MyFloridaMarketPlace MyFloridaMarketPlace Change Request Board August 30, 2007
Jan 12, 2016
MyFloridaMarketPlace
MyFloridaMarketPlace Change Request Board
August 30, 2007
Page - 2
Agenda
CRB Organization
Failed Purchase Order Process discussion – Action requested
Operational Reporting – Action requested
MFMP equipment relocation to Shared Resource Center
MFMP / Applicability to Executive Order 07-126
Scorecard update
Page - 3
CRB Organization
Current agency CRB membership will remain the same for the remainder of the fiscal year with the addition of DMS
In January, the MFMP team will solicit interest from agencies about participating on the CRB
If additional agencies express interest in participating, the team will review current membership and meeting attendance history as part of considerations for rotating members
Additional Representation – In addition to agency members and the CRB chairperson, the MFMP team will also be requesting representatives from State Purchasing and DFS Audit
Page - 4
CRB Organization
Prioritization: Provide input into the prioritization of MyFloridaMarketPlace system enhancements, taking into account the applicability across the enterprise of users
Design Confirmation: Provide guidance to the MyFloridaMarketPlace team about preferred functionality and assist with confirming the functional requirements for prioritized system enhancements
Communication: Provide input into the best methods and vehicles to communicate system enhancements to the user community
Following the role that the CRB has played to date, the board will continue to focus on the following:
Page - 5
Current Failed Purchase Order Notification Process
The Customer Service Desk (CSD) identifies failed purchase orders (PO) due to problems with the vendor’s preferred ordering method (fax or e-mail).
The CSD attempts to send the PO via an alternative method (e.g. if previously fax, they will try e-mail, etc.). The CSD will not attempt to resend the PO if the vendor has already been flagged for having invalid data (ID XX/XX).
If the PO is still unsuccessful, the CSD will attempt to contact the vendor by phone and get current information from them, send the order and update the vendor’s information in Vendor Registration. The agency only receives notification that the PO was resent
successfully if the PO had attachments. The agency will be notified in this communication to send the attachments directly to the vendor as they are unable to. NOTE: if there are no attachments then the agency is never notified.
Page - 6
Current Failed Purchase Order Notification Process cont.
If the CSD cannot contact the vendor, the vendor’s name will be marked with Invalid Data, the month and year this is effective. Ex: Geyer Painting Inc. ID: 08/07(001_Geyer Painting Inc. Tallahassee) .
If the vendor cannot be contacted, the agency is notified about the failed PO and the CSD will stop attempting to contact the vendor to send the PO.
If an agency chooses to continue to submit orders to a vendor flagged as having invalid data, the CSD is not required to continue to try and send the PO.
We request that agencies assist us by reaching out to vendors, and getting them to update their information in Vendor Registration.
Page - 7
MFMP Failed Purchase Order Notification
A report request has been submitted to capture and report failed PO information.
This report will assist agencies in knowing what POs failed, why, and the timeframe from when the PO failed to when the agency is notified the PO is successfully sent.
Report Fields:
Date PO failed to send Reason PO failed to send Date successfully sent to the vendor Method successfully sent to the vendor Date agency notified
Agency Name PUI OBO Vendor Name Vendor FEID DO #
Page - 8
Option Target Notification
Time
Impacts
Agencies are notified when the PO fails and are responsible for reaching out to the vendor
1 business day Quick turnaround to agency when PO fails; but added work for agency staff (i.e., contacting vendor, getting PO and attachments to vendor)
Agency would now get all failed orders, including those that the CSD currently resends without having to involve agency (e.g., vendor’s fax machine was turned off)
CSD tries to resend order via an alternate method. If the vendor is not reached, the agency is notified within 2 business days
2 business days CSD may be able to make contact with vendor and therefore prevent agency from having to resend PO
Agency will still be contacted to send attachments
CSD tries to contact the vendor via all methods (email, fax, and phone). If the vendor is not reached, the agency is notified within 4 business days
4 business days CSD exhausts all available contact methods, and may be able to make contact with vendor and therefore prevent agency from having to resend PO
Agency will still be contacted to send attachments
Proposed Options (Going Forward)
Page - 9
Operational Reporting
History Last Fall, several agencies indicated that there were additional
MyFloridaMarketPlace reporting needs Since that time, additional agency requested reports as well as upgraded
system search export functionality in MFMP 2.0 have provided expanded options for users
The team would still like to investigate any additional reporting needs Depending on the additional needs, a change request may be needed to
provide an operational reporting solution
Today There are several reporting solutions currently available:
System search export Analysis Reports posted to the FTP site
Over 25 reports are run and posted daily 3 reports are run and posted weekly 7 reports are run and posted monthly
Page - 10
Operational Reporting
The team is investigating reporting solutions, including the following: New reporting database New MFMP environment to be used for reporting Enhanced report request functionality
Access database Agencies are permitted to have 8 report requests implemented per month
Next Steps Discuss reporting needs Select CRB design team
Page - 11
MFMP Shared Resource Center Move
MFMP hardware and operations relocating to DMS Shared Resource Center Relocation will occur 9/14 – 9/16 Testing involves performance, data migration, and functional verifications Schedule of events:
9/14/07 6:00 PM Eastern: MFMP Shutdown 9/14/07 6:00 PM – 9/16/07 8:00 AM Eastern: Server relocation,
configuration and testing 9/16/07 8:00 AM – 2:00 PM Eastern: Functional verification 9/16/07 7:00 PM Eastern: Go/No go for production 9/17/07 7:00 AM Eastern: MFMP return to production
Communications will be distributed at key points during the weekend Contingency plan for Monday, 9/17/07 will follow the upgrade approach
In the unlikely event additional time is needed, Monday will be used At 2:00 PM Eastern, if conditions persist, MFMP will revert back to Miami
Data Center
Page - 12
Agency buyers utilize MFMP information for making purchasing decisions
User is able to identify available ‘green’ products from MFMP catalog search results
Report
Report
Report
myGreenFlorida
User completes purchasing process
myGreenFlorida provides reporting data for enterprise analysis of ‘green’ spend
Executive Order / MFMP enhancements
Page - 13
Functional Steps within MFMP
Step 1: User adds catalog items to a requisition and can specifically search for ‘green’ products within MFMP
Page - 14
Functional Steps within MFMP
Step 2: User is presented with a set of search results with a ‘green’ indicator included as part of the product description. As an example icon, a tree is used to indicate a green catalog item. The user then uses the ‘Add to Cart’ button to include as part of the requisition.
This allows line item data to be captured and ultimately used for reporting purposes.
Page - 15
Scorecard Update
Pilot extended through January 2008
Received great feedback from a couple agencies Agencies with shadow purchasing systems skewed benchmark levels CR 32 – Queue Report design feedback How do we account for procure to pay utilization? Method of procurement
Project team willing to work with Agencies to review scorecard – very limited takers
Page - 16
Next Meeting / Time and Location
Next meeting will be scheduled for October
If there is a need for any interim meetings or discussions, the team will reach out to the CRB members to schedule (e.g., Acceptance Testing for CR #32, Operational Reporting Discussion)