N etLink II User Guide PCO Module. Main screen at start up. Name and access level The “Red Bar” Project Modules Project search options Search entry field Timeout countdown. Enter Project Number. Enter the project number on the main search. For project name and number will populate below. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: N etLink II User Guide  PCO Module

1

NetLink II User Guide PCO Module

Page 2: N etLink II User Guide  PCO Module

Click icon to add picture

1. Name and access level

2. The “Red Bar”

3. Project Modules

4. Project search options

5. Search entry field

6. Timeout countdown

MAIN SCREEN AT START UP

2

Page 3: N etLink II User Guide  PCO Module

Enter the project number on the main search. For project name and number wi l l populate below.

Locate the Potential Change Orders module on the left gray bar.

3

ENTER PROJECT NUMBER

Page 4: N etLink II User Guide  PCO Module

Potential Change Order information wi l l be entered in three tabs shown at the top of the screen:

1. AE Estimate

2. Contractor Estimate

3. Pending Change Order

4

PCO MODULE

Page 5: N etLink II User Guide  PCO Module

Here is an example of data entered on the AE Estimate tab.

This information is completed by the AE or CM.

5

PCO MODULE

Page 6: N etLink II User Guide  PCO Module

Here is an example of data entered on the Contractor Estimate tab.

This information is completed by the AE or CM.

6

PCO MODULE

Page 7: N etLink II User Guide  PCO Module

Here is an example of data entered on the Pending Change Order tab.

This information is completed by the Contracts Administrator.

7

PCO MODULE

Page 8: N etLink II User Guide  PCO Module

To enter a new PCO (and you have already cl icked on an exist ing record) you wi l l need to cl ick on the Clear Potential CO red button at the bottom of the screen. This wil l clear al l the previous Potential CO Information.

8

PCO MODULEAE ESTIMATE TAB

Page 9: N etLink II User Guide  PCO Module

AE or CM enters the PCO date and the PCO number.

Next cl ick on the PCO type drop down menu and select the appropriate type.

9

PCO MODULEAE ESTIMATE TAB

Page 10: N etLink II User Guide  PCO Module

Next cl ick on the PCO reason drop down menu and select the appropriate reason.

10

PCO MODULEAE ESTIMATE TAB

Page 11: N etLink II User Guide  PCO Module

Next cl ick on the Cost Basis drop down menu and select the cost basis.

11

PCO MODULEAE ESTIMATE TAB

Page 12: N etLink II User Guide  PCO Module

Next cl ick on the Budget Category drop down menu and select the appropriate budget category.

12

PCO MODULEAE ESTIMATE TAB

Page 13: N etLink II User Guide  PCO Module

Next enter the PCO est imate amount and the date the PCO was est imate .

I f i t i s ant ic ipated that the change wi l l rev ise the construct ion complete date the new date should be entered in the Revised Pr j Complet ion sect ion.

13

PCO MODULEAE ESTIMATE TAB

Page 14: N etLink II User Guide  PCO Module

Click icon to add picture

Now you wi l l need to scrol l down to the lower section of the page and complete the Keywords (wi l l show in the search results at the top of the screen), the Descript ion, and the Justification. Al l fields are required.

14

PCO MODULEAE ESTIMATE TAB

Page 15: N etLink II User Guide  PCO Module

After the keywords, description and just ification is entered cl ick on the Save as New Potential CO.

15

PCO MODULEAE ESTIMATE TAB

Page 16: N etLink II User Guide  PCO Module

I f any changes are needed on the PCO cl ick on any of the penci l icons and make the appropriate change. Once changed cl ick on the Update Potential CO button.

16

PCO MODULEAE ESTIMATE TAB

Page 17: N etLink II User Guide  PCO Module

Click icon to add picture

I f the PCO is a Change Directive (aka Field Work Order) you wil l be able to print the Change Directive (FWO) form here.

17

PCO MODULEAE ESTIMATE TAB

Page 18: N etLink II User Guide  PCO Module

Click icon to add picture

Move to the next tab to complete the Contractor Est imates . Once the Contractor has provided the AE wi th thei r pr ic ing the informat ion is entered here .

Not ice that the PCO No. h ighl ighted on the AE Est imate tab carr ies over to this tab in the PCO Detai l Informat ion sect ion.

18

PCO MODULECONTRACTOR ESTIMATES

Page 19: N etLink II User Guide  PCO Module

Cl ick on the Contract drop down menu and select the appropriate contract.

19

PCO MODULECONTRACTOR ESTIMATES

Page 20: N etLink II User Guide  PCO Module

Next entered the amount the contractor has quoted for the PCO work and the date the contractor provided the quote.

Then c l ick the Save as New PCO Detai l red button.

20

PCO MODULECONTRACTOR ESTIMATES

Page 21: N etLink II User Guide  PCO Module

I f any changes are needed on the PCO cl ick on any of the penci l icons and make the appropriate change. Once changed cl ick on the Update PCO Detai l red button.

21

PCO MODULECONTRACTOR ESTIMATES

Page 22: N etLink II User Guide  PCO Module

From this screen you can pr int the Change Order form (you may need to use the scrol l bar on the r ight) .

Print the Change Order, attach appropriate back up documentat ion, s ign the change order, and route to the contractor for s ignature.

22

PCO MODULECONTRACTOR ESTIMATES

Page 23: N etLink II User Guide  PCO Module

Once the contractor returns the signed change order the AE or CM wil l scan the change order and email i t to the appropriate Contracts Administrator.

The CA wi l l complete the processing and return approved change orders to the Contractor, AE, CM ( if appl icable) and Project Manager.

23

PCO MODULEAE AND CONTRACT

ESTIMATES COMPLETE

Page 24: N etLink II User Guide  PCO Module

The following section is for Contracts Administrator use only.

24

PCO MODULECONTRACTS

ADMINISTRATORS

Page 25: N etLink II User Guide  PCO Module

The PCO needs to be created prior to moving on to the Pending Change Order tab.

First check the box in the PCO Detai l Search Results sect ion.

Next hit the red Create a Pending CO button.

25

PCO MODULE

Page 26: N etLink II User Guide  PCO Module

Once the red Create a Pending CO button is selected the system wi l l move you to the Pending Change Order tab.

Enter the dates here and hit the red Update Pending CO button.

26

PCO MODULE

Page 27: N etLink II User Guide  PCO Module

Print the Change Order Routing Sl ip and route for signature.

Once signed update the PM and DOP dates and hit the Apply Pending CO red button.

27

PCO MODULE

Page 28: N etLink II User Guide  PCO Module

Entering the Funding.

For local funded projects the PO number wi l l populate, as well as the funding source for the Design and FOD fee.

For state funded projects the PO number wi l l be pending.

28

PCO MODULE

Page 29: N etLink II User Guide  PCO Module

When complete hit the red Create Change Order button.

I f a l l goes wel l you wil l receive a dialog box stating that the change order has been appl ied.

29

PCO MODULE