Page 1
ID Task
Mode
Task Name Duration PredecessorsOwner Start Finish Actual Finish
1 MSD I 83 days Mon 8/25/14 Wed 12/17/14 NA
2 Phase I: Problem Definition (1-3) 2.6 wks Tue 8/26/14 Thu 9/11/14 Thu 9/11/14
12 Phase II: Systems Design (4-6) 3 wks Fri 9/12/14 Thu 10/2/14 Thu 10/2/14
20 Phase III: Subsystems Design (7-9) 3.6 wks Fri 10/3/14 Tue 10/28/14 Wed 10/29/14
70 Phase IV: Detailed Design (10-12) 2.8 wks Thu 10/30/14 Tue 11/18/14 Tue 11/18/14
94 Phase V: Complete Design (13-15) 17 days Thu 11/13/14 Fri 12/5/14 Fri 12/5/14
108 Gate Review (16) 1 day Team Tue 12/9/14 Tue 12/9/14 Tue 12/9/14
109
110 MSD II 78 days Mon 1/26/15 Mon 5/11/15 NA
111 Phase I: Subsystem Level Preparation (1-2) 10 days Mon 1/26/15 Fri 2/6/15 NA
112 Received Parts (Week 1) 5 days 99 Morgan Fri 11/28/14 Thu 12/4/14 NA
113 Inspect Parts (Week 1/2) 10 days 112 Team Fri 12/5/14 Thu 12/18/14 NA
114 Risk: Pump cannot be accurately controlled with actual tubing (R4)
NA
115 Reservoir Lid Drilled (Week 2) 3 days Rob Mon 2/2/15 Wed 2/4/15 NA
8/3 8/17
August 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 2
ID Task
Mode
Task Name Duration PredecessorsOwner Start Finish Actual Finish
116 Polycarbonate Sheets and Drawings to Machine Shop (Week 1/2)
5 days 99 Collin/Sarah/MichelleFri 11/28/14 Thu 12/4/14 NA
117 If any concerns, Follow up with SMEs 10 days Team Mon 1/26/15 Fri 2/6/15 NA
118 Critical Design Review (If Failed Gate Review)
0 days 108 Team Wed 12/10/14 Wed 12/10/14 NA
119 Phase II: Subsystem Level Build and Test (3-5)
16 days Sat 2/7/15 Fri 2/27/15 NA
120 Autoclave Testing of Components 1 day? 113 Kate Fri 12/19/14 Fri 12/19/14 NA
121 Assembly of Growth Chamber (Week 4) 5 days 122 Sarah/RobWed 12/10/14 Tue 12/16/14 NA
122 Returned Machined Components (Week 3)
3 days 116 Collin/Sarah/MichelleFri 12/5/14 Tue 12/9/14 NA
123 Chanel Volume Test (Week 3) 5 days 122 Kate Wed 12/10/14 Tue 12/16/14 NA
124 Risk: System doesn't allow for media exchange (30)
NA
125 pH Test Plan B (Week 3) 6 days 112 Rob Fri 12/5/14 Fri 12/12/14 NA
126 Risk: Not Enough Gas Exchange (R33) NA
127 Bubble Testing (Week 3) 5 days 112 Morgan Fri 12/5/14 Thu 12/11/14 NA
128 Risk: Bubbles in system do not disappear (29)
NA
8/3 8/17
August 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 3
ID Task
Mode
Task Name Duration PredecessorsOwner Start Finish Actual Finish
129 Key Sub-System Functional Demo 0 days Team Wed 12/24/14 Wed 12/24/14 NA
130 Phase III: Subsystem and System Level Build, Test, and Integrate (6-8)
16 days Sat 2/28/15 Fri 3/20/15 NA
131 Assembly of Chamber with Tubes and Pump
3 days Collin/Sarah/MichelleTue 3/3/15 Thu 3/5/15 NA
132 Preliminary Testing of Complete System 9 days 131 Morgan/Kate/RobFri 3/6/15 Wed 3/18/15 NA
133 Preliminary Integrated Systems Demonstration
1 day 132 Team Thu 3/19/15 Thu 3/19/15 NA
134 Phase IV: System Level Build, Test, and Integrate (9-11)
15 days Mon 3/30/15 Fri 4/17/15 NA
135 Testing of Complete System 11 days 133 Team Sat 3/21/15 Fri 4/3/15 NA
136 Troubleshoot final errors 7 days 135 Mon 4/6/15 Tue 4/14/15 NA
137 Full Integrated System Demonstration with Customer
0 days 136 Team Wed 4/15/15 Wed 4/15/15 NA
138 Phase V: Verification and Validation (12-15) 19 days Sat 4/18/15 Wed 5/13/15 NA
139 Comparisons and Verification 9 days 132,137Team Wed 4/15/15 Fri 4/24/15 NA
140 Poster Complete 11 days 135 Mon 4/6/15 Sat 4/18/15 NA
141 Imagine RIT 0 days 140 Mon 4/20/15 Mon 4/20/15 NA
8/3 8/17
August 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 4
ID Task
Mode
Task Name Duration PredecessorsOwner Start Finish Actual Finish
142 Write Up of Report 8 days 139,137Team Mon 4/27/15 Wed 5/6/15 NA
143 Hand Off to Customer (Week 14) 0 days Team Tue 5/12/15 Tue 5/12/15 NA
144 Final Edits to EDGE 2 days 135,140,141 Wed 5/6/15 Thu 5/7/15 NA
145 Final Paper Submitted (Week 14) 0 days Thu 5/7/15 Thu 5/7/15 NA
146 Team Assessment 2 days 145 Tue 5/12/15 Wed 5/13/15 NA
147 Evaluation of Success 2 days 145 Tue 5/12/15 Wed 5/13/15 NA
148 Final Project Poster Presentation (Week 15)
0 days Team Tue 5/12/15 Tue 5/12/15 NA
149 Gate Review (16) 7 days Team Wed 5/13/15 Thu 5/21/15 NA
8/3 8/17
August 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 5
8/17 8/31 9/14 9/28 10/12 10/26 11/9 11/23 12/7 12/21 1/4 1/18
August 1 September 1 October 1 November 1 December 1 January 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 6
12/10
8/17 8/31 9/14 9/28 10/12 10/26 11/9 11/23 12/7 12/21 1/4 1/18
August 1 September 1 October 1 November 1 December 1 January 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 7
12/24
4/15
4/20
8/17 8/31 9/14 9/28 10/12 10/26 11/9 11/23 12/7 12/21 1/4 1/18
August 1 September 1 October 1 November 1 December 1 January 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 8
5/12
5/7
5/12
8/17 8/31 9/14 9/28 10/12 10/26 11/9 11/23 12/7 12/21 1/4 1/18
August 1 September 1 October 1 November 1 December 1 January 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 9
1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21
January 1 February 1 March 1 April 1 May 1 June 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 10
12/10
1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21
January 1 February 1 March 1 April 1 May 1 June 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 11
12/24
4/15
4/20
1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21
January 1 February 1 March 1 April 1 May 1 June 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14
Page 12
5/12
5/7
5/12
1/18 2/1 2/15 3/1 3/15 3/29 4/12 4/26 5/10 5/24 6/7 6/21
January 1 February 1 March 1 April 1 May 1 June 1
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: C:\Users\Michelle\Docu
Date: Thu 12/18/14