Morning Magic - Refit
Morning Magic - Refit
Morning Magic is a Swarbrick built S&S34 launched in 1981.
She was built as a racing version with the tall rig, pilot berths
and different galley configuration to the "cruising" version. Until
May 2007 as far as we know, she had spent her life on Pittwater
with the only apparent work done on her in that time being the
replacement of her diesel engine in 2003 and some paintwork topside
and down below. The survey carried out by Peter Kershaw late in
2006 identified a bad case of osmosis with a large number of
blisters noted. In all other respects the survey uncovered very
little of consequence in respect to construction and condition.
Obviously, as the broker, Andrew Coffey noted, the original rigging
would need replacement along with the installation of a complete
set of electronics.
I had been looking for an S&S design for some time having
made offers for a S&S36 early in 2005 and then considering the
S&S designed Catalina 38's present in numbers on the west coast
of the USA. The cost and trouble involved in getting them to
Australia made me look more closely at other local options. Morning
Magic offered me almost exactly what I was after although I would
have preferred an extra couple of feet and no osmosis. I wanted
something that was structurally sound and a motor - anything else
that could be used would be a bonus (like a serviceable mast). My
intent was to rebuild the interior, rigging, fittings and have the
hull fixed.
May 2007
The new Volvo MD2030 Sail Drive had only 35 hours on the clock
when she arrived at Yaringa ready to start the rejuvenation
process. At that point it was intended to scape the bottom, attend
to the blisters, replace all the standing rigging, install a
furler, move deck hardware to enable single hand operation,
re-wiring, provision for shore power, tidy up the interior, replace
all thru hulls and plumbing, and to think about a number of other
features such as wheel steering, pressurised hot water, shower,
etc.
Throughout May and June we began removing the accumulated junk,
crockery, sails, cushions, hull carpet, food, paint, tools, books,
... that came with the boat so that we could determine what needed
to be done.
July 2007
The hull was grit blasted to remove the gel coat, gunk and
antifoul in early July 2007 and the process of pressure washing
down the hull went on for a number of weeks. Moisture readings,
while not all that accurate provide an indication of the amount of
moisture still in the hull with noticeable increases around the
depressions where the blisters were worst. She had been out of the
water for around 7 weeks at this point and will be moved inside to
dry out. Once dry, epoxy or more correctly vinyl ester GRP will be
applied to the depressions. The important aspect here is that the
hull must be completely dry before work commences. Already (later
in July) the moisture readings have reduced - to around 0.7% on
average but there are spots that are as high as 3% or more.
Topsides the readings are around 0.2 to 0.4% so I am aiming for a
consistent reading of about 0.5%. This should be achieved once she
is moved inside.
August 2007
While the hull is washed down and dries out (outside), the
interior and mast are being worked on. The mast and boom have been
stripped of all fittings and the paint removed ready for
rebuilding. Mast steps, new shrouds, halyards, fittings, etc will
be fitted with a furler. The first stage consisted of sanding back
the surface paint to the raw metal using a rotary sander at about
2500rpm with a paint stripping disk. This removed just about all
the paint apart from some of the green etching primer. The next
stage is to use an orbital sander with 80 paper to buff up the
metal. Then to hand over the mast and boom to the riggers to do
their thing.
Inside the wiring, lining and plumbing is being removed (with
some difficulty). Tables, water tanks, head, sinks are all out
ready for refurbishment. The fuel tank and a couple of the thru
hulls are trying patience but there isn't much destruction left.
New switchboard, wind, depth, log, VHF radio have been ordered and
the re-building will commence in coming weeks. New timber panelling
and a false ceiling is to be installed which will hide all the deck
hardware fittings and cabling.
I decided to try bringing her back to her original state as much
as possible in respect of the materials used in the saloon - this
means paint stripping and lots of it. Each of the partitions is to
be stripped of paint and brought back to its varnished beauty.
The wiring is also being replaced along with the installation of
shore power.
September 2007
MM is moved inside - ready for an alcohol wash and dry. The hull
moisture readings remain around 0.7% with a few spots as high as
2.2%. The mast and boom have been sanded back to the bare metal
ready for painting next week. Still having trouble with the brass
thru hull fittings which are "welded" together. They will need to
be grinded out and replaced as the hull thickness where they have
been installed is roughly half the thickness of the rest of the
hull. Besides it is mainly silicon that is providing the watertight
seal as the fittings are loose in the holes - troublesome fittings
are the head output and cockpit drain outlets.
The shrouds attached to the lower spreaders are also proving a
difficulty removing as the spindle into the end of the spreader has
corroded on both spreaders requiring expert extraction - brute
force hasn't worked. With Duncan's help we now have the mast,
speaders, boon etched primed and undercoated.
Late September - There are patches on the hull that don't seem
to be drying as rapidly as one would expect. We will try applying
some heat and the pressure washing with detergent and/or metho. The
sanding of the gelcoat has commenced at the waterline which
together with a sand all over the bottom has at least made her look
more presentable. The moisture readings have reduced with the
higher readings now under 2%. The thru hull fittings are all out
with only a couple able to be recovered. The instrument panel has
been installed together with the radios. Shore Power connector and
circuit breaker has been installed and cabling commenced.
Still to think about:-
October 2007
The hull is drying out nicely with a couple of spots that
approach 2%. Readings from inside the hull are averaging less than
0.5% however the readings taken from the outside are somewhat
higher. No idea why? The skeg and rudder average over 1%. All the
windows have been removed and the 6mm perspex is to be replaced
(existing ones have bad UV discolouration). The chrome frames,
inside and out are pitted and prices are being sought for
re-chroming. We are also considering the interior fitout with
current thinking being to re-veneer the bulkheads while using
laminate on the cabin sides and stern end.
The depressions in the hull laminate where the worst blisters
were have been ground out along with the gel coat up to the
waterline. Vinyl ester GRP has been used to fill the depressions
and the hull roughly faired. While the whole hull has not dried out
as much as I expected and there is one spot (which I can't account
for) I am not unduly concerned - the readings from inside are OK,
there has been no leakage of the matter that usually comes with
osmosis (the reddish coloured oose), the hull laminate looks good
and there is no evidence of the structure being compromised - the
hull is about 1/4 to 3/8th of an inch thick and is solid.
The mast has had its final coat of paint and is like new - now
awaiting its fittings.
Planning for the deck hardware has commenced and now includes an
anchor winch - new hatches, 2 ST sheet winches, clutches, main
sheet traveller, etc. The hull is expected to be completed by mid
November. The drying period has been around 5 months and I'm
reasonably confident that I won't get any further appreciable
improvement.
The hull is now having resin applied and a 450 gram chopped mat
then 225 gm split strand mat applied. More vinyl ester resin and an
80gm tissue layer. Sanding and fairing then a final coat of
thickened resin is to be applied. All deck hardware has been
removed and the holes in the cabin top are to be plugged. It is
likely that the topsides will need to be painted in which case a
new colour scheme has to be considered.
November 2007
Hull liner has been ordered along with laminate for the interior
windows section and stern end of the saloon. Existing winches which
will be relocated, have been cleaned and put back together ready
for installation. The 2.7mm laminate is being used to replace the
plywood used along the cabin sides where the windows are located
and at the stern end of the saloon. The ply in parts had started to
degrade particularly where water had seeped in around the cockpit
compass and log.
The mast, standing and running rigging and deck hardware is
expected to cost upward of $20k. Hatches, mast steps, some of the
deck hardware has arrived. Work on the rigging will commence in a
fortnight. The deck and cabin top is to be painted before
installing the deck hardware.
December 2007
The fibreglassing of the hull is now complete. All that remains
is final fairing and a coat of paint. Work has commenced on the
repainting of the deck with the stripping of the beige enamel paint
from the original blue paintwork.
The internal laminate has been cut to rough size but required
the preparation of templates as there doesn't appear to be a 90
degree angle anywhere in the boat. I'm still unsure whether to
install the panels without the windows cut, cut the windows to
approx size then install or try to accurately cut the windows then
struggle with aligning the panels. The contact glue would suggest
the second option then use a router to trim the window cutouts to
size. Down below still looks a mess! -
GHD Studios have been busy with the job of removing the enamel
paint using wire brushes and masking all the remaining fittings
ready for painting next week. All holes and blemishes have been
filled and a recess for the sounder transducer created.
Windows replacement
Plumbing
Conduits for mast cabling
Deck Hardware
Dodger
Instrument Panel (wind, log, depth)
Pedestal Steering
Hatch replacements
Hull Lining
Shower and Head reinstallation
New Thru Hulls
Pressure Water
Hot Water
Recommended services -
Survey by Peter Kershaw (02 9918 9289)
Hull work on MM is being undertaken by GHD Studios at Yaringa
(Chris Holloway 5977 4434).
Spars, rigging and deck hardware by Superior Spars & Rigging
(Duncan & Linda Sandell 5977 3991)
Road transport by Ken Johnson Boat Haulage (0428 568 367)
Sail work by David Ryan of Ryan Sails (5977 4988)
Yacht brokerage - Andrew Coffey at the Quays, Church Point
Pittwater - reputable and honest. 9986 0040
Topsides with the masking almost finished.
Recess cut into bow about 3' from the keel for the sounder.
December 2007 continued
And finally some progress on the down below areas I have been
concentrating on. The first of the interior panels have been
installed.
Undercoating of the deck, locker covers and assorted topside
features has been completed along with the finished coat of a navy
blue band (masked in the photo) along the cabin sides. The final
coats will be applied this week.
The cradle supports for the hull have been relocated to allow
the final glassing of the hull - note that all thru hull openings
have also been glassed over. This photo shows the head outlet and
washbasin outlet. There are a total of 3 one and a half inch and 3
three quarter inch fittings along with the log and depth holes.
The final coats of topsides paint has been applied and masking
removed - starting to take shape at last. The brightwork when
installed - window frames, winches, clutches, etc will lift the
navy stripe and contrasting off white deck. Sun glare from the deck
may be a problem initially but the more white than cream deck will
soften with time. Two more sections of inside laminate have been
installed with 4 more to go. Hatches, windows, deck hardware are
now expected to be installed in early January. At that point she
will be ready to be moved out of the shed and antifouled.
At this stage the professional painting, osmosis treatment and
hull restoration by GHD Studios is expected to cost $9500 plus
"extras" (patching, depth sounder transducer mount, etc). The
anchor winch, ST winches, mast steps, Profurl furler, 2 Lewmar
hatches, 4 triple clutches and deck organisers have all been
sourced locally through Superior Spars. Purchasing direct from USA
and elsewhere would likely have made some savings.
January 2008
Recommended services -
Hull work on MM is being undertaken by GHD Studios at Yaringa
(Chris Holloway 5977 4434).
Spars, rigging and deck hardware by Superior Spars & Rigging
(Duncan & Linda Sandell 5977 3991)
Sail work by David Ryan of Ryan Sails (5977 4988)
The mast has now had its steps installed and is awaiting conduit
and cabling, light fittings, etc.
Painted cockpit. The next major tasks to be attempted in January
after the joinery and hull work is complete is the plumbing and
electrical work. I have decided to install a head holding tank and
Y switch now rather than wait until it becomes regulated. Finding a
place for the tank is not easy even a 50 lt flexible one. Under the
V berth and lose valuable sail storage space or under the divan
next to the SS water tank?
Valuable assistance and advice has been received from members of
the S&S34 Association based in Perth especially Simon
Torvaldsen who is building a brand new S&S34 from the same
moulds that Morning Magic was derived.
see http://www.ss34.org
The deck hardware is being prepared for installation now that
the topsides are complete and the internal panelling installed. The
sections of 2.7mm laminate were glued in place then trimmed using a
router (using the window openings as the guide). The joins will be
covered with wood trim.
The window frames and perspex are ready for installation when
slightly longer screws are obtained - they will look something like
the above. The hull meanwhile is waiting on a final covering of
"gunk" as it is described and an undercoat before the antifoul.
Above the waterline should come up with a polish only. There are
a few small chips in the stern which will need patching but other
than that the hull will soon be finished ready for the thru hull
installations and plumbing.
February 2008
Progress has slowed again due to my work commitments and changes
in ownership of Superior Spars - we are now waiting on Craig to
start putting the final touches to the deck hardware and mast. In
the meantime the hull is 2 undercoats off antifoul.
The last of the major hardware expenses - 2 self tailing ST50
Arco winches have arrived. I intend using 2 of the Barlow halyard
winches removed from the cabin top for spinnaker winches.
.
.
.
.
.
.
.
.
.
.
Applying the "gunk" prior to final fairing and painting.
.
HoldingTank from WRENGCO tanks
Assistance from the Yacht Doctor - Joe Tarantino 0400 156
390
Painting by Bruce (GHD Studios)
- So far - about 2 months later than expected and pobably $8k
over budget and climbing (there was no intention of stripping the
interior, providing anchor winches, re-painting topsides,
re-chroming fittings, total re-wiring and replumbing, etc when the
budget was formulated).
February 2008 -
Nearing the end of the hull work - a light sand and the fitting
of the thru hull fittings then a wait until the final undercoat
followed by antifoul within 12 hours.
Interior also slowly taking shape with slowly the operative
word. People who should know have told me that it won't be finished
on my schedule - I'm sure it would have if I had the time. A few
hours a week is not enough. The laminate is completed and the
window frames in place (not yet sealed and mounted permanently) and
the rear hatch mount prepared (require enlarging the opening in the
cabin roof by about 6 inches).
The cable dangling through the ceiling is the power cable for
the instruments. Teak veneer has been ordered and should be applied
in 4 or 5 weeks and then the trim can be fixed. The photo below
gives and idea of what the coachroof will look like with windows in
place. Sikkens oiling of the grab rails, toe rail and hatch
surrounds just completed along with bulkhead compass mounting.
March 2008
And now for another major decision - the above waterline
paintwork (which I thought was gelcoat) has apparently already been
painted. My intention was to buff up the hull and that's about all.
However, we have found that the paint is patchy in places and with
a little rubbing the top coat will rub off leaving undercoat
exposed. The decision is either to leave it for 18 months and then
have it painted or spend the money now - there goes a new main
sail!
Decision made - Morning Magic is to become a blue hull with
white trim and waterline. Wrong again! The hull is not as uniform
as I'd thought and my expert painter (Bruce) convinced me that a
navy blue gloss will show up the hull imperfections - better to
stick with the off white rather than torture board significant
areas of the hull. So the hull will be off white (with navy trim,
waterline and maybe some additional stripes).
Hull preparations for painting.
April 2008
Olin's birthday is rapidly approaching and there is now no
chance of getting near the water before May or June. The above
waterline has been primed and with a few hours sanding is almost
ready for the top coat. Delays again due to illness and work
priorities has meant that no work has been possible for the last
few weeks.
After pumping out over 80 litres of diesel from the fuel tank we
finally got the tank out from under the port divan and sure enough
a small hole was discovered in the seam. The tank is now with
Superior Masts & Rigging to be fixed. A LCD TV and new electric
head have been purchased and the framework commenced in the port
pilot berth to construct bookcases, storage and mounting for the
TV. The starboard pilot berth will remain as a berth. Happy
birthday Olin!
Shiny new paintwork - awaiting boot and cove line, final hull
primer, skin fittings and antifoul by end of month.
With Joe Tarantino's help the skin fittings, tranducer and log
are now installed (difficult to be both inside and outside the hull
at the same time). The fuel tank has been repaired and pressure
tested although I don't expect too many years service (4 holes
being repaired).
May 2008 -
Interior painting has now been finished along with sea cock
installation. The new bow fitting is being fabricated along with
the mast collar. Apart from misplacing halyard fittings and the
mast base the rigging is going well. Inside the teak veneer is
ready for installation. The genoa winches have been removed ready
for mounting the new Arco ST50 self tailing winches
New bow fitting with dual anchor roller
15 1200mm lengths of teak veneer is in the process of being
applied inside. Outside the bottom has had its final sand ready for
the final undercoat and antifoul.
Old and new mast collar awaiting the fitting of halyard
blocks.
Plastic holding tank made to measure. Inlet and vent connections
shown. Outlet is in the bottom on the right side. Expecting to take
the waste from the Jabsco electric toilet to the tank inlet (above
waterline) while the output goes to a Y valve to select discharge
or pump out.
The tank will be secured behind a panel with an inspection
port.
The cove strip has now been added.
June 2008 -
It's now 14 June and while she was ready to emerge from the shed
it hasn't quite happened. Small matter of no winches to strap her
onto the cradle.
That was last week - this week the new winches are fitted
(including the spinnaker winches) but still in the shed. Should be
released in a couple of days.
And finally the first coat of antifoul -
Now that we are outside things are progressing - the mast is to
be stepped on Thursday 3/7/08. Interior lacquering is complete and
have started on the hull liner.
July 2008 -
In the meantime, wiring and construction of a bookcase and mount
for a LCD TV proceeds. The photo below gives an idea of how the
teak has come up on the bulkheads.
Morning Magic about to emerge from the shed 4 June 2008.
We are on the move!!! 18 June 2008. The mast is also finished
and ready to be stepped. Looks beautiful thanks to Lisa, Craig and
Matt. Joe has also finished the head plumbing.
Wiring and cabling is well on the way. Expect to be back in the
water around the end of July or August 2008.
The mast went up a day late but what's a day in 400? More
cabling, joinery for the battery and anchor winch, more hull
lining, and mucking about. Cables from the mast have been run.
Rather than run cables loosely through the hull I have elected to
use the square and rectangular profile conduit. On the starboard
side I have the transducer cables (log, depth and wind from the
mast) with mast lighting, cabin lighting, speaker. On the port side
I have a larger rectangular profile containing high current cables
for paralleling/charging the forward battery, lighting, speaker,
12v outlets, emergency nav lights. Under floor the VHF arial cable
and 12v for bilge pump and water pump. Through the ceiling (when
I've worked out what to do about lining) will be some lighting and
power for the instruments.
The boot stripe is also now on.
Safety lines are currently being replaced and internal potable
water and waste plumbing commenced. A couple of leaks around window
screws to be attended to and the mass of wires brought back to the
switchboard now ready for terminating. The switchboard panel (with
VHF, CD radio, Volvo controls) needs to be able to be removed as a
unit so all cabling is being terminated in plug/sockets.
We now have a tentative arrangement for re-launching - in the
week commencing 11 August. The date is determined by my painter
Bruce, from GHD Studios, having a couple of weeks leave then
allowing 2 weeks for suitable days weather wise to polish and apply
the final antifoul.
By that time we should have a new bilge pump operating and the
wiring/plumbing completed. Unfortunately Joe Tarantino isn't well
and that has slowed internal plumbing and fitout. I'm wishing Joe
all the best.
Craig and Matt have been busy with safety line replacement, deck
fittings (clutches, winches, organisers), finishing the anchor
winch and aligning the mast. Cabling termininations are proceeding
along with hull lining and reinstallation of cushions.
August 2008 -
Work continues rather slowly - the hull has now been polished
and the Sail Drive leg antifouled. All is now in readiness for the
final antifoul and launching. We have still much to do below and a
few more items like the blocks and jib sheet cars on deck. The main
sheet traveller is also being replaced.
A possible solution to the ceiling headlining has been found -
more about that later. The 240v shore power is complete but the 12v
terminating is continuing along with last minute cable runs. The
construction of the bookcases is almost complete while I am about
to start on the forward battery and joinery in the V berth.
Hot water looks like being delayed so the plumbing will be
confined to cold water at this point. A Jabasco pump and
accumulator has been installed for pressurised water. The Plastimo
stove & oven has been sitting in my office for months now -
almost time to start that installation too.
A new phase commences - on the water.
Polished up & ready for the water.
Launched - 4pm 6 August 2008
Supreme Marine are to complete the service on the Volvo Sail
Drive this week. Once I finish the electrics and the fuel leak we
will be able to take her out for some motorised sea trials.
David Ryan has been examining the current complement of sails -
maybe another season in the main, genoa can't be adapted to the
furler so looking at No 2 and 3 to see if there is any life left in
them. Longer term he will fabricate a new main and genoa.
Bruce Marsom from GHD Studios did an excellent job on Morning
Magic's paint work. She certainly looks like a new boat which is
not that far from fact. Craig and Matt from Superior Masts and
Spars also performed brilliantly to get the rigging sorted out.
Again, the only things not touched were the stauntions and
pushpit.
***
The rigging has been adjusted, mast top fittings in place (VHF,
anometer, windex), radar reflector and halyards run so she is
starting to look like she could do some sailing. Down below the
wiring continues along with installing the auto bilge pump.
Purchased the superceded ST4000 from Bob Clow which on first glance
fits perfectly on the cockpit locker side of the cockpit.
One problem has re-surfaced. I had thought that my diesel leak
was due to tank corrosion but after having it repaired and pressure
tested and 50lt of diesel loaded I find there is fuel in the bunded
area. Damn - it turns out to be the only piece of hose I haven't
replaced - the feed pipe to the tank has a crack where it enters
the tank and in spite of my double hose clips it leaks!
More hose replacement of the type I had so much trouble with
replacing the cockpit drains.
September 2008 -
Not a lot to report - very slow finishing off the wiring and
internals. The motor service hasn't happened yet as a result of my
slowness in finishing the electrics.
Small jobs being finished off. Sisalation fitted to the cabin
ceiling in preparation for the lining. Most jobs need doing two or
three times before I get them right. Forward ventilator now doesn't
leak but the fuel leak is still there! Maybe it wasn't the hose.
More investigation needed.
Costs continue to rise as bills are finalised for hull and
rigging refurbishment but should slow appreciably now - costs to
date all up around $112,500 but this includes insurance, TV,
survey, slipping, transport from Pittwater, etc, etc.
The only appreciable costs remaining are a couple of new sails
and dodger.
October 2008 -
The 30 hour service on the Volvo is complete so we are nearing
sea trials. A bit more wiring and plumbing to go. The TV and now
the stove has been mounted but gas plumbing still outstanding.
Started in the forward berth where a 3rd battery is to be installed
to power the anchor winch and toilet. The foreberth hull liner is
next to go on.
Ceiling liner
Galley with sinks installed
Head holding tank and Y valve access
Electronics supplied and advice provided by Bob Clow of Clow
Marine Electronics
Dodger by Jason of Peninsula Marine Covers
Rigging, stainless steel work and hardware supplied through
Superior Masts and Rigging - Craig, Matt and Lisa.
Volvo serviced by Justin of Supreme Marine.
The deisel leak is interesting in that it gets to a level and
doesn't go any further which indicates the leak to be higher in the
tank. Foreward liner cut to size and teak toerail received a long
overdue coat of Sikens.
Jason from Mermaid Marine Covers has set up the frame for the
dodger and finalised the design so we will have a nice new navy
blue addition before long. The forward liner is installed and the
ceiling tacked in place - the sisalation coupled with the felt
backing of the ceiling mat has made a noticeable impact on heat in
the saloon. Still haven't finished wiring but with the purchase of
a new battery or two that should speed up. Also need to source a
gas tank and plumber to install the oven.
Installed two GEL 100AH 700CCA batteries and a voltage sensitive
relay, finished off the ceiling (almost), fitting trim here and
there.
November -
David Ryan (sailmaker) has examined all the sails and we have
decided on a new genoa and main but in the meantime he is going to
adapt the No2 jib for the furler with UV strip, etc. The No4 jib is
still in excellent condition so it will be adapted as well. The
storm sail and storm trysail are also in good condition apart from
the corroded rings which he is going to replace. The drifter is
also useable after he replaces one of the rings so we will have a
spare main and a genoa that is too light to be of much use.
Back inside I found that I am short a couple of cables from the
forepeak back to the cockpit for the anchor winch! At least now
I've checked all the circuits and have all nav lights (and
emergency nav), cabin leds, pumps, radios and instumentation
operating. And the motor reliably starts and stops.
Plumbing to the head will be the next challenge while trying to
avoid more holes than are absolutely necessary to feed the hoses.
Hot water not yet resolved.
And the new dodger.
December 2008 -
With a name and registration number. Not long now. Awaiting some
sails and a hot water service (probably delay further). We now have
27m of L type 8mm SC chain on the anchor winch. Wiring still not
completed.
More wiring to a solar panel but forward winch & head still
to be wired along with the voltage sensitive relay between the
batteries.
Our old sails have been repaired by David Ryan Sails and are now
on board - we should get a season out of them until the new furling
No 1 and main are finished. The No 2 has been converted for furling
with an UV strip in the meantime. The trisail and storm jib are
still serviceable and a No 3 put away. I was able to recover
various blocks so the main sheet is now working and a bit more
mucking about with the vang blocks should result in a yacht that
can sail (at least in Western Port - no Sydney to Hobart yet).
The water heater mounts are being prepared behind the engine
between the rudder stock and engine exhaust. We purchased a 25lt
Kuuma heater which, with mm to spare, just fits into the cockpit
locker - then hopefully through into its home position.
A door between the saloon and head has been constructed and
fitted (numerous times) and is getting close to being the correct
size. The problems again are the numerous curves involved.
***
January 2009 -
Strong points in the cockpit, water heater fitted, cockpit
anchor winch switch fitted, halyard tidies installed, saloon door
fitted - awfully close now. Lazy jacks, jack stays, finish plumbing
and electrical work still to go.
15 January 2009 after 20 long months of effort we are sailing
again.
We've now had a second outing this time with First Mate on
board. Everything worked to her satisfaction so I've managed to get
through my first exam.
***
February 2009 -
Work continues on the water heater, plumbing and electrics while
waiting on sails. There is the matter of cabin trim that I've also
been putting off and the laminex in the head that remains
unfinished.
Almost completed galley.
Plumbing nearly completed - pressurised water OK except for a
connection on the galley flick mixer - it leaks. Hint - don't
disconnect hoses with the system pressurised. Open the taps
beforehand! Otherwise get wet.
Shakedown - LAUNCHED
With a 20 knot breeze, a 25 year old mainsail, No 2 headsail we
could still manage around 9 knots over ground (a couple of knot
tide helps). A very happy skipper (after a nervous start - I was
more concerned about getting in and out of the pen without
scratches and embarassments). As it turned out MM handled
beautifully in reverse, forward, under power or sail.
Thanks to all who worked on her to bring her back to what most
onlookers think is a new boat.
Wiring of the anchor winch and toilet near enough to complete -
continuing with the plumbing which is still a few days away.
Various pieces of trim to be installed - aiming for an April
completion. Craig has fitted a beautifully crafted gas bottle
holder on the stern and we now have a whisker pole on board.
Water heater installed (conduit to be fastened and engine
heating to be connected). In respect of the latter after reading
the volvo manual it says something about being a closed system -
maybe no engine heating! More research.
Still a few leaks in the pressurised water to be sorted. Toilet
electrics now finished but winch yet to be tested. Permanent 500W
invertor has been installed and some fine tuning of the
switchboard. The hot water connection to the motor is now resolved
after noticing a photo of a Volvo 2030D on a Bavaria34 which had
hot water - two plugs on the front of the motor is where the
takeoff and return connections are made. Also, now thinking about
an emergency crank for the motor - the flywheel looks like it takes
one but there has to be a decompression release somewhere on the
engine.
March 2009 -
Canvas hatch covers have now been installed, winch tested and
quarter berth opening port installed. Finally some rain in
Melbourne - lots of leaks. couple of the windows, multiple spots
around hatches. Re-tightened all window screws, and a bit of epoxy
here and there overcame the majority. Fitted the locker doors in
the head. Checked oven and grill on the stove.