MRP Report for MRP 5/15/2012 Overdue Week 1 Week 2 Week 3 Week 4 Item: A100 LT = 1 SS = 50 Gross Requirement 0 0 0 300 0 Scheduled Receipt 0 70 0 0 120 Projected On Hand 80 150 150 50 170 Projected Net Requirement 0 0 0 200 0 Planned Order Receipt 0 0 0 200 0 Planned Order Release 0 0 200 0 0 Item: B100 LT = 2 SS = 80 Gross Requirement 0 0 0 0 260 Scheduled Receipt 0 0 130 50 0 Projected On Hand 120 120 250 300 80 Projected Net Requirement 0 0 0 0 40 Planned Order Receipt 0 0 0 0 40 Planned Order Release 0 0 40 0 0 Item: C200 Part LT = 1 Gross Requirement 0 0 310 0 0 Scheduled Receipt 0 90 0 60 0 Projected On Hand 400 490 180 240 240 Projected Net Requirement 0 0 0 0 0 Planned Order Receipt 0 0 0 0 0 Planned Order Release 0 0 0 0 475 Item: D200 Part LT = 2 Gross Requirement 0 0 240 0 0 Scheduled Receipt 0 0 0 0 0 Projected On Hand 375 375 135 135 135 Projected Net Requirement 0 0 0 0 0 Planned Order Receipt 0 0 0 0 0 Planned Order Release 0 0 0 200 0 Item: E200 Assembly LT = 1 Gross Requirement 0 0 40 0 0 Scheduled Receipt 0 0 240 0 100 Final Product LS = LFL UM = Each Final Product LS = LFL UM = Each SS = 100 LS = EOQ UM = Each SS = 100 LS = FOQ UM = Each SS = 100 LS = LUC UM = Each
23

MRP-latihan

Oct 24, 2014

Download

Documents

Intin Nurwati
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MRP-latihan

MRP Report for MRP

5/15/2012 Overdue Week 1 Week 2 Week 3 Week 4 Week 5

Item: A100 Final Product LT = 1 SS = 50 LS = LFL ABC = A

Gross Requirement 0 0 0 300 0 80Scheduled Receipt 0 70 0 0 120 0Projected On Hand 80 150 150 50 170 90Projected Net Requirement 0 0 0 200 0 0Planned Order Receipt 0 0 0 200 0 0Planned Order Release 0 0 200 0 0 0

Item: B100 Final Product LT = 2 SS = 80 LS = LFL ABC = A

Gross Requirement 0 0 0 0 260 0Scheduled Receipt 0 0 130 50 0 0Projected On Hand 120 120 250 300 80 80Projected Net Requirement 0 0 0 0 40 0Planned Order Receipt 0 0 0 0 40 0Planned Order Release 0 0 40 0 0 140

Item: C200 Part LT = 1 SS = 100 LS = EOQ ABC = B

Gross Requirement 0 0 310 0 0 340Scheduled Receipt 0 90 0 60 0 0Projected On Hand 400 490 180 240 240 375Projected Net Requirement 0 0 0 0 0 210Planned Order Receipt 0 0 0 0 0 475Planned Order Release 0 0 0 0 475 0

Item: D200 Part LT = 2 SS = 100 LS = FOQ ABC = B

Gross Requirement 0 0 240 0 0 140Scheduled Receipt 0 0 0 0 0 0Projected On Hand 375 375 135 135 135 195Projected Net Requirement 0 0 0 0 0 111Planned Order Receipt 0 0 0 0 0 200Planned Order Release 0 0 0 200 0 400

Item: E200 Assembly LT = 1 SS = 100 LS = LUC ABC = B

Gross Requirement 0 0 40 0 0 140Scheduled Receipt 0 0 240 0 100 0

UM = Each

UM = Each

UM = Each

UM = Each

UM = Each

Page 2: MRP-latihan

Projected On Hand 100 100 300 300 400 260Projected Net Requirement 0 0 0 0 0 0Planned Order Receipt 0 0 0 0 0 0Planned Order Release 0 0 0 0 0 0

Item: F300 Assembly LT = 2 SS = 120 LS = PPB ABC = C

Gross Requirement 0 0 400 0 475 0Scheduled Receipt 0 250 0 0 0 210Projected On Hand 350 600 200 200 830 1,040Projected Net Requirement 0 0 0 0 415 0Planned Order Receipt 0 0 0 0 1,105 0Planned Order Release 0 0 1,105 0 0 0

Item: G300 Component LT = 2 SS = 150 LS = EOQ ABC = C

Gross Requirement 0 0 0 200 0 400Scheduled Receipt 0 0 0 70 0 0Projected On Hand 300 300 300 170 170 665Projected Net Requirement 0 0 0 0 0 399Planned Order Receipt 0 0 0 0 0 895Planned Order Release 0 0 0 895 0 895

UM = Each

UM = Each

Page 3: MRP-latihan

Week 6 Week 7 Week 8 Week 9 Week 10 Total

0 0 120 0 350 8500 0 0 0 0 190

90 90 50 50 500 0 80 0 350 6300 0 80 0 350 6300 80 0 350 0 630

0 140 0 270 0 6700 0 0 0 0 180

80 80 80 80 800 140 0 270 0 4500 140 0 270 0 4500 270 0 0 0 450

Type = Part

0 620 0 350 0 1,6200 0 0 0 0 150

375 230 230 355 3550 651 0 368 0 1,2290 475 0 475 0 1,425

475 0 475 0 0 1,425

Type = Part

0 350 0 350 0 1,0800 0 0 0 0 0

195 245 245 295 2950 368 0 368 0 8470 400 0 400 0 1,0000 400 0 0 0 1,000

0 270 0 0 0 4500 0 0 0 0 340

Source = MADE

Type = Final Product

A.Demand = 2,000

@Cost = 200

SetupCost = 500

H.Cost = 20

Source = MADE

Type = Final Product

A.Demand = 3,000

@Cost = 250

SetupCost = 600

H.Cost = 30

Source = MADE

A.Demand = 6,000

@Cost = 50

SetupCost = 150

H.Cost = 8

Source = MADE

A.Demand = 4,000

@Cost = 40

SetupCost = 150

H.Cost = 6

Source = MADE

Type = Assembly

A.Demand = 4,500

@Cost = 60

SetupCost = 200

H.Cost = 10

Page 4: MRP-latihan

260 106 106 106 1060 116 0 0 0 1160 116 0 0 0 116

116 0 0 0 0 116

707 160 475 700 0 2,9170 0 0 0 0 460

333 173 932 232 232522 168 499 735 0 2,339

0 0 1,234 0 0 2,3391,234 0 0 0 0 2,339

116 400 0 0 0 1,1160 0 0 0 0 70

549 1,044 1,044 1,044 1,044122 420 0 0 0 941

0 895 0 0 0 1,7900 0 0 0 0 1,790

Source = BUY

Type = Assembly

A.Demand = 20,000

@Cost = 15

SetupCost = 50

H.Cost = 2

Source = BUY

Type = Component

A.Demand = 16,000

@Cost = 10

SetupCost = 50

H.Cost = 2

Page 5: MRP-latihan

Keterangan

MPSII (SS, OH)GR, OHPRLS

MPSII (SS, OH)GR, OHPRLS

MPSII (SS, OH)GR, OHPRlLS

Page 6: MRP-latihan

Overdue Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

Item: C200 Part LT = 1 SS = 100 LS = EOQ ABC = B

Gross Requirement 0 0 310 0 0 340 0Scheduled Receipt 0 90 0 60 0 0 0Projected On Hand 400 490 180 240 240 375 375Projected Net Requirement 0 0 0 0 0 210 0Planned Order Receipt 0 0 0 0 0 475 0Planned Order Release 0 0 0 0 475 0 475

Gross Requirement 310 340Schedule Receipt 90 60Projected On Hand 400 490 180 240 240 -100Net Requirement 200Scraap 5% 10Projected Net Requirement 210

SS 100 100 100 100 100 100

UM = Each

Source = MADE

1 2 3 4 5 6 7 8 9 100

100

200

300

400

500

600

700

Gross SS OH

Page 7: MRP-latihan

Week 7 Week 8 Week 9 Week 10 Total EOQ (^)D 6000S 150

620 0 350 0 1,620 H 80 0 0 0 150 Q 474.34

230 230 355 355651 0 368 0 1,229475 0 475 0 1,425

0 475 0 0 1,425

620 350

-620 -350 355620 350

31 18651 368 1229

100 100 100 100

Type = Part

A.Demand = 6,000

@Cost = 50

SetupCost = 150

H.Cost = 8

1 2 3 4 5 6 7 8 9 100

100

200

300

400

500

600

700

Gross SS OH

Page 8: MRP-latihan

475

Page 9: MRP-latihan

Overdue Week 1 Week 2 Week 3 Week 4 Week 5

Item: D200 Part LT = 2 SS = 100 LS = FOQ ABC = B

Gross Requirement 0 0 240 0 0 140Scheduled Receipt 0 0 0 0 0 0Projected On Hand 375 375 135 135 135 195Projected Net Requirement 0 0 0 0 0 111Planned Order Receipt 0 0 0 0 0 200Planned Order Release 0 0 0 200 0 400

Gross Requirement 240 140Schedule Receipt 200Projected On Hand 375 375 135 135 135 195Net Requirement 105Scraap 5% 5.25Projected Net Requirement 110.25

UM = Each

Page 10: MRP-latihan

Week 6 Week 7 Week 8 Week 9 Week 10 Total Multiplier

0 350 0 350 0 1,0800 0 0 0 0 0

195 245 245 295 2950 368 0 368 0 8470 400 0 400 0 1,0000 400 0 0 0 1,000

350 350400 400

195 245 245 295 295350 350

17.50 17.50367.50 367.50

Source = MADE

Type = Part

A.Demand = 4,000

@Cost = 40

SetupCost = 150

H.Cost = 6

Page 11: MRP-latihan

200

Page 12: MRP-latihan

Overdue Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

Item: E200 LT = 1 SS = 100 LS = LUC ABC = B

Gross Requirement 0 0 40 0 0 140 0Scheduled Receipt 0 0 240 0 100 0 0Projected On Hand 100 100 300 300 400 260 260Projected Net Requirement 0 0 0 0 0 0 0Planned Order Receipt 0 0 0 0 0 0 0Planned Order Release 0 0 0 0 0 0 116

Gross Requirement 40 140Schedule Receipt 240 100Projected On Hand 100 100 300 300 400 260 260Net RequirementScraap 5%Projected Net Requirement

Sub-Assembly

UM = Each

Source = MADE

Page 13: MRP-latihan

Week 7 Week 8 Week 9 Week 10 Total LUC

T

270 0 0 0 450 1 2 30 0 0 0 340 1 1 0

106 106 106 106 2 2 0116 0 0 0 116 3 3 0116 0 0 0 116 4 4 0

0 0 0 0 116 5 5 06 6 07 7 116

2707 1 116

-10 8 2 0110 9 3 0

5.50 10 4 0115.50

Type = Assembly

A.Demand = 4,500

@Cost = 60

SetupCost = 200

H.Cost = 10

Week

Kebutuhan RT

Page 14: MRP-latihan

TRC (T) TRC (T)/Unit

4 5 6 7 = C+6 8 = 7/40 0 0 200 0.000 0 0 200 0.000 0 0 200 0.000 0 0 200 0.000 0 0 200 0.000 0 0 200 0.00

116 6960 6960 7160 61.72

116 0 0 200 1.72116 0 0 200 1.72116 0 0 200 1.72116 0 0 200 1.72

Kebutuhan Komulatif

Beaya Simpan h.P(T-1)

RT

Beaya Simpan Komulatif

Page 15: MRP-latihan

Overdue Week 1 Week 2 Week 3 Week 4 Week 5

Item: F300 Component LT = 2 SS = 120 LS = PPB ABC = C

Gross Requirement 0 0 400 0 475 0Scheduled Receipt 0 250 0 0 0 210Projected On Hand 350 600 200 200 830 1,040Projected Net Requirement 0 0 0 0 415 0Planned Order Receipt 0 0 0 0 1,105 0Planned Order Release 0 0 1,105 0 0 0

Gross Requirement 400 475Schedule Receipt 250 210Projected On Hand 350 600 200 200 -275Net Requirement 395Scraap 5% 19.75Projected Net Requirement 414.75

UM = Each

Page 16: MRP-latihan

Week 6 Week 7 Week 8 Week 9 Week 10 Total

707 160 475 700 0 2,9170 0 0 0 0 460

333 173 932 232 232522 168 499 735 0 2,339

0 0 1,234 0 0 2,3391,234 0 0 0 0 2,339

707 160 475 700 2917460

-497 -160 -475 -700497 160 475 700

24.85 8.00 23.75 35.00521.85 168.00 498.75 735.00

Source = BUY

Type = Assembly

A.Demand = 20,000

@Cost = 15

SetupCost = 50

H.Cost = 2

Page 17: MRP-latihan

PPBS 65H 0.03846154

EPP 1690Rule APP<EPP

Lot 1

Kelompok periode Ukuran Lot

Week 4 415 0Week 4 dan 5 415 0Week 4, 5, dan 6 937 1044Week 4, 5, 6, dan 7 1105 1548 dipilihWeek 4, 5, 6, 7, dan 8 1604 3544 kegedean

Lot 2

Kelompok periode Ukuran Lot

Week 8 499 0Week 8 dan 9 1234 735Week 8, 9, dan 10 1234 735

Accumulated Part-Periode (APP)

Accumulated Part-Periode (APP)

Page 18: MRP-latihan

Overdue Week 1 Week 2 Week 3 Week 4 Week 5

Item: G300 Component LT = 2 SS = 150 LS = EOQ ABC = C

Gross Requirement 0 0 0 200 0 400Scheduled Receipt 0 0 0 70 0 0Projected On Hand 300 300 300 170 170 665Projected Net Requirement 0 0 0 0 0 399Planned Order Receipt 0 0 0 0 0 895Planned Order Release 0 0 0 895 0 895

Gross Requirement 200 400Schedule Receipt 70Projected On Hand 300 300 300 170 170 -230Net Requirement 380Scraap 5% 19Projected Net Requirement 399

UM = Each

Page 19: MRP-latihan

Week 6 Week 7 Week 8 Week 9 Week 10 Total EOQ (^)DS

116 400 0 0 0 1,116 H0 0 0 0 0 70 Q

549 1,044 1,044 1,044 1,044122 420 0 0 0 941

0 895 0 0 0 1,7900 0 0 0 0 1,790

116 400

-116 400116 400

5.80 20.00121.8 420.00

Source = BUY

Type = Component

A.Demand = 16,000

@Cost = 10

SetupCost = 50

H.Cost = 2

Page 20: MRP-latihan

1600050

2894.43 895

Page 21: MRP-latihan

pembahasanNettingtime phasingBOM EXPLODINGPERHITUNGAN