Reproduced with permission of the copyright owner. Further reproduction prohibited without permission. MULTI-PROJECT SCHEDULING AND CONTROL: A PROCESS-BASED COMPARATIVE STUDY OF TH... Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management Journal; Jun 2004; 35, 2; ABI/INFORM Global pg. 39
12

MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Mar 12, 2018

Download

Documents

phamminh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

MULTI-PROJECT SCHEDULING AND CONTROL: A PROCESS-BASED COMPARATIVE STUDY OF TH...Izack Cohen; Avishai Mandelbaum; Avraham ShtubProject Management Journal; Jun 2004; 35, 2; ABI/INFORM Globalpg. 39

Page 2: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 3: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

June 2004 Project Management Journal • 41

able delays of the critical chain.Consequently, feeding buffers areadded at the end of each non-criticalactivity chain (“pushing” the latterback in time, in response to a “latestart”). The feeding buffers thus pro-tect the critical chain from variationsof non-critical chains and allow criti-cal-chain activities to start early, whenpossible. According to Leach (1999),a feeding-buffer capacity is set to 50%of the duration of its non-criticalactivity chain.

Step S5: Control.Buffer monitoring provides a

quick grasp of project status, which, inturn, enables adaptive control.Specifically, buffer consumption thatreaches a predefined threshold (e.g.,two-thirds of the buffer size or, equiva-lently, one-third of the slack timeremains unused; Leach, 1999) triggersan early warning toward taking somepreventive managerial action. Moredetails are provided later in this paper.

Multiple projects are accommo-dated by combining single-projectscheduling with TOC (Goldratt, 1984)and CC principles, notably theemphasis on reducing multi-tasking(Herroelen & Leus, 2001; Leach,1999). To this end, project start-timesare staggered, which turns the multi-project system into a “pull” systemwith newly determined release/starttimes. Following are the relevantdetails.

Scheduling and control of a multi-project system:

Step M1: Treat each project as asingle project.

Individually schedule each of themulti-projects, using the four steps forscheduling a single project, as describedin Steps S1–S4.

Step M2: Stagger projectsaccording to the bottleneck resource.

First identify the bottleneck,namely the most constrainingresource (often by simply usingmanagerial experience). Thenrelease projects sequentially, by stag-gering them, so that the bottleneckworks continuously and there is noidle time.

Step M3: Create a capacity buffer.A time buffer, called a capacity

buffer, is associated with the bottle-neck, and its role is to ensure bottle-neck availability. The capacity bufferdecouples between bottleneck activi-ties that belong to successive projects,thus determining projects’ start times.Since, based on a literature survey,there is no standard way to set the sizeof this capacity buffer, we set its base-case size at 50% of the duration of thebottleneck activity. We then analyzethe effect of alternative sizes by varyingthe values through 8.3%, 16.7%,83.3% and 116.7%.

Step M4: Control.As with single projects, scheduling

control of multi-projects is buffer-based: when allocating an idleresource, top priority is given to criti-cal-chain activities over non-critical-chain activities; secondary priority isgiven to activities of projects with thehighest level of project buffer utiliza-tion or, equivalently, the least slacktime. Least priority, in turn, is given toactivities of projects with the highestfeeding buffer consumption.

From Project to Process ManagementFollowing Adler et al. (1995), wemodel a multi-project organization asa stochastic processing network. Adleret al. (1995) validated the modelbased on an actual research and devel-opment organization, showing thatthe model simulated quite accuratelyits performance.

In the model of a stochastic pro-cessing network, each network noderepresents a group of (one or more)statistically identical resources, whoperform the same type of activities andwho are able to do so in parallel.When several activities of a project can

start being processed at the same time,we refer to the phenomenon as a“fork;” when an activity cannot beginuntil its predecessor activities havebeen completed, we call it a “join.”(Consequently, such models are oftenreferred to as fork-join queues. Forexample, see Nelson & Tantawi, 1988.)The time required to complete anactivity is called its processing time(duration) and the intervals betweensuccessive project releases are “inter-arrival times.” The reciprocal of the

Table 1 / Cohen

Inter-arrival Exp(1/3.25)

Activity A 1 3 Exp(1/6)

Activity B 2 2 Exp(1/5)

Activity C 3 3 Exp(1/4)

Activity D 4 1 Exp(1/3)

Resource Number of Time � Type Resources Distribution

Table 1. Characteristics of our multi-project system: number of resource-units per type, processing time distribution and inter-arrival time distribution. The notation Exp(l) represents anexponential distribution with probability density function f(t)= le–lt (and expectation 1/l)

Fig 1 / Cohen

A, 1

B, 2

C, 3

D, 4

Resource Queue Synchronization Queue Activity Type (I), Resource Type (#)I, #

FS

Figure 1. The Stochastic Processing Network approach for representing a multi-project system

PMI-010 June_PMJ 9/22/04 12:55 PM Page 41

Page 4: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 5: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 6: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 7: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 8: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 9: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 10: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 11: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Page 12: MULTI-PROJECT SCHEDULING AND CONTROL: A …ie.technion.ac.il/serveng/References/MultiProject_Scheduling_and... · Izack Cohen; Avishai Mandelbaum; Avraham Shtub Project Management

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.