Page 1 of 26 Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Job No : T-5099 Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B ) Name of Bidder : PT. Truba Jaya Engineering MATERIAL REQUISITION PLAN ( MRP ) PERIODE : JUNE up to NO NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL A Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days A - WELDING CONSUMABLE : 1 CS Welding rods AWS, E-7018 2,5mm Kg - 2 CS Welding rods AWS, E-7018 3,2mm Kg 3 CS Welding rods AWS, E-7018 4,0mm Kg 4 CS Welding wire/TIG / TGS-50 2,4mm Kg 5 SS Welding rods Kg 6 SS Welding wire/TIG 2,4mm Kg 7 Alloy (P91/P11) Welding rods Kg 8 Alloy (P91/P11) Welding wire/TIG Kg 9 Alumina Nozle 10N48 Size. 6, Weldcraft Ea 10 Alumina Nozle 10N47 Size. 7, Weldcraft Ea 11 Alumina Nozle 10N46 Size. 8. Weldcraft Ea 12 Collet Ea 13 Body Collet Ea 14 Long Back Cup Ea 15 Tungsten Rod Dia 2,4mm Lgh 16 Brushes ( Hand Brush / Sikat ) C/S Size, 4" Ea 17 Dark Glass No. 10 or 11 Ea. 18 Clear Glass Ea. 19 Welding Glove ( Good Quality ) CIG Pair 20 Argon Glove ( Good Quality ) Yellow Colour Pair 21 Welding Appron + Sleeve ( Good Quality ) Set 22 Welding Shield / Kap Las Blue Eagle Ea. 23 Welding Holder 500 Amp / Sunritsu Ea. 24 Earth Clamp / Stang Grounding 300 Amp / Sunritsu Ea 25 Hose, Oxygene / Acetylene Bridgestone Mtr 26 Hose, Argon Size 1/4" Mtr 27 Hose, Clamp SS Size 1/2" Ea. 28 Pen Light 2 Battery Energizer Set 29 Masking Tape Size 1" , Nasuha Roll 30 Masking Tape Size 2" , Nasuha Roll 31 Permanent Marker ( White - Yellow ) Snowman Ea 32 Solid Marker ( White - Yellow ) Sakura Ea 33 Penetran , Developer , Cleaner Magnaflux Set 34 Stainless Steel Cleaner Nikko Can 35 Brushes ( Hand Brush / Sikat ) S/S Size, 4" Ea
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
A - WELDING CONSUMABLE :1 CS Welding rods AWS, E-7018 2,5mm Kg - - Essab / Nikko Steel
2 CS Welding rods AWS, E-7018 3,2mm Kg or Eqvalent
3 CS Welding rods AWS, E-7018 4,0mm Kg
4 CS Welding wire/TIG / TGS-50 2,4mm Kg Kobe Steel
5 SS Welding rods Kg
6 SS Welding wire/TIG 2,4mm Kg
7 Alloy (P91/P11) Welding rods Kg
8 Alloy (P91/P11) Welding wire/TIG Kg
9 Alumina Nozle 10N48 Size. 6, Weldcraft Ea or Spartex
10 Alumina Nozle 10N47 Size. 7, Weldcraft Ea or Spartex
11 Alumina Nozle 10N46 Size. 8. Weldcraft Ea or Spartex
12 Collet Ea or Spartex
13 Body Collet Ea or Spartex
14 Long Back Cup Ea or Spartex
15 Tungsten Rod Dia 2,4mm Lgh
16 Brushes ( Hand Brush / Sikat ) C/S Size, 4" Ea
17 Dark Glass No. 10 or 11 Ea.
18 Clear Glass Ea.
19 Welding Glove ( Good Quality ) CIG Pair
20 Argon Glove ( Good Quality ) Yellow Colour Pair
33 Penetran , Developer , Cleaner Magnaflux Set ( 3 Can )
34 Stainless Steel Cleaner Nikko Can
35 Brushes ( Hand Brush / Sikat ) S/S Size, 4" Ea
Page 2 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
36 Tee Socket ( Male/Female ) Legrand Ea
B - FITTER CONSUMABLE :1 Grinding Disk CS 4X6 Pcs
2 Cutting Disk CS 4X3 Pcs
3 Grinding Disk CS 7x6 Pcs
4 Cutting Disk CS 7x3 Pcs
5 Grinding Disk SS 4X6 , Flexovit Pcs
6 Cutting Disk SS 4X6 , Flexovit Pcs
7 Brushes ( Hand Brush / Sikat ) Size 4" Set
8 Fitter Glove Combination Ea
9 Cotton Glove / Polkadot , Bintil2 Ea
10 Slate Pencil Merk Ferari Set
11 Cutting Tip / Nozzle No. 1 - 2 - 3 Victor Ea
12 Cutting Tip / Nozzle No. 1 - 2 - 3 Chiyoda Ea
13 Measuring Tape 5 Mtr, Ea
14 Seal Tape / Teflon Size 1" Roll
15 Cotton Rags / Kain Majun Standart Kg
16 Piano Wire Stainless Steel Size 0,5mm Mtr
C - GASES & DIESEL FUEL ( Solar ) :1 Argon Prority 99,999 % Botol
D - SAFETY CONSUMABLE :1 Safety Gogles SKF or Krisbow Ea.
2 Safety Helmet C/W Chain Strap MSA Ea.
3 Safety Shoes (Staff) King, 805 Pair
4 Safety Shoes (Labor) King Pair
5 Safety Fire Blanket sheet
6 Safety Body Harness Karam or Eqvalent Ea.
7 Safety Belt Fujidenko Ea.
8 Safety Ear Plug Fetalit Pair
Page 3 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
9 Fire Extinguisher refill Tube
10 Dust Masker 3M , Type 8210 Ea
11 Safety Life Line ( Wire Rope ) Size 9mm Roll Certificate
12 Cotton Masker Ea.
13 Safety Eye Wear ( Black /Clear ) Pair
14 Baricade Red & White Colour 500 Mtr/Roll Roll
15 Baricade Black & Yellow 500 Mtr/Roll Roll
16 Paint Spray ( White, Yellow, Red ) Suzuki / Phylox Can
17 Super Thinner ( 5 Ltr/Can ) Avian Can
18 Sand Paper / Amples No. 300 . 400 Sheet
E - ELECTRICAL CONSUMABLE :1 Electric Tape Unibel / Black Roll
2 Cable Power NYY ( For Electric Line ) 3 X 2,5mm / Black Mtr
3 Cable Power NYYHY ( For Extention Cable 3 X 2,5mm / Black Mtr
18 Carbon Brush for Electric Grinder Machine Size 4" Set
19 Carbon Brush for Electric Grinder Machine Size 7" Set
20 Electric Socket / Stop Kontak 3 Lobang Unicon Ea.
21 Socket Tee / Cabang 3 Unicon Ea.
F - SCAFFOLDING TOOL / TEMPORARY CONSUMABLE :1 Scafolding Plank or Asiba Sheet
2 Scafolding Pipe pcs @6 m
Page 4 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
3 Scafolding Clamp ( Fixed & Swivel ) Ea
4 Scafolding Frame Ea
5 Scafolding Bracing Ea
6 Ratchet Wrench for Scaffolding Clamp 17 - 21mm , MCC Ea
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
H - FITTER TOOLS :1 Cutting Torch Victor or Equvalent Set
2 Regulator Oxygene Victor or Equvalent ea
3 Regulator Acetyline Victor or Equvalent ea
4 Flash Back Aristor for Regulator Victor or Equvalent Set
5 Flash Back Aristor for Cutting Torch Victor or Equvalent Set
6 Electric Grinder 4" Makita / Hitachi Unit
7 Electric Grinder 5" Makita / Hitachi Unit
8 Electric Grinder 7" Makita / Hitachi Unit
9 Electric Baby Grinder 2" Makita / Hitachi Unit
10 Air Baby Grinder 2" Makita / Hitachi Unit
11 Electric Speed Cutter 14" Makita / Hitachi Unit
12 Electric Drilling 10 - 16mm Makita / Hitachi Unit
13 Otomatic Speed Cutting Ea
14 Pipe Otomatic Cutting Ea
15 Drive saw 4" Ea
16 Flaring tool dia 13mm Ea
17 concrete drill machine dia 13mm Ea
18 chipping hammer Ea
19 Manual pipe bender 13mm Ea
20 Hydraulic pipe bender Ea
21 Hydraulic jack 1~10 ton Ea
22 Hydraulic jack 30~50 ton Ea
23 Tube cutter Ea
24 Pre-heating torch / Burner Chiyoda or Eqvalent Ea
25 Table vice 4~6" Ea
26 Vacuum cleaner Bosch Ea
27 Pneumatic grinder 100~200mm Ea
28 Pneumatic & electric straight grinder Ea
29 Sledge hammer Ea
30 Tapper drill bit 10-24mm Ea
31 Manual tapping set max 14" Ea
32 Reamer 8-32mm Ea
33 Torque wrench 100-900 cm-kg Ea
34 Impact wrench 1/2" Makita / Hitachi Ea
35 Impact wrench 3/4" Makita / Hitachi Ea
36 Wire cutter 14" Ea
Page 6 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
37 Rachet spanner w/ sharp end Ea
38 Socket wrench 46 -80 Ea
39 Rachet handle 1" sq dr Tekiro Ea
40 Striking wrench 27-55 mm Ea
41 Shear wrench 16,20,22,24 mm Makita / Hitachi Ea
42 Carpenter Square 24" X 16" Ea
43 Carpenter Square 12" X 8" Ea
44 Adjustable wrench 12" , Diamond / Tekiro Ea
45 Adjustable wrench 14" , Diamond / Tekiro Ea
46 Pipe wrench 14" ,Fukung Ea
47 Pipe wrench 18" ,Fukung Ea
48 Oxygene / Acetyline Key std size Ea
49 Tip Cleaner for Nozzle Krisbow Ea
50 Punch ( Drip ) Size 4 " or 6" Ea
I - WELDER TOOLS :1 Welding Electric Drying Oven 200 kg Ea
J - LIFTING TOOLS :1 Chain Block 1 Ton Vital or Elephan ea
2 Chain Block 2 Ton Vital or Elephan ea
3 Chain Block 3 Ton Vital or Elephan ea
4 Chain Block 5 Ton Vital or Elephan ea
5 Chain Block 10 Ton Vital or Elephan ea
6 Shackle 2 - 3 Ton ea
7 Pull lift 3 ton ea
Page 7 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
8 Turn buckle ea
9 pulley block 4 roll 30 ton ea
10 pulley block 4 roll 15 ton ea
11 pulley block 3 roll 15 ton ea
12 pulley block 2 roll 10 ton ea
13 single pulley block 15 ton ea
14 single pulley block 10 ton ea
15 single pulley block 6 ton ea
16 single pulley block 5 ton ea
17 single pulley block 3 ton ea
18 single pulley block 1 ton ea
19 wire rope dia 22x800m Kiswire roll @ 800 m
20 wire rope dia 20x200m Kiswire roll @ 200 m
21 wire rope dia 10x200m Kiswire roll @ 200 m
22 wire rope dia 14x200m Kiswire roll @ 200 m
23 wire rope dia 12x200m Kiswire roll @ 200 m
24 wire rope dia 9x200m Kiswire roll @ 200 m
25 sling wire dia 65x16m Kiswire roll @ 16 m
26 sling wire dia 50x25m Kiswire roll @ 25 m
27 sling wire dia 38x12m Kiswire roll @ 12 m
28 sling wire dia 38x10m Kiswire roll @ 10 m
29 sling wire dia 38x2m Kiswire roll @ 2 m
30 sling wire dia 34x15m Kiswire roll @ 15 m
31 sling wire dia 24x10m Kiswire roll @ 10 m
32 sling wire 10 m Kiswire ea
33 sling wire 12 m Kiswire ea
34 wire rope 9 mm iwrc mtr Kiswire mtr
35 wire rope 12 mm iwrc mtr Kiswire mtr
36 wire rope 16 mm iwrc mtr Kiswire mtr
37 wire rope 20 mm iwrc mtr Kiswire mtr
38 manila rope dia 12x300m Gurita or Eqvalent roll @ 300 m
39 manila rope dia 16x300m Gurita or Eqvalent roll @ 300 m
40 manila rope dia 25x300m Gurita or Eqvalent roll @ 300 m
41 safety rope (nylon) dia 1/2"x200m roll @ 200 m
42 lever block 5 ton Vital or Elephan ea
43 lever block 3 ton Vital or Elephan ea
44 lever block 1.5 ton Vital or Elephan ea
Page 8 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
45 lever block 1 ton Vital or Elephan ea
46 pin 3/4" x 5" ea
47 Eagle Clamp 1 ton Crosby , Elephan ea
48 Eagle Clamp 2 ton Crosby , Elephan ea
49 Eagle Clamp 3 ton Crosby , Elephan ea
50 Eagle Clamp 5 ton Crosby , Elephan ea
K - COMMON TOOLS :1 Hammer Steel 1-2 kg Ea.
2 Hammer Steel / Palu 2-5 kg Ea.
3 Hammer Steel / Palu Bronze 5-10 kg Ea.
4 Cutting Pliers / Tang potong 7" Ea.
5 Combination Pliers / Tang 8" Ea.
6 Long Nose Pliers 6" Ea.
7 Eclipse Driver / Obeng - 3.2 mm Ea.
8 Eclipse Driver + 3.2 mm Ea.
9 Eclipse Driver - 6 mm Ea.
10 Eclipse Driver + 6 mm Ea.
11 Hacksaw / Gergaji besi 12" Ea.
12 Hand Tool Box 3 Layer Ea.
13 Spectrum analizer Ea.
14 Tube expander lot
15 Aluminium Ladder Size 2 X 4 Mtr Ea.
GRAND TOTAL
Prepared by, ( TOP ==> Term Of Payment )
Checked by,
Page 9 of 17
Project : KALTIM-5 PROJECT. BONTANG, EAST KALAMANTAN Revisi : 0Job No : T-5099Title of Work : Piping Aboveground Work AMMONIA ( P1A & P1B )Name of Bidde : PT. Truba Jaya Engineering
MATERIAL REQUISITION PLAN ( MRP )PERIODE : JUNE up to NOVEMBER 2013 ( 6 MONTH )
NO DESCRIPTION SIZE / BRAND QUANTITY UNIT PRICE TOTAL AMOUNT REMARKS
Volume Unit TOP 30 Days TOP 45 60 Days TOP 30 Days TOP 45 60 Days
Approved by,
17 single pulley block 3 ton Kondo ea 1,700,000 ea Kondo
18 single pulley block 1,5 ton Kondo ea 800,000 ea Kondo
19 wire rope dia 22mm Kiswire roll @ 800 m 72,000 Kiswire roll @ 800 m Kiswire
20 wire rope dia 20mm Kiswire roll @ 200 m 60,000 Kiswire roll @ 200 m Kiswire
21 wire rope dia 10mm Kiswire roll @ 200 m 24,000 Kiswire roll @ 200 m Kiswire
22 wire rope dia 14mm Kiswire roll @ 200 m 34,000 Kiswire roll @ 200 m Kiswire
23 wire rope dia 12mm Kiswire roll @ 200 m 29,000 Kiswire roll @ 200 m Kiswire
24 wire rope dia 9mm Kiswire roll @ 200 m 21,000 Kiswire roll @ 200 m Kiswire
25 sling wire dia 65mm Kiswire roll @ 16 m Kiswire roll @ 16 m Kiswire
26 sling wire dia 50mm Kiswire roll @ 25 m Kiswire roll @ 25 m Kiswire
27 sling wire dia 38mm Kiswire roll @ 12 m 198,000 Kiswire roll @ 12 m Kiswire
28 sling wire dia 38mm Kiswire roll @ 10 m 198,000 Kiswire roll @ 10 m Kiswire
29 sling wire dia 38mm Kiswire roll @ 2 m 198,000 Kiswire roll @ 2 m Kiswire
30 sling wire dia 34mm Kiswire roll @ 15 m Kiswire roll @ 15 m Kiswire
31 sling wire dia 24mm Kiswire roll @ 10 m 84,000 Kiswire roll @ 10 m Kiswire
32 sling wire 10 m Kiswire ea 24,000 Kiswire ea Kiswire
33 sling wire 12 m Kiswire ea 29,000 Kiswire ea Kiswire