Top Banner
SIKA AT WORK MOUNT ALBERT RESERVOIR WATERPROOFING: SIKA SARNAFIL ®
2

Mount Albert Reservoir Project Reference - Sika New Zealand · 2020-07-07 · MOUNT ALBERT RESERVOIR CHALLENGES The replacement of the earth fill both from the point of view of potential

Aug 11, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Mount Albert Reservoir Project Reference - Sika New Zealand · 2020-07-07 · MOUNT ALBERT RESERVOIR CHALLENGES The replacement of the earth fill both from the point of view of potential

SIKA AT WORKMOUNT ALBERT RESERVOIR WATERPROOFING: SIKA SARNAFIL®

Page 2: Mount Albert Reservoir Project Reference - Sika New Zealand · 2020-07-07 · MOUNT ALBERT RESERVOIR CHALLENGES The replacement of the earth fill both from the point of view of potential

© S

ika

(NZ)

Lim

ited

/ 12

.05.

2017

Sika (NZ) LTDPO BOX 19192Avondale, Auckland 1746New Zealand

ContactPhone 0800 745 269Fax 0800 745 232www.sika.co.nz

PRODUCT DESCRIPTIONThe Mt Albert Reservoir is a huge 31,500m3 water reservoir buried on the southern side of Mt Albert, a volcanic peak in Auckland City. The reservoir’s concrete roof was cracking and had roots growing through it into the drinking water tank. The roof was fully buried under the ground. This meant all grass and earth had to be removed to expose the roof. Until this was done we could not have an exact idea about the condition of the substrate.

PROJECT REQUIREMENT

The requirement was for a sheet membrane system that would be resistant to plant root growth and to prevent both dirty water and any future plant growth from penetrating the membrane

The replacement of the earth once completed could not be allowed to puncture or damage the membrane. The membrane needed to be terminated and made water tight past the construction joint between the roof and the walls

MOUNT ALBERT RESERVOIR

CHALLENGESThe replacement of the earth fill both from the point of view of potential damage and the need to get trucks on to the finished membrane to apply the new fill.

SIKA SOLUTIONSika Sarnafil® G 476-20

PROJECT SIZE6,000m2

PROJECT PARTICIPANTSMain Contractor: Watercare Services LtdSpecialist Contractor: HydroproofSika Contact: Mike O’Brien