MS Project Luc Appelmans
45

MS Project Luc Appelmans. Agenda Introduction What is involved in Project management User Interface Creating a new project Tracking a project.

Dec 28, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

MS Project

Luc Appelmans

Page 2: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 2

Page 3: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 3

Page 4: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Project management factors

• Set of one-off activities• Deliverable• Timescale• Resources• Budget• Business Objectives• Cost/benefit analysis• Phased Approach• Progress Reporting

• Project management• People management• Clear and agreed Scope• Management of

expectations• Risk management• Experience• Project planning and

administration

04/19/23 4

Page 5: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Project Triangle

04/19/23 5

Time C

ost

Scope

• Deliverable• Phases• Tasks• Tracking

• Resources• Assignments• Tracking

• Milestones• Tracking

Page 6: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Tasks: SMART

Specific

Measurable

Achievable

Relevant

Timed

04/19/23 6

Page 7: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 7

Page 8: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

MS Project User Interface

Let’s check out the MS Project User Interface Open MS Project Make sure the toolbars are well placed Activate the View Bar Open the file:

01 Short Film Project 15a.mpp

04/19/23 8

Tips:•Magic button: “Go To Selected Task”•Button with no name (Right Click)•Zoom with Ctrl + Mouse wheel

Page 9: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 9

Page 10: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

The exercise

An office needs to be completely modified and refreshed

Therefore: The office needs to move to another place The construction works need to be executed When terminated the office is moved back

The example is kept simple on purpose

04/19/23 10

Page 11: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 1

Create a new project Please code following tasks:

04/19/23 11

Decision takingPackingTransportEmpty OfficesDemolition interior partitionsInstallation new interior partitionsCeilingRenovated OfficesOrdering of wall paper/paint/carpetNew lightingNew socketsOrdering of furniturePaintingPlacing wall paperCarpetingRefreshed OfficesTransportUnpackingOffices ready to use

Tips:•Use the Insert and Delete keys•Use the Right Click

Page 12: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 2

Define January 1, 2009 as the start date of the project Project / Project Information...

Jan 1 and Jan 2 are non-working days Tools / Change Working Time...

The company is not working the Friday afternoon

04/19/23 12

Page 13: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 2 (2)

Code the task durations:

04/19/23 13

Decision takingPacking 1,5dTransport 0,5dEmpty OfficesDemolition interior partitions 2dInstallation new interior partitions 3dCeiling 3dRenovated OfficesOrdering of wall paper/paint/carpetNew lighting 1,5dNew sockets 2dOrdering of furniturePainting 2dPlacing wall paper 1dCarpeting 1dRefreshed OfficesTransport 0,5dUnpacking 1,5dOffices ready to use

Page 14: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 2 (3)

Please regroup the tasks in following summary tasks:

The decision taking is not part of a summary task

04/19/23 14

Moving outConstruction worksImprovement worksMoving in

Page 15: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Types of links

04/19/23 15

SS

PPFSFS

Default: finish to startDefault: finish to start

SS

PPFFFF

Finish to finishFinish to finish

SS

PPSFSF

Start to finishStart to finish

SS

PPSSSS

Start to start Start to start

Overlap / lag are possible

Page 16: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

How creating links

4 Possibilities to create links: 1st method:

Click on the ID of the primary task Ctrl + Click on the ID of the secondary task Click on the “link tasks” icon

2nd method: Enter the ID of the primary task in the “Predecessor” column

of the secondary task 3rd method:

Enter the primary task via the Task Detail form of the secondary task (Predecessors Tab)

4th method: Drag the primary task over the secondary task

Other Tip: You can change the type of link when double clicking on the link line

04/19/23 16

Page 17: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 3

The links between the tasks are: The moving out can only start after the decision taking The demolition of interior partitions starts when the offices are empty The installation of new interior partitions can only occur when the old partitions

are demolished The ceiling can only be done when the new interior partitions are placed The order of wall paper/paint/carpet is launched at the same time as the ceiling is

starting The new lighting must wait that the ceiling is terminated The new sockets cannot be placed before the new lighting was completed The painting and the ordering of furniture must wait until the new sockets were

placed The wall paper is placed after the painting was done The carpet works can start when the wall paper was placed The moving in can only be done when the offices are refreshed All other logical links

04/19/23 17

Page 18: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 4

Perform the following: The decision taking takes 2 hours BUT it

remains a milestone! Insert a recurrent task within this summary

task.The meetings will be daily and will last for 15 minutes during the construction works.

The new sockets can be installed 0,5 days earlier.

The carpeting must finish no later than the 4th of February.

04/19/23 18

Page 19: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Resources

Once a plan was made you still need to identify who will perform these tasks

These are the Resources, one can have different types of resources: People Machines Consumables (not really a resource but added for

cost calculations)

Resources might not be available at all times Resources have a cost04/19/23 19

Page 20: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 5

Go to the Resources Sheet Add following resources:

Director, Department Responsible, A (part-time 50%) secretary, We have 4 employees in the department, A team of 3 movers with a truck and an elevator 2 plasterers 2 electricians. 3 carpet installers who will place the carpets. 2 painters who will use the ordered paint. They work ¾ of the

time. Paint used by the painters.

Make sure the initials are unique04/19/23 20

Page 21: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 6

Complete following information regarding the resources: Each mover is paid 100€ per hour, the truck costs 120€ when used, the

elevator 100€ when used; everything is paid at arrival The plasterers are paid 80€/h prorated based on the work performed The electricians are paid 85€/h prorated based on the work performed The carpet installers are paid 75€/h once the work was terminated The painters are paid 70€/h at the end of their work. They will use the

ordered paint which costs 40€ per unit (e.g. 5L pot).

Assign each resource to a group: Internal, External, Equipment, Material

Check out the calendars!!

04/19/23 21

Page 22: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Formula

DURATION x UNITS = WORK

Examples :

One week (duration) = 40 hours

A person at 100 % (units) = 100 %

The total work (work) = 40 hours

A week (duration) = 40 hours

Two persons at 100 % (units) = 200 %

The total work (work) = 80 hours

04/19/23 22

Page 23: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Effort Driven scheduling

MS Project seem to react differently when Adding for the first time resources or modifying assigned resources!!

1st time ADDING Resources: The system calculates the Work

Modifying assigned Resources: The work is kept and the duration is adapted

By default the “Effort Driven” flag is activated!

04/19/23 23

Page 24: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

How to Assign Resources

04/19/23 24

4 Possibilities to assign resources: 1st method (not appropriate for multiple resources):

Click on a task Click on the Assign resource button Enter the assignment percentage in opened window

2nd method (most appropriate): Menu: Window – Split Select required resources and enter units Click on OK

3rd method (for assigning same resources to multiple tasks): Double Click on Task to obtain Task Information view Select Resources Tab Select Resources and Units then click on OK

4th method (useful for copying same assignments): Use Resource Names column

Page 25: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 7

The resources are assigned as follows: The decision needs to be taken by the director and the

department responsible. All department people will spent 1/4th of their time with

packing their files and other personal things, except the secretary who will work 50% of his / her available time to this task. The director is not doing any packing.All the rest will be packed and transported by the movers

The meetings will be attended by the department responsible and the plasterers, the work is performed by the plasterers.

The Improvement works will be done by the correspondent specialists; the orders will be placed by the secretary. The painters will use 15 units/pots of paint.

The moving in happens the same way as the moving out.

04/19/23 25

Page 26: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Changing the Gantt chart

Fast changing the look of the Gantt chart can be done via the Gantt Chart Wizard

You can adapt each object on the Gantt chart. Right Click on the screen and select Bar Styles

04/19/23 26

Page 27: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 8

Change the Gantt chart to make sure it only shows the resources initials

Add the project summary task (Tools/Options/View tab)

View the « Gantt Chart Wizard » (Format)

Execute a print preview Look at the options for improving the print

layout, use the print preview

04/19/23 27

Page 28: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 9

Let’s look at the Resource usage Activate the view: Resource Usage Do a Split (Windows) Visualize the Gantt in the 2nd half of the screen Click Hide Subtasks after selecting the resource name column Position on the Plasterers and click on « Go to selected tasks » Add the “Overallocation” info on the screen at the right

Do what? Increase the number of plasterers Diminish the Work but keep the same duration Keep the work and increase the duration

Let’s increase the units of plasterers to 220% Double click on Plasterers in the Resource Usage

04/19/23 28J2

Page 29: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 9 (2)

Let’s look at the Resource usage Position on the Electricians and click on « Go to

selected tasks »

Do what? Suppose that increasing the number of electricians is not

possible Diminish the Work but keep the same duration Keep the work and increase the duration

Click on the task “New sockets” and click on Assignment information (or double click)

Change the units from 200% to 100% for this task The duration of the task increases, but the option exists to

decrease the work. (click on the icon ) Please reduce the work!

04/19/23 29J2

Page 30: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 9 (3)

Open project Move08 We will ask MS Project to eliminate the capacity problems Check the end of the project date and time (before the leveling calculation)

Now re-check the end of the project (date & time). It is a good adjustment, which is not always the case!

04/19/23 30J2

Page 31: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Presenting the plan

When the plan is completed it needs to be presented and hopefully approved

Some possibilities are: Easy copy/paste of the Gantt chart Analysis toolbar

04/19/23 31

Page 32: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 32

Page 33: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 10

We need to keep the APPROVED PLAN: The Baseline = The Reference (approved) Plan!!

Creation of the baseline: You can use Move09b as starting point Tools / Tracking / Save Baseline

The views: Tracking Gantt More Views / Task Sheet + View / Table /

Variance

04/19/23 33

Page 34: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 11

There are several ways to track the project: Tools / Tracking / Update Project; Date = 8 January 2009

This updates the project up till that date. It supposes that the work was performed as planned. Very approximate approach.

Gantt Chart + View / Table / Work Move the column “%W.Comp.” after Work; code:

100% for Demolition interior partitions 20% for “Installation of new interior partitions” Now pull the completion line to include the Tuesday (see Tracking

Toolbar) 100% for daily meetings 3 , 4 and 5

The completion is entered at the task level. The completed work is automatically calculated for all resources.

04/19/23 34

Page 35: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 12

There are several ways to track the project:

Enter the work performed Move the column “Actual” after the column “Work”

Enter 48h as “Actual” for the task “New interior partitions” Enter 56h as “Actual” for the task “Ceiling” (see what is

happening to Work!!) Use Tracking Toolbar to indicate the tasks Daily Meetings 6

through 10 are completed

The actuals are still entered at the task level!! Check the Tracking Gantt

How do we need to obtain 100% for the summary task “Construction Works”?

04/19/23 35

Page 36: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 13

There are several ways to track the project:

Enter the actuals per resource and task per day View / Task Usage and select table Work Format / Detail / Work and Actual Work

Enter 128h as “Actual” for the task “Improvement works”(in the main screen)

Make sure you have the Actual Work field in the sub screen (right)

Enter 12h for the Movers for “Transport” on 03/02 Enter 3h for the Movers for “Transport” on 04/02 Enter 4h for the Truck for “Transport” on 03/02 Enter 4h for the Elevator for “Transport” on 03/02 Be careful as the way you enter the time spent it will impact following

tasks

Here we enter very detailed task actuals

04/19/23 36

Page 37: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 14

Analyze the project: Project / Project Information / Statistics or

Select Tracking Gantt Activate the filter: Project / Filtered For:../ More

Filters Select Slipping Tasks

View / Task Sheet Select the table “Variance” via the button left

above (Select All button) Select the table “Cost” via the button left above

(Select All button) and filter on Cost Overbudget

04/19/23 37

Page 38: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 38

Page 39: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Sharing resources

04/19/23 39

SharedResources

(project)

Project 1 Project 2 Project 3

• A project (called here Shared Resources) only contains the resources with their calendars and availabilities

• The other projects are linked to the Resources project to plan the resources

Page 40: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 15

Open following projects: Wingtip Toys Commercial 20a Parnell Aerospace Promo 20b

Create a new Resources project Share the resources in the projects Wingtip and Parnell:

Tools / Resource Sharing / Share Resources Select “Use resources” and choose “Resources”

Analyze the resources in the project “Resources”

Close all projects then: Open the project “Resources” Create a new project and execute Assign Resources Tools / Resource Sharing / Share Resources Create a task Re-execute Assign Resources

04/19/23 40

Page 41: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 41

Page 42: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Exercise 16: Consolidated project

Open following projects: Wingtip Toys Commercial 20a (without opening “Resources”) Parnell Aerospace Promo 20b (without opening “Resources”)

Execute Windows / New Window and select the two projects The consolidated project has been created. You can save it. Analyze the resources in the project “Resources”

It is possible to create links between tasks of the different projects: In the consolidated project, But also in the individual projects, example:

In the project Wingtip Toys click on task 5, Fine cut edit Click on “Task Information” and select the tab “Predecessors” In the ID column (under the 4) enter: “Parnell Aerospace Promo 20b\8”

04/19/23 42

Page 43: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Agenda

Introduction What is involved in Project management User Interface Creating a new project Tracking a project Sharing Resources Consolidation of projects Final Recap Exercise

04/19/23 43

Page 44: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

What did we see?

Creation of a plan with: Tasks and sub-tasks The different links between tasks

Creation of resources with: The number of units and the related costs

The assignment of resources to tasks The tracking of the project:

A rough tracking Or a very detailed tracking

Analysing the data, the schedule, the costs, the capacity

Printing of the plans The sharing of resources and consolidated projects

04/19/23 44

Page 45: MS Project Luc Appelmans. Agenda  Introduction  What is involved in Project management  User Interface  Creating a new project  Tracking a project.

Recap Exercise

Ski planning!! Planning of a ski vacation long time in

advance Difficulties are:

No project start dateAdaptations to the calendarSpecial ways to use links

See separate exercise sheet with details.

04/19/23 45