would suggest. Further, since NT2 is fully utilized in theBase Case, there is limited opportunity for increased benefits due to an increase insystem load. NT2 cannot be accelerated in response to higher demand, but othercapacity can be delayed in response to low demand under the “without NT2”
A. Present Values WITH NT2:Savings by
Case Probability Case Probability Case Probability Case Present Value Probability Scenarioh 0.25 h 0.25 h 0.25 hhh 61,720 0.01563 193 h 0.25 h 0.25 m 0.50 hhm 55,621 0.03125 125 h 0.25 h 0.25 l 0.25 hhl 51,490 0.01563 63 h 0.25 m 0.50 h 0.25 hmh 48,568 0.03125 177 h 0.25 m 0.50 m 0.50 hmm 43,855 0.06250 103 h 0.25 m 0.50 l 0.25 hml 40,684 0.03125 52 h 0.25 l 0.25 h 0.25 hlh 36,631 0.01563 139 h 0.25 l 0.25 m 0.50 hlm 33,184 0.03125 23 h 0.25 l 0.25 l 0.25 hll 30,821 0.01563 (63) m 0.50 h 0.25 h 0.25 mhh 61,546 0.03125 367 m 0.50 h 0.25 m 0.50 mhm 55,447 0.06250 299 m 0.50 h 0.25 l 0.25 mhl 51,316 0.03125 237 m 0.50 m 0.50 h 0.25 mmh 48,385 0.06250 360 m 0.50 m 0.50 m 0.50 mmm 43,681 0.12500 277 m 0.50 m 0.50 l 0.25 mml 40,510 0.06250 226 m 0.50 l 0.25 h 0.25 mlh 36,457 0.03125 313 m 0.50 l 0.25 m 0.50 mlm 33,010 0.06250 197 m 0.50 l 0.25 l 0.25 mll 30,647 0.03125 111 l 0.25 h 0.25 h 0.25 lhh 61,371 0.01563 542 l 0.25 h 0.25 m 0.50 lhm 55,272 0.03125 474 l 0.25 h 0.25 l 0.25 lhl 51,141 0.01563 412 l 0.25 m 0.50 h 0.25 lmh 48,210 0.03125 535 l 0.25 m 0.50 m 0.50 lmm 43,506 0.06250 452 l 0.25 m 0.50 l 0.25 lml 40,335 0.03125 401 l 0.25 l 0.25 h 0.25 llh 36,282 0.01563 488 l 0.25 l 0.25 m 0.50 llm 32,835 0.03125 372 l 0.25 l 0.25 l 0.25 lll 30,472 0.01563 286
A. Probability-weighted Present Value WITH NT2 44,337 1.00000
B. Present Values WITHOUT NT2:
Case Probability Case Probability Case Present Value Probabilityh 0.25 h 0.25 hh 61,913 0.06250 h 0.25 m 0.50 hm 55,746 0.12500 h 0.25 l 0.25 hl 51,553 0.06250 m 0.50 h 0.25 mh 48,745 0.12500 m 0.50 m 0.50 mm 43,958 0.25000 m 0.50 l 0.25 ml 40,736 0.12500 l 0.25 h 0.25 lh 36,770 0.06250 l 0.25 m 0.50 lm 33,207 0.12500 l 0.25 l 0.25 ll 30,758 0.06250
B. Probability-weighted Present Value WITHOUT NT2 44,606 1.00000
Probability-weighted PV Savings (Cost) WITH NT2 269 (Result A minus Result B; 2003 USD million)
POWER DEMAND GAS PRICE
CONSTRUCTION COST POWER DEMAND GAS PRICE SCENARIO RESULTS (2003 USD million)
SCENARIO RESULTS (2003 USD million)
Economic Evaluation 4 8
scenarios. A High natural gas price increases savings by US$83 million, while a Lowprice reduces savings by US$51 million. In this regard, it should be noted that naturalgas price projections are not perfectly symmetrical around the Base Case (seeAppendix A3), resulting in somewhat greater savings under high gas price scenarios.
In fact, there is only one combination, the most adverse future possible from theperspective of NT2 (high capital costs, low demand, and low gas prices), thatproduces and unfavorable result, and this by a very small margin with an extremelylow probability of occurrence.
5.4 Sensitivity Analysis
The results of the cost-risk analysis can be better understood by studying thesensitivity of the Base Case to changes in modeling assumptions and the values ofindividual variables. This section reports on the following specific cases:
Sensitivity to changes in the date of commercial operation
Sensitivity to changes in the forecasts of key variables
Sensitivity to changes in the probability distribution adopted for the cost-risk analysis.
5.4.1 Delay in Commercial OperationThe Base Case economic analysis “with NT2” presumes an October 2009 startingdate; we have separately established that this COD minimizes total system cost. Asalready noted, this is both the earliest feasible starting date and the date ofcommercial operation selected by PROSCREEN under Base Case assumptions (seeSection 4.2).
However, the project PPA, which was signed in November 2003, faced manyunanticipated delays, so it is certainly possible that the estimated October 2009 CODwill not be achieved. We tested the impact of a two-year delay (i.e., an October 2011COD) on the net savings (cost) due to implementing the NT2 project. This case iscompared with the Base Case in Table 21.
The delay of NT2 necessitates an early investment in thermal capacity of 1170 MWto meet system reliability requirements; 1400 MW of additional combined cyclecapacity is required in FY2010, coupled with delay of 230 MW of gas turbinecapacity. Although the total capacity mix is identical to the Base Case as soon asNT2 is commissioned in FY2012, this early investment, and associated higher fuelcosts, increases the total Study Period cost of the "with NT2" scenario.
As shown in the table, a two-year delay would reduce the net real resource savings toabout US$146 million, a net benefit reduction of about US$130 million.
Economic Evaluation 4 9
Table 21. Sensitivity of Base Case to Delay of Commercial Operation
5.4.2 Changes in the Forecasts of Key Variables
Changes in the Demand Forecast
The spread between the high and low demand forecasts adopted for this study isdramatic: By FY2012, the Low Case is only 75 percent of the Base Case, while theHigh Case is 125 percent. Not surprisingly, system expansion requirements areextremely different as a result. Table 22 compares the expansion plans requiredunder the two load forecasts.
The table suggests that savings "with NT2" would be modestly increased with higher-than-expected demand (US$299 million vs. US$277 in the Base Case). (Note thesubstantial requirement for gas turbine investment in order to meet FY2006 loadgrowth.)
Savings under a low demand forecast are significantly reduced (US$198 million). Thisresult follows from the fact that new gas-fired generation is not required in the“without NT2” case until FY2013.
Changes in the Price of Natural Gas and Other Fuels
Differences between high and low fuel price forecasts adopted for the study are notas dramatic as the spread noted for the demand forecast. (The prices adopted forthese sensitivity scenarios are reported in Appendix A3.) When scenarios are runwith either high or low fuel prices, gas remains the fuel of choice for incrementalcapacity both “with NT2” and "without NT2".
As might be expected, the low gas price scenario resulting in lower total Study Periodsavings (US$226 million) than the high gas price scenario (US$361 million). Morethermal plant reconditioning is justified under the low fuel price scenario; higher gasprices make relatively less efficient reconditioned units uneconomic in comparison withmore efficient new capacity.
Table 23 compares the Base Case results with the expected savings from NT2assuming higher and lower fuel prices.
PRESENT VALUE OF COSTS Without NT2(US$ million) Oct-09 Oct-11 A. Planning Period (2003-2014) 26,200 26,272 26,304 B. End-Effects Period 17,481 17,540 17,654 C. Study Period (A + B) 43,681 43,812 43,958
PV of Savings with NT2 A. Planning Period (2003-2014) 104 32 B. End-Effects Period 173 114 C. Study Period (A + B) 277 146 % of total cost 0.63% 0.33%
With NT2
Economic Evaluation 5 0
Table 22. Sensitivity of Results to the Load Forecast
Notes: CC - gas-fired combined cycle, GT - gas turbine.
PRESENT VALUE OF COSTS(US$ million) With NT2 Without NT2 With NT2 Without NT2 A. Planning Period (2003-2014) 21,596 21,637 31,120 31,227 B. End-Effects Period 11,413 11,570 24,326 24,519 C. Study Period (A + B) 33,010 33,208 55,447 55,746
PV of Savings with NT2 A. Planning Period (2003-2014) 41 107 B. End-Effects Period 157 193 C. Study Period (A + B) 198 300 % of total cost 0.60% 0.54%
Notes: CC - gas-fired combined cycle, GT - gas turbine.
PRESENT VALUE OF COSTS(US$ million) With NT2 Without NT2 With NT2 Without NT2 A. Planning Period (2003-2014) 24,441 24,531 28,714 28,854 B. End-Effects Period 16,069 16,205 19,671 19,892 C. Study Period (A + B) 40,510 40,736 48,385 48,746
PV of Savings with NT2 A. Planning Period (2003-2014) 90 140 B. End-Effects Period 136 221 C. Study Period (A + B) 226 361 % of total cost 0.56% 0.75%
Savings (Cost) Due to Selecting Nam Theun 2Difference in Accumulated Present Value (US$ million)
-40
0
40
80
120
160
200
240
280
320
360
2010 2015 2020 2025 2030 2035
US
$ m
illi
on
with NT2 Economic Base Case Low Gas Price High Gas Price
Economic Evaluation 5 2
Changes in NT2 Capital Cost
Sensitivity analyses reflecting changes in the load forecast and in fuel prices requirecompletely new runs of the PROSCREEN model for both the “with NT2” and“without NT2” cases, since modifying these parameters will impact the entire systemexpansion plan.
Changes in the capital cost of NT2, however, only affect the cost of a single plant, soreliable estimates of the resulting impact on the least-cost system expansion plan canbe prepared by simply adjusting the present value cost of the Base Case “with NT2”by the present value of the change in NT2 capital cost implied by the High and Lowcapital cost scenarios. (The required adjustments are summarized in Table 17.)
Table 24 compares the Base Case results with the expected savings from NT2assuming higher and lower capital costs for NT2. Not surprisingly, the decrease(increase) in savings produced by a 30 percent increase (decrease) in cost is dramatic.Even under the high capital cost assumption, however, NT2 produces a real netbenefit to the regional economy (US$103 million).
Table 24. Sensitivity to Changes in NT2 Capital Cost
Changes in Cost-Risk Probabilities
The selection of appropriate probabilities of occurrence for the assumed Base, Low,and High parameter values in the cost-risk analysis requires a combination ofexperience, judgment and – when available – historical evidence,38 and uncertaintyremains about the values adopted.
38 See, for example, Bacon, Robert W., John E. Besant-Jones, and Jamshid Heidarian, EstimatingConstruction Costs and Schedules: Experience with power generation projects in developing countries. WorldBank Technical Paper No. 325. Energy Series, 1996. Besant-Jones has expanded on this work in aninternal Bank document, "Assigning Probabilities to Scenarios for Risk Analysis – The Case ofHydropower Project Construction Costs".
PRESENT VALUE OF COSTS Without NT2(US$ million) BASE CASE LOW HIGH A. Planning Period (2003-2014) 26,200 26,200 26,200 26,304 B. End-Effects Period 17,481 17,307 17,656 17,654 C. Study Period (A + B) 43,681 43,507 43,856 43,958
PV of Savings with NT2 A. Planning Period (2003-2014) 104 104 104 B. End-Effects Period 173 347 (1) C. Study Period (A + B) 277 452 103 % of total cost 0.63% 1.04% 0.23%
Note: NT2 capital cost adjustments for the high and low cases has been allocated entirelyto the End-Effects Period; PROSCREEN would allocate these adjustments to thePlanning Period as well.
With NT2
Economic Evaluation 5 3
To address this uncertainty, we have re-calculated the cost-risk matrix to determinean estimated “switching value”39 at which the net savings from NT2 would disappear(i.e., the net present value would be zero). In other words, we have determined howpessimistic our cost-risk probability assumptions would need to be in order toeliminate the Base Case savings reported in Table 19. Specifically,
We first assumed a very minimal "positive" probability that future eventswould prove advantageous to NT2 (i.e., would increase savings "withNT2"). Specifically, we assumed a notional 5 percent probability of (i)construction cost at the low cost estimate, (ii) demand at the high loadforecast, and (iii) natural gas price at the high fuel price forecast.
We then calculated the “negative” probability (i.e., the probability thatfuture events would be adverse to NT2) at which the net present value ofsavings from investment in NT2 would be zero. “Negative” is defined ashigh construction costs, low demand, and low natural gas price; all of theseassumption values reduce the advantages of NT2 in relation to alternativesources of generation. (Of course, the “medium” probability is the residual,i.e., 1.0 minus the positive and negative probabilities.)
We hasten to add that we are not as pessimistic about the future as this scenarioimplies: NT2 construction costs already incorporate premiums for risk; natural gasprices were already at historic lows when fuel prices were defined for this study; andthe current consensus among economists regarding medium-term growth of the Thaieconomy is very optimistic. Nevertheless, the scenario does serve to illustrate thedegree of pessimism required to make NT2 a marginal investment.
Table 25 shows the results of the switching value analysis. With positive assumptionvalues limited to a 5 percent probability, negative assumption values would berequired in seven of every eight scenarios (87 percent probability), and base caseassumption values reduced to an 8 percent probability, in order to eliminate theexpected savings from NT2.
While there is no such thing as certainty in the field of economic forecasting, theanalysis indicates that – from the perspective of real resource costs – the net benefitsaccruing from the inclusion of NT2 in the least-cost plan appear to be relativelyrobust.
39 The “switching value” is usually defined as the percentage change in a variable which would causethe project outcome to change. For our purposes, we have not calculated percentage changes in theprobabilities adopted for the cost-risk matrix.
Economic Evaluation 5 4
Table 25. Economic Cost-Risk Sensitivity Test
A. Present Values WITH NT2:Savings by
Case Probability Case Probability Case Probability Case Present Value Probability Scenarioh 0.87 h 0.05 h 0.05 hhh 61,720 0.00218 193 h 0.87 h 0.05 m 0.08 hhm 55,621 0.00348 125 h 0.87 h 0.05 l 0.87 hhl 51,490 0.03785 63 h 0.87 m 0.08 h 0.05 hmh 48,568 0.00348 177 h 0.87 m 0.08 m 0.08 hmm 43,855 0.00555 103 h 0.87 m 0.08 l 0.87 hml 40,684 0.06048 52 h 0.87 l 0.87 h 0.05 hlh 36,631 0.03785 139 h 0.87 l 0.87 m 0.08 hlm 33,184 0.06048 23 h 0.87 l 0.87 l 0.87 hll 30,821 0.65876 (63) m 0.08 h 0.05 h 0.05 mhh 61,546 0.00020 367 m 0.08 h 0.05 m 0.08 mhm 55,447 0.00032 299 m 0.08 h 0.05 l 0.87 mhl 51,316 0.00348 237 m 0.08 m 0.08 h 0.05 mmh 48,385 0.00032 360 m 0.08 m 0.08 m 0.08 mmm 43,681 0.00051 277 m 0.08 m 0.08 l 0.87 mml 40,510 0.00555 226 m 0.08 l 0.87 h 0.05 mlh 36,457 0.00348 313 m 0.08 l 0.87 m 0.08 mlm 33,010 0.00555 197 m 0.08 l 0.87 l 0.87 mll 30,647 0.06048 111 l 0.05 h 0.05 h 0.05 lhh 61,371 0.00013 542 l 0.05 h 0.05 m 0.08 lhm 55,272 0.00020 474 l 0.05 h 0.05 l 0.87 lhl 51,141 0.00218 412 l 0.05 m 0.08 h 0.05 lmh 48,210 0.00020 535 l 0.05 m 0.08 m 0.08 lmm 43,506 0.00032 452 l 0.05 m 0.08 l 0.87 lml 40,335 0.00348 401 l 0.05 l 0.87 h 0.05 llh 36,282 0.00218 488 l 0.05 l 0.87 m 0.08 llm 32,835 0.00348 372 l 0.05 l 0.87 l 0.87 lll 30,472 0.03785 286
A. Probability-weighted Present Value WITH NT2 33,122 1.00000
B. Present Values WITHOUT NT2:
Case Probability Case Probability Case Present Value Probabilityh 0.05 h 0.05 hh 61,913 0.00250 h 0.05 m 0.08 hm 55,746 0.00399 h 0.05 l 0.87 hl 51,553 0.04351 m 0.08 h 0.05 mh 48,745 0.00399 m 0.08 m 0.08 mm 43,958 0.00638 m 0.08 l 0.87 ml 40,736 0.06951 l 0.87 h 0.05 lh 36,770 0.04351 l 0.87 m 0.08 lm 33,207 0.06951 l 0.87 l 0.87 ll 30,758 0.75709
B. Probability-weighted Present Value WITHOUT NT2 33,122 1.00000
Probability-weighted PV Savings (Cost) WITH NT2 0 (Result A minus Result B; 2003 USD million)
SCENARIO RESULTS (2003 USD million)
SCENARIO RESULTS (2003 USD million)POWER DEMAND GAS PRICE
CONSTRUCTION COST POWER DEMAND GAS PRICE
Conc lu s ion 5 5
6 CONCLUSION
Our economic assessment of the project concludes that the decision to purchaseNT2 power offers significant savings to the regional power system. Based on thecomprehensive probability-weighted real resource cost-risk analysis, a real savings (i.e.,in present value terms at 2003 prices) on the order of US$269 million will accrue tothe region over the lifetime of the plant, equivalent to approximately US$0.012 perkWh sold from the NT2 project.
As summarized in Chapters 5, there are many potential circumstances in which thedecision to develop NT2 could provide far greater real resource cost savings to theregional economy. Most notable among these is a scenario of higher-than-expectedgas prices and/or higher than expected demand growth. The decision to “lock-in” ina major source of capacity at fixed price is robust to a wide range of behavior for thekey uncertain factors that influence the project’s long-term value-added. In particular,the individual scenarios show that the project is very robust with respect to fossil fuelprice volatility, a feature of energy markets in recent decades that is expected topersist.
Terms of Reference 5 7
A1 Terms of Reference
Terms of Reference for Determining the Economic Least-Cost Justification forthe Nam Theun 2 Regional Hydro-electric Power Project
[A] Context
The World Bank has received the Thailand Power Scenario Study (TPSS)40 andacknowledges its valuable contribution to understanding the commercial rationale ofthe Nam Theun 2 (NT2) Project in the context of the Thai power system. Elementsfrom the TPSS are adopted as indicated in this terms of reference (ToR), whichdescribes the next stage of the economic due diligence the Bank requires41 todetermine whether the project has a satisfactory economic cost-risk profile for theregional42 power market. The main distinguishing characteristics of this second stageanalysis are threefold: (i) to the greatest extent feasible, all values reflect real economicresource costs, (ii) the scope of work includes both the Thai and Laotian electricitymarkets, and (iii) the risk analysis consists of an integrated multi-event probabilisticframework that produces one overall quantitative result showing whetherimplementing the NT2 project for 2009 would be an acceptable economic investmentfor the power sector.
To meet the Bank’s project preparation schedule, timeliness is of the essence. Tofacilitate this objective, the tasks in this ToR that are identified in Section [G] are tobe completed, reviewed and delivered to the Bank latest June 5, 2003. The remainingtasks are due by August 1, 2003.
The Bank acknowledges that the full participation of the Electricity GeneratingAuthority of Thailand (EGAT) is important to the conduct of this study. The Bankexpects the Consultant to work with EGAT much in the manner done for the TPSS.Because the multiple scenario analysis required to implement this ToR may need asubstantial commitment of EGAT’s human and computer resources over a relativelyshort period of time, the Bank is prepared to help the Consultant and EGATaccommodate operational constraints in this respect.
[B] Study Outcome
The study outcome will be determined by means of the results profile shown in Annex1: “Cost-Risk Framework”. This profile provides for calculating the probability- 40 “Thailand Power Scenario Study”, by Robert Vernstrom, consulting economist, Bangkok, March2003. The World Bank financed and supervised this study.
41 World Bank guidelines for the economic evaluation of investment operations, including electricpower projects: OP 10.04 and GP 4.45.
42 “Regional” means Laos and Thailand in this Terms of Reference.
Terms of Reference 5 8
weighted present value (PV) costs of either implementing or not implementing NT2for 2009, given the interplay of several major uncertain factors – project cost, long-term demand for electricity and long-term economic value of natural gas as well as thesuggested probabilities of occurrence for Base Case, Lower and Higher estimates ofthese variables. The difference between the probability weighted PV cost ofimplementing the project in 2009 versus that of not implementing it is the decisioncriteria for this analysis by showing whether the project is an acceptable economicinvestment for the regional power market.
The following sections describe the Bank’s requirements for this stage of its economicdue diligence. Because the Bank is specifying these requirements for the purpose of areal resource cost-based analysis, neither the Consultant nor EGAT would be heldaccountable for specific assumptions and values that the Bank requires or to whichthe Bank agrees. The Bank acknowledges that the methods and values used in thisstudy for its purposes are completely without prejudice to different ones that EGATmay consider as more appropriate for its own operating context and requirements.
[C] Basic Parameters
1. All values will be expressed in terms of real US dollars of 2003.2. The discount rate will be 10% real.3. The power system reliability criterion for generation capacity expansion is
EGAT’s standard of 15% reserve margin over forecast peak load.4. All costs will exclude internal fiscal transfers (e.g. taxes and subsidies).5. NT2 is commissioned in 2009 in the “with project” case, or not at all in the
“without project’ case.6. The expected values of NT2 production for primary energy and secondary
energy are as stated in the TPSS. The study will check whether it is reliable toassume that the probability of under-achieving these values is negligible, andshall document evidence to support this assumption.
7. The scenarios with NT2 should include a carbon credit of $x per ton ofcarbon displaced by NT2 to be credited against the operating costs of NT2.The Bank will confirm the acceptable unit value per ton carbon.
8. The system expansion period will end in the year that the NT2 projectoutput would be fully absorbed under the low demand forecast. The durationof the run-out period for end effects will be till the year at which the residualvalue in that year would discount to an insignificant present value. The Bankwill discuss with the consultant how the power system model neutralizes endeffects before the model runs are undertaken.
9. The EGAT plant retirement schedule is adopted, subject to reportingrequirements described in Section [F].
[D] Variables
[D.1] Demand Forecast:
1. The Base Case Demand Forecast used in the Thailand Power Scenario Studyis acceptable for the Thai load. For Laotian demand, the Bank recommends a
Terms of Reference 5 9
Base Case in which Laos fully absorbs 200GWh of energy in the year theproject is commissioned.
2. For both countries the Low Case demand forecast will be keyed off the BaseCase forecast using the following equation, reflecting the percentage gapbetween these forecasts the Bank considers appropriate by year 10 into theforecast period (based on forecasting experience in Thailand and elsewhere):
(1+grL)^10 = 0.75*(1+grB)^10
where grL means Low Case growth rate of demand and grB means Base Casegrowth rate of demand.
3. The High Case load forecast will be symmetrical to that of the Low Case. Thegrowth rate for the High Case (“grH”) will therefore be determined accordingto the following formula:
(1+grH)^10 = 1.25*(1+grB)^10
[D.2] NT2 Project
1. The Bank will provide the real cash flows for the Base Case economicinvestment and operating costs of the NT2 project based on data from theproject sponsor’s financial model. This cash flow series will exclude transfersand sunk costs, but include incremental sponsor development costs thatreflect use of real resources.
2. The High Case for the construction cost of NT2 will be 30% above of theexpected construction cost used for the Base Case. The Low Case for theconstruction cost of NT2 will be 30% below that of the Base Case.
[D.3] Other Power Generation Technologies
1. The screening curve analysis of the type used in the TPSS will be deployedusing real economic costs to determine the least-cost alternative options,using the same technologies as in the TPSS. It is expected that as in the TPSS,natural gas will emerge as the primary alternative to NT2. In case it does not,several aspects of this ToR related to fuel value and fuel value risk will need tobe revised accordingly.
2. The real economic costs of alternative generation capacity will also includeprivate sector incremental development costs appropriate to thosetechnologies.
3. The Bank recommends that there be a spread of about USD200/kW toappropriately reflect the EPC cost difference between GT and CCGT plant.
4. The Bank will confirm with the consultant the actual EPC costs anddevelopment cost margins to be used for GT and CCGT capacity.
5. The Consultant will assume that Laos’ alternative to NT2 for meeting thatportion of its demand would be import of electricity from Thailand.
[D.4] Oil Products and Natural Gas
Terms of Reference 6 0
1. The Bank will confirm with the consultant the real values it considersacceptable for oil product prices in the screening curve analysis, as well as theBase, Low and High natural gas price trajectories.
2. The coal prices in the TPSS may be adopted, unless it seems appropriate tomake some adjustment in relation to the assumptions for natural gas and oilproduct prices to be used in this study.
[D.5] Transmission
1. The project-associated transmission works in Laos are included in the projectcost.
2. The project-associated incremental transmission costs for Thailand need to bedetermined in co-operation with EGAT on a basis that does not include anyother future hydro exports from Laos to Thailand, because of theiruncertainty, notwithstanding the higher level of potential exports containedin the MoU between the two countries on power exports from Laos toThailand.
3. If EGAT and the consultant believe that the non-NT2 options also requireincremental generation-associated transmission works, the economic costs ofthese should be determined and included.
[E] Modeling
1. The Consultant will use EGAT’s Proscreen Model as in the TPSS, subject tothe custom parameter and variable assumptions made for this study.
2. Before the modeling begins, Bank staff will obtain from EGAT and theconsultant, by verbal and documentary communication, a clear understandingof how this model works, especially but not limited to the following factors: (i)optimization and simulation characteristics, (ii) treatment of mixed hydro-thermal capacity (valuation of stored water, optimization of hydro-electricreservoir management), (iii) dispatching optimization (stacking merit order anddispatching algorithm), and (iv) calculation of end effects.
3. In these model runs, NT2 and all other generation capacity on the regionalpower system – including existing capacity owned and operated by IPPs - willbe subject to economic dispatch for meeting incremental demand and thespecified amount of Laotian demand, without consideration of contractualtake-or-pay constraints.
4. Before proceeding with paragraph E5 below, two sensitivity tests are required:(i) for the MMM case (ref. Annex 1) a “with” and “without” NT2 comparisonin a situation where the commissioning of NT2 is delayed for 24 months, theinvestment cash flow being extended over the additional time period, and (ii)the same test but with a 30% cost over-run of NT2 (the HMM case of Annex1). The results of these tests should be reported to the Bank beforecommencing the model runs described below, to determine whether it wouldbe appropriate to amend the cost-risk analysis framework (Annex 1).
5. To complete the Cost-Risk Framework (Annex 1), a total of 18 scenario runswill be required, 9 with NT2 and 9 without NT2 as described in the Annex.The scenarios are formed from combinations of two planning variables –
Terms of Reference 6 1
power demand and natural gas price. Three cases– high, base, low – are usedfor each of these variables.
6. The 9 scenarios run with NT2 will be expanded to 27 scenarios by combiningmanually the three cases for the construction cost of NT2 with the results ofthese scenarios.
7. The probabilities associated with the High, Medium and Low assumptions arestated in Annex 1.
8. A second set of model runs for these scenarios will be carried out underwhich the economic values are converted to commercial values, but expressedin real US dollars of 2003, using the same framework as in Annex 1, in orderto assess the commercial sustainability of the NT2 Power Purchase Agreementagainst the underlying economic trends in the regional power market.
[F] Reporting
This study will serve a number of purposes eventually involving a considerable range ofaudiences within and outside of the World Bank. For this reason, it is essential thatthe reporting of this work be thorough and self-standing, so that the assumptions,methods and corresponding results are detailed, transparent and easilyunderstandable.
Without limitation to the generality of this requirement, the Bank stresses theimportance of comprehensive documentation, in Annexes as appropriate, for certainkey aspects:
1. The economic characteristics of the NT2 project.2. The Base Case demand forecast (forecasting methods, key input assumptions,
benchmark data and main results per consumer category);3. Justification for NT2 hydrological performance assumption;4. Explanation for assuming in respect of NT2 that there is no systemic bias in
the estimated construction cost for NT2, namely that no difference should beassumed between Base Case estimated and Base Case expected project cost;
5. The valuation of oil products and natural gas;6. The status of the individual power plants included in the EGAT retirement
schedule adopted for this study;7. Model characteristics and modeling implementation;8. Description of the logic underlying the cost-risk decision framework;9. Explanation of results, and enhanced explanation of any counter-intuitive
results;10. Explanation of differences in values and results between the economic and
commercial model runs; and11. For the commercial runs, how the PPA revenues are composed and converted
to US dollar terms.12. For data output, the Bank requires the present values of each of the major
components contributing to the total PV cost of each scenario, in order tofacilitate a clear understanding of the reasons for differences in total PV costbetween scenarios. The Bank also requires production and value data for thedispatch of each plant at five year intervals in the MMM case, to better
Terms of Reference 6 2
understand how the model handles the merit order, and the contribution inenergy and cost of each operating facility.
[G] Timing of Deliverables
Items required for June 5th, 2003:
The results of the model runs; this includes all the aforementioned factors necessaryfor operating the model and to be agreed with the Bank.
Value Probability Value Probability Value Probability Value Probability
h 0.25 h 0.25 h 0.25 hhh 0.01563h 0.25 h 0.25 m 0.50 hhm 0.03125h 0.25 h 0.25 l 0.25 hhl 0.01563h 0.25 m 0.50 h 0.25 hmh 0.03125h 0.25 m 0.50 m 0.50 hmm 0.06250h 0.25 m 0.50 l 0.25 hml 0.03125h 0.25 l 0.25 h 0.25 hlh 0.01563h 0.25 l 0.25 m 0.50 hlm 0.03125h 0.25 l 0.25 l 0.25 hll 0.01563m 0.50 h 0.25 h 0.25 mhh 0.03125m 0.50 h 0.25 m 0.50 mhl 0.06250m 0.50 h 0.25 l 0.25 mhi 0.03125m 0.50 m 0.50 h 0.25 mmh 0.06250m 0.50 m 0.50 m 0.50 mmm 0.12500m 0.50 m 0.50 l 0.25 mml 0.06250m 0.50 l 0.25 h 0.25 mlh 0.03125m 0.50 l 0.25 m 0.50 mlm 0.06250m 0.50 l 0.25 l 0.25 mll 0.03125l 0.25 h 0.25 h 0.25 lhh 0.01563l 0.25 h 0.25 m 0.50 lhm 0.03125l 0.25 h 0.25 l 0.25 lhl 0.01563l 0.25 m 0.50 h 0.25 lmh 0.03125l 0.25 m 0.50 m 0.50 lmm 0.06250l 0.25 m 0.50 l 0.25 lml 0.03125l 0.25 l 0.25 h 0.25 llh 0.01563l 0.25 l 0.25 m 0.50 llm 0.03125l 0.25 l 0.25 l 0.25 lll 0.01563
WGTD PV 1.00000[B] Present Values Without NT2
Value Probability Value Probability Value Probability
h 0.25 h 0.25 hhh 0.06250h 0.25 m 0.50 hhm 0.12500h 0.25 l 0.25 hhl 0.06250m 0.50 h 0.25 hmh 0.12500m 0.50 m 0.50 hmm 0.25000m 0.50 l 0.25 hml 0.12500l 0.25 h 0.25 hlh 0.06250l 0.25 m 0.50 hlm 0.12500l 0.25 l 0.25 hll 0.06250
WGTD PV 1.00000
0.00000Net PV with NT2
Power Demand Gas Price Scenario
Cost-Risk Analysis Matrix[A] Present Values with NT2
Construction Cost Power Demand Gas Price Scenario
Thailand Demand Forecast 6 5
A2 Thailand Demand Forecast
This appendix provides details of Thailand’s official Aug-02 load forecast. Thisforecast, supplemented by Lao PDR domestic load to be served by NT2 (75 MWcapacity and 300 GWh generation), is the Base Case load forecast for our regionalstudy.
This appendix includes the following tables:
Table A2-1. EGAT Total Generation Requirement Forecast
Table A2-2. EGAT Total Sales Forecast
Table A2-3. MEA Purchases and Sales Forecast by Customer Class
Table A2-4. PEA Purchases and Sales Forecast by Customer Class
Thailand Demand Forecast 6 6
Table A2-1. EGAT Total Generation Requirement Forecast
Table A3-1. Economic Fuel Prices Adopted for the Study (constant US$2003)
Following the table is an excerpt from Appendix 7 of the Economics Annex of WorldBank's draft Project Appraisal Document for the NT2 Project, which outlines themethodology employed to develop the natural gas price projections adopted for thecurrent study.
An important component of the economic due diligence on the NT2 project is todetermine whether NT2 is cost-effective for the Thai power system, as the project’sprimary purpose and underlying bankability relates to the Thai power market. Thiscost-effectiveness is assessed by evaluating whether the project is least-cost for theduty-service envisaged. One of the most important determining factors is the value ofnatural gas that would be used in combined cycle gas turbines, as these are the mostlikely economic alternative to NT2.
The long-term supply and demand outlook for natural gas, and its opportunity costwhether as an export or import commodity are key factors determining theappropriate principles for calculating its economic value. The industry has grownconsiderably and the long-term supply: demand picture has evolved over the pastseveral decades. As well, because of the commercial interests at stake between buyersand sellers, competition for the market between sellers, the real uncertainty aboutfuture demand and supply conditions and the complexity of the contractingarrangements, this is an industry that doles out information very cautiously. Theinsights leading to the valuations presented in this note rely for the most part onverbally communicated confidential information from players active in the industry,some power sector documentation and some relevant oil price projections providedby the World Bank. While this is not the optimal basis for the purpose at hand, it wassufficient for developing reasonable valuations.
This note develops the value series in the following steps:
1. Principles of commodity valuation;2. Evidence of long term supply and demand for natural gas in Thailand;3. Comments on the market structure;4. Implications of (2) and (3) for the approach to valuation;5. Insights about economic value from contracting principles (GPAs) in Thailand;6. Calculations and projections (Base, low and high gas value cases).
Natural gas may be valued at its economic resource costs of finding, developing,producing (EDP) and transporting the commodity (supply cost basis), or at itsopportunity value as an export commodity or import requirement (border pricebasis). It may also be appropriate to include a depletion premium (also called a “usercost”). This reflects the possibility that an increased current use of the resourceaccelerates the time path to depletion, at which point a “backstop” price would bepaid for the commodity that replaces it.
The supply cost basis is appropriate where the potential supply of natural gas is verylarge relative to the market, with little likelihood over an economically meaningful timeperiod that foregone economic export potential or heavy domestic use would triggerborder prices as the key determinant of economic value. Save for these circumstances,border prices, or a combination of supply cost and depletion premium based on
Fuel Price Assumptions 7 4
expected border prices should be the valuation basis. Which to use is informed by thedata.Economic supply costs are the real costs incurred over time of finding, developing,producing and transporting the commodity, net of taxes and royalties. Border pricesare projected real f.o.b. netbacks to the wellhead in respect of forgone exports, or c.i.f.import values in respect of imported gas, net of taxes and royalties. The user cost is aprice signal that tells consumers the present value consequences of an increase in theiruse of an exhaustible resource. It compensates the resource owner who may choosewhether to leave the resource in the ground for future appreciation or produce itsooner. The calculation of a user cost requires knowing the time path to depletion,the shape of the marginal cost curves with and without the incremental consumptionover that time and the likely cost of the backstop at depletion time. The moreuncertain the basis of the supply, demand and cost projections, the lower theexpected backstop value, the further off the expected depletion time and the flatterthe marginal cost curves, the less the attention that should be focused on user costs.All of these factors indicate that user costs should not be computed for Thailand.
On the whole, the industry is optimistic about both the resource base and demandgrowth. Evidence of this optimism is these companies’ continued commitment ofresources to exploration and development as needed, the creation of long term jointarrangements between countries sharing resources in the Gulf of Thailand43, and aone billion dollar pipeline from the Gulf to the mainland (target of January 2006).Existing transportation capacity is nearing saturation. The new line will almost doubleexisting transportation capacity. This capacity should be fully utilized by 2015, basedon projected demand growth of about 6% per year.
The R/P ratio is now about 20. This is higher than the industry typically considersideal, and is partly the result of conservatively regulated reservoir depletion rates, aswell as strenuous effort to expand the industry over the past two decades. Given thiscomfortable supply position, the market will pace reserves additions; however therewill be a rush between companies to reserve capacity in the new pipeline. This meansdeveloping new GPAs over the next few years and proving-up the necessary reservesas required.
The industry views demand as driving new contracts. Producers use demand forecastsfrom PTT and EGAT to do their E&P planning. Hence supply will evolve to meetgrowing demand.
Several sources say that supply costs have declined dramatically over the past twentyyears with major advances in exploration and drilling technology. The latter isespecially important for the Gulf of Thailand, which is geologically fractured. Theysuggest that future E&P costs should decrease very gradually in well-known areas, butcosts could increase due to more difficult production conditions and higher CO2
content of the gas in certain other off shore areas. It is not clear whether to believethat aggregate supply costs in the future will remain about the same, increase
43 These include the Myanmar Thailand joint area and the Thai Kampuchea overlap – there is adispute about resource sharing between the latter.
Fuel Price Assumptions 7 5
moderately or decrease moderately. The supply from Myanmar is about 50% costlierthan that from Thailand, and has a 30% share in the market. This share varies fromperiod to period, its value being uncertain over the long term.
Regarding demand, the power sector absorbs about 80% of consumption and theindustrial sector the other 20%. This split is likely to be sustained. Assuming thatpower sector and industrial demand continue to grow at 6% per year over the longterm, gas supply from known areas should be adequate for at least the next severaldecades.
The basic market structure is one of monopoly buyer and competition betweensellers. The four majors are UNOCAL, TotalElfFina, PTT (now privatized) and Mitsui.There are several other companies with a smaller presence in the E&P business. Stiffdownward pressure on prices is exercised by a vigilant public, vigilant government andthe monopoly buyer (PTT) having a window on the producing industry through itsown E&P subsidiary. Several industry players assert that the producers do not cohere,they are not coordinated, and they are vying with each other for market share.
The predominant transaction form is long-term contracts covering the life of aconcession, with regulated depletion rates (1 in 6000) to prevent reserves lossthrough accelerated depletion. Each concession has its own particular cost structureand gas quality; hence the detailed contract terms vary from contract to contract.However, there is a general pricing structure common to most contracts.
The following factors distilled from the foregoing discussion seem most pertinent tothe choice of valuation approach:
i. there is apparent comfort in respect of long-term supply from domestic reservesand the MTJDA, with no issue of export opportunity cost;
ii. a minority share of gas comes from Myanmar, it being expected that this sharewill vary moderately over time; the time period to depletion – if it ever happens– is far off for backstop values to have much weight in present value terms;
iii. there are competitive pressures characterizing the contracting process, suchthat the terms of the contracts can be said to reflect a market-based valuationof the cost recovery and remuneration levels needed to keep the producers inoperation;
iv. in general, there is uncertainty about the size of future reserves additions andtheir incremental costs, the predominant view in the industry being optimistic onsupply and rather unclear about whether marginal cost will increase moderatelyor decrease moderately.
Under these conditions, it seems most appropriate to base the economic value ofnatural gas on:
i. the cost of discovery, development and production for local supply as evidencedin current pool pricing;
ii. border price for the Myanmar supply, iii. removal of taxes and royalties from domestic production, iv. addition of the PTT marketing margin and
Fuel Price Assumptions 7 6
v. estimated LRMC of gas transmission on a postage stamp basis (there being noinformation available allowing the computation of point to point marginal costtransmission pricing).
Because each GPA differs and we do not have access to the individual contracts, itwas necessary to create a “typical contract” the key elements of which industryinterviewees claimed to be representative of the average.
The basic pricing structure, valid for the duration of the contract, is as follows. In thecontracts, the current gas price payable to producers is specified in THB. It is theresult of applying a series of indices (contained in one formula) to a base price.
The indexation formula applied to the Base Price reflects changes in: (i) the fob priceof 3.5%S HFO Singapore, (ii) a petroleum industry machinery inflation index reflectingUSD inflation, (iii) the Thai CPI reflecting Thai domestic inflation, (iv) an exchangerate adjuster and (v) a constant. Given that our numeraire in this project analysis isUSD, the machinery index, the Thai CPI index and the exchange rate adjuster wouldbe offsetting in future price projections using the PPP method of exchange rateprojection. When working in USD prices rather than THB prices, the only necessaryelement of the index is the HFO adjuster, having a weight of about 30% in the index.PTT charges EGAT and IPPs a marketing margin of 1.75% of the sales price, plus apostage-stamp pipeline toll.
The pen-ultimate step for moving from commercial value to economic value is toremove transfers from the commercial price, these being royalties and taxes. Theroyalty rate for new reserves is 12.5% of the producers’ selling price. The actualamount of income tax producers pay in total or per mmbtu of gas sold cannot beknown without access to company accounts, and we have no such access. Anapproximation of the income tax load is made by taking the difference between theprojected producer selling price net of royalties from the foregoing steps, deducting anadvised producer EDP cost, the residual being gross profit, of which 50% is deductedin taxes. These deductions of income taxes and royalties are made only for the Thaiportion of gas supply, because Myanmar is beyond the welfare boundary of theanalysis. At the welfare boundary Thailand faces a border price, and any embeddedtaxes and royalties going to the Government of Myanmar are included in economiccosts facing Thailand, therefore not deducted.
The final calculation is to convert the nominal economic natural gas values into realvalues by deflating the nominal series with the MUV index. This is the index theWorld Bank uses for converting hydrocarbon prices between real and nominal values.
Low and High Value Projections: The gas value projections for the low andhigh cases consist of two changes to the base case presented above:
Firstly, the values of HFO to be used in the price adjustment index are recalculatedusing high and low price projections for the World Bank Crude Mix. These latter
Fuel Price Assumptions 7 7
projections were prepared per World Bank methodology44 as done when it publishedthese ranges in the past. The current projection is asymmetrical, reflecting anassessment that oil prices are unlikely to be sustained over the long term at pricesbelow USD 12.00/bbl or above USD 33.00/bbl (current) within a 70% range ofpossible outcomes.
Secondly, the Myanmar share is decreased or increased moderately in the low andhigh price projections respectively, according to the range of conceivable Myanmarshare mentioned by industry participants.
Thus, the low price trajectory reflects the combined impact of a lower valuedinternational hydrocarbon market along with a more plentiful outlook for Thai supplyat no increase in marginal cost, hence less involvement of costlier Myanmar bordervalues, while the high trajectory reflects the reverse. We believe that the range socreated accounts for the two key uncertainties going forward: (i) the future value ofworld oil, and (ii) the degree of future Thai exposure to (costlier) imported naturalgas.
On the whole, the low price is about 12% below, and the high price about 16% abovethe base price (USD 2.27/mmbtu base, versus USD 2.00 low and USD 2.64 high).
The range appears moderately skewed on the high side. One reason for this lays in thecrude oil price projections. For example, in 2011, low case crude oil is 40% cheaperthan in the Base Case, while high case crude is 50% more expensive (minus 8 dollarsversus plus 10 dollars on a 20 dollar base). The second reason is the change ofMyanmar share between the high and low cases. This change differently impacts thecomposite tax and royalty deductions removed from the Base price. For example, thehigher the Myanmar share, the less the weight of taxes and royalties to be deductedfrom the composite pre-tax gas price, leaving the net economic price higher than itwould have been had the Myanmar share not been increased. Put otherwise, moreexposure to international border prices reduces the weight of domestic transfers tobe removed from the composite commercial value in getting to economic value. Thereverse applies too.
The valuation methodology described above was back-casted to 2002 excludingadjustments from commercial to economic value, and the result indicated an error of+2.5% for the back-casted value relative to the average actual paid-up value for theyear. Considering all the components in this calculation and possible differences inspecific months included as “2002” between sources, this error is insignificant.
In the final analysis, these gas price projections partly determine the value of NT2relative to that of using CCGT capacity in its place. One industry participant believesthat Thai natural gas contracts are priced about the lowest of contracts anywhere,for the kind of term and geological structures at play. When the base case levelizedeconomic gas value is combined with the other costs of the CCGT option, the result
44 These series are no longer official Bank series, as the Bank does not prepare them in the formalmanner it did when they were published.
Fuel Price Assumptions 7 8
is USD 0.028/kWh at 74% plant factor. This value sits well within the (rather low)range of CCGT economic supply prices assessed for other CCGT projects.
The year to year projected economic natural gas prices used in the cost risk analysisare as follows (USD of 2003 per mmbtu):
Bang Pakong Block 1-2 Gas 2x[(4x60.7)+(137.5)] 760.6Block 3-4 Gas 2x[(2x104)+(1x99)] 614.0
Nam Phong Block 1-2 Gas 2x[(2x121)+(1x113)] 710.0South Bangkok Block 1 Gas (2x110)+(1x115) 335.0
Block 2 Gas (2x202)+(1x220) 624.0Wang Noi Block 1-2 Gas 2x[(2x223)+(1x205)] 1,302.0
Block 3 Gas (2x236)+(1x257) 729.0Total 5,074.6
D. Gas Turbine Power PlantLan Krabu Gas (4x14)+(2x16)+(4x20) 168.0Nong Chok 1-2 Diesel 3x122 366.0Surat Thani Gas 2x122 244.0
Total 778.0E. Diesel
Mae Hong Son Diesel 1x6 6.0Total 6.0
F. Renewable Energy SourceTotal 0.534 0.5
G. Purchased PowerKhanom Thermal Oil/Gas 2x75 150.0Khanom CC Gas (4x112)+(1x226) 674.0Rayong CC Block 1-4 Gas 4x[(2x103)+(1x102)] 1,232.0Ratchaburi Thermal Gas 2x720 1,440.0Ratchaburi CC Block 1-3 Gas 3x[(2x230)+(1x265)] 2,175.0Tri Energy Gas (2x224)+(1x252) 700.0Independent Power Gas (2x230)+(1x240) 700.0Bo Win Power Gas (2x356.5) 713.0Eastern Power&Electric Gas 350 350.0SPP - 1837.2 1,837.2Theun Hinboun Hydro - 2x115 214.0Houay Ho Hydro - 2x75 126.0EGAT-TNB Tie Line - 300 300.0
Total 10,611.2Grand Total 25,647.0
Note: FY2003 installed capacity reported in the Study is based on mid-year estimates, and therefore varies slightly from the actual end-year data reported above; differences generally relate to SPP scheduling.
Detailed Plant Data (Existing System) 8 1
Table A4-2. Existing Hydro Power Plant Data
Power Plant Est. Life Commission
(years) Date Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Total
Grand Total 90 222 562 1,343 1,433 1,768 1,768 1,837 1,837 1,897 2,120
Note: The Study, based on mid-year estimates, assumes somewhat different SPP additions than the most recent assumptions reported above: 128.9 MW in FY2003, 60 MW in FY2004, 80 MW in FY2005, and none thereafter.
-Renewable energy
Small Producers Project
Detailed Plant Data (Existing System) 8 3
Table A4-4. Schedule of Planned Plant Retirements
Power Plant Rating Year(s) of Year of Planned Life(MW) Commissioning Retirement (Years)
Gas Turbine PlantLan Krabu 2x16+2x14 1969-70 Depending on gas availabilityLan Krabu 4x20 1981 Depending on gas availabilityNong Chok 3x122 1995 2016 21Surat 2x122 2001 2016 15
1/ Candidates for reconditioning. 2/ Retirement advanced due to planned availability of lower cost resources in South.
How PROSCREEN Works 8 5
A5 How PROSCREEN Works
PROSCREEN selects the least-cost plan by identifying the expansion scenario withthe lowest present value over a user-specified period (the “objective function”). Toachieve this objective requires a user manual over a foot thick and model inputspecification of several hundred pages. While it is beyond the scope of the currentstudy to explain these details, the following paragraphs attempt to describe themethodology in layman’s terms.
PROSCREEN divides the “Study Period” into two parts:
the “Planning Period”, defined for the current study as FY2003-14, inwhich decisions regarding system operation and expansion are analyzedannually and sub-annually (i.e., for user-defined seasons). The duration ofthe Planning Period has been selected based on preliminary model runsindicating (i) that NT2 is a least-cost addition to the Base Case expansionplan as of October 2009 (FY2010), and (ii) that NT2 would be fullyabsorbed into the regional power system by that date under the Lowdemand forecast (see Chapter 2).
The “End Effects Period” in which sophisticated programming techniquesanalyze differences between alternatives (e.g., due to different lives andoperating characteristics) beyond the Planning Period horizon. Withoutend effects analysis, results would be biased against commissioning capital-intensive units near the end of the planning period.
The objective function for our analysis is based on the Study Period, which representsthe sum of both the Planning Period and End-Effects Period results.
Production Costing and System Dispatch
The production costing procedure used by PROSCREEN has two stages. In the firststage, operation of hydro generation, transactions (i.e., IPP purchases), and economicoperation of pumped storage is simulated. The result of this first stage is the seasonalthermal load duration curve. In the second stage, the expected operation of thethermal units within the year is simulated based on a probabilistic technique. Theresults are production costs and the associated level of reliability.
Dispatch of non-thermal resources. Resources are dispatched to meet systemload (modeled as typical weekly load shapes) without regard to cost in thefollowing order:
Transactions (e.g. contract purchases) are dispatched eitheraccording to an hourly profile or designated shape (e.g., peak-
How PROSCREEN Works 8 6
shaving, valley-filling, etc.). Although many SPPs are thermal, they areall treated as must-run transactions.
Hydro generation is dispatched simply as monthly generation whichcontributes to meeting system load, peak-shaving where possible.Available monthly hydro generation is exogenously determined byEGAT. (While PROSCREEN permits more complex modeling ofhydro resources, these capabilities are not used by EGAT, sincehydro makes up a relatively small portion of the total system.)
Pumped Storage is dispatched when (and if) off-peak pumping foron-peak generation is economically justified.
Dispatch of thermal resources. Each in-service thermal unit is dispatchedaccording to standard probabilistic production costing procedures. Any“must-run” units are dispatched first, followed by enough other units ineconomic order45 to meet system load and resource requirements.
Evaluating Expansion Alternatives
PROSCREEN uses a mathematical approach called “dynamic programming” todetermine the combination of sequential, interrelated decisions which produce thedesired least-cost result. Specifically, for each year of the Planning Period, allcombinations of expansion alternatives are evaluated; each combination (known as a“state”) that meets user-defined goals (i.e., to provide required capacity and targetreserve margin) is defined as a feasible state. A feasible state includes:
Capital costs expressed as the economic carrying cost associated with eachcandidate in the state; and
Production costs derived from a complete probabilistic dispatch of the totalsystem including both existing and candidate units.
The present value of capital and production costs determines the accumulated cost ofeach feasible state.
For the next year, each of these “origin states” becomes a starting point forgenerating additional states which are feasible in the current year. Again, all possiblecombinations of the initial state and alternative resource additions are considered.Each feasible state for the year is defined by the required additions, the origin state,and the cumulative objective function value to date. This process continues throughthe Planning Period, with the objective function value for each year equal to theobjective function value for the “origin state” plus the present value of productionand capital cost from the current state.
After the last year of the Planning Period is analyzed, end-effects are considered toaccount for differences in operating characteristics, fuel costs, O&M costs, and the
45 As modified to reflect fuel contract and availability constraints.
How PROSCREEN Works 8 7
lives of the alternatives resources beyond the Planning Period. The End Effects Periodtotal costs are equal to the present value of capital costs plus production costs.Capital costs equal the economic carrying costs associated with each year of thespecified End Effects Period. (Since EGAT adopts the model option of an infinite EndEffects Period, this calculation is analogous to a perpetuity.) Production costs equalthe total system cost from a single-period simulation representing this same end-effects period; the dispatch is based on a constant load (the load from the last year ofthe Planning Period) and time-weighted inputs for fuel and operating costs.
Economic Base Case with NT2 – Detail 8 9
A6 Economic Base Case with NT2 – Detail
This appendix includes the following tables:
Table A6-1. Demand and Supply Balance
Table A6-2. System Costs by Plant Group
Table A6-3. Fuel Use by Type
Table A6-4. Fuel Type by Individual Plant
Economic Base Case with NT2 – Detail 9 0
Table A6-1. Demand and Supply Balance – Economic Base Case with NT2
TOTAL COSTTOTAL UTILITY COST 3,711,489 3,959,122 4,262,465 4,571,546 4,910,909 5,251,712 PRESENT VALUE OF COST 2,095,039 2,031,655 1,988,471 1,938,782 1,893,368 1,840,693 ACCUM. PRESENT VALUE 16,507,030 18,538,680 20,527,150 22,465,940 24,359,300 26,200,000
1/ See attached table of fuel usage by type. 2/ Capital costs for each addition discounted to the year of commissioning. 3/ Capital cost data exclude NT2 associated transmission; post-PROSCREEN manual adjustment by author.
Economic Base Case with NT2 – Detail 9 4
Table A6-3. Fuel Use by Type – Economic Base Case with NT2