NAESB OASIS Recommendation Network Service on OASIS (NITS on OASIS) EC Presentation 8/16/2011 Page 1 NITS on OASIS EC Presentation
Mar 27, 2015
NAESB OASIS Recommendation
Network Service on OASIS(NITS on OASIS)EC Presentation
8/16/2011 Page 1NITS on OASIS EC Presentation
Overview
OASIS was developed initially to facilitate submission of Point-to-Point requests and to document the approval process. In Order 890, FERC decided that transmission providers and network customers should use OASIS to request designation of new network resources and to terminate designation of network resources. NAESB was given the responsibility for designing new templates.
8/16/2011 2NITS on OASIS EC Presentation
Informal Comments
The Wholesale Electric Quadrant OASIS Subcommittee is preparing a recommendation for NITS on OASIS. The subcommittee requested informal comments from industry participants on a draft version of the new standards. The subcommittee is using the comments to modify and refine the draft standard before submitting it to the Executive Committee. – The informal comment period ended on July 29, 2011. – The OS reviewed concept-related comments on
August 2-4, 2011.
8/16/2011 3NITS on OASIS EC Presentation
NITS on OASIS Recommendation- Recommendation Summary + 5 Parts
WEQ NITS Draft Recommendationhttp://www.naesb.org/pdf4/weq_oasis071911w1.doc
Proposed Revisions to the OASIS Acronym and Glossary (WEQ000): http://www.naesb.org/pdf4/weq_oasis070111reqcom_a4.doc
Proposed Revisions to the OASIS (WEQ001):
http://www.naesb.org/pdf4/weq_oasis070111reqcom_a1.doc
Proposed Revisions to the OASIS S&CPs (WEQ002): http://www.naesb.org/pdf4/weq_oasis070111reqcom_a2.doc
Proposed Revisions to the WEQ OASIS Data Dictionary (WEQ003): http://www.naesb.org/pdf4/weq_oasis070111reqcom_a3.doc
Proposed Revisions to the WEQ Implementation Guide (WEQ013): http://www.naesb.org/pdf4/weq_oasis070111reqcom_a6.doc
8/16/2011 4NITS on OASIS EC Presentation
Key Order 890 Requirements
Order 890 provided substantial guidance on treatment of a Designated Network Resource (DNR):
• Qualifications for a DNR• Attestation of DNR to be submitted through OASIS
with each request to designate a new network resource
• Temporary and Permanent Termination of a DNR• Concomitant evaluation of a request for temporary
undesignation of a DNR and a related request for transmission service
8/16/2011 5NITS on OASIS EC Presentation
pro forma OATT (link)
• Part III governs Network Integration Transmission Service (NITS)
• Section 29.2 governs the application process– Application on OASIS– Customer identification and eligibility– Network Load information– Network Resource information & attestation– Identification of customer-owned transmission– Term of service and customer attestation
8/16/2011 6NITS on OASIS EC Presentation
pro forma OATT (continued)
• Section 30: Network Resources– Rules for designation of a new network resource
(Section 30.2)– Termination of Network Resources (Section 30.3)
• Indefinite Termination• Temporary Termination• Evaluation of Temporary Termination concomitantly
with related service requests
• Section 31: Designation of Network Load
8/16/2011 7NITS on OASIS EC Presentation
NAESB NITS Recommendation• Application for Network Service placed on OASIS• Transactions (loads, DNRs, non-designated
resources) handled on OASIS on a customer-by-customer basis
• Optional provision for tracking scheduling rights• Customer may assign agent(s) to administer
OASIS transactions• New process facilitate handling of concomitant
evaluation of a single undesignation coupled with a single request for service
8/16/2011 8NITS on OASIS EC Presentation
Technical Changes
• Pre-submittal work space will permit a customer to assemble information prior to official submittal (queuing) of request
• New templates – none of the existing templates are used for NITS (See WEQ-002)– Different structure for making request– CSV templates
8/16/2011 9NITS on OASIS EC Presentation
Data Structure for NITS
The general structure of the information conveyed in a given Input Template using the NITS CSV Format is shown below:
8/16/2011 10NITS on OASIS EC Presentation
Flow Diagrams: NITS Application Process(WEQ-013)
8/16/2011 11NITS on OASIS EC Presentation
8/16/2011 12NITS on OASIS EC Presentation
8/16/2011 13NITS on OASIS EC Presentation
Flow Diagrams: Designate a Network Resource(WEQ-013)
8/16/2011 14NITS on OASIS EC Presentation
START
AddDNR(01) Process Map Note: This process map does not illustrate all possible NITS DNR Addition scenarios.
NITS Process Map: AddDNR (01)Typical Scenarios ONLY, 06-27-2011 Revision 1
Questions/Comments/Errata: e-mail [email protected] or [email protected](This box shall be removed prior to publication in the S&CP booklet.)
Customer: “Is the DNR already a defined named NITS Resource under the NITS Application [WEQ 002-6.3.2.12]
1No
Yes
Customer:Defines
Resource
OASIS Template:NewNITSRequest9 AddNITSDNR 9 NITSResourceDescription NITSNITSResourceForecast (optional) NITSResourceDesignation NITSResourceCapacity NITSSchedulingRights AuxiliaryTransmission (optional)
OASIS Template:INPUT Template9 REQUEST Template 9 DATA Template(s)
Key to WEQ-002 Data Template elements used in this Process Map:
Templates use a nested hierarchy. As shown in Example A below, to use a DATA template, a specific INPUT and REQUEST template must also be referenced. Hence, the scenarios here show the first three levels of the hierarchy.
OASIS Template:NewNITSRequest9 NewNITSApplication 9 NITSService NITSCustomer NITSAgent
Example A:
Example B:
In Example B below, the INPUT template is NewNITSRequest, the REQUEST template is NewNITSApplication, and the DATA templates are NITSService, NITSCustomer, and NITSAgent.
NOTE: The AuxiliaryTransmission data template is used only for resources identified as OFF_SYSTEM
Customer:References previously
defined Resource
OASIS Template:NewNITSRequest9 AddNITSDNR 9 NITSResourceDescription NITSNITSResourceForecast (optional) Go to
AddDNR (02)
8/16/2011 15NITS on OASIS EC Presentation
From AddDNR
(02)
NITS Process Map: AddDNR (02)Typical Scenarios ONLY, 06-27-2011 Revision 1
Questions/Comments/Errata: e-mail [email protected] or [email protected](This box shall be removed prior to publication in the S&CP booklet.)
Customer: Does the AddDNR request require an update before TP assessment?
1Yes
No
AddDNR(02) Process Map Note: This process map does not illustrate all possible NITS DNR Addition scenarios.
OASIS Template:UpdateNITSRequest9 AddNITSDNR 9 NITSResourceDescription NITSNITSResourceForecast (optional) NITSResourceDesignation NITSResourceCapacity NITSSchedulingRights AuxiliaryTransmission (optional)
Customer:Updates DNR
Customer:Submits NITS
DNR request to Transmission
Provider
OASIS/ Transmission Provider: I s the DNR request Deficient?
2No
Yes
TP/ TSIP:Sets status of
NITS DNR request to RECEIVED
OASIS Template:UpdateNITSRequest9 AddNITSDNR ASSIGNMENT_REF (STATUS = QUEUED)
OASIS:Sets status of DNR request to COMPLETED
DNR request processed as described in Business Practice Standards, including the NITS Modification of ServiceState Diagram.
8/16/2011 16NITS on OASIS EC Presentation