    Using Microsoft Project for Project management

    Project Management

    Information systems projects are known to be late and/or over budget primarily because

    of poor project management. Project management requires that we identify all the

    activities of the project, the start/end of each activity and the resources allocated to theactivity. Because of the large number of activities, and the dependencies among them,

    we typically use a specialized project management software package, such as Microsoft

    Project.Project management covers the processes of: initiating, executing, controlling, and

    closing the project. The first step in project management is to define all the tasks that we

    need to complete in order to achieve the project goal. For each task we define theduration that is how long it takes to complete the task.Two diagrams are created in MS Project. The Gantt Chart (named for Henry Gantt, a

    pioneer of project management techniques) provides a graphical presentation of the

    project. It displays each task as a horizontal bar with the length corresponding to the

    duration of the task.The Network Diagram graphically highlights the interdependencies of the tasks. Each

    task is displayed as a box containing the start, finish, duration and % completion of thetask. The tasks are linked together through link lines, thus creating a picture of how the

    tasks are sequenced. The Network Diagram highlights the critical path of the project.

    The critical path is the series of tasks that determines the finish date of the project.

    After you enter the tasks into MS Project, you can view the Gantt chart or Network

    Diagram by selecting the view options.

    Using Microsoft Project:

    1) Click on Start/Programs/Microsoft Project.2) The following screen shows up (Figure 1.1)

  • 8/9/2019 MS Project Lab1

    2/17

    Fig 1.1 Blank Project screen

    3) Next, we enter the tasks that we have identified for our project.

    Suppose, that for the initial phase of Project Planning we identified 5 tasks:1. Defining the problem,

    2. Producing Product schedule,3. Confirming project feasibility Schedule

    4. Staffing the project , and

    5. Launching the project.We next, defined the subtasks for each of the 5 tasks. Note that it is easier to

    estimate the start/end times for the smaller subtasks. The tasks, subtasks and the

    duration in days, are as follows:1. Defining the problem;

    1.1) Meeting with the users. 2 days

    1.2) Defining scope. 1 day.1.3) Writing business benefits. 1 day.1.4) Writing statement of needs. 1 day.

    1.5) Defining system capabilities. 1 day.

    1.6) Defining context diagram. 1 day.

    2. Producing Product Schedule:

    2.1) Developing work breakdown structure. 1 day.

  • 8/9/2019 MS Project Lab1

    3/17

    2.2) Estimate resources duration. 1 day.

    2.3) Developing Pert chart. 2 days.

    3. Confirming project feasibility:3.1) Identifying intangible cost. 1 day.

    3.2) Estimate tangible cost. 1 day.

    3.4) Do cost/benefit analysis. 2 days.3.5) Evaluate organization feasibility. 1 day.

    3.6) Evaluate technical feasibility. 2 days.

    3.7) Evaluate schedule feasibility. 1 day.3.8) Evaluate resource availability. 1 day.

    4. Staffing the project:

    4.1) Develop a project resource plan. 1 day.

    4.2) Identify and request tech staff. 1 day.4.3) Meet with users, identify staff. 1 day.

    4.4) Organize project team. 1 day.

    4.5) Conduct team-building exercises. 3 days.

    5. Launching the project:5.1) Prepare presentation material. 1 day.

    5.2) Make executive presentation. 1 day.5.3) Set up project facilities. 3 days.

    5.4) Conduct official kick-off meeting. 1 day.

    4) Next, we enter the tasks into the blank Project Window. Enter 1. Projectplanning Phase in the Task Name column. Note that the duration of a task is

    defaulted to 1 day (followed by a ?), and the Start and finish fields are filled up

    accordingly, as shown in figure 1.2. You may change the duration as necessary.

    The total time to complete the entire project will be calculated by MS Project as

    you enter all the tasks.

  • 8/9/2019 MS Project Lab1

    4/17

    Figure 1.2 Filling the task

    5) The following are definitions of the fields:Duration: tells you how long it takes to complete a particular task.

    Start: the date you want to start that particular task.

    Finish: the date you will finish that particular task.The Start and finish dates are automatically filled in once you specify the

    duration of the task.Predecessors: the tasks that must be completed before you can start a particular

    task.

    Resource Names: the names of people who would perform that particular task.

    6) Now, enter the first sub-task of the task you just entered, i.e. 1.1 define theproblem. To indicate that it is a subtask, we indent it to the right by clicking on

    the right green arrow on the menu bar as shown in the figure below.

  • 8/9/2019 MS Project Lab1

    5/17

    Figure 1.3 Entering the tasks

    7) Next, we enter Resource Names (i.e. the names of people who will perform the

    task.) There are two ways to enter resources; double click on the particular fieldof Resource names and select Resource tab (as shown in Fig 1.3), or right click on

    a particular field, select Task Information and click on Resources tab (as shown in

    Fig 1.4 and Fig 1.5):

  • 8/9/2019 MS Project Lab1

    6/17

    Fig 1.3: Double clicking on the particular field and selecting the Resources tab.

  • 8/9/2019 MS Project Lab1

    7/17

    Fig 1.4: Right clicking on the particular field, and selecting Task Information.

  • 8/9/2019 MS Project Lab1

    8/17

    Fig 1.5: Selecting Resource tab

    8) We enter in this window two fields: Resource Name and Units. Resource Name

    identifies the resource, (for example, it can be name of a person or machine). TheUnits field identifies the percentage of the resource being used to accomplish this

    task. Ex., in Fig 1.6 we enter Mary as the resource name, and the 100% indicates

    that Mary will spend 100% of her time performing the task. Click the OK tabonce you entered the data.

  • 8/9/2019 MS Project Lab1

    9/17

    Fig 1.6: Entering the data in Resource name and Units fields before clicking OK button.

  • 8/9/2019 MS Project Lab1

    10/17

    Fig 1.7: Screen display after entering the Resources Names

    9) We continue populating the Tasks, duration, Resources Names and Predecessors

    Fields in the project as shown in the Figure below. We have to ensure that each

    sub-task is indented (to the right) of the related task (by using the green rightarrow on the menu bar). To indent the task to the left, use the green left arrow on

    the menu bar.

    10) Next we update the Predecessors Field. A predecessor task is the task that must

    be completed before starting a particular task. The predecessor is identified by the

    Predecessor ID that is entered in the ID field. The ID is the row number of thetask in the main window. To enter predecessors, we either double click on the

    particular field of Predecessors and select the Predecessors tab (as shown in Fig

    1.8) or right click on that particular field and select Predecessors tab (as shown inFig 1.9):

  • 8/9/2019 MS Project Lab1

    11/17

    Fig 1.8: Double clicking on the particular field and selecting the Predecessors tab.

  • 8/9/2019 MS Project Lab1

    12/17

    Fig 1.9: Right clicking on the particular field ,select Task Information

  • 8/9/2019 MS Project Lab1

    13/17

    Fig 2.0: Clicking on the Predecessors tab

    10a) In our example, the predecessor of ID 1.1.2 Define the scope field is the task 1.1.1

    Meet with users. Its ID is 3 as entered in Fig 2.0. Notice that as soon as we tab to goto the next field, all the information (Task Name) of that ID is displayed

    automatically as in Figure 2.1.

  • 8/9/2019 MS Project Lab1

    14/17

    Fig 2.1: Predecessor Data entered

  • 8/9/2019 MS Project Lab1

    15/17

    Fig 2.2 Numbering subtasks

    11) Notice that we can have multiple predecessors for a particular task. We enter them

    one by one likewise. Also notice that the duration for the tasks are automatically

    calculated according to the subtasks assigned to it. For example, in Fig 2.2 we havetwo subtasks (1.1.1 with 2 days and 1.1.2 with 1 day) for a task (1.1). Then the

    duration of task 1.1 is automatically calculated as 3 days. Similarly, 1.1 Define theproblem is the only subtask of 1.Project planning phase. So, 1. Project planning

    phase has the same duration as 1.1 Define the problem.

    12) Populate the remaining fields as shown in Fig 2.3

  • 8/9/2019 MS Project Lab1

    16/17

    Fig 2.3 The completed tasks

    13) Notice that a Gantt chart is drawn as you enter the tasks (on the right hand side of

    your project). You can view other diagrams such as: Netwroks (PERT),

    Resources, etc, using the View menu on the tool bar.A Gantt chart from the options on the left hand corner of the project as shown in

    Fig 2.4

  • 8/9/2019 MS Project Lab1

    17/17

    Fig 2.4: Gantt chart for the tasks

    14) Similarly we can view the various graphs: Pert Chart, Task Usage, Resource Graph,

    and Resource Usage by selecting them from the option on the left corner. Microsoft

    Project has provided this additional functionality so that you can view your task scheduleand the resources being used for their maximum utilization.

    PRINT & SUBMIT Figure 2.4