Ass et Man Asset Management Group (Wasl) File: Cover Created: 07-Apr-12 Printed on 05/07/2012 at 08:05 June-2012 Al Muraqqabat Mixed Use Development Monthly Progress Report 003 07-May-12 004 07-Jun-12 005 07-Jul-12 Monthly Project Progress Sameh Kandil Monthly Project Progress Monthly Project Progress REV. DATE Printed names here confirm that the document has been signed off approved, the original held by Document Control Regards, Raouf Ezzat REASON FOR ISSUE PREPARED CHECKED APPROVED Raouf Ezzat Project Manager File: Cover Created: 07-Apr-12 Printed on 05/07/2012 at 08:05
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Asset Man
Asset Management Group (Wasl)
File: CoverCreated: 07-Apr-12Printed on 05/07/2012 at 08:05
June-2012
Al Muraqqabat Mixed Use Development
Monthly Progress Report
003 07-May-12
004 07-Jun-12
005 07-Jul-12
Monthly Project Progress Sameh Kandil
Monthly Project Progress
Monthly Project Progress
REV. DATE
Printed names here confirm that the document has been signed off approved, the original held by Document Control
Regards,
Raouf Ezzat
REASON FOR ISSUE PREPARED CHECKED APPROVED
Raouf EzzatProject Manager
File: CoverCreated: 07-Apr-12Printed on 05/07/2012 at 08:05
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
1.0 Table of Contents
2.0 PROJECT STATUS SUMMARY ....................................................................................................... 2
6.0 PROJECT PROGRAM UPDATE ..................................................................................................... 6
6.1 COMPLETED & IN PROGRESS ACTIVITIES ............................................................................................ 6 6.2 PACKGE PLANNED VS ACTUAL PERCENTAGES .................................................................................... 6 6.3 TWO MONTHS LOOKAHEAD PROGRAM ................................................................................................ 6
7.1 CIVIL AND ARCHITECTURAL LOG .......................................................................................................... 7 7.2 MEP AND SPECIALITY WORKS LOG .................................................................................................... 7
9.1 HSE PROGRESS STATUS .................................................................................................................. 9 9.2 MANHOURS AND FIRST AID HISTOGRAM.............................................................................................. 9
Any comments, questions, or concerns regarding this Status Report or the project in general should be directed to (Raouf Ezzat / Sameh Kandil, [email protected] / Sameh. [email protected])
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
2.0 PROJECT STATUS SUMMARY
Project Title : Al Muraqqabat Mixed Use Development Project No. : 269Location : Report No : 5Client : Asset Management Group (WASL) Period Ending : 30-Jun-12
1.0- Safety This Period Previous To DateN/A N/A N/A
151,580 479,090 630,670 / / /
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Monthly Report No.05 - June-2012
Dubai
N MiMonthly Report No - 05 (Up to 30-June-11)Lost Time Injury (LTI)
N/A N/A N/A
2.0-Quality NCR Status Issued by Client Internal Audits OperationalIssued by Suppliers
Issued by Subcontractor
Issued 8 - - - -Closed 7 - - - -Open 1 - - - -
* Safety figures are for Workers and Staff Manpower.
3.0- Executive Summary
Contract TypeContract Duration
Near Misses
Contract Value (AED)
Details
285,000,000 Lump Sum640 Days
This Period To Date4 0- Progress
Commencement Date as per Contract
1729310Activities Remaining to Start
% Time Elapsed
Completion date as per Contract
Activities in Progress
15-Feb-1215-Nov-13
10355873
Calendar Days ElapsedCalendar Days Remaining
13750321%
Activities Completed
Revise Completion date as per Approved EOTExpected Completion DateTotal Calendar Days (Contractual Duration)
Nil01-Feb-14
640
% Time RemainingTotal Number of Activities
79%
Planned Actual Planned Actual3.77% 2.88% 12.78% 13.54%
Staff Workers (Direct)Planned Actual Planned Actual
ASGC (Up to 30-June-12) 24 25 311 414
Total 25 414Change in Period
44 108
4.0- Progress
5.0- Manpower
Calculated Percentage
* The Planned Progress Percentage has been developed based on the Approved Program Rev.01 assigning a weight to each activity in the schedule.
AWI 205 Att. 1 Rev. 6 24 Oct. 2010 Page 1 of 2
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Monthly Report No.05 - June-2012
6.0- Significant Events 6.01-This Period:
Block A
1. Third floor slab works was casted on 18-June-2012.2. Works for fourth floor slab was started on 24-June-2012.3. Block works were started in B2,B1,Ground and first floor.4 Plaster works were started in B2
Construction
Block B
Block C
C1
C2
4. Plaster works were started in B2.
1. Columns from basement 1 to ground floor was completed.2. 1st floor slab was casted on 13-June-2012.3. Columns works,from ground to 1st floor, were started on 24-June-2012.4. Block works were started in B2.
1. 1st floor slab was casted on 30-June-2012.2. Curing work is in progress.
1. 1st floor Slab was casted on 25-June-2012.2. Columns and core walls works from ground to 1st floor were started on 28-June-2012.3. Block works were started in B2.
6.02- Areas of Concern - Late of issuing the ID drawings (IFC) and the conflict between Arch,MEP and ID
drawings.Furthermore a revised electrical load schedule was issued in June-2012.All of these delays and conflict will dramatically affect :-1- Submission the light and power drawings which are related to the approvals process to obtain the Wild Air.2- Procurement of electrical long lead items
AWI 205 Att. 1 Rev. 6 24 Oct. 2010 Page 2 of 2
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
3.0 PROJECT DASH BOARD
Al Muraqqabat Mixed Use DevelopmentProject DashboardMonthly Progress Report No. 5
GENERAL INFORMATION
June
30 2012
P ‐ 269 ‐ PROGRESS SUMMARYStatus at 30 June 2012
File Name :-Progress Dashboard Page 1 of 5 Printed On :- 05/07/2012 at 09:30
Company Contact Baseline Completion DateForecast Completion Date Last Month
Mohammed Viquarrddin/Ali Al Khateeb Forecast Date at Current MonthVariance Days (Calendar Days)
Progress by Discipline%Pld %Act %Pld %Act
1.00 100.00% 3.77% 2.88% 12.78% 13.54% 0.8%1.10 General 2% 3.02% 2.37% 31.32% 21.51% ‐9.8%1.20 Engineering 4% 11.58% 12.49% 53.22% 37.70% ‐15.5%1.30 Procurement 6% 11.31% 3.03% 29.69% 10.28% ‐19.4%1.40 Construction 80% 3.20% 2.68% 10.27% 13.69% 3.4%1 50 H di O 8% 0 00% 0 00% 0 00% 0 00% 0 0%
15‐Nov‐13
d ‐ Progress of W
ork
Client WASL Abdullah Zarooni 30‐Dec‐13
Weight %This Period Cumulative
Lead Consultant Bel Yoahah 01‐Feb‐14Main Contractor ASGC Raouf Ezzat ‐78
Variance
Overall Progress
21.51%
37.70%
10.28%
13.69%
0 00%
General
Engineering
Procurement
Construction
Handing Over
Actual %
1.50 Handing Over 8% 0.00% 0.00% 0.00% 0.00% 0.0%
Weekly Project Dashb
oar
velopm
en
0.00%
56.68%
67.88%
77.84%
85.89%
89.99%
92.50%94.43%
96.54% 97.39% 98.61% 99.66%100.00%
61.43%
75.60%
85.36%90.85%
93.31%96.27% 97.19% 98.14% 99.32%
100.00%
60.00%
70.00%
80.00%
90.00%
100.00%
s % Early Monthly
Figure.1 ‐ Overall Project Progress
Al M
uraq
qaba
t Mixed
Use Dev
C
12.78%
17.07%20.93%
25.69%
33.73%
45.25%
9.33%12.41%
14.82%18.11%
22.86%
28.94%
38.11%
50.00%
13.54%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
Feb 12 Mar 12 Apr 12 May 12 Jun 12 Jul 12 Aug 12 Sep 12 Oct 12 Nov 12 Dec 12 Jan 13 Feb 13 Mar 13 Apr 13 May 13 Jun 13 Jul 13 Aug 13 Sep 13 Oct 13 Nov 13
File Name :-Progress Dashboard Page 5 of 5 Printed On :- 05/07/2012 at 09:30
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
4.0 PROJECT S-CURVE
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Overall Progress S-Curve
85 89%
89.99%
92.50%94.43%
96.54% 97.39% 98.61% 99.66%100.00%
90.85%93.31%
96.27% 97.19% 98.14%99.32%
100.00%
90.00%
100.00%
File Name : Progress S-Curve Page 1 of 1 Printed On : 05/07/2012 at 09:05
% Accu. Actual 0.80% 3.95% 7.59% 10.66% 13.54%Actual
File Name : Progress S-Curve Page 1 of 1 Printed On : 05/07/2012 at 09:05
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
5.0 CONCRETE HISTOGRAM
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Actual Monthly 3,129.50 7,774.50 6,396.50 4,531.50 4,206.0
Accu. Actual 3,129.50 10,904.00 17,300.50 21,832.00 26,038.00
Early Planned
Late Planned
Actual
File Name : Commodoties Progress Page 1 of 1 Printed On : 05/07/2012 at 08:22
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
6.0 PROJECT PROGRAM UPDATE
6.1 COMPLETED & IN PROGRESS ACTIRIVITES
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
Al MuraqqAl Muraqqabat Mixed Use Development 597 06-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 75.14% 93.12%
GeneralGeneral 25 15-Feb-12 A 22-Mar-12 A 15-Feb-12 14-Mar-12 15-Feb-12 02-Apr-12 100% 100%
SubmissionSubmission 9 15-Feb-12 A 25-Feb-12 A 15-Feb-12 25-Feb-12 15-Feb-12 13-Mar-12 100% 100%A46740 Submission of Excavation Level 1 15-Feb-12 A 16-Feb-12 A 15-Feb-12 15-Feb-12 15-Feb-12 15-Feb-12 0 100% 100%
A46750 Submission of Water Proofing Details 2 15-Feb-12 A 20-Feb-12 A 15-Feb-12 16-Feb-12 19-Feb-12 20-Feb-12 3 100% 100%
A46760 Submission of Tower Crane Layout 7 18-Feb-12 A 25-Feb-12 A 18-Feb-12 25-Feb-12 06-Mar-12 13-Mar-12 15 100% 100%
A46770 Submission of Raft Construction Joint Layout 2 15-Feb-12 A 16-Feb-12 A 15-Feb-12 16-Feb-12 20-Feb-12 21-Feb-12 4 100% 100%
A46780 Submission of Retaining Wall Joint Layout 4 15-Feb-12 A 19-Feb-12 A 15-Feb-12 19-Feb-12 22-Feb-12 26-Feb-12 6 100% 100%ApprovalApproval 20 16-Feb-12 A 22-Mar-12 A 16-Feb-12 14-Mar-12 16-Feb-12 02-Apr-12 100% 100%A117180 Approval of Excavation Level 1 16-Feb-12 A 22-Feb-12 A 16-Feb-12 16-Feb-12 16-Feb-12 16-Feb-12 0 100% 100%
A117190 Approval of Water Proofing Details 2 19-Feb-12 A 22-Mar-12 A 19-Feb-12 20-Feb-12 21-Feb-12 22-Feb-12 2 100% 100%
A117200 Approval of Tower Crane Layout 14 26-Feb-12 A 14-Mar-12 A 26-Feb-12 14-Mar-12 14-Mar-12 02-Apr-12 13 100% 100%
A117210 Approval of Raft Construction Joint Layout 2 19-Feb-12 A 10-Mar-12 A 19-Feb-12 20-Feb-12 22-Feb-12 23-Feb-12 3 100% 100%
A117220 Approval of Retaining Wall Joint Layout 12 20-Feb-12 A 18-Mar-12 A 20-Feb-12 06-Mar-12 27-Feb-12 13-Mar-12 5 100% 100%
Hotel ApartemHotel Apartements (Block A) 129 15-Feb-12 A 30-Aug-12 153 15-Feb-12 21-Oct-12 16-Feb-12 21-Mar-13 61.51% 92.52%
Deep FoundDeep Foundation 7 15-Feb-12 A 22-Feb-12 A 15-Feb-12 23-Feb-12 16-Feb-12 23-Feb-12 100% 100%SubmissionSubmission 2 15-Feb-12 A 15-Feb-12 A 15-Feb-12 16-Feb-12 16-Feb-12 18-Feb-12 100% 100%A46720 Submission of Structural Dwgs. for Raft 2 15-Feb-12 A 15-Feb-12 A 15-Feb-12 16-Feb-12 16-Feb-12 18-Feb-12 1 100% 100%
ApprovalApproval 5 16-Feb-12 A 22-Feb-12 A 19-Feb-12 23-Feb-12 19-Feb-12 23-Feb-12 100% 100%A46730 Approval of Structural Dwgs. for Raft 5 16-Feb-12 A 22-Feb-12 A 19-Feb-12 23-Feb-12 19-Feb-12 23-Feb-12 0 100% 100%
1st Baseme1st Basement Floor Slab 37 15-Feb-12 A 18-Mar-12 A 19-Feb-12 25-Apr-12 20-Feb-12 14-Oct-12 100% 100%SubmissionSubmission 34 15-Feb-12 A 20-Feb-12 A 19-Feb-12 05-Apr-12 20-Feb-12 24-Sep-12 100% 100%A101060 Submission of Structural Dwgs. for Slab 3 15-Feb-12 A 20-Feb-12 A 23-Feb-12 26-Feb-12 23-Feb-12 26-Feb-12 0 100% 100%
A101070 Submission of Structural Dwgs. for Ret. Walls -Columns 3 15-Feb-12 A 15-Feb-12 A 19-Feb-12 21-Feb-12 20-Feb-12 22-Feb-12 1 100% 100%
A101080 Submission of Structural Dwgs. for Core Walls 2 15-Feb-12 A 15-Feb-12 A 23-Feb-12 25-Feb-12 27-Feb-12 28-Feb-12 3 100% 100%
A101090 Submission of Structural Dwgs. for Ramp 3 15-Feb-12 A 15-Feb-12 A 19-Feb-12 21-Feb-12 11-Mar-12 13-Mar-12 18 100% 100%
A101140 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 29-Mar-12 05-Apr-12 17-Sep-12 24-Sep-12 144 100% 100%ApprovalApproval 22 16-Feb-12 A 18-Mar-12 A 22-Feb-12 25-Apr-12 27-Feb-12 14-Oct-12 100% 100%A101100 Approval of Structural Dwgs. for Slab 14 21-Feb-12 A 18-Mar-12 A 27-Feb-12 15-Mar-12 27-Feb-12 15-Mar-12 0 100% 100%
A101110 Approval of Structural Dwgs. for Ret. Walls -Columns 10 16-Feb-12 A 16-Feb-12 A 22-Feb-12 06-Mar-12 29-Feb-12 13-Mar-12 5 100% 100%
A101120 Approval of Structural Dwgs. for Core Walls 10 16-Feb-12 A 29-Feb-12 A 26-Feb-12 08-Mar-12 29-Feb-12 13-Mar-12 3 100% 100%
A101130 Approval of Structural Dwgs. for Ramp 14 16-Feb-12 A 08-Mar-12 A 22-Feb-12 12-Mar-12 14-Mar-12 02-Apr-12 15 100% 100%
A101150 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 08-Mar-12 A 08-Apr-12 25-Apr-12 25-Sep-12 14-Oct-12 119 100% 100%Ground FloGround Floor Slab 38 15-Feb-12 A 27-Mar-12 A 17-Mar-12 27-May-12 17-Mar-12 17-Oct-12 100% 100%SubmissionSubmission 34 15-Feb-12 A 10-Mar-12 A 17-Mar-12 07-May-12 17-Mar-12 29-Sep-12 100% 100%A101160 Submission of Structural Dwgs. for Slab 4 15-Feb-12 A 15-Feb-12 A 26-Mar-12 29-Mar-12 27-Mar-12 31-Mar-12 1 100% 100%
A101170 Submission of Structural Dwgs. for Ret. Walls -Columns 7 21-Feb-12 A 10-Mar-12 A 17-Mar-12 24-Mar-12 17-Mar-12 24-Mar-12 0 100% 100%
A101180 Submission of Structural Dwgs. for Core Walls 7 21-Feb-12 A 10-Mar-12 A 17-Mar-12 24-Mar-12 18-Mar-12 25-Mar-12 1 100% 100%
A101240 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 30-Apr-12 07-May-12 22-Sep-12 29-Sep-12 121 100% 100%
A102200 Submission of Structural Dwgs. for Ramp 7 15-Feb-12 A 15-Feb-12 A 22-Mar-12 29-Mar-12 01-Apr-12 08-Apr-12 8 100% 100%ApprovalApproval 26 16-Feb-12 A 27-Mar-12 A 25-Mar-12 27-May-12 26-Mar-12 17-Oct-12 100% 100%A101200 Approval of Structural Dwgs. for Slab 12 16-Feb-12 A 27-Mar-12 A 01-Apr-12 16-Apr-12 01-Apr-12 16-Apr-12 0 100% 100%
A101210 Approval of Structural Dwgs. for Ret. Walls -Columns 14 13-Mar-12 A 22-Mar-12 A 25-Mar-12 11-Apr-12 26-Mar-12 12-Apr-12 1 100% 100%
A101220 Approval of Structural Dwgs. for Core Walls 14 11-Mar-12 A 19-Mar-12 A 25-Mar-12 11-Apr-12 26-Mar-12 12-Apr-12 1 100% 100%
A101250 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 08-Mar-12 A 08-May-12 27-May-12 30-Sep-12 17-Oct-12 100 100% 100%
A102210 Approval of Structural Dwgs. for Ramp 13 16-Feb-12 A 19-Mar-12 A 01-Apr-12 17-Apr-12 09-Apr-12 25-Apr-12 6 100% 100%1st Floor Sl1st Floor Slab 57 15-Feb-12 A 02-May-12 A 31-Mar-12 10-Jun-12 31-Mar-12 21-Oct-12 100% 100%SubmissionSubmission 33 15-Feb-12 A 08-Apr-12 A 31-Mar-12 21-May-12 31-Mar-12 01-Oct-12 100% 100%A101260 Submission of Structural Dwgs. for Slab 12 26-Mar-12 A 08-Apr-12 A 09-Apr-12 22-Apr-12 09-Apr-12 22-Apr-12 0 100% 100%
A101270 Submission of Structural Dwgs. for Columns 8 15-Feb-12 A 25-Feb-12 A 31-Mar-12 08-Apr-12 31-Mar-12 08-Apr-12 0 100% 100%
A101280 Submission of Structural Dwgs. for Core Walls 8 07-Mar-12 A 14-Mar-12 A 31-Mar-12 08-Apr-12 31-Mar-12 08-Apr-12 0 100% 100%
A101340 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 14-May-12 21-May-12 24-Sep-12 01-Oct-12 111 100% 100%ApprovalApproval 40 16-Feb-12 A 02-May-12 A 09-Apr-12 10-Jun-12 18-Apr-12 21-Oct-12 100% 100%A101300 Approval of Structural Dwgs. for Slab 14 09-Apr-12 A 02-May-12 A 23-Apr-12 10-May-12 23-Apr-12 10-May-12 0 100% 100%
A101310 Approval of Structural Dwgs. for Columns 14 26-Feb-12 A 05-Apr-12 A 09-Apr-12 26-Apr-12 18-Apr-12 07-May-12 7 100% 100%
A101320 Approval of Structural Dwgs. for Core Walls 14 15-Mar-12 A 27-Mar-12 A 09-Apr-12 26-Apr-12 18-Apr-12 07-May-12 7 100% 100%
A101350 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 22-May-12 10-Jun-12 02-Oct-12 21-Oct-12 92 100% 100%2nd Floor S2nd Floor Slab 73 15-Feb-12 A 22-May-12 A 21-Apr-12 05-Jul-12 21-Apr-12 01-Nov-12 94.05% 100%SubmissionSubmission 66 15-Feb-12 A 21-Apr-12 A 21-Apr-12 16-Jun-12 21-Apr-12 13-Oct-12 100% 100%A102220 Submission of Structural Dwgs. for Slab 14 03-Apr-12 A 21-Apr-12 A 05-May-12 20-May-12 05-May-12 20-May-12 0 100% 100%
A102230 Submission of Structural Dwgs. for Columns 5 06-Mar-12 A 14-Mar-12 A 21-Apr-12 25-Apr-12 21-Apr-12 25-Apr-12 0 100% 100%
A102240 Submission of Structural Dwgs. for Core Walls 7 01-Mar-12 A 10-Mar-12 A 26-Apr-12 03-May-12 26-Apr-12 03-May-12 0 100% 100%
A102280 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 09-Jun-12 16-Jun-12 06-Oct-12 13-Oct-12 99 100% 100%ApprovalApproval 60 16-Feb-12 A 22-May-12 A 26-Apr-12 05-Jul-12 03-May-12 01-Nov-12 91.07% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Overall Duration
Over
Submission & Approval of MEP Shop Drawings
Preli
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 1 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A102250 Approval of Structural Dwgs. for Slab 14 22-Apr-12 A 22-May-12 A 21-May-12 07-Jun-12 21-May-12 07-Jun-12 0 100% 100%
A102260 Approval of Structural Dwgs. for Columns 14 15-Mar-12 A 19-Apr-12 A 26-Apr-12 15-May-12 03-May-12 22-May-12 5 100% 100%
A102270 Approval of Structural Dwgs. for Core Walls 14 11-Mar-12 A 19-Mar-12 A 07-May-12 24-May-12 15-May-12 03-Jun-12 6 100% 100%
A102290 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 18-Jun-12 05-Jul-12 14-Oct-12 01-Nov-12 82 64.29% 100%3rd & 4th Fl3rd & 4th Floor Slab 74 15-Feb-12 A 13-Jun-12 A 14-May-12 01-Aug-12 14-May-12 08-Nov-12 69.05% 100%SubmissionSubmission 73 15-Feb-12 A 07-Jun-12 A 14-May-12 12-Jul-12 14-May-12 20-Oct-12 75% 100%A101360 Submission of Structural Dwgs. for Slab 14 26-Apr-12 A 07-Jun-12 A 30-May-12 14-Jun-12 31-May-12 16-Jun-12 1 100% 100%
A101370 Submission of Structural Dwgs. for Columns 9 27-Mar-12 A 01-Apr-12 A 14-May-12 23-May-12 14-May-12 23-May-12 0 100% 100%
A101380 Submission of Structural Dwgs. for Core Walls 9 18-Apr-12 A 22-Apr-12 A 14-May-12 23-May-12 15-May-12 24-May-12 1 100% 100%
A101440 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 05-Jul-12 12-Jul-12 13-Oct-12 20-Oct-12 83 0% 100%ApprovalApproval 61 16-Feb-12 A 13-Jun-12 A 24-May-12 01-Aug-12 03-Jun-12 08-Nov-12 66.07% 100%A101400 Approval of Structural Dwgs. for Slab 14 28-Apr-12 A 13-Jun-12 A 18-Jun-12 05-Jul-12 18-Jun-12 05-Jul-12 0 64.29% 100%
A101410 Approval of Structural Dwgs. for Columns 14 02-Apr-12 A 22-May-12 A 24-May-12 12-Jun-12 03-Jun-12 21-Jun-12 6 100% 100%
A101420 Approval of Structural Dwgs. for Core Walls 14 23-Apr-12 A 02-May-12 A 24-May-12 12-Jun-12 03-Jun-12 21-Jun-12 6 100% 100%
A101450 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 15-Jul-12 01-Aug-12 21-Oct-12 08-Nov-12 68 0% 100%5th & 6th Fl5th & 6th Floor Slab 120 15-Feb-12 A 15-Jul-12 109 30-Jun-12 12-Sep-12 30-Jun-12 25-Nov-12 2.38% 89.17%SubmissionSubmission 112 15-Feb-12 A 02-Jul-12 118 30-Jun-12 23-Aug-12 30-Jun-12 04-Nov-12 7.14% 97.5%A102390 Submission of Structural Dwgs. for Columns 7 19-Apr-12 A 18-Jun-12 A 30-Jun-12 07-Jul-12 30-Jun-12 07-Jul-12 0 14.29% 100%
A102400 Submission of Structural Dwgs. for Core Walls 7 29-Apr-12 A 02-Jul-12 24 30-Jun-12 07-Jul-12 30-Jun-12 07-Jul-12 0 14.29% 90%
A102380 Submission of Structural Dwgs. for Slab 12 11-Jun-12 A 13-Jun-12 A 10-Jul-12 23-Jul-12 10-Jul-12 23-Jul-12 0 0% 100%
A102440 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 14-Aug-12 23-Aug-12 28-Oct-12 04-Nov-12 60 0% 100%ApprovalApproval 99 16-Feb-12 A 15-Jul-12 91 08-Jul-12 12-Sep-12 17-Jul-12 25-Nov-12 0% 85%A102420 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 26-Jun-12 A 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7 0% 100%
A102430 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 04-Jul-12 23 08-Jul-12 25-Jul-12 17-Jul-12 05-Aug-12 7 0% 90%
A102450 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 26-Aug-12 12-Sep-12 05-Nov-12 25-Nov-12 50 0% 100%
A102410 Approval of Structural Dwgs. for Slab 14 14-Jun-12 A 15-Jul-12 20 24-Jul-12 12-Aug-12 24-Jul-12 12-Aug-12 0 0% 50%7th Floor Sl7th Floor Slab 129 15-Feb-12 A 02-Aug-12 108 25-Jul-12 03-Oct-12 25-Jul-12 12-Dec-12 0% 70.83%SubmissionSubmission 112 15-Feb-12 A 07-Jul-12 124 25-Jul-12 15-Sep-12 25-Jul-12 21-Nov-12 0% 87.5%A102470 Submission of Structural Dwgs. for Columns 9 11-Jun-12 A 18-Jun-12 A 25-Jul-12 04-Aug-12 25-Jul-12 04-Aug-12 0 0% 100%
A102480 Submission of Structural Dwgs. for Core Walls 9 11-Jun-12 A 07-Jul-12 37 25-Jul-12 04-Aug-12 25-Jul-12 04-Aug-12 0 0% 50%
A102460 Submission of Structural Dwgs. for Slab 12 11-Jun-12 A 25-Jun-12 A 13-Aug-12 28-Aug-12 13-Aug-12 28-Aug-12 0 0% 100%
A102520 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 08-Sep-12 15-Sep-12 13-Nov-12 21-Nov-12 55 0% 100%ApprovalApproval 106 16-Feb-12 A 02-Aug-12 90 05-Aug-12 03-Oct-12 28-Aug-12 12-Dec-12 0% 62.5%A102500 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 28-Jun-12 A 05-Aug-12 26-Aug-12 28-Aug-12 16-Sep-12 15 0% 100%
A102530 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 16-Sep-12 03-Oct-12 22-Nov-12 12-Dec-12 47 0% 100%
A102510 Approval of Structural Dwgs. for Core Walls 14 13-Jun-12 A 16-Jul-12 42 05-Aug-12 26-Aug-12 28-Aug-12 16-Sep-12 15 0% 50%
A102490 Approval of Structural Dwgs. for Slab 14 26-Jun-12 A 02-Aug-12 31 29-Aug-12 17-Sep-12 29-Aug-12 17-Sep-12 0 0% 0%Roof Floor Roof Floor Slab 123 15-Feb-12 A 30-Aug-12 114 14-Aug-12 02-Oct-12 14-Aug-12 15-Jan-13 0% 66.67%SubmissionSubmission 114 15-Feb-12 A 21-Aug-12 76 14-Aug-12 12-Sep-12 14-Aug-12 27-Nov-12 0% 66.67%A101470 Submission of Structural Dwgs. for Columns 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0 0% 50%
A101480 Submission of Structural Dwgs. for Core Walls 9 18-Jun-12 A 21-Aug-12 5 14-Aug-12 26-Aug-12 14-Aug-12 26-Aug-12 0 0% 50%
A101540 Submission of Structural Dwgs. for Staircase 9 15-Feb-12 A 15-Feb-12 A 03-Sep-12 12-Sep-12 18-Nov-12 27-Nov-12 62 0% 100%ApprovalApproval 101 16-Feb-12 A 30-Aug-12 95 27-Aug-12 02-Oct-12 13-Sep-12 15-Jan-13 0% 66.67%A101550 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 13-Sep-12 02-Oct-12 26-Dec-12 15-Jan-13 71 0% 100%
A101510 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 13 0% 50%
A101520 Approval of Structural Dwgs. for Core Walls 14 19-Jun-12 A 30-Aug-12 24 27-Aug-12 13-Sep-12 13-Sep-12 02-Oct-12 13 0% 50%Upper RoofUpper Roof Floor Slab 18 15-Feb-12 A 19-Apr-12 A 24-Sep-12 21-Oct-12 24-Feb-13 21-Mar-13 0% 100%SubmissionSubmission 7 15-Feb-12 A 15-Feb-12 A 24-Sep-12 01-Oct-12 24-Feb-13 03-Mar-13 0% 100%A101640 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 15-Feb-12 A 24-Sep-12 01-Oct-12 24-Feb-13 03-Mar-13 125 0% 100%
ApprovalApproval 14 16-Feb-12 A 19-Apr-12 A 02-Oct-12 21-Oct-12 04-Mar-13 21-Mar-13 0% 100%A101650 Approval of Structural Dwgs. for Staircase 14 16-Feb-12 A 19-Apr-12 A 02-Oct-12 21-Oct-12 04-Mar-13 21-Mar-13 104 0% 100%
Hotel (Block Hotel (Block B) 124 06-Feb-12 A 01-Oct-12 81 15-Feb-12 15-Jan-13 23-Feb-12 28-Feb-13 41.89% 88.92%
Deep FoundDeep Foundation 19 15-Feb-12 A 22-Feb-12 A 15-Feb-12 07-Mar-12 23-Feb-12 20-Mar-12 100% 100%SubmissionSubmission 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 23-Feb-12 26-Feb-12 100% 100%A102540 Submission of Structural Dwgs. for Raft 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 23-Feb-12 26-Feb-12 7 100% 100%
ApprovalApproval 14 18-Feb-12 A 22-Feb-12 A 19-Feb-12 07-Mar-12 01-Mar-12 20-Mar-12 100% 100%A102550 Approval of Structural Dwgs. for Raft 14 18-Feb-12 A 22-Feb-12 A 19-Feb-12 07-Mar-12 01-Mar-12 20-Mar-12 9 100% 100%
1st Baseme1st Basement Floor Slab 56 15-Feb-12 A 31-Mar-12 A 10-Mar-12 18-Jun-12 10-Mar-12 13-Nov-12 100% 100%SubmissionSubmission 40 15-Feb-12 A 20-Feb-12 A 10-Mar-12 28-May-12 10-Mar-12 23-Oct-12 100% 100%A104100 Submission of Structural Dwgs. for Water Tank 3 15-Feb-12 A 20-Feb-12 A 10-Mar-12 12-Mar-12 18-Apr-12 21-Apr-12 34 100% 100%
A102560 Submission of Structural Dwgs. for Slab 13 15-Feb-12 A 20-Feb-12 A 10-Apr-12 24-Apr-12 10-Apr-12 24-Apr-12 0 100% 100%
A102570 Submission of Structural Dwgs. for Ret. Walls -Columns 3 15-Feb-12 A 15-Feb-12 A 10-Mar-12 12-Mar-12 10-Mar-12 12-Mar-12 0 100% 100%
A102580 Submission of Structural Dwgs. for Core Walls 4 15-Feb-12 A 15-Feb-12 A 04-Apr-12 08-Apr-12 04-Apr-12 08-Apr-12 0 100% 100%
A102590 Submission of Structural Dwgs. for Ramp 12 15-Feb-12 A 16-Feb-12 A 10-Mar-12 22-Mar-12 29-Mar-12 11-Apr-12 17 100% 100%
A102640 Submission of Structural Dwgs. for Staircase 12 15-Feb-12 A 20-Feb-12 A 15-May-12 28-May-12 10-Oct-12 23-Oct-12 124 100% 100%ApprovalApproval 37 16-Feb-12 A 31-Mar-12 A 13-Mar-12 18-Jun-12 12-Apr-12 13-Nov-12 100% 100%A104110 Approval of Structural Dwgs. for Water Tank 14 21-Feb-12 A 10-Mar-12 A 13-Mar-12 01-Apr-12 22-Apr-12 09-May-12 28 100% 100%
A102600 Approval of Structural Dwgs. for Slab 14 21-Feb-12 A 31-Mar-12 A 25-Apr-12 14-May-12 25-Apr-12 14-May-12 0 100% 100%
A102610 Approval of Structural Dwgs. for Ret. Walls -Columns 13 16-Feb-12 A 16-Feb-12 A 13-Mar-12 29-Mar-12 15-Apr-12 01-May-12 23 100% 100%
A102620 Approval of Structural Dwgs. for Core Walls 14 16-Feb-12 A 29-Feb-12 A 09-Apr-12 26-Apr-12 23-Apr-12 10-May-12 10 100% 100%
A102630 Approval of Structural Dwgs. for Ramp 14 18-Feb-12 A 28-Mar-12 A 25-Mar-12 11-Apr-12 12-Apr-12 01-May-12 14 100% 100%
A102650 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 29-May-12 18-Jun-12 24-Oct-12 13-Nov-12 103 100% 100%Ground FloGround Floor Slab 51 14-Feb-12 A 01-May-12 A 29-Apr-12 25-Jul-12 29-Apr-12 19-Nov-12 80.95% 100%SubmissionSubmission 41 14-Feb-12 A 07-Apr-12 A 29-Apr-12 07-Jul-12 29-Apr-12 29-Oct-12 82.86% 100%A102720 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 30-Jun-12 07-Jul-12 20-Oct-12 29-Oct-12 94 14.29% 100%
A102680 Submission of Structural Dwgs. for Core Walls 7 07-Mar-12 A 01-Apr-12 A 14-May-12 21-May-12 14-May-12 21-May-12 0 100% 100%
A103060 Submission of Structural Dwgs. for Ramp 7 01-Apr-12 A 07-Apr-12 A 29-Apr-12 06-May-12 28-May-12 04-Jun-12 25 100% 100%
A102660 Submission of Structural Dwgs. for Slab 10 15-Mar-12 A 26-Mar-12 A 19-May-12 29-May-12 19-May-12 29-May-12 0 100% 100%
A102670 Submission of Structural Dwgs. for Ret. Walls -Columns 7 07-Mar-12 A 18-Mar-12 A 29-Apr-12 06-May-12 29-Apr-12 06-May-12 0 100% 100%ApprovalApproval 37 21-Feb-12 A 01-May-12 A 07-May-12 25-Jul-12 24-May-12 19-Nov-12 80% 100%A102690 Approval of Structural Dwgs. for Slab 14 27-Mar-12 A 26-Apr-12 A 30-May-12 19-Jun-12 30-May-12 19-Jun-12 0 100% 100%
A102700 Approval of Structural Dwgs. for Ret. Walls -Columns 14 19-Mar-12 A 01-May-12 A 07-May-12 24-May-12 24-May-12 12-Jun-12 13 100% 100%
A102710 Approval of Structural Dwgs. for Core Walls 14 01-Apr-12 A 01-May-12 A 22-May-12 10-Jun-12 27-May-12 13-Jun-12 3 100% 100%
A102730 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 08-Jul-12 25-Jul-12 30-Oct-12 19-Nov-12 79 0% 100%
A103070 Approval of Structural Dwgs. for Ramp 14 08-Apr-12 A 21-Apr-12 A 07-May-12 24-May-12 05-Jun-12 25-Jun-12 21 100% 100%1st Floor Sl1st Floor Slab 70 06-Feb-12 A 16-Jun-12 A 24-May-12 02-Sep-12 24-May-12 02-Jan-13 52.88% 100%SubmissionSubmission 52 06-Feb-12 A 03-Jun-12 A 24-May-12 11-Aug-12 24-May-12 12-Dec-12 72.92% 100%A102740 Submission of Structural Dwgs. for Slab 12 25-Apr-12 A 05-May-12 A 18-Jun-12 01-Jul-12 18-Jun-12 01-Jul-12 0 91.67% 100%
A102750 Submission of Structural Dwgs. for Columns 7 06-Feb-12 A 25-Feb-12 A 24-May-12 31-May-12 24-May-12 31-May-12 0 100% 100%
A102760 Submission of Structural Dwgs. for Core Walls 7 24-Apr-12 A 02-May-12 A 06-Jun-12 13-Jun-12 06-Jun-12 13-Jun-12 0 100% 100%
A102800 Submission of Structural Dwgs. for Staircase 7 20-Feb-12 A 03-Jun-12 A 04-Aug-12 11-Aug-12 05-Dec-12 12-Dec-12 100 0% 100%ApprovalApproval 53 21-Feb-12 A 16-Jun-12 A 03-Jun-12 02-Sep-12 21-Jun-12 02-Jan-13 42.86% 100%A102770 Approval of Structural Dwgs. for Slab 14 06-May-12 A 16-Jun-12 A 02-Jul-12 19-Jul-12 02-Jul-12 19-Jul-12 0 0% 100%
A102780 Approval of Structural Dwgs. for Columns 14 26-Feb-12 A 24-May-12 A 03-Jun-12 21-Jun-12 21-Jun-12 10-Jul-12 13 100% 100%
A102790 Approval of Structural Dwgs. for Core Walls 14 03-May-12 A 14-May-12 A 14-Jun-12 04-Jul-12 25-Jun-12 12-Jul-12 6 71.43% 100%
A102810 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 16-Jun-12 A 12-Aug-12 02-Sep-12 13-Dec-12 02-Jan-13 84 0% 100%2nd Floor S2nd Floor Slab 71 13-Feb-12 A 21-Jun-12 A 20-Jun-12 04-Oct-12 20-Jun-12 28-Feb-13 9.52% 100%SubmissionSubmission 55 13-Feb-12 A 07-Jun-12 A 20-Jun-12 16-Sep-12 20-Jun-12 10-Feb-13 25% 100%A103080 Submission of Structural Dwgs. for Slab 12 23-May-12 A 07-Jun-12 A 10-Jul-12 23-Jul-12 10-Jul-12 23-Jul-12 0 0% 100%
A103090 Submission of Structural Dwgs. for Columns 7 06-Mar-12 A 14-Mar-12 A 20-Jun-12 27-Jun-12 20-Jun-12 27-Jun-12 0 100% 100%
A103100 Submission of Structural Dwgs. for Core Walls 7 25-Apr-12 A 24-May-12 A 01-Jul-12 08-Jul-12 01-Jul-12 08-Jul-12 0 0% 100%
A103140 Submission of Structural Dwgs. for Staircase 7 13-Feb-12 A 20-Feb-12 A 09-Sep-12 16-Sep-12 03-Feb-13 10-Feb-13 120 0% 100%ApprovalApproval 54 21-Feb-12 A 21-Jun-12 A 28-Jun-12 04-Oct-12 17-Jul-12 28-Feb-13 1.79% 100%A103110 Approval of Structural Dwgs. for Slab 14 24-May-12 A 21-Jun-12 A 24-Jul-12 12-Aug-12 24-Jul-12 12-Aug-12 0 0% 100%
A103120 Approval of Structural Dwgs. for Columns 14 15-Mar-12 A 04-Jun-12 A 28-Jun-12 17-Jul-12 17-Jul-12 05-Aug-12 13 7.14% 100%
A103130 Approval of Structural Dwgs. for Core Walls 14 26-May-12 A 04-Jun-12 A 09-Jul-12 26-Jul-12 17-Jul-12 05-Aug-12 6 0% 100%
A103150 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 17-Sep-12 04-Oct-12 11-Feb-13 28-Feb-13 100 0% 100%3rd & 4th Fl3rd & 4th Floor Slab 107 14-Feb-12 A 14-Aug-12 162 16-Jul-12 29-Oct-12 16-Jul-12 28-Feb-13 0% 79.17%SubmissionSubmission 100 14-Feb-12 A 05-Aug-12 170 16-Jul-12 08-Oct-12 16-Jul-12 10-Feb-13 0% 87.5%A102830 Submission of Structural Dwgs. for Columns 7 08-Apr-12 A 07-Jun-12 A 16-Jul-12 23-Jul-12 16-Jul-12 23-Jul-12 0 0% 100%
A102820 Submission of Structural Dwgs. for Slab 11 14-Jun-12 A 20-Jun-12 A 01-Aug-12 13-Aug-12 01-Aug-12 13-Aug-12 0 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Submission of Structural Dwgs. for Core Walls
b
Approval of Structural Dwgs. for Core Walls
b Approval of Structural Dwgs. for Slab
s
s Submission of Structural Dwgs. for Core Walls
b
s
s Approval of Structural Dwgs. for Core Walls
ab Approval of Structural Dwgs. for Slab
ns Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
s Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
b
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 2 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A102840 Submission of Structural Dwgs. for Core Walls 8 11-Jun-12 A 05-Aug-12 12 23-Jul-12 31-Jul-12 23-Jul-12 31-Jul-12 0 0% 50%
A102880 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 01-Oct-12 08-Oct-12 03-Feb-13 10-Feb-13 101 0% 100%ApprovalApproval 84 21-Feb-12 A 14-Aug-12 135 26-Jul-12 29-Oct-12 09-Aug-12 28-Feb-13 0% 75%A102860 Approval of Structural Dwgs. for Columns 14 09-Apr-12 A 16-Jun-12 A 26-Jul-12 14-Aug-12 09-Aug-12 30-Aug-12 10 0% 100%
A102890 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 09-Oct-12 29-Oct-12 11-Feb-13 28-Feb-13 84 0% 100%
A102850 Approval of Structural Dwgs. for Slab 14 16-Jun-12 A 14-Aug-12 13 14-Aug-12 04-Sep-12 14-Aug-12 04-Sep-12 0 0% 50%
A102870 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 14-Aug-12 10 01-Aug-12 22-Aug-12 09-Aug-12 30-Aug-12 6 0% 50%5th & 6th Fl5th & 6th Floor Slab 110 14-Feb-12 A 28-Aug-12 152 09-Aug-12 05-Dec-12 09-Aug-12 27-Feb-13 0% 62.5%SubmissionSubmission 110 14-Feb-12 A 07-Aug-12 162 09-Aug-12 13-Nov-12 09-Aug-12 09-Feb-13 0% 68.75%A103180 Submission of Structural Dwgs. for Core Walls 8 29-Apr-12 A 05-Aug-12 30 18-Aug-12 28-Aug-12 18-Aug-12 28-Aug-12 0 0% 50%
A103170 Submission of Structural Dwgs. for Columns 8 19-Apr-12 A 07-Aug-12 16 09-Aug-12 18-Aug-12 09-Aug-12 18-Aug-12 0 0% 25%
A103160 Submission of Structural Dwgs. for Slab 12 26-Jun-12 A 30-Jun-12 A 06-Sep-12 19-Sep-12 06-Sep-12 19-Sep-12 0 0% 100%
A103220 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 06-Nov-12 13-Nov-12 02-Feb-13 09-Feb-13 71 0% 100%ApprovalApproval 49 21-Feb-12 A 28-Aug-12 127 23-Aug-12 05-Dec-12 17-Sep-12 27-Feb-13 0% 58.33%A103230 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 14-Nov-12 05-Dec-12 10-Feb-13 27-Feb-13 58 0% 100%
A103210 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 15-Aug-12 34 30-Aug-12 18-Sep-12 17-Sep-12 04-Oct-12 12 0% 50%
A103200 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 28-Aug-12 28 23-Aug-12 11-Sep-12 17-Sep-12 04-Oct-12 17 0% 25%7th Floor Sl7th Floor Slab 104 14-Feb-12 A 17-Sep-12 80 13-Sep-12 15-Jan-13 13-Sep-12 27-Feb-13 0% 66.67%SubmissionSubmission 93 14-Feb-12 A 06-Sep-12 80 13-Sep-12 25-Dec-12 13-Sep-12 09-Feb-13 0% 66.67%A103250 Submission of Structural Dwgs. for Columns 7 11-Jun-12 A 06-Sep-12 16 13-Sep-12 20-Sep-12 13-Sep-12 20-Sep-12 0 0% 50%
A103260 Submission of Structural Dwgs. for Core Walls 7 11-Jun-12 A 06-Sep-12 20 22-Sep-12 29-Sep-12 22-Sep-12 29-Sep-12 0 0% 50%
A103300 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 18-Dec-12 25-Dec-12 02-Feb-13 09-Feb-13 37 0% 100%ApprovalApproval 81 21-Feb-12 A 17-Sep-12 66 23-Sep-12 15-Jan-13 18-Oct-12 27-Feb-13 0% 66.67%A103280 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 17-Sep-12 38 23-Sep-12 10-Oct-12 21-Oct-12 08-Nov-12 20 0% 50%
A103290 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 17-Sep-12 37 30-Sep-12 17-Oct-12 18-Oct-12 07-Nov-12 14 0% 50%
A103310 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 26-Dec-12 15-Jan-13 10-Feb-13 27-Feb-13 30 0% 100%Roof Floor Roof Floor Slab 110 14-Feb-12 A 01-Oct-12 118 03-Oct-12 25-Nov-12 03-Oct-12 27-Feb-13 0% 75%SubmissionSubmission 99 14-Feb-12 A 22-Sep-12 118 03-Oct-12 04-Nov-12 03-Oct-12 09-Feb-13 0% 75%A102910 Submission of Structural Dwgs. for Columns 7 18-Jun-12 A 22-Sep-12 16 03-Oct-12 10-Oct-12 03-Oct-12 10-Oct-12 0 0% 50%
A102960 Submission of Structural Dwgs. for Staircase 7 14-Feb-12 A 20-Feb-12 A 28-Oct-12 04-Nov-12 02-Feb-13 09-Feb-13 79 0% 100%ApprovalApproval 86 21-Feb-12 A 01-Oct-12 99 11-Oct-12 25-Nov-12 30-Oct-12 27-Feb-13 0% 75%A102940 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 01-Oct-12 33 11-Oct-12 31-Oct-12 30-Oct-12 19-Nov-12 12 0% 50%
A102970 Approval of Structural Dwgs. for Staircase 14 21-Feb-12 A 26-Mar-12 A 05-Nov-12 25-Nov-12 10-Feb-13 27-Feb-13 65 0% 100%
Residentail (BResidentail (Block C) 125 15-Feb-12 A 03-Sep-12 126 15-Feb-12 24-Dec-12 26-Feb-12 25-Mar-13 46.32% 86.72%
Deep FoundDeep Foundation 8 15-Feb-12 A 29-Feb-12 A 15-Feb-12 23-Feb-12 26-Feb-12 20-Mar-12 100% 100%SubmissionSubmission 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 26-Feb-12 28-Feb-12 100% 100%A103320 Submission of Structural Dwgs. for Raft 3 15-Feb-12 A 16-Feb-12 A 15-Feb-12 18-Feb-12 26-Feb-12 28-Feb-12 9 100% 100%
ApprovalApproval 5 17-Feb-12 A 29-Feb-12 A 19-Feb-12 23-Feb-12 14-Mar-12 20-Mar-12 100% 100%A103330 Approval of Structural Dwgs. for Raft 5 17-Feb-12 A 29-Feb-12 A 19-Feb-12 23-Feb-12 14-Mar-12 20-Mar-12 18 100% 100%
1st Baseme1st Basement Floor Slab 38 15-Feb-12 A 31-Mar-12 A 08-Mar-12 05-Jun-12 08-Mar-12 08-Nov-12 100% 100%SubmissionSubmission 37 15-Feb-12 A 20-Feb-12 A 08-Mar-12 16-May-12 08-Mar-12 20-Oct-12 100% 100%A103340 Submission of Structural Dwgs. for Slab 12 15-Feb-12 A 20-Feb-12 A 04-Apr-12 17-Apr-12 04-Apr-12 17-Apr-12 0 100% 100%
A103350 Submission of Structural Dwgs. for Ret. Walls -Columns 7 15-Feb-12 A 16-Feb-12 A 08-Mar-12 15-Mar-12 08-Mar-12 15-Mar-12 0 100% 100%
A103360 Submission of Structural Dwgs. for Core Walls 7 15-Feb-12 A 16-Feb-12 A 03-Apr-12 10-Apr-12 03-Apr-12 10-Apr-12 0 100% 100%
A103370 Submission of Structural Dwgs. for Water Tank 7 15-Feb-12 A 15-Feb-12 A 08-Mar-12 15-Mar-12 27-Mar-12 03-Apr-12 16 100% 100%
A103420 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 09-May-12 16-May-12 13-Oct-12 20-Oct-12 131 100% 100%ApprovalApproval 26 16-Feb-12 A 31-Mar-12 A 18-Mar-12 05-Jun-12 08-Apr-12 08-Nov-12 100% 100%A103380 Approval of Structural Dwgs. for Slab 14 21-Feb-12 A 22-Mar-12 A 18-Apr-12 07-May-12 18-Apr-12 07-May-12 0 100% 100%
A103390 Approval of Structural Dwgs. for Ret. Walls -Columns 14 18-Feb-12 A 19-Feb-12 A 18-Mar-12 04-Apr-12 11-Apr-12 30-Apr-12 18 100% 100%
A103400 Approval of Structural Dwgs. for Core Walls 14 18-Feb-12 A 21-Feb-12 A 11-Apr-12 30-Apr-12 12-Apr-12 01-May-12 1 100% 100%
A103410 Approval of Structural Dwgs. for Water Tank 14 16-Feb-12 A 10-Mar-12 A 18-Mar-12 04-Apr-12 08-Apr-12 25-Apr-12 15 100% 100%
A103430 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 17-May-12 05-Jun-12 21-Oct-12 08-Nov-12 108 100% 100%Ground FloGround Floor Slab 48 15-Feb-12 A 11-Apr-12 A 15-Apr-12 01-Jul-12 15-Apr-12 21-Feb-13 98.81% 100%SubmissionSubmission 37 15-Feb-12 A 18-Mar-12 A 15-Apr-12 10-Jun-12 15-Apr-12 03-Feb-13 100% 100%A103440 Submission of Structural Dwgs. for Slab 12 01-Mar-12 A 18-Mar-12 A 10-May-12 23-May-12 10-May-12 23-May-12 0 100% 100%
A103450 Submission of Structural Dwgs. for Ret. Walls -Columns 7 06-Mar-12 A 12-Mar-12 A 15-Apr-12 22-Apr-12 15-Apr-12 22-Apr-12 0 100% 100%
A103460 Submission of Structural Dwgs. for Core Walls 7 06-Mar-12 A 14-Mar-12 A 29-Apr-12 06-May-12 10-May-12 17-May-12 10 100% 100%
A103500 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 03-Jun-12 10-Jun-12 27-Jan-13 03-Feb-13 195 100% 100%ApprovalApproval 35 19-Feb-12 A 11-Apr-12 A 23-Apr-12 01-Jul-12 21-May-12 21-Feb-13 98.21% 100%A103470 Approval of Structural Dwgs. for Slab 14 19-Mar-12 A 11-Apr-12 A 24-May-12 12-Jun-12 24-May-12 12-Jun-12 0 100% 100%
A103480 Approval of Structural Dwgs. for Ret. Walls -Columns 14 13-Mar-12 A 29-Mar-12 A 23-Apr-12 10-May-12 21-May-12 07-Jun-12 20 100% 100%
A103490 Approval of Structural Dwgs. for Core Walls 14 15-Mar-12 A 27-Mar-12 A 07-May-12 24-May-12 21-May-12 07-Jun-12 10 100% 100%
A103510 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 11-Jun-12 01-Jul-12 04-Feb-13 21-Feb-13 162 92.86% 100%1st Floor Sl1st Floor Slab 52 15-Feb-12 A 26-May-12 A 16-May-12 02-Aug-12 16-May-12 12-Dec-12 69.05% 100%SubmissionSubmission 44 15-Feb-12 A 18-Apr-12 A 16-May-12 15-Jul-12 16-May-12 21-Nov-12 75% 100%A103520 Submission of Structural Dwgs. for Slab 12 02-Apr-12 A 18-Apr-12 A 02-Jun-12 14-Jun-12 03-Jun-12 16-Jun-12 1 100% 100%
A103530 Submission of Structural Dwgs. for Columns 7 13-Mar-12 A 25-Mar-12 A 16-May-12 23-May-12 16-May-12 23-May-12 0 100% 100%
A103540 Submission of Structural Dwgs. for Core Walls 7 14-Mar-12 A 28-Mar-12 A 26-May-12 02-Jun-12 27-May-12 03-Jun-12 1 100% 100%
A103580 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 08-Jul-12 15-Jul-12 13-Nov-12 21-Nov-12 106 0% 100%ApprovalApproval 38 19-Feb-12 A 26-May-12 A 24-May-12 02-Aug-12 12-Jun-12 12-Dec-12 66.07% 100%A103550 Approval of Structural Dwgs. for Slab 14 19-Apr-12 A 26-May-12 A 18-Jun-12 05-Jul-12 18-Jun-12 05-Jul-12 0 64.29% 100%
A103560 Approval of Structural Dwgs. for Columns 14 26-Mar-12 A 07-Apr-12 A 24-May-12 12-Jun-12 12-Jun-12 02-Jul-12 13 100% 100%
A103570 Approval of Structural Dwgs. for Core Walls 14 29-Mar-12 A 08-Apr-12 A 03-Jun-12 21-Jun-12 12-Jun-12 02-Jul-12 7 100% 100%
A103590 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 11-Apr-12 A 16-Jul-12 02-Aug-12 22-Nov-12 12-Dec-12 89 0% 100%2nd Floor S2nd Floor Slab 77 15-Feb-12 A 19-Jun-12 A 09-Jun-12 29-Aug-12 09-Jun-12 14-Mar-13 44.35% 100%SubmissionSubmission 52 15-Feb-12 A 11-Jun-12 A 09-Jun-12 07-Aug-12 09-Jun-12 24-Feb-13 68.75% 100%A103860 Submission of Structural Dwgs. for Slab 12 23-Apr-12 A 11-Jun-12 A 20-Jun-12 03-Jul-12 20-Jun-12 03-Jul-12 0 75% 100%
A103870 Submission of Structural Dwgs. for Columns 7 12-Apr-12 A 17-Apr-12 A 09-Jun-12 16-Jun-12 09-Jun-12 16-Jun-12 0 100% 100%
A103880 Submission of Structural Dwgs. for Core Walls 7 12-Apr-12 A 17-Apr-12 A 09-Jun-12 16-Jun-12 20-Jun-12 27-Jun-12 9 100% 100%
A103920 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 31-Jul-12 07-Aug-12 17-Feb-13 24-Feb-13 164 0% 100%ApprovalApproval 59 19-Feb-12 A 19-Jun-12 A 18-Jun-12 29-Aug-12 01-Jul-12 14-Mar-13 32.14% 100%A103890 Approval of Structural Dwgs. for Slab 14 24-Apr-12 A 19-Jun-12 A 04-Jul-12 23-Jul-12 04-Jul-12 23-Jul-12 0 0% 100%
A103900 Approval of Structural Dwgs. for Columns 14 18-Apr-12 A 01-May-12 A 18-Jun-12 05-Jul-12 01-Jul-12 18-Jul-12 9 64.29% 100%
A103910 Approval of Structural Dwgs. for Core Walls 14 18-Apr-12 A 01-May-12 A 18-Jun-12 05-Jul-12 02-Jul-12 19-Jul-12 10 64.29% 100%
A103930 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 08-Aug-12 29-Aug-12 25-Feb-13 14-Mar-13 136 0% 100%3rd & 4th Fl3rd & 4th Floor Slab 111 15-Feb-12 A 24-Jul-12 188 26-Jun-12 26-Sep-12 26-Jun-12 10-Mar-13 8.33% 75%SubmissionSubmission 101 15-Feb-12 A 04-Jul-12 205 26-Jun-12 08-Sep-12 26-Jun-12 18-Feb-13 25% 87.5%A103610 Submission of Structural Dwgs. for Columns 8 08-Apr-12 A 20-Jun-12 A 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0 50% 100%
A103600 Submission of Structural Dwgs. for Slab 13 26-Apr-12 A 11-Jun-12 A 08-Jul-12 22-Jul-12 08-Jul-12 22-Jul-12 0 0% 100%
A103660 Submission of Structural Dwgs. for Staircase 7 15-Feb-12 A 18-Feb-12 A 01-Sep-12 08-Sep-12 11-Feb-13 18-Feb-13 134 0% 100%
A103620 Submission of Structural Dwgs. for Core Walls 8 20-Jun-12 A 04-Jul-12 9 26-Jun-12 04-Jul-12 26-Jun-12 04-Jul-12 0 50% 50%ApprovalApproval 87 19-Feb-12 A 24-Jul-12 156 05-Jul-12 26-Sep-12 16-Jul-12 10-Mar-13 0% 68.75%A103630 Approval of Structural Dwgs. for Slab 14 28-Apr-12 A 25-Jun-12 A 23-Jul-12 09-Aug-12 23-Jul-12 09-Aug-12 0 0% 100%
A103670 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 09-Sep-12 26-Sep-12 19-Feb-13 10-Mar-13 112 0% 100%
A103640 Approval of Structural Dwgs. for Columns 14 09-Apr-12 A 04-Jul-12 24 05-Jul-12 24-Jul-12 18-Jul-12 06-Aug-12 9 0% 75%
A103650 Approval of Structural Dwgs. for Core Walls 14 21-Jun-12 A 24-Jul-12 7 05-Jul-12 24-Jul-12 16-Jul-12 02-Aug-12 7 0% 0%5th & 6th Fl5th & 6th Floor Slab 109 16-Feb-12 A 29-Jul-12 182 23-Jul-12 24-Oct-12 23-Jul-12 06-Mar-13 0% 56.25%SubmissionSubmission 101 16-Feb-12 A 14-Jul-12 194 23-Jul-12 06-Oct-12 23-Jul-12 16-Feb-13 0% 68.75%A103940 Submission of Structural Dwgs. for Slab 10 18-Jun-12 A 30-Jun-12 A 16-Aug-12 02-Sep-12 16-Aug-12 02-Sep-12 0 0% 100%
A103950 Submission of Structural Dwgs. for Columns 7 19-Apr-12 A 11-Jul-12 27 23-Jul-12 30-Jul-12 23-Jul-12 30-Jul-12 0 0% 50%
A104000 Submission of Structural Dwgs. for Staircase 7 16-Feb-12 A 18-Feb-12 A 29-Sep-12 06-Oct-12 09-Feb-13 16-Feb-13 108 0% 100%
A103960 Submission of Structural Dwgs. for Core Walls 8 29-Apr-12 A 14-Jul-12 39 06-Aug-12 14-Aug-12 06-Aug-12 14-Aug-12 0 0% 25%ApprovalApproval 85 19-Feb-12 A 29-Jul-12 152 31-Jul-12 24-Oct-12 22-Aug-12 06-Mar-13 0% 50%A104010 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 07-Oct-12 24-Oct-12 17-Feb-13 06-Mar-13 90 0% 100%
A103980 Approval of Structural Dwgs. for Columns 14 21-Apr-12 A 22-Jul-12 35 31-Jul-12 21-Aug-12 22-Aug-12 10-Sep-12 14 0% 50%
A103970 Approval of Structural Dwgs. for Slab 14 19-Jun-12 A 25-Jul-12 39 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0 0% 25%
A103990 Approval of Structural Dwgs. for Core Walls 14 30-Apr-12 A 29-Jul-12 33 15-Aug-12 05-Sep-12 27-Aug-12 13-Sep-12 6 0% 25%7th Floor Sl7th Floor Slab 104 16-Feb-12 A 16-Aug-12 135 26-Aug-12 25-Nov-12 26-Aug-12 06-Mar-13 0% 66.67%SubmissionSubmission 94 16-Feb-12 A 07-Aug-12 135 26-Aug-12 04-Nov-12 26-Aug-12 16-Feb-13 0% 66.67%A104030 Submission of Structural Dwgs. for Columns 7 11-Jun-12 A 07-Aug-12 27 26-Aug-12 02-Sep-12 26-Aug-12 02-Sep-12 0 0% 50%
A104040 Submission of Structural Dwgs. for Core Walls 7 11-Jun-12 A 07-Aug-12 27 03-Sep-12 10-Sep-12 03-Sep-12 10-Sep-12 0 0% 50%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s Submission of Structural Dwgs. for Core Walls
b Approval of Structural Dwgs. for Slab
s Approval of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Core Walls
Submission of Structural Dwgs. for Columns
ab
Approval of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
s Approval of Structural Dwgs. for Columns
s Approval of Structural Dwgs. for Core Walls
ns Submission of Structural Dwgs. for Columns
ns Approval of Structural Dwgs. for Columns
ls Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
ls Approval of Structural Dwgs. for Core Walls
ab
Submission of Structural Dwgs. for Columns
Submission of Structural Dwgs. for Core Walls
Approval of Structural Dwgs. for Columns
ab Approval of Structural Dwgs. for Slab
Approval of Structural Dwgs. for Core Walls
s Submission of Structural Dwgs. for Columns
s Submission of Structural Dwgs. for Core Walls
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 3 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A104080 Submission of Structural Dwgs. for Staircase 7 16-Feb-12 A 18-Feb-12 A 28-Oct-12 04-Nov-12 09-Feb-13 16-Feb-13 85 0% 100%ApprovalApproval 81 19-Feb-12 A 16-Aug-12 113 03-Sep-12 25-Nov-12 30-Sep-12 06-Mar-13 0% 66.67%A104060 Approval of Structural Dwgs. for Columns 14 12-Jun-12 A 16-Aug-12 42 03-Sep-12 20-Sep-12 30-Sep-12 17-Oct-12 19 0% 50%
A104070 Approval of Structural Dwgs. for Core Walls 14 12-Jun-12 A 16-Aug-12 42 11-Sep-12 30-Sep-12 30-Sep-12 17-Oct-12 13 0% 50%
A104090 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 05-Nov-12 25-Nov-12 17-Feb-13 06-Mar-13 70 0% 100%Roof Floor Roof Floor Slab 109 16-Feb-12 A 03-Sep-12 119 13-Sep-12 24-Dec-12 13-Sep-12 12-Mar-13 0% 75%SubmissionSubmission 98 16-Feb-12 A 25-Aug-12 119 13-Sep-12 04-Dec-12 13-Sep-12 20-Feb-13 0% 75%A103690 Submission of Structural Dwgs. for Columns 7 18-Jun-12 A 25-Aug-12 30 13-Sep-12 20-Sep-12 13-Sep-12 20-Sep-12 0 0% 50%
A103740 Submission of Structural Dwgs. for Staircase 7 16-Feb-12 A 18-Feb-12 A 26-Nov-12 04-Dec-12 13-Feb-13 20-Feb-13 65 0% 100%ApprovalApproval 85 19-Feb-12 A 03-Sep-12 99 23-Sep-12 24-Dec-12 17-Oct-12 12-Mar-13 0% 75%A103720 Approval of Structural Dwgs. for Columns 14 19-Jun-12 A 03-Sep-12 45 23-Sep-12 10-Oct-12 17-Oct-12 06-Nov-12 18 0% 50%
A103750 Approval of Structural Dwgs. for Staircase 14 19-Feb-12 A 31-Mar-12 A 05-Dec-12 24-Dec-12 21-Feb-13 12-Mar-13 54 0% 100%Upper RoofUpper Roof Floor Slab 23 03-Mar-12 A 25-Mar-12 A 24-Nov-12 20-Dec-12 26-Feb-13 25-Mar-13 0% 100%SubmissionSubmission 7 03-Mar-12 A 10-Mar-12 A 24-Nov-12 01-Dec-12 26-Feb-13 05-Mar-13 0% 100%A103820 Submission of Structural Dwgs. for Staircase 7 03-Mar-12 A 10-Mar-12 A 24-Nov-12 01-Dec-12 26-Feb-13 05-Mar-13 78 0% 100%
ApprovalApproval 14 11-Mar-12 A 25-Mar-12 A 03-Dec-12 20-Dec-12 06-Mar-13 25-Mar-13 0% 100%A103830 Approval of Structural Dwgs. for Staircase 14 11-Mar-12 A 25-Mar-12 A 03-Dec-12 20-Dec-12 06-Mar-13 25-Mar-13 65 0% 100%
Hotel ApartemHotel Apartements (Block A) 88 29-Mar-12 A 25-Jun-12 A 07-May-12 26-Aug-12 07-May-12 05-Nov-12 48.18% 100%
2nd Baseme2nd Basement Floor 25 29-Mar-12 A 23-Apr-12 A 07-May-12 05-Jun-12 07-May-12 21-Oct-12 100% 100%SubmissionSubmission 9 29-Mar-12 A 08-Apr-12 A 07-May-12 16-May-12 07-May-12 16-May-12 100% 100%A119010 Submission of Block Work Setting Out Plan for 2nd Basement 9 29-Mar-12 A 08-Apr-12 A 07-May-12 16-May-12 07-May-12 16-May-12 0 100% 100%
ApprovalApproval 14 09-Apr-12 A 23-Apr-12 A 17-May-12 05-Jun-12 02-Oct-12 21-Oct-12 100% 100%A119290 Approval of Block Work Setting Out Plan for 2nd Basement 14 09-Apr-12 A 23-Apr-12 A 17-May-12 05-Jun-12 02-Oct-12 21-Oct-12 95 100% 100%
1st Baseme1st Basement Floor 24 26-Apr-12 A 17-May-12 A 17-May-12 13-Jun-12 17-May-12 13-Aug-12 100% 100%SubmissionSubmission 8 26-Apr-12 A 05-May-12 A 17-May-12 26-May-12 17-May-12 26-May-12 100% 100%A119410 Submission of Block Work Setting Out Plan for 1st Basement 8 26-Apr-12 A 05-May-12 A 17-May-12 26-May-12 17-May-12 26-May-12 0 100% 100%
ApprovalApproval 14 06-May-12 A 17-May-12 A 27-May-12 13-Jun-12 25-Jul-12 13-Aug-12 100% 100%A119550 Approval of Block Work Setting Out Plan for 1st Basement 14 06-May-12 A 17-May-12 A 27-May-12 13-Jun-12 25-Jul-12 13-Aug-12 42 100% 100%
Ground FloGround Floor 25 11-Jun-12 A 24-Jun-12 A 20-Jun-12 18-Jul-12 20-Jun-12 05-Nov-12 36.36% 100%SubmissionSubmission 8 11-Jun-12 A 19-Jun-12 A 20-Jun-12 28-Jun-12 20-Jun-12 28-Jun-12 100% 100%A118450 Submission of Block Work Setting Out Plan for Ground 8 11-Jun-12 A 19-Jun-12 A 20-Jun-12 28-Jun-12 20-Jun-12 28-Jun-12 0 100% 100%
ApprovalApproval 14 21-Jun-12 A 24-Jun-12 A 01-Jul-12 18-Jul-12 16-Oct-12 05-Nov-12 0% 100%A118480 Approval of Block Work Setting Out Plan for Ground 14 21-Jun-12 A 24-Jun-12 A 01-Jul-12 18-Jul-12 16-Oct-12 05-Nov-12 75 0% 100%
Typical FlooTypical Floors 26 29-May-12 A 25-Jun-12 A 30-Jun-12 26-Aug-12 30-Jun-12 09-Sep-12 2.27% 100%GeneralGeneral 26 29-May-12 A 25-Jun-12 A 30-Jun-12 26-Aug-12 30-Jun-12 09-Sep-12 2.27% 100%SubmissiSubmission 8 29-May-12 A 07-Jun-12 A 30-Jun-12 04-Aug-12 30-Jun-12 04-Aug-12 6.25% 100%A117470 Submission of Block Work Setting Out Plan for 1st Floor 8 29-May-12 A 07-Jun-12 A 30-Jun-12 08-Jul-12 30-Jun-12 08-Jul-12 0 12.5% 100%
A117230 Submission of Block Work Setting Out Plan for 2nd Floor 8 29-May-12 A 07-Jun-12 A 26-Jul-12 04-Aug-12 26-Jul-12 04-Aug-12 0 0% 100%ApprovalApproval 14 09-Jun-12 A 25-Jun-12 A 09-Jul-12 26-Aug-12 05-Aug-12 09-Sep-12 0% 100%A117490 Approval of Block Work Setting Out Plan for 2nd Floor 14 09-Jun-12 A 25-Jun-12 A 05-Aug-12 26-Aug-12 05-Aug-12 26-Aug-12 0 0% 100%
A117480 Approval of Block Work Setting Out Plan for 1st Floor 14 09-Jun-12 A 25-Jun-12 A 09-Jul-12 26-Jul-12 21-Aug-12 09-Sep-12 29 0% 100%
Hotel (Block Hotel (Block B) 83 12-Apr-12 A 29-Jul-12 160 19-May-12 03-Oct-12 28-May-12 10-Feb-13 25% 68.18%
2nd Baseme2nd Basement Floor 68 12-Apr-12 A 02-May-12 A 19-May-12 14-Jun-12 28-May-12 08-Jan-13 100% 100%SubmissionSubmission 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 28-May-12 05-Jun-12 100% 100%A123210 Submission of Block Work Setting Out Plan for 2nd Basement 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 28-May-12 05-Jun-12 8 100% 100%
ApprovalApproval 14 22-Apr-12 A 02-May-12 A 28-May-12 14-Jun-12 19-Dec-12 08-Jan-13 100% 100%A123490 Approval of Block Work Setting Out Plan for 2nd Basement 14 22-Apr-12 A 02-May-12 A 28-May-12 14-Jun-12 19-Dec-12 08-Jan-13 141 100% 100%
1st Baseme1st Basement Floor 24 26-Apr-12 A 17-May-12 A 03-Jul-12 31-Jul-12 12-Jul-12 10-Oct-12 0% 100%SubmissionSubmission 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 12-Jul-12 21-Jul-12 0% 100%A123610 Submission of Block Work Setting Out Plan for 1st Basement 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 12-Jul-12 21-Jul-12 8 0% 100%
ApprovalApproval 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 23-Sep-12 10-Oct-12 0% 100%A123770 Approval of Block Work Setting Out Plan for 1st Basement 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 23-Sep-12 10-Oct-12 49 0% 100%
Typical FlooTypical Floors 32 11-Jun-12 A 29-Jul-12 160 28-Aug-12 03-Oct-12 06-Sep-12 10-Feb-13 0% 36.36%GeneralGeneral 32 11-Jun-12 A 29-Jul-12 160 28-Aug-12 03-Oct-12 06-Sep-12 10-Feb-13 0% 36.36%SubmissiSubmission 15 11-Jun-12 A 28-Jun-12 A 28-Aug-12 15-Sep-12 06-Sep-12 16-Dec-12 0% 100%A121790 Submission of Block Work Setting Out Plan for 2nd Floor 8 20-Jun-12 A 28-Jun-12 A 06-Sep-12 15-Sep-12 08-Dec-12 16-Dec-12 75 0% 100%
A122030 Submission of Block Work Setting Out Plan for 1st Floor 8 11-Jun-12 A 20-Jun-12 A 28-Aug-12 05-Sep-12 06-Sep-12 15-Sep-12 8 0% 100%ApprovalApproval 20 21-Jun-12 A 29-Jul-12 133 06-Sep-12 03-Oct-12 22-Oct-12 10-Feb-13 0% 0%A122040 Approval of Block Work Setting Out Plan for 2nd Floor 14 30-Jun-12 A 29-Jul-12 133 16-Sep-12 03-Oct-12 21-Jan-13 10-Feb-13 87 0% 0%
A122070 Approval of Block Work Setting Out Plan for 1st Floor 14 21-Jun-12 A 29-Jul-12 72 06-Sep-12 25-Sep-12 22-Oct-12 11-Nov-12 32 0% 0%
Residential AResidential Apartments (Block C) 68 12-Apr-12 A 30-Jun-12 A 19-May-12 13-Aug-12 19-May-12 13-Nov-12 42.31% 100%
2nd Baseme2nd Basement Floor 68 12-Apr-12 A 11-Jun-12 A 19-May-12 14-Jun-12 19-May-12 13-Nov-12 100% 100%SubmissionSubmission 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 19-May-12 27-May-12 100% 100%A121110 Submission of Block Work Setting Out Plan for 2nd Basement 8 12-Apr-12 A 21-Apr-12 A 19-May-12 27-May-12 19-May-12 27-May-12 0 100% 100%
ApprovalApproval 14 22-Apr-12 A 11-Jun-12 A 28-May-12 14-Jun-12 24-Oct-12 13-Nov-12 100% 100%A121390 Approval of Block Work Setting Out Plan for 2nd Basement 14 22-Apr-12 A 11-Jun-12 A 28-May-12 14-Jun-12 24-Oct-12 13-Nov-12 104 100% 100%
1st Baseme1st Basement Floor 24 26-Apr-12 A 17-May-12 A 03-Jul-12 31-Jul-12 03-Jul-12 01-Nov-12 0% 100%SubmissionSubmission 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 03-Jul-12 11-Jul-12 0% 100%A121510 Submission of Block Work Setting Out Plan for 1st Basement 8 26-Apr-12 A 05-May-12 A 03-Jul-12 11-Jul-12 03-Jul-12 11-Jul-12 0 0% 100%
ApprovalApproval 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 14-Oct-12 01-Nov-12 0% 100%A121670 Approval of Block Work Setting Out Plan for 1st Basement 14 06-May-12 A 17-May-12 A 12-Jul-12 31-Jul-12 14-Oct-12 01-Nov-12 64 0% 100%
Ground FloGround Floor 8 20-Jun-12 A 30-Jun-12 A 05-Aug-12 13-Aug-12 05-Aug-12 13-Aug-12 0% 100%SubmissionSubmission 8 20-Jun-12 A 30-Jun-12 A 05-Aug-12 13-Aug-12 05-Aug-12 13-Aug-12 0% 100%A120780 Submission of Block Work Setting Out Plan for Ground 8 20-Jun-12 A 30-Jun-12 A 05-Aug-12 13-Aug-12 05-Aug-12 13-Aug-12 0 0% 100%
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
A126360 Approval of HVAC Layout & Details 14 12-Jun-12 A 27-Jun-12 A 15-Apr-12 02-May-12 16-Oct-12 05-Nov-12 129 100% 100%
A126420 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 24-Apr-12 13-May-12 24-Apr-12 13-May-12 0 100% 100%
A126370 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 15-Apr-12 02-May-12 25-Sep-12 14-Oct-12 114 100% 100%
A126380 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 15-Apr-12 02-May-12 25-Sep-12 14-Oct-12 114 100% 100%4th Floor4th Floor 50 03-May-12 A 21-Jun-12 A 14-Apr-12 03-Jun-12 07-May-12 14-Nov-12 100% 100%SubmissionSubmission 33 03-May-12 A 10-Jun-12 A 14-Apr-12 14-May-12 07-May-12 24-Oct-12 100% 100%A126480 Submission of Drainage Layout & Details 13 27-May-12 A 10-Jun-12 A 14-Apr-12 28-Apr-12 07-May-12 21-May-12 20 100% 100%
A126490 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 14-Apr-12 28-Apr-12 11-Sep-12 25-Sep-12 126 100% 100%
A126500 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 17-Apr-12 28-Apr-12 14-Oct-12 24-Oct-12 151 100% 100%
A126570 Submission of MEP Builder Work Layout 14 03-May-12 A 19-May-12 A 29-Apr-12 14-May-12 22-May-12 06-Jun-12 20 100% 100%
A126520 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 17-Apr-12 28-Apr-12 20-Sep-12 01-Oct-12 131 100% 100%
A126530 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 17-Apr-12 28-Apr-12 20-Sep-12 01-Oct-12 131 100% 100%ApprovalApproval 30 20-May-12 A 21-Jun-12 A 29-Apr-12 03-Jun-12 07-Jun-12 14-Nov-12 100% 100%A126630 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 29-Apr-12 16-May-12 26-Sep-12 15-Oct-12 105 100% 100%
A126640 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 29-Apr-12 16-May-12 26-Sep-12 15-Oct-12 105 100% 100%
A126650 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 29-Apr-12 16-May-12 28-Oct-12 14-Nov-12 126 100% 100%
A126720 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 15-May-12 03-Jun-12 07-Jun-12 27-Jun-12 17 100% 100%
A126670 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 29-Apr-12 16-May-12 02-Oct-12 21-Oct-12 109 100% 100%
A126680 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 29-Apr-12 16-May-12 02-Oct-12 21-Oct-12 109 100% 100%5th Floor5th Floor 46 08-May-12 A 21-Jun-12 A 24-May-12 28-Jun-12 29-May-12 09-Dec-12 100% 100%SubmissionSubmission 29 08-May-12 A 10-Jun-12 A 24-May-12 07-Jun-12 29-May-12 18-Nov-12 100% 100%A126780 Submission of Drainage Layout & Details 13 27-May-12 A 10-Jun-12 A 24-May-12 07-Jun-12 29-May-12 12-Jun-12 4 100% 100%
A126790 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 03-Oct-12 17-Oct-12 110 100% 100%
A126800 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 06-Nov-12 18-Nov-12 134 100% 100%
A126870 Submission of MEP Builder Work Layout 6 13-May-12 A 19-May-12 A 29-May-12 04-Jun-12 03-Jun-12 09-Jun-12 4 100% 100%
A126820 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 13-Oct-12 23-Oct-12 115 100% 100%
A126830 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 13-Oct-12 23-Oct-12 115 100% 100%ApprovalApproval 30 20-May-12 A 21-Jun-12 A 05-Jun-12 28-Jun-12 10-Jun-12 09-Dec-12 100% 100%A126930 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 15-Oct-12 04-Nov-12 88 100% 100%
A126940 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 18-Oct-12 07-Nov-12 91 100% 100%
A126950 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 19-Nov-12 09-Dec-12 111 100% 100%
A127020 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 05-Jun-12 25-Jun-12 10-Jun-12 28-Jun-12 3 100% 100%
A126970 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 10-Jun-12 28-Jun-12 24-Oct-12 13-Nov-12 95 100% 100%
A126980 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 10-Jun-12 28-Jun-12 24-Oct-12 13-Nov-12 95 100% 100%6th Floor6th Floor 46 08-May-12 A 21-Jun-12 A 24-May-12 24-Jul-12 24-May-12 18-Dec-12 88% 100%SubmissionSubmission 29 08-May-12 A 10-Jun-12 A 24-May-12 04-Jul-12 24-May-12 27-Nov-12 93.94% 100%A127080 Submission of Drainage Layout & Details 13 27-May-12 A 10-Jun-12 A 24-May-12 07-Jun-12 24-May-12 07-Jun-12 0 100% 100%
A127090 Submission of Water Supply Layout & Details 13 12-May-12 A 26-May-12 A 24-May-12 07-Jun-12 17-Oct-12 03-Nov-12 122 100% 100%
A127100 Submission of Fire Fighting Layout & Details 10 08-May-12 A 19-May-12 A 28-May-12 07-Jun-12 17-Nov-12 27-Nov-12 142 100% 100%
A127170 Submission of MEP Builder Work Layout 10 08-May-12 A 19-May-12 A 24-Jun-12 04-Jul-12 24-Jun-12 04-Jul-12 0 60% 100%
A127120 Submission of Lighting Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 21-Oct-12 03-Nov-12 122 100% 100%
A127130 Submission of Power Layout & Details 10 20-May-12 A 30-May-12 A 28-May-12 07-Jun-12 21-Oct-12 03-Nov-12 122 100% 100%ApprovalApproval 30 20-May-12 A 21-Jun-12 A 10-Jun-12 24-Jul-12 05-Jul-12 18-Dec-12 83.33% 100%A127230 Approval of Drainage Layout & Details 14 10-Jun-12 A 21-Jun-12 A 10-Jun-12 28-Jun-12 01-Nov-12 21-Nov-12 100 100% 100%
A127240 Approval of Water Supply Layout & Details 14 27-May-12 A 03-Jun-12 A 10-Jun-12 28-Jun-12 04-Nov-12 22-Nov-12 101 100% 100%
A127250 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 10-Jun-12 28-Jun-12 28-Nov-12 18-Dec-12 118 100% 100%
A127320 Approval of MEP Builder Work Layout 14 20-May-12 A 26-May-12 A 05-Jul-12 24-Jul-12 05-Jul-12 24-Jul-12 0 0% 100%
A127270 Approval of Lighting Layout & Details 14 31-May-12 A 12-Jun-12 A 10-Jun-12 28-Jun-12 04-Nov-12 22-Nov-12 101 100% 100%
A127280 Approval of Power Layout & Details 14 31-May-12 A 13-Jun-12 A 10-Jun-12 28-Jun-12 04-Nov-12 22-Nov-12 101 100% 100%7th Floor7th Floor 51 07-May-12 A 21-Jun-12 A 11-Jun-12 17-Jul-12 11-Jun-12 13-Dec-12 51.85% 100%SubmissionSubmission 44 07-May-12 A 17-Jun-12 A 11-Jun-12 27-Jun-12 11-Jun-12 24-Nov-12 100% 100%A127380 Submission of Drainage Layout & Details 14 11-Jun-12 A 17-Jun-12 A 11-Jun-12 27-Jun-12 11-Jun-12 27-Jun-12 0 100% 100%
A127390 Submission of Water Supply Layout & Details 14 12-May-12 A 27-May-12 A 11-Jun-12 27-Jun-12 29-Oct-12 13-Nov-12 115 100% 100%
A127400 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 14-Jun-12 27-Jun-12 11-Nov-12 24-Nov-12 123 100% 100%ApprovalApproval 34 20-May-12 A 21-Jun-12 A 28-Jun-12 17-Jul-12 14-Nov-12 13-Dec-12 7.14% 100%A127530 Approval of Drainage Layout & Details 14 18-Jun-12 A 21-Jun-12 A 28-Jun-12 17-Jul-12 14-Nov-12 05-Dec-12 96 7.14% 100%
A127540 Approval of Water Supply Layout & Details 14 28-May-12 A 03-Jun-12 A 28-Jun-12 17-Jul-12 14-Nov-12 05-Dec-12 96 7.14% 100%
A127550 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 28-Jun-12 17-Jul-12 25-Nov-12 13-Dec-12 102 7.14% 100%Roof FloorRoof Floor 27 07-May-12 A 05-Jun-12 A 07-Jul-12 07-Aug-12 06-Nov-12 10-Dec-12 0% 100%SubmissionSubmission 11 07-May-12 A 19-May-12 A 07-Jul-12 18-Jul-12 06-Nov-12 19-Nov-12 0% 100%A127740 Submission of Fire Fighting Layout & Details 11 07-May-12 A 19-May-12 A 07-Jul-12 18-Jul-12 06-Nov-12 19-Nov-12 101 0% 100%
ApprovalApproval 14 20-May-12 A 05-Jun-12 A 19-Jul-12 07-Aug-12 20-Nov-12 10-Dec-12 0% 100%A127890 Approval of Fire Fighting Layout & Details 14 20-May-12 A 05-Jun-12 A 19-Jul-12 07-Aug-12 20-Nov-12 10-Dec-12 84 0% 100%
Hotel (Block Hotel (Block B) 129 08-Feb-12 A 18-Jul-12 205 15-Feb-12 07-Aug-12 15-Feb-12 24-Mar-13 95% 90.74%
2nd Baseme2nd Basement Floor 91 08-Feb-12 A 18-Jul-12 196 15-Feb-12 26-Mar-12 15-Feb-12 13-Mar-13 100% 89.71%SubmissionSubmission 75 08-Feb-12 A 23-Apr-12 A 15-Feb-12 06-Mar-12 15-Feb-12 23-Feb-13 100% 100%A128230 Submission of Drainage Layout & Details 4 10-Mar-12 A 14-Mar-12 A 15-Feb-12 19-Feb-12 15-Feb-12 19-Feb-12 0 100% 100%
A128240 Submission of Water Supply Layout & Details 10 23-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 06-Feb-13 17-Feb-13 295 100% 100%
A128250 Submission of Fire Fighting Layout & Details 10 22-Feb-12 A 03-Mar-12 A 18-Feb-12 28-Feb-12 17-Jan-13 29-Jan-13 279 100% 100%
A128260 Submission of HVAC Layout & Details 10 07-Mar-12 A 17-Mar-12 A 18-Feb-12 28-Feb-12 27-Jan-13 06-Feb-13 286 100% 100%
A128270 Submission of MEP Cordination Layout 10 12-Apr-12 A 23-Apr-12 A 25-Feb-12 06-Mar-12 24-Dec-12 05-Jan-13 253 100% 100%
A128280 Submission of MEP Builder Work Layout 4 08-Feb-12 A 12-Feb-12 A 15-Feb-12 19-Feb-12 15-Feb-12 19-Feb-12 0 100% 100%
A128290 Submission of Lighting Layout & Details 10 09-Feb-12 A 20-Feb-12 A 18-Feb-12 28-Feb-12 16-Dec-12 26-Dec-12 252 100% 100%
A128300 Submission of Power Layout & Details 10 29-Mar-12 A 09-Apr-12 A 18-Feb-12 28-Feb-12 16-Dec-12 26-Dec-12 252 100% 100%
A128310 Submission of Fire Alarm Layout & Details 10 23-Feb-12 A 07-Mar-12 A 18-Feb-12 28-Feb-12 12-Feb-13 23-Feb-13 300 100% 100%ApprovalApproval 73 13-Feb-12 A 18-Jul-12 163 20-Feb-12 26-Mar-12 20-Feb-12 13-Mar-13 100% 83.33%A128380 Approval of Drainage Layout & Details 14 15-Mar-12 A 17-Mar-12 A 20-Feb-12 08-Mar-12 18-Feb-13 07-Mar-13 252 100% 100%
A128390 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 29-Feb-12 19-Mar-12 18-Feb-13 07-Mar-13 245 100% 100%
A128400 Approval of Fire Fighting Layout & Details 14 04-Mar-12 A 08-Mar-12 A 29-Feb-12 19-Mar-12 30-Jan-13 18-Feb-13 232 100% 100%
A128420 Approval of MEP Cordination Layout 14 24-Apr-12 A 06-May-12 A 07-Mar-12 26-Mar-12 30-Jan-13 18-Feb-13 227 100% 100%
A128430 Approval of MEP Builder Work Layout 14 13-Feb-12 A 05-Mar-12 A 20-Feb-12 08-Mar-12 20-Feb-12 08-Mar-12 0 100% 100%
A128440 Approval of Lighting Layout & Details 14 21-Feb-12 A 29-Feb-12 A 29-Feb-12 19-Mar-12 27-Dec-12 16-Jan-13 210 100% 100%
A135510 Approval of Power Layout & Details 14 10-Apr-12 A 24-Apr-12 A 29-Feb-12 19-Mar-12 27-Dec-12 16-Jan-13 210 100% 100%
A128410 Approval of HVAC Layout & Details 14 18-Mar-12 A 09-Jul-12 159 29-Feb-12 19-Mar-12 07-Feb-13 26-Feb-13 238 100% 50%
A128460 Approval of Fire Alarm Layout & Details 14 08-Mar-12 A 18-Jul-12 163 29-Feb-12 19-Mar-12 24-Feb-13 13-Mar-13 249 100% 0%1st Baseme1st Basement Floor 80 21-Feb-12 A 17-May-12 A 18-Feb-12 16-Apr-12 21-Mar-12 24-Mar-13 100% 100%SubmissionSubmission 80 21-Feb-12 A 21-Apr-12 A 18-Feb-12 27-Mar-12 21-Mar-12 04-Mar-13 100% 100%A128530 Submission of Drainage Layout & Details 10 10-Mar-12 A 18-Mar-12 A 18-Feb-12 28-Feb-12 21-Mar-12 01-Apr-12 28 100% 100%
A128540 Submission of Water Supply Layout & Details 10 21-Feb-12 A 03-Mar-12 A 10-Mar-12 20-Mar-12 13-Nov-12 25-Nov-12 208 100% 100%
A128550 Submission of Fire Fighting Layout & Details 10 01-Mar-12 A 10-Mar-12 A 10-Mar-12 20-Mar-12 04-Dec-12 15-Dec-12 224 100% 100%
A128560 Submission of HVAC Layout & Details 10 08-Mar-12 A 18-Mar-12 A 10-Mar-12 20-Mar-12 10-Nov-12 21-Nov-12 205 100% 100%
A128570 Submission of MEP Cordination Layout 10 02-Apr-12 A 12-Apr-12 A 17-Mar-12 27-Mar-12 22-Nov-12 04-Dec-12 209 100% 100%
A128580 Submission of MEP Builder Work Layout 10 10-Mar-12 A 18-Mar-12 A 25-Feb-12 06-Mar-12 28-Mar-12 08-Apr-12 28 100% 100%
A128590 Submission of Lighting Layout & Details 10 12-Mar-12 A 22-Mar-12 A 10-Mar-12 20-Mar-12 02-Oct-12 13-Oct-12 174 100% 100%
A128600 Submission of Power Layout & Details 10 18-Mar-12 A 28-Mar-12 A 10-Mar-12 20-Mar-12 02-Oct-12 13-Oct-12 174 100% 100%
A128610 Submission of Fire Alarm Layout & Details 10 04-Mar-12 A 14-Mar-12 A 10-Mar-12 20-Mar-12 10-Feb-13 20-Feb-13 280 100% 100%
A128620 Submission of CBS Layout & Details 10 04-Mar-12 A 14-Mar-12 A 10-Mar-12 20-Mar-12 21-Feb-13 04-Mar-13 290 100% 100%
A128630 Submission of CCTV,Access Control,Intercom Layout & Details 10 11-Apr-12 A 21-Apr-12 A 10-Mar-12 20-Mar-12 13-Nov-12 25-Nov-12 208 100% 100%
A128650 Submission of BMS Layout & Details 10 02-Apr-12 A 12-Apr-12 A 10-Mar-12 20-Mar-12 30-Oct-12 10-Nov-12 196 100% 100%
A128660 Submission of Data & Telephone Layout & Details 10 08-Apr-12 A 18-Apr-12 A 10-Mar-12 20-Mar-12 08-Nov-12 20-Nov-12 204 100% 100%ApprovalApproval 52 28-Feb-12 A 17-May-12 A 29-Feb-12 16-Apr-12 09-Apr-12 24-Mar-13 100% 100%A135520 Approval of Power Layout & Details 6 29-Mar-12 A 05-Apr-12 A 21-Mar-12 09-Apr-12 14-Oct-12 01-Nov-12 144 100% 100%
A128680 Approval of Drainage Layout & Details 14 19-Mar-12 A 27-Mar-12 A 29-Feb-12 19-Mar-12 27-Nov-12 17-Dec-12 189 100% 100%
A128690 Approval of Water Supply Layout & Details 14 04-Mar-12 A 13-Mar-12 A 21-Mar-12 09-Apr-12 26-Nov-12 16-Dec-12 173 100% 100%
A128700 Approval of Fire Fighting Layout & Details 14 11-Mar-12 A 18-Mar-12 A 21-Mar-12 09-Apr-12 16-Dec-12 03-Jan-13 186 100% 100%
A128710 Approval of HVAC Layout & Details 14 19-Mar-12 A 29-Mar-12 A 21-Mar-12 09-Apr-12 22-Nov-12 12-Dec-12 171 100% 100%
A128720 Approval of MEP Cordination Layout 14 15-Apr-12 A 24-Apr-12 A 28-Mar-12 16-Apr-12 05-Dec-12 24-Dec-12 174 100% 100%
A128730 Approval of MEP Builder Work Layout 14 28-Feb-12 A 21-Mar-12 A 07-Mar-12 26-Mar-12 09-Apr-12 26-Apr-12 23 100% 100%
A128740 Approval of Lighting Layout & Details 14 25-Mar-12 A 29-Mar-12 A 21-Mar-12 09-Apr-12 14-Oct-12 01-Nov-12 144 100% 100%
A128770 Approval of CBS Layout & Details 14 15-Mar-12 A 21-Mar-12 A 21-Mar-12 09-Apr-12 05-Mar-13 24-Mar-13 241 100% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s
s
s
Approval of HVAC Layout & Details
Approval of Fire Alarm Layout & Details
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 6 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
SubmissionSubmission 27 17-Mar-12 A 16-Apr-12 A 22-Sep-12 30-Oct-12 05-Feb-13 10-Mar-13 0% 100%A53720 Submission of Swimming Pool Layout & Details for Block A 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 19-Feb-13 04-Mar-13 123 0% 100%
A53730 Submission of Swimming Pool 's Water Prrofing for Block A 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 25-Feb-13 10-Mar-13 128 0% 100%
A118850 Submission of Swimming Pool Layout & Details for Block B 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 05-Feb-13 18-Feb-13 111 0% 100%
A118860 Submission of Swimming Pool 's Water Prrofing for Block B 12 17-Mar-12 A 29-Mar-12 A 22-Sep-12 04-Oct-12 11-Feb-13 24-Feb-13 116 0% 100%
A118870 Submission of Swimming Pool Layout & Details for Block C 12 03-Apr-12 A 16-Apr-12 A 15-Oct-12 30-Oct-12 10-Feb-13 23-Feb-13 95 0% 100%
A118880 Submission of Swimming Pool 's Water Prrofing for Block C 12 03-Apr-12 A 16-Apr-12 A 15-Oct-12 30-Oct-12 13-Feb-13 26-Feb-13 98 0% 100%
Method 0f SMethod 0f Statements 130 15-Feb-12 A 28-Jun-12 A 15-Feb-12 08-Aug-12 21-Feb-12 17-Nov-12 88.03% 100%
CivilCivil 130 15-Feb-12 A 25-Jun-12 A 15-Feb-12 24-Jun-12 21-Feb-12 15-Oct-12 100% 100%
A46480 Sub & App- MOS for Raft Slab Construction 4 15-Feb-12 A 23-Feb-12 A 15-Feb-12 19-Feb-12 21-Feb-12 25-Feb-12 5 100% 100%
A46500 Sub & App- MOS for Backfilling 30 15-Feb-12 A 15-Feb-12 A 20-May-12 24-Jun-12 11-Sep-12 15-Oct-12 95 100% 100%
A46510 Sub & App- MOS for Slabs Construction 17 20-Feb-12 A 10-Mar-12 A 20-Feb-12 10-Mar-12 26-Feb-12 15-Mar-12 5 100% 100%
A46520 Sub & App- MOS for Columns Construction 17 18-Feb-12 A 07-Mar-12 A 18-Feb-12 07-Mar-12 23-Feb-12 13-Mar-12 5 100% 100%
A46530 Sub & App- MOS for Retaining Walls Construction 18 18-Feb-12 A 08-Mar-12 A 18-Feb-12 08-Mar-12 22-Feb-12 13-Mar-12 4 100% 100%
A46540 Sub & App- MOS for Ramp Construction 17 21-Feb-12 A 11-Mar-12 A 21-Feb-12 11-Mar-12 14-Mar-12 02-Apr-12 19 100% 100%
A46550 Sub & App- MOS for Staircase Construction 30 11-Jun-12 A 25-Jun-12 A 19-May-12 23-Jun-12 10-Sep-12 14-Oct-12 95 100% 100%
A46560 Sub & App- MOS for Core Walls Constrcution 14 19-Feb-12 A 05-Mar-12 A 19-Feb-12 05-Mar-12 27-Feb-12 13-Mar-12 7 100% 100%
ArchitecturalArchitectural 30 11-Jun-12 A 28-Jun-12 A 30-May-12 08-Aug-12 17-Sep-12 17-Nov-12 43.33% 100%
A46570 Sub & App- MOS for Blocks Works 30 11-Jun-12 A 28-Jun-12 A 30-May-12 04-Jul-12 17-Sep-12 21-Oct-12 91 86.67% 100%
A46580 Sub & App- MOS for Plaster Works 30 11-Jun-12 A 28-Jun-12 A 05-Jul-12 08-Aug-12 10-Oct-12 17-Nov-12 81 0% 100%
Hotel AparteHotel Apartements (Block A) 124 15-Feb-12 A 01-Sep-12 78 18-Feb-12 04-Oct-12 18-Feb-12 28-Nov-12 79.73% 99.43%
Foundation LFoundation Level 13 15-Feb-12 A 28-Feb-12 A 18-Feb-12 11-Mar-12 18-Feb-12 11-Mar-12 100% 100%
Earth WorksEarth Works 8 15-Feb-12 A 15-Feb-12 A 18-Feb-12 28-Feb-12 18-Feb-12 28-Feb-12 100% 100%A1370 Excavation and Compaction 8 15-Feb-12 A 15-Feb-12 A 18-Feb-12 26-Feb-12 18-Feb-12 26-Feb-12 0 100% 100%
A1400 Base Coarse and Compaction 8 15-Feb-12 A 15-Feb-12 A 20-Feb-12 28-Feb-12 20-Feb-12 28-Feb-12 0 100% 100%Deep FoundDeep Foundation 13 15-Feb-12 A 28-Feb-12 A 22-Feb-12 11-Mar-12 22-Feb-12 11-Mar-12 100% 100%A1060 Laying Polythene Sheet & Blinding 7 15-Feb-12 A 15-Feb-12 A 22-Feb-12 29-Feb-12 22-Feb-12 29-Feb-12 0 100% 100%
A1080 Water Proofing & Screed 3 15-Feb-12 A 16-Feb-12 A 23-Feb-12 26-Feb-12 23-Feb-12 26-Feb-12 0 100% 100%
A1100 Raft Slab 1000 mm RC Works 13 15-Feb-12 A 28-Feb-12 A 26-Feb-12 11-Mar-12 26-Feb-12 11-Mar-12 0 100% 100%
A1160 MEP Works inside Raft Slab 4 20-Feb-12 A 23-Feb-12 A 27-Feb-12 01-Mar-12 07-Mar-12 11-Mar-12 8 100% 100%
1st Basemen1st Basement Floor Slab 102 15-Feb-12 A 24-Apr-12 A 12-Mar-12 30-Jun-12 14-Mar-12 21-Oct-12 100% 100%
Walls and CWalls and Columns 15 03-Mar-12 A 19-Mar-12 A 12-Mar-12 28-Mar-12 14-Mar-12 09-Apr-12 100% 100%A1110 Core Wall RC Works 6 13-Mar-12 A 19-Mar-12 A 14-Mar-12 20-Mar-12 14-Mar-12 20-Mar-12 0 100% 100%
A1120 Retaining Wall 250 mm RC Works 15 05-Mar-12 A 12-Mar-12 A 12-Mar-12 28-Mar-12 14-Mar-12 31-Mar-12 2 100% 100%
A1130 Ramp Wall RC Works 6 08-Mar-12 A 13-Mar-12 A 17-Mar-12 22-Mar-12 03-Apr-12 09-Apr-12 15 100% 100%
A1140 Columns RC Works 10 03-Mar-12 A 10-Mar-12 A 13-Mar-12 24-Mar-12 14-Mar-12 25-Mar-12 1 100% 100%SlabSlab 94 15-Feb-12 A 24-Apr-12 A 17-Mar-12 30-Jun-12 17-Mar-12 21-Oct-12 100% 100%A1150 MEP Works inside Slab 6 13-Mar-12 A 19-Mar-12 A 20-Mar-12 26-Mar-12 07-Apr-12 12-Apr-12 15 100% 100%
A1170 1st Basement Floor Slab RC Works 24 13-Mar-12 A 20-Mar-12 A 17-Mar-12 12-Apr-12 17-Mar-12 12-Apr-12 0 100% 100%
A1180 Curing for Slab 3 21-Mar-12 A 27-Mar-12 A 14-Apr-12 16-Apr-12 13-Sep-12 16-Sep-12 128 100% 100%
A1190 Strike Formwork 3 21-Apr-12 A 24-Apr-12 A 12-May-12 14-May-12 17-Sep-12 19-Sep-12 107 100% 100%
A1200 Ramp Slab RC Works 5 15-Mar-12 A 20-Mar-12 A 21-Mar-12 26-Mar-12 08-Apr-12 12-Apr-12 15 100% 100%
A1320 Water Proofing Membrane for Ret. Walls 10 29-Feb-12 A 06-Mar-12 A 17-May-12 28-May-12 23-Sep-12 03-Oct-12 107 100% 100%
A1330 Gunited Concrete 50 mm for Ret. Walls 10 15-Feb-12 A 16-Feb-12 A 29-May-12 09-Jun-12 04-Oct-12 15-Oct-12 107 100% 100%
A1360 Backfilling 5 22-Feb-12 A 22-Feb-12 A 25-Jun-12 30-Jun-12 16-Oct-12 21-Oct-12 95 100% 100%StairsStairs 6 20-Mar-12 A 20-Mar-12 A 24-Jun-12 30-Jun-12 15-Oct-12 21-Oct-12 100% 100%Stairs 1Stairs 1 6 20-Mar-12 A 20-Mar-12 A 24-Jun-12 30-Jun-12 15-Oct-12 21-Oct-12 100% 100%A1380 Stairs RC Works (2nd Basement to 1st Basement) 6 20-Mar-12 A 20-Mar-12 A 24-Jun-12 30-Jun-12 15-Oct-12 21-Oct-12 95 100% 100%
Ground FloorGround Floor Slab 53 15-Feb-12 A 23-May-12 A 14-Apr-12 12-Jul-12 14-Apr-12 24-Oct-12 96.62% 100%
Walls and CWalls and Columns 26 25-Mar-12 A 11-Apr-12 A 14-Apr-12 30-Apr-12 14-Apr-12 03-May-12 100% 100%A1220 Core Wall RC Works 6 25-Mar-12 A 01-Apr-12 A 15-Apr-12 21-Apr-12 15-Apr-12 21-Apr-12 0 100% 100%
A1230 Retaining Wall 250 mm RC Works 15 07-Apr-12 A 11-Apr-12 A 14-Apr-12 30-Apr-12 14-Apr-12 30-Apr-12 0 100% 100%
A1240 Ramp Wall RC Works 7 02-Apr-12 A 03-Apr-12 A 18-Apr-12 25-Apr-12 26-Apr-12 03-May-12 7 100% 100%
A1250 Columns RC Works 10 25-Mar-12 A 27-Mar-12 A 14-Apr-12 24-Apr-12 14-Apr-12 24-Apr-12 0 100% 100%SlabSlab 45 15-Feb-12 A 23-May-12 A 17-Apr-12 09-Jul-12 17-Apr-12 24-Oct-12 97.43% 100%A1260 MEP Works inside Slab 5 10-Apr-12 A 18-Apr-12 A 25-Apr-12 30-Apr-12 02-May-12 07-May-12 6 100% 100%
A1270 Ground Floor Slab RC Works 18 03-Apr-12 A 18-Apr-12 A 17-Apr-12 07-May-12 17-Apr-12 07-May-12 0 100% 100%
A1280 Curing for Slab 3 19-Apr-12 A 25-Apr-12 A 08-May-12 10-May-12 07-Aug-12 09-Aug-12 77 100% 100%
A1290 Strike Formwork 3 03-May-12 A 23-May-12 A 04-Jun-12 06-Jun-12 11-Aug-12 13-Aug-12 57 100% 100%
A1300 Ramp Slab RC Works 6 14-Apr-12 A 14-Apr-12 A 23-Apr-12 29-Apr-12 01-May-12 07-May-12 7 100% 100%
A1340 Water Proofing Membrane for Ret. Walls 10 03-Apr-12 A 10-Apr-12 A 10-Jun-12 21-Jun-12 26-Sep-12 07-Oct-12 90 100% 100%
A1350 Gunited Concrete 50 mm for Ret. Walls 10 15-Feb-12 A 16-Feb-12 A 23-Jun-12 03-Jul-12 08-Oct-12 18-Oct-12 90 70% 100%
A1520 Backfilling 5 15-Feb-12 A 15-Feb-12 A 04-Jul-12 09-Jul-12 20-Oct-12 24-Oct-12 90 0% 100%StairsStairs 6 12-Apr-12 A 18-Apr-12 A 07-Jul-12 12-Jul-12 18-Oct-12 24-Oct-12 0% 100%Stair 1Stair 1 6 12-Apr-12 A 18-Apr-12 A 07-Jul-12 12-Jul-12 18-Oct-12 24-Oct-12 0% 100%A1530 Stairs RC Works (1st Basement to Ground) 6 12-Apr-12 A 18-Apr-12 A 07-Jul-12 12-Jul-12 18-Oct-12 24-Oct-12 87 0% 100%
1st Floor Slab1st Floor Slab 42 22-Apr-12 A 15-Jun-12 A 08-May-12 05-Aug-12 08-May-12 06-Nov-12 90.44% 100%
Walls and CWalls and Columns 10 22-Apr-12 A 01-May-12 A 08-May-12 17-May-12 08-May-12 17-May-12 100% 100%A1390 Core Wall RC Works 6 23-Apr-12 A 28-Apr-12 A 08-May-12 14-May-12 08-May-12 14-May-12 0 100% 100%
A1420 Columns RC Works 9 22-Apr-12 A 01-May-12 A 08-May-12 17-May-12 08-May-12 17-May-12 0 100% 100%SlabSlab 36 29-Apr-12 A 15-Jun-12 A 13-May-12 05-Jul-12 13-May-12 17-Oct-12 96.25% 100%A1430 MEP Works inside Slab 5 06-May-12 A 13-May-12 A 19-May-12 23-May-12 29-May-12 03-Jun-12 9 100% 100%
A1440 1st Floor Slab RC Works 19 29-Apr-12 A 14-May-12 A 13-May-12 03-Jun-12 13-May-12 03-Jun-12 0 100% 100%
A1450 Curing for Slab 3 16-May-12 A 20-May-12 A 04-Jun-12 06-Jun-12 11-Oct-12 14-Oct-12 108 100% 100%
A1460 Strike Formwork 3 06-Jun-12 A 15-Jun-12 A 03-Jul-12 05-Jul-12 15-Oct-12 17-Oct-12 87 0% 100%StairsStairs 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 22-Oct-12 06-Nov-12 0% 100%Stair 1Stair 1 6 29-Apr-12 A 14-May-12 A 30-Jul-12 05-Aug-12 22-Oct-12 30-Oct-12 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
Sub & App- GSM System
Sub & App- MATV/ Interactive TV System
Sub & App- Generators
Sub & App- Telephone System
Sub & App- DBs
Sub & App- MDBs
Sub & App- SMDBs
Sub & App- Pool Finishes
Sub & App- Pool Equipments
Sub & App- Water Proofing for Swimming Pool
Sub & App- Pool Electrical Items
s Order&Delivery- Plaster Materials
s Order&Delivery- Blocks
Order&Delivery- Chilled Water Pipes-Fittings-Valves
Walls and CWalls and Columns 9 16-May-12 A 24-May-12 A 04-Jun-12 13-Jun-12 04-Jun-12 13-Jun-12 100% 100%A1560 Core Wall RC Works 6 17-May-12 A 21-May-12 A 04-Jun-12 10-Jun-12 04-Jun-12 10-Jun-12 0 100% 100%
A1570 Columns RC Works 9 16-May-12 A 24-May-12 A 04-Jun-12 13-Jun-12 04-Jun-12 13-Jun-12 0 100% 100%SlabSlab 31 19-May-12 A 04-Jul-12 55 09-Jun-12 29-Jul-12 09-Jun-12 09-Sep-12 93.47% 100%A1580 MEP Works inside Slab 5 22-May-12 A 30-May-12 A 14-Jun-12 20-Jun-12 26-Jun-12 01-Jul-12 9 100% 100%
A1590 2nd Floor Slab RC Works 19 19-May-12 A 30-May-12 A 09-Jun-12 01-Jul-12 09-Jun-12 01-Jul-12 0 94.74% 100%
A1600 Curing for Slab 3 31-May-12 A 06-Jun-12 A 02-Jul-12 04-Jul-12 03-Sep-12 05-Sep-12 52 0% 100%
A1610 Strike Formwork 3 21-Jun-12 A 04-Jul-12 55 26-Jul-12 29-Jul-12 06-Sep-12 09-Sep-12 34 0% 95%StairsStairs 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 04-Nov-12 13-Nov-12 0% 100%Stair 1Stair 1 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 04-Nov-12 10-Nov-12 0% 100%A1630 Stairs RC Works (1st to 2nd) 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 04-Nov-12 10-Nov-12 59 0% 100%
Stair 2Stair 2 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 07-Nov-12 13-Nov-12 0% 100%A1640 Stairs RC Works (1st to 2nd) 6 26-May-12 A 30-May-12 A 25-Aug-12 30-Aug-12 07-Nov-12 13-Nov-12 62 0% 100%
3rd Floor Slab3rd Floor Slab 18 02-Jun-12 A 25-Jun-12 A 02-Jul-12 18-Sep-12 02-Jul-12 21-Nov-12 0% 100%
Walls and CWalls and Columns 9 02-Jun-12 A 10-Jun-12 A 02-Jul-12 11-Jul-12 02-Jul-12 11-Jul-12 0% 100%A1650 Core Wall RC Works 6 02-Jun-12 A 05-Jun-12 A 02-Jul-12 08-Jul-12 02-Jul-12 08-Jul-12 0 0% 100%
A1660 Columns RC Works 9 02-Jun-12 A 10-Jun-12 A 02-Jul-12 11-Jul-12 02-Jul-12 11-Jul-12 0 0% 100%SlabSlab 13 07-Jun-12 A 25-Jun-12 A 08-Jul-12 24-Jul-12 08-Jul-12 28-Aug-12 0% 100%A1670 MEP Works inside Slab 4 09-Jun-12 A 16-Jun-12 A 09-Jul-12 12-Jul-12 17-Jul-12 21-Jul-12 7 0% 100%
A1680 3rd Floor Slab RC Works 12 07-Jun-12 A 18-Jun-12 A 08-Jul-12 21-Jul-12 08-Jul-12 21-Jul-12 0 0% 100%
A1690 Curing for Slab 3 19-Jun-12 A 25-Jun-12 A 22-Jul-12 24-Jul-12 26-Aug-12 28-Aug-12 28 0% 100%StairsStairs 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 11-Nov-12 21-Nov-12 0% 100%Stair 1Stair 1 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 11-Nov-12 18-Nov-12 0% 100%A1710 Stairs RC Works (2nd to 3rd) 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 11-Nov-12 18-Nov-12 49 0% 100%
Stair 2Stair 2 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 14-Nov-12 21-Nov-12 0% 100%A1720 Stairs RC Works (2nd to 3rd) 6 09-Jun-12 A 18-Jun-12 A 12-Sep-12 18-Sep-12 14-Nov-12 21-Nov-12 52 0% 100%
Walls and CWalls and Columns 9 19-Jun-12 A 26-Jun-12 A 22-Jul-12 31-Jul-12 22-Jul-12 31-Jul-12 0% 100%A1730 Core Wall RC Works 6 23-Jun-12 A 26-Jun-12 A 22-Jul-12 28-Jul-12 22-Jul-12 28-Jul-12 0 0% 100%
A1740 Columns RC Works 9 19-Jun-12 A 24-Jun-12 A 22-Jul-12 31-Jul-12 22-Jul-12 31-Jul-12 0 0% 100%SlabSlab 12 25-Jun-12 A 05-Jul-12 29 26-Jul-12 08-Aug-12 26-Jul-12 08-Aug-12 0% 90%A1750 MEP Works inside Slab 4 25-Jun-12 A 04-Jul-12 30 30-Jul-12 02-Aug-12 05-Aug-12 08-Aug-12 5 0% 90%
A1760 4th Slab RC Works 12 25-Jun-12 A 05-Jul-12 29 26-Jul-12 08-Aug-12 26-Jul-12 08-Aug-12 0 0% 90%StairsStairs 6 25-Jun-12 A 01-Sep-12 74 29-Sep-12 04-Oct-12 19-Nov-12 28-Nov-12 0% 90%Stair 1Stair 1 6 25-Jun-12 A 01-Sep-12 71 29-Sep-12 04-Oct-12 19-Nov-12 25-Nov-12 0% 90%A1790 Stairs RC Works (3rd to 4th) 6 25-Jun-12 A 01-Sep-12 71 29-Sep-12 04-Oct-12 19-Nov-12 25-Nov-12 41 0% 90%
Stair 2Stair 2 6 25-Jun-12 A 01-Sep-12 74 29-Sep-12 04-Oct-12 22-Nov-12 28-Nov-12 0% 90%A1800 Stairs RC Works (3rd to 4th) 6 25-Jun-12 A 01-Sep-12 74 29-Sep-12 04-Oct-12 22-Nov-12 28-Nov-12 44 0% 90%
Hotel (BlockHotel (Block B) 114 15-Feb-12 A 09-Jul-12 163 18-Feb-12 07-Oct-12 18-Feb-12 05-Mar-13 70.25% 97.34%
Foundation LFoundation Level 55 03-Mar-12 A 12-Apr-12 A 18-Feb-12 30-Apr-12 18-Feb-12 30-Apr-12 100% 100%
Earth WorksEarth Works 9 03-Mar-12 A 07-Apr-12 A 18-Feb-12 27-Mar-12 18-Feb-12 27-Mar-12 100% 100%Part 1 (B1)Part 1 (B1) 9 03-Mar-12 A 19-Mar-12 A 18-Feb-12 03-Mar-12 18-Feb-12 13-Mar-12 100% 100%A12320 Excavation and Compaction 8 03-Mar-12 A 18-Mar-12 A 18-Feb-12 26-Feb-12 18-Feb-12 26-Feb-12 0 100% 100%
A12330 Base Coarse and Compaction 8 04-Mar-12 A 19-Mar-12 A 23-Feb-12 03-Mar-12 05-Mar-12 13-Mar-12 9 100% 100%Part 2 (B2)Part 2 (B2) 9 03-Mar-12 A 07-Apr-12 A 12-Mar-12 27-Mar-12 12-Mar-12 27-Mar-12 100% 100%A12730 Excavation and Compaction 8 03-Mar-12 A 04-Apr-12 A 12-Mar-12 20-Mar-12 12-Mar-12 20-Mar-12 0 100% 100%
A12740 Base Coarse and Compaction 8 04-Mar-12 A 07-Apr-12 A 19-Mar-12 27-Mar-12 19-Mar-12 27-Mar-12 0 100% 100%Deep FoundDeep Foundation 48 11-Mar-12 A 12-Apr-12 A 01-Mar-12 30-Apr-12 12-Mar-12 30-Apr-12 100% 100%Part 1 (B1)Part 1 (B1) 36 11-Mar-12 A 30-Mar-12 A 01-Mar-12 08-Apr-12 12-Mar-12 18-Apr-12 100% 100%A11520 Laying Polythene Sheet & Blinding 5 11-Mar-12 A 19-Mar-12 A 01-Mar-12 06-Mar-12 12-Mar-12 17-Mar-12 9 100% 100%
A11530 Water Proofing & Screed 7 13-Mar-12 A 20-Mar-12 A 06-Mar-12 13-Mar-12 17-Mar-12 24-Mar-12 9 100% 100%
A11540 Raft Slab 1000 mm RC Works (Part 1) 25 24-Mar-12 A 30-Mar-12 A 11-Mar-12 08-Apr-12 21-Mar-12 18-Apr-12 9 100% 100%
A11580 MEP Works inside Raft Slab 7 25-Mar-12 A 27-Mar-12 A 14-Mar-12 21-Mar-12 11-Apr-12 18-Apr-12 24 100% 100%Part 2 (B2)Part 2 (B2) 42 18-Mar-12 A 12-Apr-12 A 24-Mar-12 30-Apr-12 24-Mar-12 30-Apr-12 100% 100%A12750 Laying Polythene Sheet & Blinding 4 19-Mar-12 A 07-Apr-12 A 24-Mar-12 27-Mar-12 24-Mar-12 27-Mar-12 0 100% 100%
A12760 Water Proofing & Screed 6 18-Mar-12 A 09-Apr-12 A 27-Mar-12 02-Apr-12 27-Mar-12 02-Apr-12 0 100% 100%
A12780 Raft Slab 1000 mm RC Works (Part 2) 25 07-Apr-12 A 12-Apr-12 A 02-Apr-12 30-Apr-12 02-Apr-12 30-Apr-12 0 100% 100%
A12770 MEP Works inside Raft Slab 10 09-Apr-12 A 10-Apr-12 A 03-Apr-12 14-Apr-12 19-Apr-12 30-Apr-12 14 100% 100%
1st Basemen1st Basement Floor Slab 94 15-Feb-12 A 09-Jun-12 A 09-Apr-12 15-Aug-12 02-May-12 05-Mar-13 95.67% 100%
Walls and CWalls and Columns 27 01-Apr-12 A 03-May-12 A 09-Apr-12 12-May-12 02-May-12 16-Jun-12 100% 100%Part 1 (B1)Part 1 (B1) 13 01-Apr-12 A 18-Apr-12 A 09-Apr-12 06-May-12 09-May-12 20-May-12 100% 100%A11550 Core Wall RC Works 8 15-Apr-12 A 18-Apr-12 A 28-Apr-12 06-May-12 12-May-12 20-May-12 12 100% 100%
A11560 Retaining Wall 250 mm RC Works (Part 1) 10 04-Apr-12 A 07-Apr-12 A 09-Apr-12 19-Apr-12 09-May-12 20-May-12 26 100% 100%
A11570 Columns RC Works 6 07-Apr-12 A 15-Apr-12 A 10-Apr-12 16-Apr-12 10-May-12 16-May-12 26 100% 100%
A12340 Tank Wall RC Works 6 01-Apr-12 A 18-Apr-12 A 10-Apr-12 16-Apr-12 10-May-12 16-May-12 26 100% 100%Part 2 (B2)Part 2 (B2) 26 02-Apr-12 A 03-May-12 A 02-May-12 12-May-12 02-May-12 16-Jun-12 100% 100%A12810 Core Wall RC Works 6 16-Apr-12 A 23-Apr-12 A 03-May-12 09-May-12 07-Jun-12 13-Jun-12 30 100% 100%
A12820 Retaining Wall 250 mm RC Works (Part 2) 8 23-Apr-12 A 30-Apr-12 A 03-May-12 12-May-12 07-Jun-12 16-Jun-12 30 100% 100%
A12790 Columns RC Works 8 21-Apr-12 A 01-May-12 A 02-May-12 10-May-12 02-May-12 10-May-12 0 100% 100%
A12800 Tank Wall RC Works 6 02-Apr-12 A 03-May-12 A 02-May-12 08-May-12 07-Jun-12 13-Jun-12 31 100% 100%
A12610 Ramp Wall RC Works 8 16-Apr-12 A 22-Apr-12 A 02-May-12 10-May-12 02-May-12 10-May-12 0 100% 100%SlabSlab 94 15-Feb-12 A 09-Jun-12 A 03-May-12 04-Aug-12 12-May-12 21-Nov-12 97.13% 100%A11590 MEP Works inside Slab 5 23-Apr-12 A 03-May-12 A 03-May-12 08-May-12 07-Jun-12 12-Jun-12 30 100% 100%
A11600 1st Basement Floor Slab RC Works 25 11-Apr-12 A 06-May-12 A 15-May-12 12-Jun-12 15-May-12 12-Jun-12 0 100% 100%
A11610 Curing for Slab 3 26-Apr-12 A 12-May-12 A 13-Jun-12 16-Jun-12 21-Oct-12 23-Oct-12 108 100% 100%
A11620 Strike Formwork 3 20-May-12 A 09-Jun-12 A 10-Jul-12 12-Jul-12 24-Oct-12 29-Oct-12 89 0% 100%
A12200 Ramp Slab RC Works 5 15-Apr-12 A 26-Apr-12 A 12-May-12 16-May-12 12-May-12 16-May-12 0 100% 100%
A11720 Water Proofing Membrane for Ret. Walls 7 10-Mar-12 A 08-Apr-12 A 16-Jul-12 23-Jul-12 01-Nov-12 08-Nov-12 89 0% 100%
A11730 Gunited Concrete 50 mm for Ret. Walls 7 15-Feb-12 A 16-Feb-12 A 24-Jul-12 31-Jul-12 10-Nov-12 18-Nov-12 89 0% 100%
A11820 Backfilling 3 15-Feb-12 A 15-Feb-12 A 01-Aug-12 04-Aug-12 19-Nov-12 21-Nov-12 89 0% 100%StairsStairs 13 22-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 14-Nov-12 05-Mar-13 0% 100%Stairs 1Stairs 1 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 14-Nov-12 21-Nov-12 0% 100%A12350 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 14-Nov-12 21-Nov-12 79 0% 100%
Stairs 2Stairs 2 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 07-Jan-13 13-Jan-13 0% 100%A12360 Stairs RC Works (2nd Basement to 1st Basement) 6 23-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 07-Jan-13 13-Jan-13 122 0% 100%
Stairs 3Stairs 3 6 22-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 27-Feb-13 05-Mar-13 0% 100%A12370 Stairs RC Works (2nd Basement to 1st Basement) 6 22-Apr-12 A 26-Apr-12 A 09-Aug-12 15-Aug-12 27-Feb-13 05-Mar-13 165 0% 100%
Ground FloorGround Floor Slab 65 15-Feb-12 A 10-Jun-12 A 13-Jun-12 15-Sep-12 13-Jun-12 25-Dec-12 63.91% 100%
Walls and CWalls and Columns 21 28-Apr-12 A 30-May-12 A 13-Jun-12 08-Jul-12 13-Jun-12 08-Jul-12 85.65% 100%A11640 Core Wall RC Works 15 28-Apr-12 A 20-May-12 A 14-Jun-12 02-Jul-12 14-Jun-12 02-Jul-12 0 86.67% 100%
A11650 Retaining Wall 250 mm RC Works 21 29-Apr-12 A 29-May-12 A 13-Jun-12 08-Jul-12 13-Jun-12 08-Jul-12 0 66.67% 100%
A11660 Columns RC Works 11 28-Apr-12 A 30-May-12 A 13-Jun-12 26-Jun-12 13-Jun-12 26-Jun-12 0 100% 100%
A117050 Ramp Wall RC Works 6 10-May-12 A 20-May-12 A 13-Jun-12 20-Jun-12 26-Jun-12 02-Jul-12 10 100% 100%SlabSlab 62 15-Feb-12 A 10-Jun-12 A 20-Jun-12 02-Sep-12 20-Jun-12 26-Nov-12 51.53% 100%A11670 MEP Works inside Slab 10 14-May-12 A 02-Jun-12 A 21-Jun-12 02-Jul-12 30-Jun-12 10-Jul-12 7 80% 100%
A11680 Ground Floor Slab RC Works 18 08-May-12 A 03-Jun-12 A 20-Jun-12 10-Jul-12 20-Jun-12 10-Jul-12 0 50% 100%
A11690 Curing for Slab 3 24-May-12 A 10-Jun-12 A 11-Jul-12 14-Jul-12 04-Oct-12 07-Oct-12 71 0% 100%
A117060 Ramp Slab RC Works 7 20-May-12 A 23-May-12 A 21-Jun-12 28-Jun-12 03-Jul-12 10-Jul-12 10 100% 100%
A11740 Water Proofing Membrane for Ret. Walls 7 02-May-12 A 26-May-12 A 12-Aug-12 21-Aug-12 06-Nov-12 13-Nov-12 70 0% 100%
A11750 Gunited Concrete 50 mm for Ret. Walls 7 15-Feb-12 A 16-Feb-12 A 22-Aug-12 29-Aug-12 14-Nov-12 22-Nov-12 70 0% 100%
A11830 Backfilling 3 15-Feb-12 A 15-Feb-12 A 30-Aug-12 02-Sep-12 24-Nov-12 26-Nov-12 70 0% 100%StairsStairs 12 20-May-12 A 03-Jun-12 A 09-Sep-12 15-Sep-12 20-Nov-12 25-Dec-12 0% 100%Stairs 1Stairs 1 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 20-Nov-12 26-Nov-12 0% 100%A12380 Stairs RC Works (1st Basement toGround) 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 20-Nov-12 26-Nov-12 59 0% 100%
Stairs 2Stairs 2 6 20-May-12 A 23-May-12 A 09-Sep-12 15-Sep-12 05-Dec-12 11-Dec-12 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
rk Strike Formwork
ab
ks
ks
ab MEP Works inside Slab
ks 4th Slab RC Works
h) Stairs RC Works (3rd to 4th)
h) Stairs RC Works (3rd to 4th)
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 12 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
Walls and CWalls and Columns 12 29-May-12 A 20-Jun-12 A 11-Jul-12 21-Jul-12 11-Jul-12 21-Jul-12 0% 100%A11760 Core Wall RC Works 6 29-May-12 A 10-Jun-12 A 11-Jul-12 17-Jul-12 15-Jul-12 21-Jul-12 3 0% 100%
A11770 Columns RC Works 9 03-Jun-12 A 20-Jun-12 A 11-Jul-12 21-Jul-12 11-Jul-12 21-Jul-12 0 0% 100%SlabSlab 19 06-Jun-12 A 01-Jul-12 100 22-Jul-12 08-Aug-12 22-Jul-12 30-Oct-12 0% 100%A11780 MEP Works inside Slab 5 07-Jun-12 A 24-Jun-12 A 22-Jul-12 26-Jul-12 31-Jul-12 05-Aug-12 8 0% 100%
A11790 1st Floor Slab RC Works 13 06-Jun-12 A 25-Jun-12 A 22-Jul-12 05-Aug-12 22-Jul-12 05-Aug-12 0 0% 100%
A11800 Curing for Slab 3 26-Jun-12 A 01-Jul-12 100 06-Aug-12 08-Aug-12 28-Oct-12 30-Oct-12 67 0% 80%StairsStairs 7 21-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 03-Jan-13 21-Feb-13 0% 100%Stairs 1Stairs 1 6 21-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 03-Jan-13 09-Jan-13 0% 100%A12410 Stairs RC Works (Ground to 1st floor) 6 21-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 03-Jan-13 09-Jan-13 76 0% 100%
Stairs 2Stairs 2 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 17-Jan-13 23-Jan-13 0% 100%A12420 Stairs RC Works (Ground to 1st floor) 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 17-Jan-13 23-Jan-13 88 0% 100%
Stairs 3Stairs 3 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 02-Feb-13 07-Feb-13 0% 100%A12430 Stairs RC Works (Ground to 1st floor) 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 02-Feb-13 07-Feb-13 100 0% 100%
Stairs 4Stairs 4 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 16-Feb-13 21-Feb-13 0% 100%A109130 Stairs RC Works (Ground to 1st floor) 6 23-Jun-12 A 25-Jun-12 A 01-Oct-12 07-Oct-12 16-Feb-13 21-Feb-13 112 0% 100%
Walls and CWalls and Columns 30 12-Apr-12 A 22-May-12 A 09-Jun-12 03-Jul-12 09-Jun-12 03-Jul-12 93.85% 100%A10310 Core Wall RC Works 15 18-Apr-12 A 13-May-12 A 10-Jun-12 27-Jun-12 10-Jun-12 27-Jun-12 0 100% 100%
A10320 Retaining Wall 250 mm RC Works 21 24-Apr-12 A 21-May-12 A 09-Jun-12 03-Jul-12 09-Jun-12 03-Jul-12 0 85.71% 100%
A10340 Columns RC Works 11 12-Apr-12 A 22-May-12 A 09-Jun-12 21-Jun-12 09-Jun-12 21-Jun-12 0 100% 100%SlabSlab 68 15-Feb-12 A 02-Jul-12 198 13-Jun-12 28-Aug-12 13-Jun-12 02-Mar-13 85.33% 98.59%A10350 MEP Works inside Slab 8 14-May-12 A 29-May-12 A 24-Jun-12 02-Jul-12 24-Jun-12 02-Jul-12 0 75% 100%
A10360 Ground Floor Slab RC Works 16 01-May-12 A 29-May-12 A 13-Jun-12 02-Jul-12 13-Jun-12 02-Jul-12 0 87.5% 100%
A10370 Curing for Slab 3 17-May-12 A 30-May-12 A 03-Jul-12 05-Jul-12 24-Oct-12 29-Oct-12 95 0% 100%
Walls and CWalls and Columns 12 19-May-12 A 23-Jun-12 A 03-Jul-12 12-Jul-12 03-Jul-12 12-Jul-12 0% 100%A10460 Core Wall RC Works 6 26-May-12 A 20-Jun-12 A 03-Jul-12 09-Jul-12 03-Jul-12 09-Jul-12 0 0% 100%
A10470 Columns RC Works 9 19-May-12 A 23-Jun-12 A 03-Jul-12 12-Jul-12 03-Jul-12 12-Jul-12 0 0% 100%SlabSlab 11 02-Jun-12 A 02-Jul-12 100 08-Jul-12 22-Jul-12 08-Jul-12 30-Oct-12 0% 99.99%A10480 MEP Works inside Slab 5 02-Jun-12 A 28-Jun-12 A 14-Jul-12 18-Jul-12 14-Jul-12 18-Jul-12 0 0% 100%
A10490 1st Floor Slab RC Works 10 02-Jun-12 A 30-Jun-12 A 08-Jul-12 18-Jul-12 08-Jul-12 18-Jul-12 0 0% 100%
A10500 Curing for Slab 3 14-Jun-12 A 02-Jul-12 100 19-Jul-12 22-Jul-12 28-Oct-12 30-Oct-12 82 0% 50%StairsStairs 17 04-Jun-12 A 30-Jun-12 A 09-Sep-12 06-Oct-12 13-Dec-12 01-Apr-13 0% 100%Stairs 1Stairs 1 6 04-Jun-12 A 10-Jun-12 A 09-Sep-12 15-Sep-12 13-Dec-12 19-Dec-12 0% 100%A11290 Stairs RC Works (Ground to 1st floor) 6 04-Jun-12 A 10-Jun-12 A 09-Sep-12 15-Sep-12 13-Dec-12 19-Dec-12 78 0% 100%
Stairs 2Stairs 2 6 04-Jun-12 A 09-Jun-12 A 16-Sep-12 22-Sep-12 04-Feb-13 10-Feb-13 0% 100%A11300 Stairs RC Works (Ground to 1st floor) 6 04-Jun-12 A 09-Jun-12 A 16-Sep-12 22-Sep-12 04-Feb-13 10-Feb-13 115 0% 100%
Stairs 3Stairs 3 6 18-Jun-12 A 30-Jun-12 A 23-Sep-12 29-Sep-12 19-Mar-13 25-Mar-13 0% 100%A11310 Stairs RC Works (Ground to 1st floor) 6 18-Jun-12 A 30-Jun-12 A 23-Sep-12 29-Sep-12 19-Mar-13 25-Mar-13 146 0% 100%
Stairs 4Stairs 4 6 18-Jun-12 A 30-Jun-12 A 30-Sep-12 06-Oct-12 26-Mar-13 01-Apr-13 0% 100%A109210 Stairs RC Works (Ground to 1st floor) 6 18-Jun-12 A 30-Jun-12 A 30-Sep-12 06-Oct-12 26-Mar-13 01-Apr-13 146 0% 100%
Public AreaPublic Area 3 24-Jun-12 A 30-Aug-12 42 26-Aug-12 01-Sep-12 11-Oct-12 17-Oct-12 0% 10%Garbage RGarbage Room 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 0% 10%Finishing Finishing Works 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 0% 10%Wet WorWet Works 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 0% 10%A14500 Block Works 3 24-Jun-12 A 30-Aug-12 42 29-Aug-12 01-Sep-12 15-Oct-12 17-Oct-12 40 0% 10%
Corridor &Corridor & Lift Lobby 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%Finishing Finishing Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%Wet WorWet Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 0% 10%A9810 Block Works 3 24-Jun-12 A 27-Aug-12 42 26-Aug-12 28-Aug-12 11-Oct-12 14-Oct-12 40 0% 10%
Hotel (BlockHotel (Block B) 8 11-Jun-12 A 28-Jun-12 A 15-Oct-12 03-Nov-12 09-Jan-13 05-Feb-13 0% 100%
2nd Basemen2nd Basement Floor 8 11-Jun-12 A 28-Jun-12 A 15-Oct-12 03-Nov-12 09-Jan-13 05-Feb-13 0% 100%
Public AreaPublic Area 8 11-Jun-12 A 28-Jun-12 A 15-Oct-12 03-Nov-12 09-Jan-13 05-Feb-13 0% 100%Boiler RooBoiler Room 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 0% 100%Finishing Finishing Works 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 0% 100%Wet WorWet Works 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 0% 100%A54270 Block Works 8 11-Jun-12 A 28-Jun-12 A 23-Oct-12 03-Nov-12 28-Jan-13 05-Feb-13 77 0% 100%
GSM RoomGSM Rooms 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 0% 100%Finishing Finishing Works 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 0% 100%Wet WorWet Works 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 0% 100%A54500 Block Works 5 11-Jun-12 A 28-Jun-12 A 17-Oct-12 22-Oct-12 12-Jan-13 16-Jan-13 69 0% 100%
MechanicaMechanical Room 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 0% 100%Finishing Finishing Works 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 0% 100%Wet WorWet Works 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 0% 100%A105090 Block Works 2 11-Jun-12 A 28-Jun-12 A 15-Oct-12 16-Oct-12 09-Jan-13 10-Jan-13 69 0% 100%
Residential Residential Apartments (Block C) 6 11-Jun-12 A 28-Jun-12 A 16-Aug-12 02-Sep-12 14-Nov-12 29-Nov-12 0% 100%
2nd Basemen2nd Basement Floor 6 11-Jun-12 A 28-Jun-12 A 16-Aug-12 02-Sep-12 14-Nov-12 29-Nov-12 0% 100%
Public AreaPublic Area 6 11-Jun-12 A 28-Jun-12 A 16-Aug-12 02-Sep-12 14-Nov-12 29-Nov-12 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s
ks Plaster Works
s
ks Plaster Works
s
ks Plaster Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
ks Block Works
s
s
s
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 14 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
Lift LobbyLift Lobby 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 0% 100%Finishing Finishing Works 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 0% 100%Wet WorWet Works 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 0% 100%A67580 Block Works 5 11-Jun-12 A 28-Jun-12 A 16-Aug-12 23-Aug-12 14-Nov-12 20-Nov-12 73 0% 100%
MechanicaMechanical Rooms 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 0% 100%Finishing Finishing Works 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 0% 100%Wet WorWet Works 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 0% 100%A67170 Block Works 2 11-Jun-12 A 28-Jun-12 A 25-Aug-12 26-Aug-12 21-Nov-12 22-Nov-12 73 0% 100%
Pump RooPump Room 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 0% 100%Finishing Finishing Works 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 0% 100%Wet WorWet Works 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 0% 100%A67310 Block Works 6 11-Jun-12 A 28-Jun-12 A 27-Aug-12 02-Sep-12 24-Nov-12 29-Nov-12 73 0% 100%
M Jun Jul A S Oct N D Jan F Mar Apr M J Jul A S Oct N D
2012 2013
s
s
s
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Data Date : 01-Jul-12 Page : 15 of 15Printed On : 05-Jul-12
Actual Work
Remaining Work
Critical Remaining Work
Project Implementation ScheduleUpdated Schedule up to 30-June-12
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
6.0 PROJECT PROGRAM UPDATE
6.2 PACKAGES PLANNED VS ACTUAL PERCENTAGES
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Total Float Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Schedule %Complete
Performance %Complete
Al MuraqqAl Muraqqabat Mixed Use Development 597 06-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 12.78% 13.54%
24-Mar-12 Project Implementation Schedule - Rev 01 On 11-April-20...
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Client: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
6.0 PROJECT PROGRAM UPDATE
6.3 TWO MONTHS LOOKAHEAD PROGRAM
Activity ID Activity Name OriginalDuration
Actual / Forecast Start
Actual / Forecast Finish
Actual /Forecast Total
Float
Planned Early Start
Planned Early Finish
Planned Late Start
Planned Late Finish
PlannedTotal Float
Planned %Complete
Actual %Complete
Al MuraAl Muraqqabat Mixed Use Development 597 15-Feb-12 A 01-Feb-14 -64 15-Feb-12 15-Nov-13 15-Feb-12 15-Nov-13 23.29% 5.95%
Typical Typical Floors 56 01-Jul-12 05-Sep-12 119 25-Aug-12 16-Oct-12 25-Aug-12 29-Jan-13 0% 0%GeneralGeneral 46 01-Jul-12 25-Aug-12 62 25-Aug-12 16-Oct-12 25-Aug-12 07-Nov-12 0% 0%SubmSubmission 46 01-Jul-12 25-Aug-12 62 25-Aug-12 16-Oct-12 25-Aug-12 07-Nov-12 0% 0%A1172 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 01-Jul-12 09-Jul-12 45 25-Aug-12 02-Sep-12 25-Aug-12 02-Sep-12 0 0% 0%
A1172 Submission of Block Work Setting Out Plan for 7th Floor 8 14-Aug-12 25-Aug-12 62 08-Oct-12 16-Oct-12 30-Oct-12 07-Nov-12 17 0% 0%ApproApproval 14 10-Jul-12 29-Jul-12 37 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0% 0%A1175 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 10-Jul-12 29-Jul-12 37 03-Sep-12 20-Sep-12 03-Sep-12 20-Sep-12 0 0% 0%
Typical Typical Floors 63 21-Jun-12 A 04-Sep-12 164 06-Sep-12 08-Nov-12 22-Oct-12 21-Mar-13 0% 0%GeneralGeneral 57 21-Jun-12 A 28-Aug-12 148 06-Sep-12 04-Nov-12 22-Oct-12 24-Feb-13 0% 0%SubmSubmission 41 10-Jul-12 28-Aug-12 131 16-Sep-12 04-Nov-12 17-Dec-12 04-Feb-13 0% 0%A1218 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 10-Jul-12 18-Jul-12 131 16-Sep-12 24-Sep-12 17-Dec-12 25-Dec-12 75 0% 0%
A1218 Submission of Block Work Setting Out Plan for 7th Floor 8 18-Aug-12 28-Aug-12 131 24-Oct-12 04-Nov-12 27-Jan-13 04-Feb-13 75 0% 0%ApproApproval 34 21-Jun-12 A 07-Aug-12 136 06-Sep-12 14-Oct-12 22-Oct-12 24-Feb-13 0% 0%A1220 Approval of Block Work Setting Out Plan for 2nd Floor 14 30-Jun-12 A 29-Jul-12 133 16-Sep-12 03-Oct-12 21-Jan-13 10-Feb-13 87 0% 0%
A1220 Approval of Block Work Setting Out Plan for 1st Floor 14 21-Jun-12 A 29-Jul-12 72 06-Sep-12 25-Sep-12 22-Oct-12 11-Nov-12 32 0% 0%
A1220 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 19-Jul-12 07-Aug-12 136 25-Sep-12 14-Oct-12 05-Feb-13 24-Feb-13 90 0% 0%CorridCorridor / Public Areas 47 10-Jul-12 04-Sep-12 164 06-Sep-12 08-Nov-12 22-Nov-12 21-Mar-13 0% 0%SubmSubmission 40 10-Jul-12 27-Aug-12 155 06-Sep-12 03-Nov-12 22-Nov-12 03-Mar-13 0% 0%A1223 Submission of Landscaping's Water Proofing Details 8 10-Jul-12 18-Jul-12 111 06-Sep-12 15-Sep-12 22-Nov-12 01-Dec-12 63 0% 0%
A1219 Submission of Reflected Ceil ing Layout 8 24-Jul-12 01-Aug-12 165 30-Sep-12 08-Oct-12 11-Feb-13 19-Feb-13 109 0% 0%
A1208 Approval of Wet Area Ceramic & Pocalin Layout for Toilets 14 14-Aug-12 04-Sep-12 145 30-Sep-12 17-Oct-12 14-Mar-13 02-Apr-13 114 0% 0%Typical Typical Floors 53 01-Jul-12 02-Sep-12 162 14-Aug-12 16-Oct-12 14-Aug-12 17-Mar-13 0% 0%GeneralGeneral 40 01-Jul-12 15-Aug-12 44 14-Aug-12 02-Oct-12 14-Aug-12 08-Oct-12 0% 0%SubmSubmission 24 01-Jul-12 28-Jul-12 43 14-Aug-12 12-Sep-12 14-Aug-12 18-Sep-12 0% 0%A1199 Submission of Block Work Setting Out Plan for 1st Floor 8 01-Jul-12 09-Jul-12 38 14-Aug-12 25-Aug-12 14-Aug-12 25-Aug-12 0 0% 0%
A1196 Submission of Block Work Setting Out Plan for 2nd Floor 8 10-Jul-12 18-Jul-12 38 26-Aug-12 03-Sep-12 26-Aug-12 03-Sep-12 0 0% 0%
A1197 Submission of Block Work Setting Out Plan for 3rd to 6th Floor 8 19-Jul-12 28-Jul-12 43 04-Sep-12 12-Sep-12 10-Sep-12 18-Sep-12 5 0% 0%ApproApproval 27 10-Jul-12 15-Aug-12 36 26-Aug-12 02-Oct-12 26-Aug-12 08-Oct-12 0% 0%A1199 Approval of Block Work Setting Out Plan for 1st Floor 14 10-Jul-12 29-Jul-12 31 26-Aug-12 12-Sep-12 26-Aug-12 12-Sep-12 0 0% 0%
A1199 Approval of Block Work Setting Out Plan for 2nd Floor 14 19-Jul-12 07-Aug-12 31 04-Sep-12 23-Sep-12 04-Sep-12 23-Sep-12 0 0% 0%
A1199 Approval of Block Work Setting Out Plan for 3rd to 6th Floor 14 29-Jul-12 15-Aug-12 36 13-Sep-12 02-Oct-12 19-Sep-12 08-Oct-12 4 0% 0%CorridCorridor / General 25 02-Aug-12 02-Sep-12 162 18-Sep-12 16-Oct-12 14-Feb-13 17-Mar-13 0% 0%SubmSubmission 8 02-Aug-12 11-Aug-12 162 18-Sep-12 26-Sep-12 14-Feb-13 25-Feb-13 0% 0%A1212 Submission of Staircase Layout & Details 8 02-Aug-12 11-Aug-12 160 18-Sep-12 26-Sep-12 14-Feb-13 23-Feb-13 122 0% 0%
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
7.0 PROCUREMENT LOG
7.1 CIVIL & ARCHITECTURAL LOG
Al Muraqqabat Mixed Use DevelopmentMaterials Procurement Log - Rev 00Civil and Architectural Works
Code A :- Approved , Code B :- Approved As Noted , Code C :- Resubmit , Code B/C :- Approved As Noted and Resubmit , Code D :- Rejected
Planned Actual Planned Actual Planned Actual Planned Actual Planned ActualPlannedDays
2.2 Water Proofing for Swimming Pool United Technology 06-Jul-12 02-Mar-12 21-Jul-12 14-Mar-12 04-Aug-12 28-Mar-12 05-Aug-12 15-Aug-12 80 10-Nov-12 B/C
2.3 Electrical Items United Technology 06-Jul-12 12-Apr-12 21-Jul-12 26-Apr-12 04-Aug-12 05-Aug-12 15-Aug-12 80 10-Nov-12 C2.3 Electrical Items United Technology 06 Jul 12 12 Apr 12 21 Jul 12 26 Apr 12 04 Aug 12 05 Aug 12 15 Aug 12 80 10 Nov 12 C
2.5 Pocalin for Pool Deck 06-Jul-12 21-Jul-12 04-Aug-12 05-Aug-12 15-Aug-12 100 05-Dec-12
2.6 Swimming Pool Equipments United Technology 06-Jul-12 12-Apr-12 21-Jul-12 26-Apr-12 04-Aug-12 05-Aug-12 15-Aug-12 120 29-Dec-12 C
3 Façade Cleaning System Danway 12-Aug-12 13-Jun-12 27-Aug-12 10-Sep-12 11-Sep-12 21-Sep-12 110 22-Jan-13 Code B on 26June-2012
4 Irrigation System Green Dunes for Irrigation Works 15-Jul-12 30-Mar-12 14-Aug-12 03-Apr-12 28-Aug-12 29-Aug-12 08-Sep-12 90 16-Dec-12 C
File :- Material Status Report - Rev 00 Page 2 of 2 Printed On :- 05/07/2012 at 08:09
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
7.0 PROCUREMENT LOG
7.2 MEP & SPECIALITY WORKS LOG
Al Muraqqabat Mixed Use DevelopmentMaterials Procurement Log - Rev 00MEP and Speciality Works
Code A :- Approved , Code B :- Approved As Noted , Code C :- Resubmit , Code B/C :- Approved As Noted and Resubmit , Code D :- Rejected
Planned Actual Planned Actual Planned Actual Planned Actual Planned ActualPlannedDays
PPR Pi Fi i V l (W ) 21 M 12 0 A 12 26 M 12 19 A 12 24 J 12 20 A 12 30 A 12 30 24 M 128 PPR Pipes -Fittings-Valves (Water) 21-Mar-12 05-Apr-12 26-May-12 19-Apr-12 24-Jun-12 20-Apr-12 30-Apr-12 30 24-May-12
Others1 Conduits and PVC Ducts MK-SAUDI EGA 10-Mar-12 25-Mar-12 16-Jan-12 08-Apr-12 29-Jan-12 09-Apr-12 19-Apr-12 40 24-May-12 B
2 Earthing & Lighting TECTRONICS 18-Jan-12 02-Feb-12 18-May-12 16-Feb-12 20-May-12 17-Feb-12 27-Feb-12 7 25-Feb-12 B2 Earthing & Lighting TECTRONICS 18 Jan 12 02 Feb 12 18 May 12 16 Feb 12 20 May 12 17 Feb 12 27 Feb 12 7 25 Feb 12 B
File :- Material Status Report - Rev 00 Page 2 of 2 Printed On :- 05/07/2012 at 08:09
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
8.0 ENGINEERING LOG
8.1 CIVIL - ARCHITECTURAL – SPECIALITY – PS LOG
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OT
B-SHOP DRAWINGS . . . . .
B.1- Civil Shop DrawingsB.1.1- General
Program Activity C General Excavation Level X 15-Feb-12 16-Feb-12 8-Jan-12 22-Feb-12 B Closed
Program Activity C General Water Proofing Details X 18-Feb-12 20-Feb-12 20-Jan-12 22-Mar-12 B Closed
Program Activity C General Raft Construction Joint Layout X 18-Feb-12 20-Feb-12 24-Jan-12 10-Mar-12 B Closed
Program Activity C General Retaining Wall Joint Layout X 19-Feb-12 6-Mar-12 20-Jan-12 18-Mar-12 B Closed
Program Activity C General Tower Crane Layout X 25-Feb-12 14-Mar-12 5-Jan-12 19-Feb-12 B Closed
B.1.2- Hotel Apartements (Block A)Deep Foundation
C Block A Structural Dwgs. for Raft X 18-Feb-12 23-Feb-12 8-Jan-12 22-Feb-12 B Closed
1st Basement Floor Slab
Program Activity C Block A Structural Dwgs. for Ret. Walls -Columns X 21-Feb-12 6-Mar-12 23-Jan-12 26-Jan-12 B Closed
269-S-RF-CL-009 C Block A Columns Reinforcement From 2nd Basement to 1st Basement X 23-Jan-12 26-Jan-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 25-Feb-12 8-Mar-12 1-Feb-12 29-Feb-12 B Closed
269-S-GE-FW-26 C Block A Core wall (CW1) formwork – Block (A) X 1-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-CW-021 C Block A Core wall reinforcement CW1 From 2nd Basement to 1st Basement X 5-Feb-12 14-Feb-12 B Closed
Program Activity C Block A Structural Dwgs. for Ramp X 21-Feb-12 12-Mar-12 8-Feb-12 10-Mar-12 B Closed
269-S-BB-RP-017 C Block A Ramp Reinforcement – Block (A) From 2nd Basement to 1st Basement X 8-Feb-12 10-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 26-Feb-12 15-Mar-12 20-Feb-12 18-Mar-12 B Closed
Notes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
g y
269-S-GN-CD-029 C Block A Concrete dimension for slab at 1st Basement Slab - Block (A) X 20-Feb-12 18-Mar-12 B Closed
269-S-RE-B1-042 C Block A 1st Basement slab reinforcement and details - Block (A) X 26-Feb-12 10-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 7-Apr-12 25-Apr-12 12-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1, Block –A. X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - Block (A) X 26-Feb-12 8-Mar-12 B Closed
Ground Floor Slab
Program Activity C Block A Structural Dwgs. for Ret. Walls -Columns X 24-Mar-12 11-Apr-12 10-Mar-12 22-Mar-12 B Closed
269-S-RF-CL-049 C Block A Columns Reinforcement - Block (A) Form 1st Basement to Ground Floor X 10-Mar-12 19-Mar-12 B Closed
269-S-GE-R-RW-0059 C Block A Retaining Wall Reinforcement From 1st Basement to Ground Floor Plan & X 12-Mar-12 22-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 24-Mar-12 11-Apr-12 10-Mar-12 19-Mar-12 B Closed
269-S-BA-CW-053 C Block A Core Wall Reinforcement - (CW1) Form 1st Basement to Ground Floor X 10-Mar-12 19-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 31-Mar-12 16-Apr-12 25-Jan-12 27-Mar-12 B Closed
269-S-BA-CD-054 C Block A Concrete Dimension for Slab & Beam at Ground Floor - Block - A X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-B1-062 C Block A Shop Drawing for Ground Floor Slab Reinforcement and Details X 15-Mar-12 27-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Ramp X 31-Mar-12 17-Apr-12 25-Jan-12 19-Mar-12 B Closed
269-S-BA-RMP-013 C Block A Ramp Concrete Dimension From 1st Basement to Ground Floor X 25-Jan-12 8-Mar-12 B Closed
269-S-BA-RP-056 C Block A Ramp reinforcement - Block (A) 1st Basement to Ground Floor X 10-Mar-12 19-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 7-May-12 27-May-12 12-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1, Block –A. X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - Block (A) X 26-Feb-12 8-Mar-12 B Closed
1st Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 8-Apr-12 26-Apr-12 25-Feb-12 5-Apr-12 B Closed
269-S-BA-CL-44 C Block A Ground Floor Columns Layout Block - A X 25-Feb-12 22-Mar-12 B Closed269 S BA CL 44 y
S-RF-CL-072 C Block A Shop drawing for Column reinforcement ground floor to first floor Block X 25-Mar-12 5-Apr-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 8-Apr-12 26-Apr-12 14-Mar-12 27-Mar-12 B Closed
269-S-BA-ST-CW-067 C Block A Shop Drawing for Core Wall Reinforcement CW1 – Ground to First Floor X 14-Mar-12 27-Mar-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 22-Apr-12 10-May-12 8-Apr-12 2-May-12 B Closed
269-S-RE-FF-087 C Block A Shop drawing for 1st Floor Slab Reinforcement and Details (Block A) X 9-Apr-12 2-May-12 B Closed
269-S-BA-CL-092 C Block A Shop drawing for Concrete Dimension for Slab & Beam at 1st Floor X 8-Apr-12 2-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 21-May-12 10-Jun-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1, Block –A. X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - Block (A) X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
2nd Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 25-Apr-12 15-May-12 14-Mar-12 19-Apr-12 B Closed
269-S-RF-CL-083 C Block A Shop dwg. for Column Reinforcement from 01st Floor to 02nd Floor X 7-Apr-12 19-Apr-12 B Closed
269-S-BB-CL-061 C Block A Shop Drawing for Column Layout at Fist Floor Block- A X 14-Mar-12 11-Apr-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 6-May-12 24-May-12 10-Mar-12 19-Mar-12 B Closed
C Block A
C Block A
Program Activity C Block A Structural Dwgs. for Slab X 20-May-12 7-Jun-12 21-Apr-12 22-May-12 B Closed
269-S-RE-SF-106 C Block A Shop drawing for 02nd Floor Slab Reinforcement and Details X 23-Apr-12 22-May-12 B Closed
269-S-BA-CD-110 C Block A Shop drawing for Concrete Dimension for Slab and Beam at 02 Floor X 21-Apr-12 22-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Staircase X 17-Jun-12 5-Jul-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed269-S-BA-ST-30 C Block A Concrete dimension for stair case S1 X 12 Feb 12 29 Feb 12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details - S1 X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
269-S-BA-ST C Block A Shop drawing for Concrete Dimension for Staircase – S8 X 26-Mar-12 7-Apr-12 B Closed
269-S-RE-SR-84 C Block A Shop drawing for Rein forcement Details for staircase – S 8 X 1-Apr-12 11-Apr-12 B Closed
3rd & 4th Floor Slab
File : -Engineering Tracking Chart - Rev 00 1 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity C Block A Structural Dwgs. for Columns X 23-May-12 12-Jun-12 1-Apr-12 22-May-12 B Closed
269-S-BA-CL--082 C Block A Shop drawing for Column Layout (2nd Floor) - Block- (A) X 1-Apr-12 11-Apr-12 B Closed
269-S-BB-CL-096 C Block A Shop drawing for Column Layout @ Third Floor Block A X 9-Apr-12 2-May-12 B Closed
269-S-RF-CL-109 C Block A Shop drawing for Column Reinforcement Block A, 2nd to 3rd Floor X 21-Apr-12 2-May-12 B Closed
269-S-RF-CL-110 C Block A Shop drawing for Column Reinforcement 03rd to 04th Floor – Block “A” 21-Apr-12 22-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Core Walls X 23-May-12 12-Jun-12 22-Apr-12 2-May-12 B Closed
269-S-BA-CW-111 C Block A Shop drawing for Core Wall Reinforcement (CW1) from 02nd to 3rd Floor X 22-Apr-12 2-May-12 B Closed
269-S-BA-ST-CW-112 C Block A Shop drawing for Core Wall Reinforcement (CW1) from 03rd to 04th X 23-Apr-12 2-May-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 17-Jun-12 5-Jul-12 26-Apr-12 13-Jun-12 B Closed &
269-S-BA-CD-114 2 C Block A Shop drawing for Concrete Dimension for Slab & Beam at 03rd Floor - X 26-Apr-12 12-Jun-12 B Closed &
269-S-RE-SF-129 C Block A Shop Drawing for 3rd Floor Slab Reinforcement and Details X 6-May-12 17-May-12 B Closed
269-S-RE-FF-151 0 C Block A Shop Drawing For 4th Floor Slab Reinforcement Details – Block “A" X 7-Jun-12 12-Jun-12 B Closed &
269-S-BA-CD-117 2 C Block A Shop drawing for Concrete Dimension for slab & Beam at 04th Floor X 26-Apr-12 13-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Staircase X 14-Jul-12 1-Aug-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
5th & 6th Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 7-Jul-12 25-Jul-12 19-Apr-12 26-Jun-12 B Closed &
269-S-BA-CL-103 C Block A Shop drawing for Column Layout @ Fourth (4th) Floor Block-A X 19-Apr-12 17-May-12 B Closed269 S BA CL 103 C Block A Shop drawing for Column Layout @ Fourth (4th) Floor Block A p y C osed
269-S-BA-CL-119 C Block A Shop drawing for Column / Core Wall Layout at 05th Floor X 29-Apr-12 13-May-12 B Closed
269-S-RE-CL-161 1 C Block A Shop Drawing for Column Reinforcement 4th Floor to 5th Floor Block- A X 12-Jun-12 16-Jun-12 B Closed &
269-S-RF-CL-170 1 C Block A Shop drawing for Column Reinforcement 05th to 06th Floor – Block “A” 18-Jun-12 26-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Core Walls X 7-Jul-12 25-Jul-12 29-Apr-12 Opened
269-S-BA-CL-119 C Block A Shop drawing for Column / Core Wall Layout at 05th Floor X 29-Apr-12 13-May-12 B Closed
269-S-BA-CW-179 C Block A Shop Drawing for Core Wall (CW1) Reinforcement from 05th to 06th X 18-Jun-12 26-Jun-12 B Closed &
269-S-BA-ST-CW-166 C Block A Shop Drawing For Core wall (CW1) Reinforcement 4th Floor to 5th floor X 13-Jun-12 25-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Slab X 23-Jul-12 12-Aug-12 11-Jun-12
269-S-RE-5F-164 0 C Block A Shop Drawing for 5th floor Slab Reinforcement Details Block – “A” X 13-Jun-12 25-Jun-12 B Closed &
269-S-RE-6F-165 0 C Block A Shop Drawing for 6th floor Slab Reinforcement Details Block – “A” X 13-Jun-12 25-Jun-12 B Closed &
269-S-BA-CD-163 1 C Block A Shop Drawing for Concrete Dimension for Slab & Beam at 6th Floor - X 12-Jun-12 UR Opened &
269-S-BA-CD-156 C Block A Shop Drawing For Concrete Dimension for Slab & Beam at 5th Floor - X 11-Jun-12 UR Opened &
Program Activity C Block A Structural Dwgs. for Staircase X 25-Aug-12 12-Sep-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
7th Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 4-Aug-12 26-Aug-12 11-Jun-12 28-Jun-12 B Closed &
269-S-RF-CL-171 C Block A Shop Drawing for Column Reinforcement from 06th to 07th Floor – Block 18-Jun-12 28-Jun-12 B Closed &
269-S-BA-CL-157 C Block A Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Core Walls X 4-Aug-12 26-Aug-12 11-Jun-12
269 S BA CL 157 C Block A Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &269-S-BA-CL-157 C Block A Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11 Jun 12 25 Jun 12 B Closed &
Program Activity C Block A Structural Dwgs. for Slab X 28-Aug-12 17-Sep-12 24-Jun-12 &
269-S-BA-CD-186 C Block A Shop Drawing for Concrete Dimension for Slab & Beam at 7th Floor 24-Jun-12 UR Opened &
269-S-RE-7F-187 C Block A Shop Drawing for 7th Floor Slab Reinforcement and Details 25-Jun-12 UR Opened &
Program Activity C Block A Structural Dwgs. for Staircase X 15-Sep-12 3-Oct-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
Roof Floor Slab
Program Activity C Block A Structural Dwgs. for Columns X 26-Aug-12 13-Sep-12 18-Jun-12
269-S-BA-CL-172 C Block A Shop drawing for Column / Core wall Layout at 7th Floor – Block “A” X 18-Jun-12 26-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Core Walls X 26-Aug-12 13-Sep-12 18-Jun-12
269-S-BA-CL-172 C Block A Shop drawing for Column / Core wall Layout at 7th Floor – Block “A” X 18-Jun-12 26-Jun-12 B Closed &
Program Activity C Block A Structural Dwgs. for Staircase X 12-Sep-12 2-Oct-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-30 C Block A Concrete dimension for stair case –S1 X 12-Feb-12 29-Feb-12 B Closed
269-S-BA-CW-053 C Block A Stair case -1 reinforcement details X 26-Feb-12 8-Mar-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
Program Activity C Block A Structural Dwgs. for Slab X 16-Sep-12 4-Oct-12
Program Activity C Block A Structural Dwgs. for Chillers Foundations X 18-Sep-12 8-Oct-12
Program Activity C Block A Structural Dwgs. for Parapets X 29-Sep-12 17-Oct-12
Upper Roof Floor Slab
P A ti it C Block A Structural Dwgs for Columns X 12 Sep 12 2 Oct 12Program Activity C Block A Structural Dwgs. for Columns X 12-Sep-12 2-Oct-12
Program Activity C Block A Structural Dwgs. for Slab X 22-Sep-12 10-Oct-12
Program Activity C Block A Structural Dwgs. for Staircase X 1-Oct-12 21-Oct-12 12-Feb-12 19-Apr-12 B Closed
269-S-BA-ST-079 C Block A Shop drawing for Concrete Dimension for Staircase – S2 X 28-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-088 C Block A Shop drawing for Steel Reinforcement Details for Staircase- S2 X 7-Apr-12 19-Apr-12 B Closed
B.1.3- Hotel (Block B)Deep Foundation
File : -Engineering Tracking Chart - Rev 00 2 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
C Block B Structural Dwgs. for Raft X 18-Feb-12 7-Mar-12 8-Jan-12 22-Feb-12 B Closed
1st Basement Floor Slab
Program Activity C Block B Structural Dwgs. for Ret. Walls -Columns X 12-Mar-12 29-Mar-12 23-Jan-12 26-Jan-12 B Closed
269-S-RF-CL-010 C Block B Columns Reinforcement (Block-B) From 2nd Basement to 1st Basement X 23-Jan-12 26-Jan-12 B Closed
Program Activity C Block B Structural Dwgs. for Water Tank X 12-Mar-12 1-Apr-12 20-Feb-12 10-Mar-12 B Closed
269-S-GEN-ST-WT-025 C Block B 2nd Basement water tank reinforcement and details – Block (B&C) X 26-Feb-12 10-Mar-12 B Closed
269-S-GN-FW-40 C Block B Water Tank no. (2&3) formwork Block -B X 20-Feb-12 25-Feb-12 B Closed
Program Activity C Block B Structural Dwgs. for Ramp X 24-Mar-12 11-Apr-12 8-Feb-12 28-Mar-12 B Closed
269-S-BB-RP-018 C Block B Ramp Reinforcement – Block (B) From 2nd Basement to 1st Basement X 8-Feb-12 28-Mar-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 8-Apr-12 26-Apr-12 5-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-CW-022 C Block B Core wall reinforcement CW 5,6 &7 Block (B) X 5-Feb-12 14-Feb-12 B Closed
269-S-GN-FW-39 C Block B Core wall (CW5, CW6, CW7) formwork, Block -B X 20-Feb-12 29-Feb-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 24-Apr-12 14-May-12 20-Feb-12 31-Mar-12 B Closed
269-S-GN-CD-037 C Block B Concrete dimension for slab at 1st Basement– Block (B) X 20-Feb-12 20-Mar-12 B Closed
269-S-RE-B1-048 C Block B 1st Basement Slab Reinforcement and details - Block (B) X 1-Mar-12 31-Mar-12 B Closed
Program Activity C Block B Structural Dwgs. for Staircase X 28-May-12 18-Jun-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B ClosedS S ,
Ground Floor Slab
Program Activity C Block B Structural Dwgs. for Ret. Walls -Columns X 6-May-12 24-May-12 18-Mar-12 1-May-12 B Closed
269-S-RF-CL-070 C Block B Shop Drawing for Column Reinforcement 1st Basement to Ground floor - X 18-Mar-12 28-Mar-12 B Closed
269-S-GE-R-RW-0081 C Block B Shop drawing for Retaining Wall Reinf.t from 1st Basement to Ground X 28-Mar-12 1-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Ramp X 6-May-12 24-May-12 7-Apr-12 21-Apr-12 B Closed
269-S-BB-RP-089 C Block B Shop drawing for Ramp Reinforcement from 01st Basement to Ground X 7-Apr-12 21-Apr-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 21-May-12 10-Jun-12 1-Apr-12 1-May-12 B Closed
269-S-BB-ST-CW-073 C Block B Shop drawing for Core Wall Reinforcement CW 5, 6 & 7 from 1st X 1-Apr-12 1-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 29-May-12 19-Jun-12 26-Mar-12 26-Apr-12 B Closed
269-S-RE-GF-099 C Block B Shop Drawing for Ground Floor Slab Reinforcement and Details X 12-Apr-12 26-Apr-12 B Closed
269-S-BC-CD-076 C Block B Shop Drawing for Concrete Dimension for Slab and Beam at Ground Floor X 26-Mar-12 7-Apr-12 B Closed
Program Activity C Block B Structural Dwgs. for Staircase X 7-Jul-12 25-Jul-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
1st Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 2-Jun-12 21-Jun-12 25-Feb-12 24-May-12 B Closed
269-S-BA-CL-45 C Block B Ground Floor Columns Layout Block - B X 25-Feb-12 22-Mar-12 B Closed
269-S-RF-CL-122 C Block B Shop drawing for Column Reinforcement from Ground Floor to 01st Floor X 30-Apr-12 24-May-12 B CLosed
Program Activity C Block B Structural Dwgs. for Core Walls X 13-Jun-12 4-Jul-12 2-May-12 14-May-12 B Closed
269-S-BB-ST-CW-123 C Block B Shop drawing for Core Wall Reinforcement CW5 & 6 from Ground Floor X 2-May-12 14-May-12 B Closed269 S BB ST CW 123 C Block B S p g C W CW & G y y B Closed
Program Activity C Block B Structural Dwgs. for Slab X 1-Jul-12 19-Jul-12 5-May-12 16-Jun-12 B Closed &
269-S-BA-CD-128 3 C Block B Shop Drawing for Concrete Dimension for Slab & Beam at 1st Floor X 5-May-12 16-Jun-12 B Closed &
269-S-RE-GF-131 0 C Block B Shop Drawing for 1st Floor Reinforcement and Details – Block - B X 23-May-12 31-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Staircase X 11-Aug-12 2-Sep-12 20-Feb-12 16-Jun-12 B Closed &
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
269-S-BA-ST-142 0 C Block B Shop Drawing for Concrete Dimension for Staircase from Ground Floor to X 3-Jun-12 16-Jun-12 B Closed &
269-S-RE-SR-143 0 C Block B Shop Drawing for Reinforcement Details for Stair case (Grid-20-22/J-K) X 2-Jun-12 12-Jun-12 B Closed &
2nd Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 27-Jun-12 17-Jul-12 14-Mar-12 4-Jun-12 B Closed
269-S-BB-CL--065 C Block B Shop Drawing for Column Layout at Fist Floor Block- B X 14-Mar-12 11-Apr-12 B Closed
269-S-RF-CL-136 0 C Block B Shop Drawing For column Reinforcement from 1st floor to 2nd floor – X 30-May-12 4-Jun-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 8-Jul-12 26-Jul-12 24-May-12 4-Jun-12 B Closed
269-S-BB-ST-CW-13 0 C Block B Shop Drawing for Corewall Reinforcement (CW5, CW6 & CW7) from 1st X 24-May-12 4-Jun-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 23-Jul-12 12-Aug-12 23-May-12 21-Jun-12 B Closed &
269-S-BA-CD-137 1 C Block B Shop Drawing for 2nd Floor Concrete Dimension for Slab & Beam – X 23-May-12 16-Jun-12 B Closed &
269-S-RE-GF-138 0 C Block B Shop Drawing For 2nd Floor Slab Reinforcement Details – Block “B” X 7-Jun-12 21-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Staircase X 16-Sep-12 4-Oct-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269 S BB ST 033 C Block B Concrete dimension for stair case S3 Block B X 20-Feb-12 29-Feb-12 B Closed269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
3rd & 4th Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 25-Jul-12 14-Aug-12 8-Apr-12 16-Jun-12 B Closed &
269-S-BB-CL-094 C Block B Shop drawing for Column Layout @ Second Floor - Block-B X 8-Apr-12 1-May-12 B Closed
File : -Engineering Tracking Chart - Rev 00 3 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
269-S-BB-CL-097 C Block B Shop drawing for Column Layout @ Third Floor Block B X 9-Apr-12 19-Apr-12 B Closed
269-S-RF-CL-147 0 C Block B Shop Drawing For column Reinforcement from 3rd floor to 4th floor – 7-Jun-12 16-Jun-12 B Closed &
269-S-RF-CL-146 0 C Block B Shop Drawing For column Reinforcement from 2nd floor to 3rd floor – 7-Jun-12 16-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Core Walls X 31-Jul-12 22-Aug-12 11-Jun-12
269-S-BB-ST-CW-153 Shop Drawing for Core wall Reinforcement (CW5&CW6) from 2nd to 3rd 11-Jun-12 23-Jun-12 B Closed &
269-S-BB-ST-CW-154 Shop Drawing for Core wall Reinforcement (CW5&CW6) from 3rd to 4th 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Slab X 13-Aug-12 4-Sep-12
269-S-BA-CD-178 C Block B Shop Drawing for Concrete Dimension for Slab & Beam at 4th Floor – 19-Jun-12 UR Opened &
269-S-RE-4F-184 C Block B Shop Drawing for 4th Floor Slab Reinforcement and Details 20-Jun-12 UR Opened &
269-S-BA-CD-169 C Block B Shop Drawing for Concrete Dimension Slab & Beam at 3rd Floor Block – 14-Jun-12 30-Jun-12 B Closed &
269-S-RE-3F-168 C Block B Shop drawing for 03rd Floor Slab Reinforcement and Details – Block “B” 18-Jun-12 28-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Staircase X 8-Oct-12 29-Oct-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
5th & 6th Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 22-Aug-12 11-Sep-12 19-Apr-12 Opened
269-S-BB-CL-104 1 C Block B Shop drawing for Column Layout @ Fourth (4th) Floor Block-B X 19-Apr-12 17-May-12 B Closed
Program Activity C Block B Structural Dwgs. for Core Walls X 29-Aug-12 18-Sep-12 29-Apr-12 Openedg y g p
269-S-BA-CL-120 C Block B Shop drawing for Column / Core Wall Layout at 05th Floor - Block “B” X 29-Apr-12 13-May-12 B CLosed
269-S-BB-ST-CW-190 C Block B Shop Drawing for Core Wall (CW5, CW6&CW7) Reinforcement from 26-Jun-12 UR Opened &
Program Activity C Block B Structural Dwgs. for Slab X 19-Sep-12 9-Oct-12 26-Jun-12
269-S-RE-6F-195 Shop Drawing for 6th Floor Slab Reinforcement and Details - Block “B” 30-Jun-12 UR Opened &
269-S-BA-CD-197 Shop Drawing for Concrete Dimension for Slab & Beam at 6th Floor - 30-Jun-12 UR Opened &
269-S-RE-5F-189 Shop Drawing for 5th Floor Slab Reinforcement and Details– Block “B” 26-Jun-12 UR Opened &
269-S-BA-CD-191 Shop Drawing for Concrete Dimension for Slab & Beam at 5th Floor 26-Jun-12 UR Opened &
Program Activity C Block B Structural Dwgs. for Staircase X 13-Nov-12 5-Dec-12 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
7th Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 22-Sep-12 10-Oct-12
Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Core Walls X 29-Sep-12 17-Oct-12
Shop Drawing of Concrete Dimention for Column/Core wall Layout for 11-Jun-12 25-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Slab X 23-Oct-12 13-Nov-12
Program Activity C Block B Structural Dwgs. for Staircase X 25-Dec-12 15-Jan-13 20-Feb-12 26-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed269 S RE SR 55 C Block B Stair case reinforcement no. (3) Block (B) B Closed
269-S-BB-ST-035 C Block B Concrete dimension for stair case –S4 Block -B X 12-Mar-12 26-Mar-12 B Closed
269-S-RE-SR-58 C Block B Reinforcement Details for Staircase – S4, Block -B X 10-Mar-12 19-Mar-12 B Closed
Roof Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 10-Oct-12 31-Oct-12 18-Jun-12
269-S-BB-CL-173 Shop drawing for Column / Core wall Layout at 7th Floor – Block “B” 18-Jun-12 27-Jun-12 B Closed &
Program Activity C Block B Structural Dwgs. for Staircase X 4-Nov-12 25-Nov-12 20-Feb-12 17-Mar-12 B Closed
269-S-BB-ST-034 C Block B Concrete dimension for stair case –S3 (Mirror) – Block -B X 20-Feb-12 5-Mar-12 B Closed
269-S-BB-ST-033 C Block B Concrete dimension for stair case –S3 Block -B X 20-Feb-12 29-Feb-12 B Closed
269-S-RE-SR-55 C Block B Stair case reinforcement no. (3) – Block (B) X 10-Mar-12 17-Mar-12 B Closed
Program Activity C Block B Structural Dwgs. for Slab X 10-Nov-12 29-Nov-12
Program Activity C Block B Structural Dwgs. for Chillers Foundations X 19-Nov-12 10-Dec-12
Program Activity C Block B Structural Dwgs. for Parapets X 13-Jan-13 22-Jan-13
Upper Roof Floor Slab
Program Activity C Block B Structural Dwgs. for Columns X 18-Nov-12 9-Dec-12
Program Activity C Block B Structural Dwgs. for Slab X 28-Nov-12 19-Dec-12
B.1.4- Residential (Block C)Deep Foundation
Program Activity C Block C Structural Dwgs. for Raft X 18-Feb-12 23-Feb-12 8-Jan-12 22-Feb-12 B Closed
1st Basement Floor Slab
Program Activity C Block C Structural Dwgs. for Ret. Walls -Columns X 17-Mar-12 4-Apr-12 24-Jan-12 31-Jan-12 B Closed
269-S-RF-CL-011 C Block C Columns Reinforcement (Block-C) From 2nd Basement to 1st Basement X 24-Jan-12 31-Jan-12 B Closed
Program Activity C Block C Structural Dwgs. for Water Tank X 17-Mar-12 4-Apr-12 5-Feb-12 10-Mar-12 B Closed
269 S GEN ST WT 025 C Block C 2nd Basement water tank reinforcement and details Block (B&C) X 5-Feb-12 10-Mar-12 B Closed269-S-GEN-ST-WT-025 C Block C 2nd Basement water tank reinforcement and details – Block (B&C) X 5-Feb-12 10-Mar-12 B Closed
269-S-GN-FW-32 C Block C Formwork for Water tank – Block C. X 13-Feb-12 22-Feb-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 10-Apr-12 30-Apr-12 5-Feb-12 21-Feb-12 B Closed
269-S-BC-ST-CW-023 C Block C Core wall reinforcement CW 8&9&10&11 Block (C) X 5-Feb-12 14-Feb-12 B Closed
269-S-GN-FW-31 C Block C Formwork for core walls (CW8, CW9, CW10, CW11) – Block C. X 13-Feb-12 21-Feb-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 17-Apr-12 7-May-12 20-Feb-12 22-Mar-12 B Closed
269-S-RE-B1-047 C Block C 1st Basement Slab Reinforcement - Block (C ) X 1-Mar-12 22-Mar-12 B Closed
File : -Engineering Tracking Chart - Rev 00 4 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
269-S-GN-CD-038 C Block C Concrete dimension for slab at 1st Basement– Block (C ) X 20-Feb-12 18-Mar-12 B Closed
Program Activity C Block C Structural Dwgs. for Staircase X 16-May-12 5-Jun-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
269-S-BA-ST-080 C Block C Shop drawing for Concrete Dimension for Staircase – S7 X 18-Mar-12 8-Apr-12 B Closed
269-S-RE-SR-85 C Block C Shop drawing for Rein forcement Details for staircase – S 7 X 1-Apr-12 11-Apr-12 B Closed
2nd Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 17-Jun-12 5-Jul-12 17-Apr-12 1-May-12 B Closed
269-S-RF-CL-093 C Block C Shop drawing for Column Reinforcement Block-C from 1st Floor to 2nd X 17-Apr-12 1-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Core Walls X 17-Jun-12 5-Jul-12 17-Apr-12 1-May-12 B Closed
269-S-BA-ST-CW-086 C Block C Shop drawing for Core Wall Reinforcement CW1 – First Floor to Second X 17-Apr-12 1-May-12 B Closed269 S BA ST CW 086 C Block C S p g C W CW S p y B Closed
269-S-BC-ST-CW-091 C Block C Shop drawing for core wall reinforcement CW 8,CW9,CW10 from 1st to X 17-Apr-12 1-May-12 B Closed
Program Activity C Block C Structural Dwgs. for Slab X 3-Jul-12 23-Jul-12 23-Apr-12 19-Jun-12 B Closed &
269-S-BA-CD-113 C Block C Shop drawing for Concrete Dimension for Slab & Beam at 02nd Floor - X 23-Apr-12 9-Jun-12 B Closed
269-S-RE-SF-145 C Block C Shop Drawing for 2nd Floor Slab Reinforcement Details – Block “C” X 11-Jun-12 19-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Staircase X 7-Aug-12 29-Aug-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
3rd & 4th Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 4-Jul-12 24-Jul-12 8-Apr-12 Opened
269-S-BC-CL-095 C Block C Shop drawing for Column Layout @ Second Floor Block-C X 8-Apr-12 21-Apr-12 B Closed
269-S-BC-CL-098 C Block C Shop drawing for Column Layout @ Third Floor Block C X 9-Apr-12 19-Apr-12 B Closed
269-S-RF-CL-176 C Block C Shop Drawing for Column Reinforcement 3rd to 4th Floor 20-Jun-12 UR Opened &
269-S-RF-CL-175 C Block C Shop Drawing for Column Reinforcement from 2nd to 3rd Floor – Block 20-Jun-12 UR Opened &
Program Activity C Block C Structural Dwgs. for Core Walls X 4-Jul-12 24-Jul-12
269-S-B-ST-CW-181 C Block C Shop Drawing for Core Wall Reinforcement (CW 8 & 9) from 2nd to 3rd X 20-Jun-12 UR Opened &
269-S-BC-ST-CW-188 C Block C Shop Drawing for Core Wall (CW 8 & 9) Reinforcement from 3rd to 4th X 25-Jun-12 UR Opened &
Program Activity C Block C Structural Dwgs. for Slab X 22-Jul-12 9-Aug-12 26-Apr-12 25-Jun-12 B Closed &
269-S-BA-CD-115 C Block C Shop drawing for Concrete Dimension for Slab & Beam at 03rd Floor - 26-Apr-12 13-May-12 B Closed
269-S-BA-CD-118 C Block C Shop drawing for Concrete Dimension for slab & Beam at 04th Floor - 29-Apr-12 16-Jun-12 B Closed &
269 S RE 4F 162 C Block C Shop Drawing For 4th Floor Slab Reinforcement Details Block “C” 11-Jun-12 25-Jun-12 B Closed &269-S-RE-4F-162 C Block C Shop Drawing For 4th Floor Slab Reinforcement Details - Block C 11-Jun-12 25-Jun-12 B Closed &
269-S-RE-SF-160 C Block C Shop Drawing for Slab Reinforcement Details from 3rd Floor- Block “C” 11-Jun-12 21-Jun-12 B Closed &
Program Activity C Block C Structural Dwgs. for Staircase X 8-Sep-12 26-Sep-12 18-Feb-12 31-Mar-12 B Closed
269-S-BC-ST-20 C Block C Concrete dimension for stair case –S6 - Block –C X 22-Feb-12 29-Feb-12 B Closed
269-S-BC-ST-19 C Block C Concrete dimension for stair case –S6 - (Mirror), Block –C [GRID 41- X 18-Feb-12 22-Feb-12 B Closed
269-S-BA-CW-052 C Block C Concrete Dimension for Staircase – S5 (Block C) X 10-Mar-12 19-Mar-12 B Closed
269-S-RE-SR-60 C Block C Shop Drawing for Reinforcement Details for Staircase – S5 - Block – C X 13-Mar-12 18-Mar-12 B Closed
Program Activity C Block C Structural Dwgs. for Parapets X 12-Dec-12 2-Jan-13Program Activity C Block C Structural Dwgs. for Parapets
Upper Roof Floor Slab
Program Activity C Block C Structural Dwgs. for Columns X 15-Oct-12 5-Nov-12
Program Activity C Block C Structural Dwgs. for Slab X 23-Oct-12 13-Nov-12
Program Activity C Block C Structural Dwgs. for Staircase X 2-Dec-12 20-Dec-12
B.2- Architectural Shop DrawingsB.2.1- Hotel Apartments (Block A)2nd Basement Floor
Program Activity A Block A Block Work Setting Out Plan for 2nd Basement X 16-May-12 5-Jun-12 12-Apr-12 26-Apr-12 B Closed
269-S-BA-Bl-101 A Block A Shop Drawing for 2nd Basement Block Work Setting-out Plan - block A 12-Apr-12 26-Apr-12 B Closed
Program Activity A Block A Staircase Layout & Details X 1-Jul-12 19-Jul-12
Program Activity A Block A Handrail Layout & Details X 23-Sep-12 11-Oct-12
Program Activity A Block A Reflected Ceiling Layout X 16-Oct-12 6-Nov-12
Program Activity A Block A Flooring X 18-Dec-12 8-Jan-13
Program Activity A Block A Doors Details X 18-Dec-12 8-Jan-13
Program Activity A Block A Sinage Layout and Details X 30-Dec-12 20-Jan-13
Program Activity A Block A Parking Layout X 12-Jan-13 31-Jan-13
Program Activity A Block A Traffic Sign Layout X 12-Jan-13 31-Jan-13
1st Basement Floor
Program Activity A Block A Block Work Setting Out Plan for 1st Basement X 26-May-12 13-Jun-12 5-May-12 17-May-12 B Closed
269-A-BB-BL-124 A Block A Shop drawing for 01st Basement Block Work Setting Out Plan - Block 5-May-12 17-May-12 B Closed
Program Activity A Block A Staircase Layout & Details X 10-Jul-12 30-Jul-12
Program Activity A Block A Reflected Ceiling Layout X 14-Aug-12 5-Sep-12
Program Activity A Block A Flooring X 3-Sep-12 23-Sep-12Program Activity A Block A Flooring X 3-Sep-12 23-Sep-12
Program Activity A Block A Doors Details X 9-Sep-12 27-Sep-12
Program Activity A Block A Handrail Layout & Details X 2-Oct-12 22-Oct-12
Program Activity A Block A Sinage Layout and Details X 28-Oct-12 18-Nov-12
Program Activity A Block A Parking Layout X 21-Jan-13 11-Feb-13
Program Activity A Block A Traffic Sign Layout X 21-Jan-13 11-Feb-13
Ground Floor
File : -Engineering Tracking Chart - Rev 00 6 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block A Block Work Setting Out Plan for Ground X 30-Jun-12 18-Jul-12 19-Jun-12 24-Jun-12 B Closed
269-A-BA-BL-182 Shop Drawing for Ground Floor Block Work Setting Out Plan – Block “A” 19-Jun-12 24-Jun-12 B Closed &
Program Activity A Block A Staircase Layout & Details X 12-Aug-12 3-Sep-12
Program Activity A Block A Reflected Ceiling Layout X 30-Sep-12 18-Oct-12
Program Activity A Block A Flooring Layout X 30-Sep-12 18-Oct-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout for Toilets X 6-Nov-12 27-Nov-12
Program Activity A Block A Handrail Layout & Details X 6-Nov-12 27-Nov-12
Program Activity A Block A Doors Details X 15-Dec-12 3-Jan-13
Program Activity A Block A Sinage Layout and Details X 25-Dec-12 15-Jan-13
Program Activity A Block A Furniture Layout and Details X 3-Jul-13 23-Jul-13
Typical Floors
General
Program Activity A Block A Block Work Setting Out Plan for 1st Floor X 8-Jul-12 26-Jul-12 7-Jun-12 25-Jun-12 B Closed
269-S-BA-BL-149 0 A Block A Shop Drawing for 1st floor Block work Setting out plan Block - A X 7-Jun-12 25-Jun-12 B Closed &
Program Activity A Block A Block Work Setting Out Plan for 2nd Floor X 4-Aug-12 26-Aug-12 7-Jun-12 23-Jun-12 B Closed
269-A-BA-BL-150 0 A Block A Shop Drawing for 2nd floor Block work Setting out plan Block - A X 7-Jun-12 23-Jun-12 B Closed &
Program Activity A Block A Block Work Setting Out Plan for 3rd to 6th Floor X 2-Sep-12 20-Sep-12
Program Activity A Block A Block Work Setting Out Plan for 7th Floor X 16-Oct-12 6-Nov-12
Corridor / General
Program Activity A Block A Staircase Layout & Details X 4-Sep-12 24-Sep-12
Program Activity A Block A Reflected Ceiling Layout X 16-Sep-12 4-Oct-12Program Activity A Block A Reflected Ceiling Layout p
Program Activity A Block A Handrail Layout & Details X 21-Oct-12 11-Nov-12
Program Activity A Block A Flooring Layout X 17-Nov-12 6-Dec-12
Program Activity A Block A Doors Details X 11-Dec-12 31-Dec-12
Program Activity A Block A Sinage Layout and Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Studio Apartements
Program Activity A Block A Wet Area Ceramic & Pocalin Layout X 4-Sep-12 24-Sep-12
Program Activity A Block A Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block A Wardrobe Details X 11-Dec-12 31-Dec-12
Program Activity A Block A Floors Layout and Details X 23-Dec-12 13-Jan-13
Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Kitchen Cabinet Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Sinage Layout and Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Mirror Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Program Activity A Block A Furniture Layout and Detals X 13-Jul-13 31-Jul-13
One Bed Room Apartements
Program Activity A Block A Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout X 21-Oct-12 11-Nov-12
Program Activity A Block A Wardrobe Details X 11-Dec-12 31-Dec-12
Program Activity A Block A Floors Layout and Details X 23-Dec-12 13-Jan-13
Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Kitchen Cabinet Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Mirror Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Sinage Layout and Details X 10-Feb-13 28-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Program Activity A Block A Furniture Layout and Detals X 13-Jul-13 31-Jul-13
Two Bed Room Apartements
Program Activity A Block A Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block A Wardrobe Details X 4-Nov-12 25-Nov-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout X 4-Nov-12 25-Nov-12
Program Activity A Block A Floors Layout and Details X 23-Dec-12 13-Jan-13
Program Activity A Block A Vanity Counter Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Kitchen Cabinet Details X 16-Jan-13 6-Feb-13
Program Activity A Block A Mirror Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Program Activity A Block A Sinage Layout and Details X 10-Feb-13 28-Feb-13
Program Activity A Block A Carpet Flooring Details X 17-Mar-13 4-Apr-13
Program Activity A Block A Furniture Layout and Detals X 13-Jul-13 31-Jul-13
Roof - Upper Roof Floor
General
Program Activity A Block A Block Work Setting Out Plan for Roof & Upper Roof X 29-Sep-12 17-Oct-12
Program Activity A Block A Roof's Water Proofing System X 7-Oct-12 28-Oct-12
P A ti it A Block A Pool Deck Layout X 26 No 12 17 Dec 12Program Activity A Block A Pool Deck Layout X 26-Nov-12 17-Dec-12
Program Activity A Block A Wet Area Ceramic & Pocalin Layout for Toilets X 27-Jan-13 14-Feb-13
Program Activity A Block A Flooring Layout X 27-Jan-13 14-Feb-13
Program Activity A Block A Staircase Layout & Details X 27-Jan-13 14-Feb-13
Program Activity A Block A Handrail Layout & Details X 27-Jan-13 14-Feb-13
Program Activity A Block A Doors Details X 29-Jan-13 18-Feb-13
Gymnasium
File : -Engineering Tracking Chart - Rev 00 7 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block A Reflected Ceiling Layout X 3-Nov-12 22-Nov-12
Program Activity A Block A Vinyl Floor Detals X 9-Feb-13 27-Feb-13
Program Activity A Block A Furniture Layout and Detals X 20-Jul-13 7-Aug-13
B.2.2- Hotel (Block B)2nd Basement Floor
Program Activity A Block B Block Work Setting Out Plan for 2nd Basement X 27-May-12 14-Jun-12 21-Apr-12 2-May-12 B Closed
269-S-BB-BL-107 A Block B Shop drawing for 2nd Basement BlockWork Setting Out Plan (Block-B) 21-Apr-12 2-May-12 B Closed
Program Activity A Block B Staircase Layout & Details X 15-Aug-12 6-Sep-12
Program Activity A Block B Handrail Layout & Details X 15-Aug-12 6-Sep-12
Program Activity A Block B Flooring X 3-Oct-12 23-Oct-12
Program Activity A Block B Doors Details X 3-Oct-12 23-Oct-12
Program Activity A Block B Sinage Layout and Details X 24-Nov-12 13-Dec-12
Program Activity A Block B Parking Layout X 22-Jan-13 12-Feb-13
Program Activity A Block B Traffic Sign Layout X 22-Jan-13 12-Feb-13
1st Basement Floor
Program Activity A Block B Block Work Setting Out Plan for 1st Basement X 11-Jul-12 31-Jul-12 5-May-12 17-May-12 B Closed
269-A-BB-BL-125 A Block B Shop drawing for 01st Basement Block Work Setting Out Plan - Block 5-May-12 17-May-12 B Closed
Program Activity A Block B Doors Details X 13-Aug-12 4-Sep-12
Program Activity A Block B Staircase Layout & Details X 27-Aug-12 16-Sep-12
Program Activity A Block B Reflected Ceiling Layout X 27-Aug-12 16-Sep-12
Program Activity A Block B Handrail Layout & Details X 8-Sep-12 26-Sep-12g y y
Program Activity A Block B Flooring X 8-Sep-12 26-Sep-12
Program Activity A Block B Sinage Layout and Details X 27-Oct-12 14-Nov-12
Program Activity A Block B Parking Layout X 2-Feb-13 20-Feb-13
Program Activity A Block B Traffic Sign Layout X 2-Feb-13 20-Feb-13
Ground Floor
Public Areas
Program Activity A Block B Block Work Setting Out Plan for Ground X 27-Aug-12 16-Sep-12
Program Activity A Block B Reflected Ceiling Layout X 29-Sep-12 17-Oct-12
Program Activity A Block B Flooring Layout X 29-Sep-12 17-Oct-12
Program Activity A Block B Wet Area Ceramic & Pocalin Layout for Toilets X 29-Sep-12 17-Oct-12
Program Activity A Block B Staircase Layout & Details X 10-Oct-12 31-Oct-12
Program Activity A Block B Handrail Layout & Details X 10-Oct-12 31-Oct-12
Program Activity A Block B Doors Details X 18-Nov-12 9-Dec-12
Program Activity A Block B Sinage Layout and Details X 18-Nov-12 9-Dec-12
Program Activity A Block B Carpet Flooring Details X 30-Mar-13 17-Apr-13
Program Activity A Block B Furniture Layout and Detals X 2-Jul-13 22-Jul-13
Restaurant
Program Activity A Block B Reflected Ceiling Layout X 25-Sep-12 15-Oct-12
Program Activity A Block B Flooring Layout X 22-Dec-12 10-Jan-13
Program Activity A Block B Sinage Layout and Details X 19-Feb-13 11-Mar-13
Program Activity A Block B Furniture Layout and Detals X 10-Jul-13 30-Jul-13
Bussiness Center & Retail
Program Activity A Block B Reflected Ceiling Layout X 5-Sep-12 25-Sep-12Program Activity A Block B Reflected Ceiling Layout p p
Program Activity A Block B Flooring Layout X 5-Nov-12 26-Nov-12
Program Activity A Block B Sinage Layout and Details X 10-Apr-13 30-Apr-13
Program Activity A Block B Furniture Layout and Detals X 2-Jul-13 22-Jul-13
Enterance Lobby & Lounge
Program Activity A Block B Reflected Ceiling Layout X 18-Nov-12 9-Dec-12
Program Activity A Block B Flooring Layout X 11-Dec-12 31-Dec-12
Program Activity A Block B Sinage Layout and Details X 10-Apr-13 30-Apr-13
Program Activity A Block B Furniture Layout and Detals X 14-Jul-13 1-Aug-13
Typical Floors
General
Program Activity A Block B Block Work Setting Out Plan for 1st Floor X 5-Sep-12 25-Sep-12 13-Jun-12
269-A-BB-BL-155 Shop Drawing for 1st Floor Block Work Setting Out Plan Block – “B” 13-Jun-12 UR Opened &
Program Activity A Block B Block Work Setting Out Plan for 2nd Floor X 15-Sep-12 3-Oct-12 28-Jun-12
269-A-BB-BL-192 A Block B Shop Drawing for Second Floor Block Work Setting Out Plan - Block “B” 28-Jun-12 UR Opened &
Program Activity A Block B Block Work Setting Out Plan for 3rd to 6th Floor X 24-Sep-12 14-Oct-12
Program Activity A Block B Block Work Setting Out Plan for 7th Floor X 4-Nov-12 25-Nov-12
Corridor / Public Areas
Program Activity A Block B Landscaping's Water Proofing Details X 15-Sep-12 3-Oct-12
Program Activity A Block B Reflected Ceiling Layout X 8-Oct-12 29-Oct-12
Program Activity A Block B Landscaping Layout & Details X 14-Oct-12 4-Nov-12
Program Activity A Block B Staircase Layout & Details X 20-Oct-12 8-Nov-12
Program Activity A Block B Handrail Layout & Details X 20-Oct-12 8-Nov-12
Program Activity A Block B Pool Deck Layout X 3-Nov-12 13-Nov-12Program Activity A Block B Pool Deck Layout X 3-Nov-12 13-Nov-12
Program Activity A Block B Doors Details X 17-Nov-12 6-Dec-12
Program Activity A Block B Sinage Layout and Details X 10-Dec-12 30-Dec-12
Program Activity A Block B Flooring Layout X 10-Dec-12 30-Dec-12
Program Activity A Block B Irrigation Layout & Details X 10-Dec-12 30-Dec-12
Program Activity A Block B Sky Light Details X 15-Jan-13 5-Feb-13
Program Activity A Block B Carpet Flooring Details X 8-Apr-13 28-Apr-13
File : -Engineering Tracking Chart - Rev 00 8 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block B Furniture Layout and Detals X 23-Jul-13 13-Aug-13
Hotel Rooms
Program Activity A Block B Reflected Ceiling Layout X 20-Oct-12 8-Nov-12
Program Activity A Block B Wet Area Ceramic & Pocalin Layout X 20-Oct-12 8-Nov-12
Program Activity A Block B Wardrobe Details X 10-Dec-12 30-Dec-12
Program Activity A Block B Floors Layout and Details X 22-Dec-12 10-Jan-13
Program Activity A Block B Mirror Details X 15-Jan-13 5-Feb-13
Program Activity A Block B Doors Details X 15-Jan-13 5-Feb-13
Program Activity A Block B Vanity Counter Details X 9-Feb-13 27-Feb-13
Program Activity A Block B Carpet Flooring Details X 8-Apr-13 28-Apr-13
Program Activity A Block B Sinage Layout and Details X 8-Apr-13 28-Apr-13
Program Activity A Block B Furniture Layout and Detals X 23-Jul-13 13-Aug-13
Roof - Upper Roof Floor
General
Program Activity A Block B Block Work Setting Out Plan for for Roof&Upper Roof X 20-Oct-12 8-Nov-12
Program Activity A Block B Roof's Water Proofing System X 31-Oct-12 21-Nov-12
Program Activity A Block B Flooring Layout X 31-Oct-12 21-Nov-12
Program Activity A Block B Doors Details X 19-Dec-12 9-Jan-13
B.2.3- Residential (Block C)2nd Basement Floor
Program Activity A Block C Block Work Setting Out Plan for 2nd Basement X 27-May-12 14-Jun-12 21-Apr-12 11-Jun-12 B Closedg y g
269-S-BC-BL-108 Shop drawing for 2nd Basement BlockWork Setting Out Plan (Block-C) 21-Apr-12 11-Jun-12 B Closed &
Program Activity A Block C Staircase Layout & Details X 11-Jul-12 31-Jul-12
Program Activity A Block C Handrail Layout & Details X 23-Jul-12 12-Aug-12
Program Activity A Block C Reflected Ceiling Layout X 15-Aug-12 6-Sep-12
Program Activity A Block C Flooring X 3-Oct-12 23-Oct-12
Program Activity A Block C Doors Details X 3-Oct-12 23-Oct-12
Program Activity A Block C Sinage Layout and Details X 17-Nov-12 6-Dec-12
Program Activity A Block C Parking Layout X 22-Jan-13 12-Feb-13
Program Activity A Block C Traffic Sign Layout X 22-Jan-13 12-Feb-13
1st Basement Floor
Program Activity A Block C Block Work Setting Out Plan for 1st Basement X 11-Jul-12 31-Jul-12 5-May-12 17-May-12 B Closed
269-A-BB-BL-126 Shop drawing for 01st Basement Block Work Setting Out Plan - Block 5-May-12 17-May-12 B Closed
Program Activity A Block C Staircase Layout & Details X 13-Aug-12 4-Sep-12
Program Activity A Block C Handrail Layout & Details X 13-Aug-12 4-Sep-12
Program Activity A Block C Reflected Ceiling Layout X 13-Aug-12 4-Sep-12
Program Activity A Block C Flooring X 27-Aug-12 16-Sep-12
Program Activity A Block C Doors Details X 8-Sep-12 26-Sep-12
Program Activity A Block C Sinage Layout and Details X 15-Dec-12 3-Jan-13
Program Activity A Block C Parking Layout X 13-Feb-13 5-Mar-13
Program Activity A Block C Traffic Sign Layout X 13-Feb-13 5-Mar-13
Ground Floor
Program Activity A Block C Block Work Setting Out Plan for Ground X 13-Aug-12 4-Sep-12 30-Jun-12
269-A-BA-Bl-188 Shop Drawing for Ground Floor Block Work Setting Out Plan - Block “C” X 30-Jun-12 UR Opened &269 A BA Bl 188 Shop Drawing for Ground Floor Block Work Setting Out Plan Block C UR Opened &
Program Activity A Block C Staircase Layout & Details X 25-Aug-12 12-Sep-12
Program Activity A Block C Flooring Layout X 1-Sep-12 19-Sep-12
Program Activity A Block C Reflected Ceiling Layout X 11-Sep-12 1-Oct-12
Program Activity A Block C Handrail Layout & Details X 11-Sep-12 1-Oct-12
Program Activity A Block C Wet Area Ceramic & Pocalin Layout for Toilets X 29-Sep-12 17-Oct-12
Program Activity A Block C Doors Details X 22-Oct-12 12-Nov-12
Program Activity A Block C Sinage Layout and Details X 24-Dec-12 14-Jan-13
Typical Floors
General
Program Activity A Block C Block Work Setting Out Plan for 1st Floor X 25-Aug-12 12-Sep-12
Program Activity A Block C Block Work Setting Out Plan for 2nd Floor X 3-Sep-12 23-Sep-12
Program Activity A Block C Block Work Setting Out Plan for 3rd to 6th Floor X 12-Sep-12 2-Oct-12
Program Activity A Block C Block Work Setting Out Plan for 7th Floor X 29-Oct-12 19-Nov-12
Corridor / Public Areas
Program Activity A Block C Staircase Layout & Details X 26-Sep-12 16-Oct-12
Program Activity A Block C Handrail Layout & Details X 26-Sep-12 16-Oct-12
Program Activity A Block C Reflected Ceiling Layout X 10-Nov-12 29-Nov-12
Program Activity A Block C Doors Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Sinage Layout and Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Flooring Layout X 5-Jan-13 23-Jan-13
One Bed Room Apartements
Program Activity A Block C Wet Area Ceramic & Pocalin Layout X 3-Nov-12 22-Nov-12
Program Activity A Block C Reflected Ceiling Layout X 17-Nov-12 6-Dec-12Program Activity A Block C Reflected Ceiling Layout X 17-Nov-12 6-Dec-12
Program Activity A Block C Wardrobe Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Floors Layout and Details X 5-Jan-13 23-Jan-13
Program Activity A Block C Vanity Counter Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Mirror Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Doors Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Sinage Layout and Details X 28-Jan-13 17-Feb-13
File : -Engineering Tracking Chart - Rev 00 9 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity A Block C Kitchen Cabinet Details X 9-Feb-13 27-Feb-13
Two Bed Room Apartements
Program Activity A Block C Wet Area Ceramic & Pocalin Layout X 8-Oct-12 29-Oct-12
Program Activity A Block C Reflected Ceiling Layout X 17-Nov-12 6-Dec-12
Program Activity A Block C Wardrobe Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Floors Layout and Details X 5-Jan-13 23-Jan-13
Program Activity A Block C Vanity Counter Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Mirror Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Doors Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Sinage Layout and Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Kitchen Cabinet Details X 9-Feb-13 27-Feb-13
Three Bed Room Apartements
Program Activity A Block C Wet Area Ceramic & Pocalin Layout for X 8-Oct-12 29-Oct-12
Program Activity A Block C Reflected Ceiling Layout X 20-Oct-12 8-Nov-12
Program Activity A Block C Wardrobe Details X 22-Dec-12 10-Jan-13
Program Activity A Block C Floors Layout and Details X 5-Jan-13 23-Jan-13
Program Activity A Block C Vanity Counter Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Mirror Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Doors Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Sinage Layout and Details X 28-Jan-13 17-Feb-13
Program Activity A Block C Kitchen Cabinet Details X 9-Feb-13 27-Feb-13g yRoof - Upper Roof Floor
General
Program Activity A Block C Block Work Setting Out Plan for Ground X 17-Nov-12 6-Dec-12
Program Activity A Block C Roof's Water Proofing System X 25-Nov-12 16-Dec-12
Program Activity A Block C Pool Deck Layout X 2-Dec-12 20-Dec-12
Program Activity A Block C Doors Details X 1-Jan-13 21-Jan-13
Program Activity A Block C Staircase Layout & Details X 1-Jan-13 21-Jan-13
Program Activity A Block C Wet Area Ceramic & Pocalin Layout for Toilets X 26-Jan-13 13-Feb-13
Program Activity A Block C Flooring Layout X 26-Jan-13 13-Feb-13
Program Activity A Block C Handrail Layout & Details X 26-Jan-13 13-Feb-13
Gymnasium
Program Activity A Block C Reflected Ceiling Layout X 19-Dec-12 9-Jan-13
Program Activity A Block C Vinyl Floor Detals X 2-Mar-13 20-Mar-13
Program Activity A Block C Furniture Layout and Detals X 30-Jul-13 20-Aug-13
B.4- Speciality Works DrawingsB.4.1- Swimming PoolsAll Buildings
Program Activity 0 SP Block A Swimming Pool Layout & Details for Block A X 6-Oct-12 24-Oct-12 18-Apr-12 3-May-12 C Opened
Program Activity 0 SP Block A Swimming Pool 's Water Prrofing for Block A X 6-Oct-12 24-Oct-12
Program Activity 0 SP Block B Swimming Pool Layout & Details for Block B X 6-Oct-12 24-Oct-12 12-Apr-12 26-Apr-12 C Opened
Program Activity 0 SP Block B Swimming Pool 's Water Proofing for Block B X 6-Oct-12 24-Oct-12
Program Activity 0 SP Block C Swimming Pool Layout & Details for Block C X 30-Oct-12 20-Nov-12 17-Apr-12 3-May-12 C Opened
Program Activity 0 SP Block C Swimming Pool 's Water Proofing for Block C X 30-Oct-12 20-Nov-12Program Activity 0 SP Block C Swimming Pool s Water Proofing for Block C
B.4.2- External FaçadeHotel Apartments (Block A)
Program Activity 0 SP Block A External Elevation - North X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block A External Elevation - South X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block A Aluminum Curtain Wall Layout & Details X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block A External Elevation - East X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block A External Elevation - West X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block A GRC Layout & Details X 24-Feb-13 14-Mar-13
Hotel (Block B)
Program Activity 0 SP Block B External Elevation - North X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block B External Elevation - South X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block B Aluminum Curtain Wall Layout & Details X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block B External Elevation - East X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block B External Elevation - West X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block B GRC Layout & Details X 24-Feb-13 14-Mar-13
Residential (Block C)
Program Activity 0 SP Block C External Elevation - North X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block C External Elevation - South X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block C Aluminum Curtain Wall Layout & Details X 14-Oct-12 4-Nov-12
Program Activity 0 SP Block C External Elevation - East X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block C External Elevation - West X 28-Oct-12 18-Nov-12
Program Activity 0 SP Block C GRC Layout & Details X 24-Feb-13 14-Mar-13
B 4 3 Façade CleaningB.4.3- Façade CleaningAll Buildings
Program Activity 0 SP Block A Glass Cleaning Machine X 16-Mar-13 3-Apr-13
Program Activity 0 SP Block B Glass Cleaning Machine X 16-Mar-13 3-Apr-13
Program Activity 0 SP Block C Glass Cleaning Machine X 16-Mar-13 3-Apr-13
B.4.4- Garbage ChutesAll Buildings
File : -Engineering Tracking Chart - Rev 00 10 of 11 Printed On :- 05/07/2012 at 08:07
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Civil - Architectural - Speciality - PS
DATA DATE
Description
30-Jun-12
Ce
rtif
ica
tes
Submitted and Still Under ReviewingSubmitted and will be resubmitted again
Planned
S.N
Sa
mp
les
Te
st
/ In
sp
ec
tio
n
Mfr
's D
ata
Action
Trade
COLOR CODING
Closed
Returned
Submitted and No Response Within 14 Days
Gu
ara
nte
e /
Wa
rra
nte
No Action
Oth
ers
Statusopened/
Ca
lcu
lati
on
s
Actual
DocumentSpecification
orBOQ Page
Planned
Rev.
Type of Submittal
Sh
op
Dra
win
gs
Building #
SD SM GT MD TI CA CT OTNotes
Submission Date
ActionCode
Returned Date
opened/Closed
ActualSub. Date
Approval Date
Program Activity 0 SP Block A Garbage Chute Layout & Details for Block A X 4-Jul-12 24-Jul-12
Program Activity 0 SP Block B Garbage Chute Layout & Details for Block B X 9-Sep-12 27-Sep-12
Program Activity 0 SP Block C Garbage Chute Layout & Details for Block C X 17-Nov-12 6-Dec-12
B.4.5- Linen ChutesHotel (Block B)
Program Activity 0 SP Block B Linen Chute Layout & Details for Block B X 3-Sep-12 23-Sep-12
B.5- Provisional Sum DrawingsB.5.1- Kitchen EquipmentsHotel (Block B)
Program Activity 0 SP Block B Kitchen Equipments Drawings X 16-Jul-12 5-Aug-12
B.5.2- Laundary EquipmentsHotel (Block B)
Program Activity 0 SP Block B Laundary Equipments Drawings X 16-Jul-12 5-Aug-12
B.5.3- Façade LightingAll Buildings
Program Activity 0 SP Block A Facade Lighitng Drawings X 11-Sep-12 1-Oct-12
Program Activity 0 SP Block B Facade Lighitng Drawings X 11-Sep-12 1-Oct-12
Program Activity 0 SP Block C Facade Lighitng Drawings X 11-Sep-12 1-Oct-12
B.5.4- Cooking StationHotel (Block B)
Program Activity 0 SP Block B Cooking Station Drawings X 31-Jul-12 22-Aug-12g y g g
B.5.5- Gymnasium EquipmentsAll Buildings
Program Activity 0 SP Block A Gymnasium Drawings 2-Apr-13 18-Apr-13
Program Activity 0 SP Block B Gymnasium Drawings 2-Apr-13 18-Apr-13
Program Activity 0 SP Block C Gymnasium Drawings 2-Apr-13 18-Apr-13
File : -Engineering Tracking Chart - Rev 00 11 of 11 Printed On :- 05/07/2012 at 08:07
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
8.0 ENGINEERINGT LOG
8.2 MEP LOG
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
B-SHOP DRAWINGS . . . . .
B.3- Electromechanical DrawingsB.3.1- Hotel Apartments (Block A)2nd Basement Floor
1 1 M Block A MEP Builder Work Layout X 1 18-Feb-12 22-Feb-12 12-Feb-12 5-Mar-12 B Closed
2 1 M Block A Drainage Layout & Details X 1 19-Feb-12 8-Mar-12 14-Mar-12 17-Mar-12 B Closed
1 1 M Block A Water Supply Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 13-Mar-12 B Closed
1 1 M Block A Fire Fighting Layout & Details X 1 28-Feb-12 19-Mar-12 3-Apr-12 8-Apr-12 B Closed
2 1 M Block A HVAC Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B/C Opened
1 1 M Block A Lighting Layout & Details X 1 28-Feb-12 19-Mar-12 20-Feb-12 29-Feb-12 B Closed
2 1 M Block A Power Layout & Details X 1 28-Feb-12 19-Mar-12 9-Apr-12 24-Apr-12 B Closed
1 1 M Block A Fire Alarm Layout & Details X 1 28-Feb-12 19-Mar-12 7-Mar-12 18-Mar-12 C Opened
1 1 M Block A CBS Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 20-Mar-12 B Closed
1 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 28-Feb-12 19-Mar-12 25-Feb-12 5-Mar-12 B Closed
0 1 M Block A ELV Layout & Details X 1 28-Feb-12 19-Mar-12
2 1 M Block A BMS Layout & Details X 1 28-Feb-12 19-Mar-12 12-Apr-12 3-May-12 B Closed
0 1 M Block A Data & Telephone Layout & Details X 1 28-Feb-12 19-Mar-12 14-Mar-12 7-Apr-12 B Closed
1 1 M Block A MEP Cordination Layout X 1 4-Mar-12 22-Mar-12 23-Apr-12 3-May-12 B Closed
0 1 M Block A LPG & Gas Detection Layout & Details X 1 8-Apr-12 26-Apr-12
1st Basement Floor
l k ild k
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
2 1 M Block A MEP Builder Work Layout X 1 26-Feb-12 15-Mar-12 18-Mar-12 21-Mar-12 B Closed
2 1 M Block A Drainage Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B Closed
1 1 M Block A Water Supply Layout & Details X 1 13-Mar-12 2-Apr-12 3-Mar-12 13-Mar-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 13-Mar-12 2-Apr-12 10-Mar-12 17-Mar-12 B Closed
1 1 M Block A HVAC Layout & Details X 1 13-Mar-12 2-Apr-12 18-Mar-12 29-Mar-12 B Closed
1 1 M Block A Lighting Layout & Details X 1 13-Mar-12 2-Apr-12 22-Mar-12 31-Mar-12 B Closed
1 1 M Block A Power Layout & Details X 1 13-Mar-12 2-Apr-12 28-Mar-12 5-Apr-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 13-Mar-12 2-Apr-12 14-Mar-12 24-Mar-12 C Opened
0 1 M Block A CBS Layout & Details X 1 13-Mar-12 2-Apr-12 14-Mar-12 21-Mar-12 B Closed
3 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 13-Mar-12 2-Apr-12 21-Apr-12 3-May-12 B Closed
0 1 M Block A ELV Layout & Details X 1 13-Mar-12 2-Apr-12
2 1 M Block A BMS Layout & Details X 1 13-Mar-12 2-Apr-12 12-Apr-12 3-May-12 B Closed
2 1 M Block A Data & Telephone Layout & Details X 1 13-Mar-12 2-Apr-12 18-Apr-12 17-May-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 18-Mar-12 5-Apr-12 12-Apr-12 24-Apr-12 B Closed
Ground Floor
1 1 M Block A Drainage Layout & Details (Low Level) X 1 3-Mar-12 21-Mar-12 10-May-12 21-May-12 B Closed
1 1 M Block A MEP Builder Work Layout X 1 11-Mar-12 29-Mar-12 24-Mar-12 2-Apr-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 21-Mar-12 10-Apr-12 29-Apr-12 24-Jun-12 B Closed &
1 1 M Block A Water Supply Layout & Details X 1 27-Mar-12 16-Apr-12 17-Apr-12 28-Apr-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 27-Mar-12 16-Apr-12 19-May-12 26-May-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 27-Mar-12 16-Apr-12 1-Apr-12 16-Apr-12 B/C Opened
0 1 M Block A Lighting Layout & Details X 1 27-Mar-12 16-Apr-12 24-Mar-12 2-Apr-12 B Closed
0 1 M Block A Power Layout & Details X 1 27-Mar-12 16-Apr-12 16-May-12 27-May-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 27-Mar-12 16-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 27-Mar-12 16-Apr-12 4-Apr-12 3-May-12 B Closed
0 1 M Block A Drainage Layout & Details (High Level) X 1 27-Mar-12 16-Apr-12 29-Apr-12 3-Jun-12 B Closed
1st Floor
0 1 M Block A Drainage Layout & Details (Low Level) X 1 21-Mar-12 10-Apr-12 29-Apr-12 3-Jun-12 B Closed
0 1 M Block A LPG & Gas Detection Layout & Details X 1 24-Mar-12 11-Apr-12
0 1 M Block A MEP Builder Work Layout X 1 1-Apr-12 19-Apr-12 29-Apr-12 3-May-12 B/C Opened
0 1 M Block A MEP Cordination Layout X 1 8-Apr-12 26-Apr-12 10-Jun-12 24-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 9-Apr-12 29-Apr-12 8-May-12 20-May-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 9-Apr-12 29-Apr-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 9-Apr-12 29-Apr-12 12-May-12 27-May-12 B Closed
0 1 M Block A Lighting Layout & Details X 1 9-Apr-12 29-Apr-12 15-May-12 26-May-12 B Closed
1 1 M Block A Power Layout & Details X 1 9-Apr-12 29-Apr-12 10-May-12 23-May-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12 14-Apr-12 3-May-12 B Closed
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12 13-May-12 23-May-12 B Closed
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12 8-May-12 17-May-12 B Closed
0 1 M Block A Drainage Layout & Details (High Level) X 1 9-Apr-12 29-Apr-12 10-Jun-12 20-Jun-12 B Closed &
2nd Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12 4-Jun-12 UR Opened
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12 4-Jun-12 C Opened &
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12 4-Jun-12 C Opened &
0 1 M Block A Drainage Layout & Details X 1 14-Apr-12 2-May-12 10-Jun-12 20-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 14-Apr-12 2-May-12 23-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 14-Apr-12 2-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 14-Apr-12 2-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block A Lighting Layout & Details X 1 14-Apr-12 2-May-12 28-May-12 12-Jun-12 B Closed &
File : -Engineering Tracking Chart - Rev 00 1 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block A Power Layout & Details X 1 14-Apr-12 2-May-12 20-May-12 27-May-12 B Closed
0 1 M Block A Fire Alarm Layout & Details X 1 14-Apr-12 2-May-12
0 1 M Block A MEP Builder Work Layout X 1 23-Apr-12 13-May-12 16-May-12 26-May-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 28-Apr-12 16-May-12
3rd Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Drainage Layout & Details X 1 14-Apr-12 2-May-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 14-Apr-12 2-May-12 23-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 14-Apr-12 2-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 14-Apr-12 2-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block A Lighting Layout & Details X 1 14-Apr-12 2-May-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 14-Apr-12 2-May-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 14-Apr-12 2-May-12
0 1 M Block A MEP Builder Work Layout X 1 23-Apr-12 13-May-12 19-May-12 26-May-12 B Closed
0 1 M Block A MEP Cordination Layout X 1 28-Apr-12 16-May-12
4th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Drainage Layout & Details X 1 28-Apr-12 16-May-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 28-Apr-12 16-May-12 26-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 28-Apr-12 16-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block A Lighting Layout & Details X 1 28-Apr-12 16-May-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 28-Apr-12 16-May-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block A MEP Cordination Layout X 1 9-May-12 29-May-12
0 1 M Block A MEP Builder Work Layout X 1 14-May-12 3-Jun-12 19-May-12 26-May-12 B Closed
5th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A MEP Builder Work Layout X 1 4-Jun-12 25-Jun-12 19-May-12 26-May-12 B Closed
0 1 M Block A Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block A MEP Cordination Layout X 1 9-Jun-12 28-Jun-12
0 1 M Block A Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
6th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block A Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 12-Jun-12 B Closed &
0 1 M Block A Power Layout & Details X 1 9-Jun-12 28-Jun-12 30-May-12 13-Jun-12 B Closed &
0 1 M Block A Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block A MEP Cordination Layout X 0 4-Jul-12 24-Jul-12
0 1 M Block A MEP Builder Work Layout X 0 4-Jul-12 24-Jul-12 19-May-12 26-May-12 B Closed
7th Floor
0 1 M Block A CCTV,Access Control,Intercom Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A ELV Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A BMS Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Data & Telephone Layout & Details X 1 9-Apr-12 29-Apr-12
0 1 M Block A Lighting Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block A Power Layout & Details X 1 26-Jun-12 16-Jul-12y
0 1 M Block A Fire Alarm Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block A Drainage Layout & Details X 1 27-Jun-12 17-Jul-12 17-Jun-12 21-Jun-12 B Closed &
0 1 M Block A Water Supply Layout & Details X 1 27-Jun-12 17-Jul-12 27-May-12 3-Jun-12 B Closed
0 1 M Block A Fire Fighting Layout & Details X 1 27-Jun-12 17-Jul-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block A MEP Cordination Layout X 0 24-Jul-12 13-Aug-12
File : -Engineering Tracking Chart - Rev 00 2 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block A MEP Builder Work Layout X 0 24-Jul-12 13-Aug-12
Roof Floor
0 1 M Block A Data & Telephone Layout & Details X 1 1-May-12 21-May-12
0 1 M Block A Lighting Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block A Power Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block A Fire Alarm Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block A Drainage Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block A Water Supply Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block A Fire Fighting Layout & Details X 0 18-Jul-12 7-Aug-12 19-May-12 5-Jun-12 B Closed
0 1 M Block A HVAC Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block A MEP Cordination Layout X 0 4-Aug-12 26-Aug-12
0 1 M Block A MEP Builder Work Layout X 0 4-Aug-12 26-Aug-12
Upper Roof Floor
0 1 M Block A Drainage Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Water Supply Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Fire Fighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A HVAC Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Lighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Power Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A Fire Alarm Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block A MEP Cordination Layout X 0 8-Aug-12 30-Aug-12
B.3.2- Hotel Apartments (Block B)2nd Basement Floor
2 1 M Block B Drainage Layout & Details X 1 19-Feb-12 8-Mar-12 14-Mar-12 17-Mar-12 B Closed
1 1 M Block B MEP Builder Work Layout X 1 19-Feb-12 8-Mar-12 12-Feb-12 5-Mar-12 B Closed
1 1 M Block B Water Supply Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 13-Mar-12 B Closed
1 1 M Block B Fire Fighting Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 8-Mar-12 B Closed
2 1 M Block B HVAC Layout & Details X 1 28-Feb-12 19-Mar-12 17-Mar-12 28-Mar-12 B/C Opened
1 1 M Block B Lighting Layout & Details X 1 28-Feb-12 19-Mar-12 20-Feb-12 29-Feb-12 B Closed
1 1 M Block B Fire Alarm Layout & Details X 1 28-Feb-12 19-Mar-12 7-Mar-12 18-Mar-12 C Opened
2 1 M Block B Power Layout & Details X 1 28-Feb-12 19-Mar-12 9-Apr-12 24-Apr-12 B Closed
1 1 M Block B MEP Cordination Layout X 1 6-Mar-12 26-Mar-12 23-Apr-12 6-May-12 B Closed
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
1st Basement Floor
2 1 M Block B Drainage Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B Closed
2 1 M Block B MEP Builder Work Layout X 1 6-Mar-12 26-Mar-12 18-Mar-12 21-Mar-12 B Closed
1 1 M Block B Water Supply Layout & Details X 1 20-Mar-12 9-Apr-12 3-Mar-12 13-Mar-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 20-Mar-12 9-Apr-12 10-Mar-12 17-Mar-12 B Closed
1 1 M Block B HVAC Layout & Details X 1 20-Mar-12 9-Apr-12 18-Mar-12 29-Mar-12 B Closed
1 1 M Block B Lighting Layout & Details X 1 20-Mar-12 9-Apr-12 22-Mar-12 31-Mar-12 B Closed
0 1 M Block B Fire Alarm Layout & Details X 1 20-Mar-12 9-Apr-12 14-Mar-12 24-Mar-12 C Opened
0 1 M Block B CBS Layout & Details X 1 20-Mar-12 9-Apr-12 14-Mar-12 21-Mar-12 B Closed
3 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 20-Mar-12 9-Apr-12 21-Apr-12 3-May-12 B Closed
0 1 M Block B ELV Layout & Details X 1 20-Mar-12 9-Apr-12
2 1 M Block B BMS Layout & Details X 1 20-Mar-12 9-Apr-12 12-Apr-12 3-May-12 B Closed
2 1 M Block B Data & Telephone Layout & Details X 1 20-Mar-12 9-Apr-12 18-Apr-12 17-May-12 B Closed
1 1 M Block B Power Layout & Details X 1 20-Mar-12 9-Apr-12 28-Mar-12 5-Apr-12 B Closed
0 1 M Block B MEP Cordination Layout X 1 27-Mar-12 16-Apr-12 12-Apr-12 24-Apr-12 B Closed
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
Ground Floor1 1 M Block B Drainage Layout & Details (Low Level) X 1 20-Mar-12 9-Apr-12 10-May-12 21-May-12 B Closed
2 1 M Block B Water Supply Layout & Details X 1 8-Apr-12 26-Apr-12 10-May-12 19-May-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 8-Apr-12 26-Apr-12 19-May-12 26-May-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block B Lighting Layout & Details X 1 8-Apr-12 26-Apr-12 27-May-12 B/C Opened &
0 1 M Block B Power Layout & Details X 1 8-Apr-12 26-Apr-12 16-May-12 23-May-12 B/C Opened
0 1 M Block B Fire Alarm Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 8-Apr-12 26-Apr-12 10-May-12 17-May-12 B Closed
0 1 M Block B ELV Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block B Data & Telephone Layout & Details X 1 8-Apr-12 26-Apr-12 20-May-12 C Opened &
0 1 M Block B Drainage Layout & Details (High Level) X 1 8-Apr-12 26-Apr-12 22-May-12 3-Jun-12 B/C Opened
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B MEP Cordination Layout X 1 15-Apr-12 3-May-12
0 1 M Block B MEP Builder Work Layout X 1 15-Apr-12 3-May-12 7-May-12 17-May-12 B Closed
1st Floor
0 1 M Block B Drainage Layout & Details (Low Level) X 1 8-Apr-12 26-Apr-12 20-May-12 3-Jun-12 B/C Opened
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B Water Supply Layout & Details X 1 28-Apr-12 16-May-12 8-May-12 20-May-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 28-Apr-12 16-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 28-Apr-12 16-May-12 25-Jun-12 UR Opened &
0 1 M Block B Lighting Layout & Details X 1 28-Apr-12 16-May-12 25-Jun-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 28-Apr-12 16-May-12 2-Jun-12 C Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 28-Apr-12 16-May-12
File : -Engineering Tracking Chart - Rev 00 3 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12 14-Apr-12 3-May-12 B Closed
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12 13-May-12 23-May-12 B Closed
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12 8-May-12 17-May-12 B Closed
0 1 M Block B Drainage Layout & Details (High Level) X 1 28-Apr-12 16-May-12 4-Jun-12 20-Jun-12 B/C Opened &
0 1 M Block B MEP Cordination Layout X 1 5-May-12 23-May-12
0 1 M Block B MEP Builder Work Layout X 1 5-May-12 23-May-12 19-May-12 26-May-12 B Closed
2nd Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B Drainage Layout & Details X 1 19-May-12 6-Jun-12 4-Jun-12 20-Jun-12 B/C Opened &
0 1 M Block B Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Lighting Layout & Details X 1 19-May-12 6-Jun-12 30-Jun-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 19-May-12 6-Jun-12 28-Jun-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B MEP Cordination Layout X 1 26-May-12 13-Jun-12
0 1 M Block B MEP Builder Work Layout X 1 26-May-12 13-Jun-12 24-May-12 30-May-12 B Closed
3rd Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 19-May-12 6-Jun-12 4-Jun-12 21-Jun-12 B Closed &
0 1 M Block B Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Lighting Layout & Details X 1 19-May-12 6-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 19-May-12 6-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B CBS Layout & Details X 1 19-May-12 6-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block B MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12
4th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 4-Jun-12 21-Jun-12 B Closed &
0 1 M Block B Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block B MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12
5th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 4-Jun-12 21-Jun-12 B Closed &
0 1 M Block B Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block B MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12
6th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 4-Jun-12 21-Jun-12 B Closed &
File : -Engineering Tracking Chart - Rev 00 4 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block B Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Power Layout & Details X 1 9-Jun-12 28-Jun-12 1-Jul-12 UR Opened &
0 1 M Block B Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block B CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B MEP Cordination Layout X 0 4-Jul-12 24-Jul-12
0 1 M Block B MEP Builder Work Layout X 0 4-Jul-12 24-Jul-12
7th Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block B Lighting Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block B Power Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block B Fire Alarm Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block B CBS Layout & Details X 1 26-Jun-12 16-Jul-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B Drainage Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block B Water Supply Layout & Details X 1 27-Jun-12 17-Jul-12 27-May-12 3-Jun-12 B Closed
0 1 M Block B Fire Fighting Layout & Details X 1 27-Jun-12 17-Jul-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block B MEP Cordination Layout X 0 24-Jul-12 13-Aug-12
0 1 M Block B MEP Builder Work Layout X 0 24-Jul-12 13-Aug-12
Roof Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B ELV Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B BMS Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Data & Telephone Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block B Lighting Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block B Power Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block B Fire Alarm Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block B CBS Layout & Details X 0 17-Jul-12 6-Aug-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block B Drainage Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block B Water Supply Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block B Fire Fighting Layout & Details X 0 18-Jul-12 7-Aug-12 19-May-12 5-Jun-12 B Closed
0 1 M Block B HVAC Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block B MEP Cordination Layout X 0 4-Aug-12 26-Aug-12
0 1 M Block B MEP Builder Work Layout X 0 4-Aug-12 26-Aug-12
Upper Roof Floor
0 1 M Block B LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block B Drainage Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Water Supply Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Fire Fighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B HVAC Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Lighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Power Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B Fire Alarm Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block B MEP Cordination Layout X 0 8-Aug-12 30-Aug-12
B.3.3- Residentail (Block C)2nd Basement Floor
2 1 M Block C Drainage Layout & Details X 1 18-Feb-12 7-Mar-12 14-Mar-12 17-Mar-12 B Closed
1 1 M Block C MEP Builder Work Layout X 1 18-Feb-12 7-Mar-12 12-Feb-12 5-Mar-12 B Closed
1 1 M Block C Water Supply Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 13-Mar-12 B Closed
1 1 M Block C Fire Fighting Layout & Details X 1 28-Feb-12 19-Mar-12 3-Mar-12 8-Mar-12 B Closed
2 1 M Block C HVAC Layout & Details X 1 28-Feb-12 19-Mar-12 17-Mar-12 27-Mar-12 B/C Opened
1 1 M Block C Lighting Layout & Details X 1 28-Feb-12 19-Mar-12 20-Feb-12 29-Feb-12 B Closed
2 1 M Block C Power Layout & Details X 1 28-Feb-12 19-Mar-12 9-Apr-12 24-Apr-12 B Closed
1 1 M Block C Fire Alarm Layout & Details X 1 28-Feb-12 19-Mar-12 7-Mar-12 18-Mar-12 C Opened
1 1 M Block C MEP Cordination Layout X 1 5-Mar-12 25-Mar-12 23-Apr-12 6-May-12 B Closed
1st Basement Floor
2 1 M Block C Drainage Layout & Details X 1 28-Feb-12 19-Mar-12 18-Mar-12 27-Mar-12 B Closed
2 1 M Block C MEP Builder Work Layout X 1 19-Mar-12 8-Apr-12 18-Mar-12 21-Mar-12 B Closed
1 1 M Block C Water Supply Layout & Details X 1 2-Apr-12 22-Apr-12 3-Mar-12 13-Mar-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 2-Apr-12 22-Apr-12 10-Mar-12 17-Mar-12 B Closed
1 1 M Block C HVAC Layout & Details X 1 2-Apr-12 22-Apr-12 18-Mar-12 29-Mar-12 B Closedy
1 1 M Block C Lighting Layout & Details X 1 2-Apr-12 22-Apr-12 22-Mar-12 31-Mar-12 B Closed
1 1 M Block C Power Layout & Details X 1 2-Apr-12 22-Apr-12 28-Mar-12 5-Apr-12 B Closed
0 1 M Block C Fire Alarm Layout & Details X 1 2-Apr-12 22-Apr-12 14-Mar-12 24-Mar-12 C Opened
0 1 M Block C MEP Cordination Layout X 1 9-Apr-12 29-Apr-12 12-Apr-12 24-Apr-12 B Closed
Ground Floor
0 1 M Block C Drainage Layout & Details (Low Level) X 1 20-Mar-12 9-Apr-12 10-May-12 21-May-12 B Closed
File : -Engineering Tracking Chart - Rev 00 5 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block C Water Supply Layout & Details X 1 8-Apr-12 26-Apr-12 17-Apr-12 28-Apr-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 8-Apr-12 26-Apr-12 19-May-12 26-May-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 8-Apr-12 26-Apr-12 1-Apr-12 16-Apr-12 B/C Opened
0 1 M Block C Lighting Layout & Details X 1 8-Apr-12 26-Apr-12 24-Mar-12 2-Apr-12 B Closed
0 1 M Block C Power Layout & Details X 1 8-Apr-12 26-Apr-12 16-May-12 27-May-12 B Closed
0 1 M Block C Fire Alarm Layout & Details X 1 8-Apr-12 26-Apr-12
0 1 M Block C Data & Telephone Layout & Details X 1 8-Apr-12 26-Apr-12 4-Apr-12 3-May-12 B Closed
0 1 M Block C Drainage Layout & Details (High Level) X 1 8-Apr-12 26-Apr-12 14-May-12 23-May-12 B Closed
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C MEP Cordination Layout X 1 15-Apr-12 3-May-12 16-May-12 23-May-12 B Closed
1 1 M Block C MEP Builder Work Layout X 1 15-Apr-12 3-May-12 24-Mar-12 2-Apr-12 B Closed
1st Floor
0 1 M Block C Drainage Layout & Details (Low Level) X 1 8-Apr-12 26-Apr-12 14-May-12 23-May-12 B Closed
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C Water Supply Layout & Details X 1 28-Apr-12 16-May-12 8-May-12 20-May-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 28-Apr-12 16-May-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 28-Apr-12 16-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block C Lighting Layout & Details X 1 28-Apr-12 16-May-12 6-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Power Layout & Details X 1 28-Apr-12 16-May-12 24-May-12 27-Jun-12 B Closed &
0 1 M Block C Fire Alarm Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12 14-Apr-12 3-May-12 B Closed
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12 13-May-12 23-May-12 B Closed
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12 11-Jun-12 UR Opened &
0 1 M Block C Drainage Layout & Details (High Level) X 1 28-Apr-12 16-May-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C MEP Cordination Layout X 1 5-May-12 23-May-12
0 1 M Block C MEP Builder Work Layout X 1 5-May-12 23-May-12 10-May-12 17-May-12 B Closed
2nd Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12 20-Jun-12 UR Opened &
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12 11-Jun-12 27-Jun-12 B Closed &
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Lighting Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 C Opened &
0 1 M Block C Power Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 C Opened &
0 1 M Block C Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C CBS Layout & Details X 1 19-May-12 6-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 1 26-May-12 13-Jun-12
0 1 M Block C MEP Builder Work Layout X 1 26-May-12 13-Jun-12 24-May-12 30-May-12 B Closed
3rd Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 19-May-12 6-Jun-12 23-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 19-May-12 6-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Lighting Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 24-Jun-12 C Opened &
0 1 M Block C Power Layout & Details X 1 19-May-12 6-Jun-12 10-Jun-12 28-Jun-12 C Opened &
0 1 M Block C Fire Alarm Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C CBS Layout & Details X 1 19-May-12 6-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 1 4-Jun-12 25-Jun-12
0 1 M Block C MEP Builder Work Layout X 1 4-Jun-12 25-Jun-12 24-May-12 30-May-12 B Closed
4th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closedpp y y
0 1 M Block C Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 24-Jun-12 C Opened &
0 1 M Block C Power Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 28-Jun-12 C Opened &
0 1 M Block C Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
File : -Engineering Tracking Chart - Rev 00 6 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block C MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block C MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12 24-May-12 30-May-12 B Closed
5th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 24-Jun-12 C Opened
0 1 M Block C Power Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 28-Jun-12 C Opened
0 1 M Block C Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 1 17-Jun-12 5-Jul-12
0 1 M Block C MEP Builder Work Layout X 1 17-Jun-12 5-Jul-12 24-May-12 30-May-12 B Closed
6th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Drainage Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 21-Jun-12 B Closed &
0 1 M Block C Water Supply Layout & Details X 1 9-Jun-12 28-Jun-12 26-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 9-Jun-12 28-Jun-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C Lighting Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 24-Jun-12 C Opened
0 1 M Block C Power Layout & Details X 1 9-Jun-12 28-Jun-12 10-Jun-12 28-Jun-12 C Opened
0 1 M Block C Fire Alarm Layout & Details X 1 9-Jun-12 28-Jun-12
0 1 M Block C CBS Layout & Details X 1 9-Jun-12 28-Jun-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C MEP Cordination Layout X 0 4-Jul-12 24-Jul-12
0 1 M Block C MEP Builder Work Layout X 0 4-Jul-12 24-Jul-12 24-May-12 30-May-12 B Closed
7th Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C ELV Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C BMS Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Data & Telephone Layout & Details X 1 28-Apr-12 16-May-12
0 1 M Block C Lighting Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block C Power Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block C Fire Alarm Layout & Details X 1 26-Jun-12 16-Jul-12
0 1 M Block C CBS Layout & Details X 1 26-Jun-12 16-Jul-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C Drainage Layout & Details X 1 27-Jun-12 17-Jul-12 21-Jun-12 UR Opened &
0 1 M Block C Water Supply Layout & Details X 1 27-Jun-12 17-Jul-12 27-May-12 3-Jun-12 B Closed
0 1 M Block C Fire Fighting Layout & Details X 1 27-Jun-12 17-Jul-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 1 27-Jun-12 17-Jul-12
0 1 M Block C MEP Cordination Layout X 0 24-Jul-12 13-Aug-12
0 1 M Block C MEP Builder Work Layout X 0 24-Jul-12 13-Aug-12
Roof Floor
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C CCTV,Access Control,Intercom Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C ELV Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C BMS Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Data & Telephone Layout & Details X 1 19-May-12 6-Jun-12
0 1 M Block C Lighting Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block C Fire Alarm Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block C CBS Layout & Details X 0 17-Jul-12 6-Aug-12 25-Apr-12 6-May-12 B/C Opened
0 1 M Block C Power Layout & Details X 0 17-Jul-12 6-Aug-12
0 1 M Block C Drainage Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block C Water Supply Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block C Fire Fighting Layout & Details X 0 18-Jul-12 7-Aug-12 19-May-12 5-Jun-12 B Closed
0 1 M Block C HVAC Layout & Details X 0 18-Jul-12 7-Aug-12
0 1 M Block C MEP Cordination Layout X 0 4-Aug-12 26-Aug-12
0 1 M Block C MEP Builder Work Layout X 0 4-Aug-12 26-Aug-12
Upper Roof Floorpp
0 1 M Block C LPG & Gas Detection Layout & Details X 1 10-Apr-12 30-Apr-12
0 1 M Block C Drainage Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Water Supply Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Fire Fighting Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C HVAC Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Lighting Layout & Details X 0 28-Jul-12 15-Aug-12
File : -Engineering Tracking Chart - Rev 00 7 of 8 Printed On :- 05/07/2012 at 08:08
Al Muraqqabat Mixed Use DevelopmentShop Drawings Log - Rev 00Electromechanical
DATA DATE
Description
Gu
ara
nte
e /
Wa
rra
nte
Ca
lcu
lati
on
s
Ce
rtif
ica
tes
No Action
Sa
mp
les
Submitted and will be resubmitted againSubmitted and No Response Within 14 Days
DocumentSpecification
orBOQ Page
Returned
COLOR CODING
TradeBuilding
#
Sh
op
Dra
win
gs
Mfr
's D
ata
Te
st
/ In
sp
ec
tio
n
Planned A l
Statusopened/
30-Jun-12
S.N Rev.Item No.
Type of Submittal
ne
d
Actual Action
Oth
ers
Closed
Submitted and Still Under Reviewing
Planned S b i i
SD SM GT MD TI CA CT OT
Returned Date
Approval Date
opened/Closed
Pla
nn Actual
Sub. DateActionCode
Notes
Submission Date
0 1 M Block C Power Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C Fire Alarm Layout & Details X 0 28-Jul-12 15-Aug-12
0 1 M Block C MEP Cordination Layout X 0 8-Aug-12 30-Aug-12
File : -Engineering Tracking Chart - Rev 00 8 of 8 Printed On :- 05/07/2012 at 08:08
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
Monthly Equipment Inspections were carried out along with the progress of the Project.
Scaffolding Inspection Report
Scaffoldings erected & Dismantled by trained personnel are being used in the site.
Equipments Monthly Inspection Report
Company owned equipments and subcontractor‘s equipments are used for the project during this month.
Temporary Site Facility Inspection Report
Temporary site facility include below mentioned inspections
1. Fire Prevention/fire extinguisher check list
2. DB check List
3. Water Cooler
Site Access Control Activities
Below mentioned steps has been taken to control access
1. Security Guards assigned at main site access
2. Sign board installed at main access and on several locations at site
3. PPE strictly implemented to site
4. Traffic control team (flagmen) provided at service roads.
5. Housekeeping team has been involved for cleaning of access road.
6. New signage’s arrangements ongoing.
May 31, 2012 HSE PROGRESS REPORT
5 ASGC
Hazardous Material Report
Below mentioned hazardous material available at site.
1. Cement
2. Diesel
3. Thinner
4. Conrep.360 FFR
5. Nitobond EP Base
6. Nitoproof 600
7. Reebol WB
8. Lkfix P80 Base
9. Concure WB clear
10. Synthetic Enamel Gloss I
Note: Above mentioned all chemical MSDS are in office file.
Record of Safety Induction Training
Safety induction for new employees (Main and subcontractor) were conducted during the month
Total number of Safety induction during the Project ‐ 1079
Training Activities & Report
Several Safety trainings were given to the site workers during the course of the project in order to maintain the Safety
Rules & Regulations as per DM.
General safety training conducted (weekly bases) for all site staff, workers, Flagman, Operator & raggers.
Heat Stress Awareness Training Conducted for all site staff and site workers. The training was conducted by the
PROLYTE distributor
Emergency Evacuation Drill Conducted 0n 23rd June 2012
Power tool awareness training on 18th June 2012
May 31, 2012 HSE PROGRESS REPORT
6 ASGC
Tool Box Talks
Following tool box topics were discussed during the course of the Project
Total number of tool box talks for the project – 318
1. Emergency evacuation procedure
2. Lifeline system
3. Working at Height
4. Portable electrical tools
5. Safe access and egress
6. Working on Scaffolding
7. Manual handling
8. Safe erection procedure for the erection of placing boom.
9. Guard rail system /barricading.
10. Safe lifting procedure.
11. Heat Stress awareness training
12. Scaffolding erecting and dismantling
13. p
Record of Disciplinary Actions
1. Issuance of warning letters
2. Deduction of salary
3. Internal memos.
4. Safety Correction Active Report.
Property Damage Report
No property damage case is reported for the Project
Revisions to The Safety Guidelines
No Amendments or Revision to HSE Guidelines
Safety Audits
Didn’t started the audit in the site
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
9.0 SAFETY REPORT
9.2 MANHOURS & FIRST AID HISTOGRAMS
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Manhours Histogram
700,000
800,000
File Name : Curves Page 1 of 1 Printed On : 05/07/2012 at 10:51
File Name : Curves Page 1 of 1 Printed On : 05/07/2012 at 10:53
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
10.0 QUALITY REPORT
10.1 COMPRESSIVE STRENGTH RESULTS FOR CONCRETE
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm258.5605956
52.555
44 6646 60.544 61.551 64.5
45.5 63.546.5 6440 50.5
45.5 55.5
A2
A2 35
45B
62.5
64OPC + GGPS + MS 12/02/2012Crane Foundation (TC3 & TC4) 47.5Block A & B
Block C 5320/02/2012 42
15/02/2012 44.5
13/02/2012
08/02/2012
11/03/201219/02/2012
12/03/2012
A2 01/03/2012
Blinding Concrete under Raft Block A
Block A 02/02/201235 OPC + GGPS + MS+WP Blinding Concrete under Raft
07/03/201235 OPC + GGPS + MS+WP Blinding Concrete under Raft Block C
Core wall & columns from 2nd to 3rd floor at Block A & Columns from Ground to 1st floor at Block B
Block A & B
Block B
Mix TypeCompressive
Strength N/mm2
Approx. Proportions of Cementitious
Material
Location / Place of Casting Building / Block No. Casting Date Crushing Date
(after 7 days)
Compressive Strength \result
after 7 days N/mm2
Avarege of Compressive
Strength Result after 7 days
N/mm2
Crushing Date (after 28 days)
Compressive Strength Result
after 28 days N/mm2
Avarege of Compressive Strength Result after 28
days N/mm2
Al Muraqqabat Mixed Use Development Monthly Progress Report
Compressive Strength Result for Concrete
Compressive Strength Result for Concrete
N/mm2
49.5
51.5
54.5
51.5
55
56.5
4949.548.555.5
09/07/201218/06/2012 4911/06/2012
09/06/2012 16/06/2012 54 07/07/2012
E 45 OPC + GGPS Columns from Ground to 1st floor at Block C-2 Block C-2
06/06/2012 13/06/2012 52 04/07/2012
E 45 OPC + GGPS
Columns from 2nd to 3rd floor at Block A, Core wall (CW6) & Columns from Ground to 1st floor at Block B & Columns from Ground to 1st floor at Block C-2 & Attic slab at 1st floor at Block -
Block A,Block B, Block C-2 &
Block C
E 45 OPC + GGPS Core wall (CW-6) & columns from Ground floor to 1st floor at Block B
Block B
5351.548.550.548
35.535
36.546.54746
42.544 5
testing after 3 days 21/06/2012 36
16/07/2012
11/07/2012
E 45 OPC + GGPSCore wall (CW8) & columns from Ground floor to 1st Block C-2 20/06/2012 27/06/2012 43 18/07/2012
45 OPC + GGPS Slab - 3rd floor at Block A Block A 18/06/2012 16/07/201225/06/2012 46.5
E 45 OPC + GGPS Slab - 3rd floor at Block A Block A 18/06/2012
49
E
53
E 45 OPC + GGPS Columns & Core wall (CW9) from Ground to 1st floor at Block C-2
Block C-2 18/06/2012 25/06/2012
E 45 OPC + GGPS Slab - 1st floor at Block C-1 Block C-1 13/06/2012 20/06/2012
44.541
47.553.552.544
46.544.5
3228.530
testing after 3 days
23/07/2012
28/06/2012 30
E 45 OPC + GGPS Slab - 1st floor at Block B Block B 25/06/2012 02/07/2012
19/07/2012
E 45 OPC + GGPS Slab - 1st floor at Block B Block B 25/06/2012
E 45 OPC + GGPS Columns & wall from 3rd to 4th floor at Block A Block A 21/06/2012 28/06/2012 45
E 45 OPC + GGPS Columns from 3rd to 4th floor at Block A Block A 20/06/2012 27/06/2012 51 18/07/2012
E 45 OPC + GGPS from Ground floor to 1st floor,Block C-2
Block C-2 20/06/2012 27/06/2012 43 18/07/2012
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
10.0 QUALITY REPORT
10.2 NCR & SITE INSTRUCTIONS LOG
Al Muraqqabat Mixed Use DevelopmentMonthly Progress ReportNCR Tracking & Site Instructions Log - Rev 00
DATA DATE
Description
NCR
SI
S.N
StatusIssue Date
30-Jun-12
Notes
Sit
e In
stru
ctio
ns
COLOR CODING
Opened
CLOSED
Actual Closure Date
ASGC Reply Date
Type of Submittal
Returned Date
No
n C
on
firm
Rep
ort
Statusopened/Clo
sed
Area
A-NCR
1 Gen. Concrete Cover X 13-Feb-12 13-Feb-12 13-Feb-12 CL Closed
2 Gen. Supervision of Work - Skilled Staff Attendance X 21-Feb-12 11-Mar-12 01-Apr-12 CL Closed
3 Gen. Supervision of Work X 22-Feb-12 29-Feb-12 18-Mar-12 CL Closed
3 Gen. Development length for columns X 29-Feb-12 13-Mar-12 CL Closed
5 Gen. Earthlings Incomplete Works X 07-Mar-12 26-Mar-12 01-Apr-12 CL Closed
6 Gen. Non Compliance to our site instruction X 15-Mar-12 26-Mar-12 01-Apr-12 CL Closed
7 Gen. Non Compliance to our site instruction X 18-Mar-12 OP Opened
8 Gen. Non Compliance for quality assurance to the cast placement X 30-Apr-12 03-May-12 12-May-12 Closed
B-Site Instructions
1 QC/CM Leakages - Water proofing works X 21-Feb-12 29-Feb-12 18-Mar-12 C Closed
1 QC,CM, TM, Q Assessemnt Bases for Mock-up Work X 06-Mar-12 O Opened
2 QC/CM Waterproofing work System X 22-Feb-12 29-Feb-12 18-Mar-12 C Closed
3 QC/CM Steel Chairs for Raft X 23-Feb-12 27-Feb-12 18-Mar-12 C Closed
4 QC/CM Engineer's Concern over Excavation Near Lift Pit X 27-Feb-12 11-Mar-12 13-Mar-12 C Closed
5 CM Curing work - Curing for Raft (Part A) X 29-Feb-12 11-Mar-12 13-Mar-12 C Closed
6 QC/CM Steel reinforcement Missed Connections X 03-Mar-12 28-May-12 28-Jun-12 C Closed
7 CM Excavation works - Engineer's Concern over Excavation near lift pit X 29-Feb-12 11-Mar-12 15-Mar-12 C Closed
8 PM Space for Car Parking X 13-Mar-12 01-Apr-12 15-Apr-12 C Closed
9 CM/QC Lack of Coordination Between site team and surveyor X 13-Mar-12 28-May-12 28-Jun-12 C Closed
11 QC Excavation Work at Block C X 15-Mar-12 28-May-12 28-Jun-12 C Closed
12 CM/QC Development Length of Pullout Bar of Staircase X 18-Mar-12 02-Apr-12 08-Apr-12 C Closed
13 TM/QC Undertaking Letter X 09-Apr-12 O Opened
14 CM/QC Site Observation - to complied by Contractor X 09-Apr-12 14-Apr-12 08-May-12 C Closed
15 QC Casting without Information X 12-Apr-12 14-Apr-12 15-Apr-12 C Closed
16 CM Authorities Approval X 16-Apr-12 02-May-12 05-May-12 C Closed
17 Quality of Works X 23-Apr-12 30-Apr-12 13-May-12 C Closed
18 Lack of Attendance X 25-Apr-12 30-Apr-12 28-Jun-12 C Closed
19 Etisalat Dead Junction Box X 30-Apr-12 O Opened
20 CM & QA/QC Quality of Works X 03-May-12 28-May-12 28-Jun-12 C Closed
21 CM & QA/QC Rusted Old Scaffolding Material Used for Slab X 03-May-12 28-May-12 28-Jun-12 C Closed
22 CM & QA/QC More Cracks Observed on "C2" at 1st Basement Slab X 09-May-12 19-May-12 C Closed
File : -Engineering Tracking Chart 1 of 1 Printed On :- 05/07/2012 at 08:37
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
11.0 FINANCIAL REPORT
11.1 SCHEDULE OF PAYMENTS
11.2 SUMMARY OF VO’S
11.3 SUMMARY OF CLIAMS
11.4 SUMMARY OF PROVISIONAL SUM
11.5 FORECASTING OF MONTHLY INVOICES (BASELINE)
Al Muraqqabat Mixed Use Development Monthly Progress Report
File: 05. Monthly Invoice Status Page 2 of 2 Printed On : 14/04/2012 at 10:28
Monthly Progress Report
Al Muraqqabat Mixed Use Development Prepared by (Sameh Kandil, Sr.Planning Engineer) Sponsor: Asset Management Group (WASL) To: (Mohammed Yousef) (Project Manager/ WASL) (Mohammed Viquaruddin) (Project Manager/ Bel Yoahah) (Ali Al Khateeb) (Resident Engineer/ Bel Yoahah)
12.0 PROGRESS PHOTOS
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Progress Photos for Block A
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:40
Elements Planned Pouring Date Actual Pouring Date Progress
Raft 11 March 2012 28 February 2012 100%
1st Basement Slab 12 April 2012 20 March 2012 100%
Ground Flor Slab 07 May 2012 18 April 2012 100%
1st Floor Slab 03 June 2012 14 May 2012 100%
2nd Floor Slab 01 July 2012 30 May 2012 100%
3rd Floor Slab 21 July 2012 18 June 2012 100%
4th Floor Slab 08 August 2012 In Progress 80%
Elements Planned Pouring Date Actual Pouring Date Progress
Columns at GF 17 May 2012 01 May 2012 100%
Core Walls at GF 14 May 2012 28 April 2012 100%
Columns at 1st Floor 13 June 2012 24 May 2012 100%
Core Walls at 1st Floor 10 June 2012 21 May 2012 100%
Columns at 2nd Floor 11 July 2012 05 June 2012 100%
Core Walls at 2nd Floor 08 July 2012 10 June 2012 100%
01. Third Floor Slab at Building A
ildi
Civil Work Architectural MEP (Incl. LPG)
Elevators External Facade
Façade Lighting
Façade Cleaning
Garbage & Linen Chute
52.98%
0% 0% 0% 0% 0% 0% 0%
65.39%
%Pld %Act
Building ‐ A
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:40
Asset Management Group (Wasl) Al Muraqqabat Mixed Use Development
Progress Photos for Block B
File : Progress Photos Page 1 of 1 Printed On : 05/07/2012 at 10:41
Elements Planned Pouring Date Actual Pouring Date Progress
Raft - B1 08 April 2012 30 March 2012 100%
Raft - B2 30 April 2012 12 April 2012 100%
1st Basement Slab - B1 26 April 2012 100%
1st Basement Slab - B2 06 May 2012 100%
Gound Floor Slab - B1 23 May 2012 100%
12 June 2012
10 July 2012Gound Floor Slab - B2 03 June 2012 100%
1st Floor Slab 05 August 2012 25 June 2012 100%
Elements Planned Pouring Date Actual Pouring Date Progress
Columns at 1st Bas. B1 26 June 2012 13 May 2012 100%
Core Walls at 1st Bas. B1 02 July 2012 10 May 2012 100%
Columns at 1st Bas. B2 26 June 2012 30 May 2012 100%
Core Walls at 1st Bas. B2 02 July 2012 20 May 2012 100%
Columns at Ground Floor 21 July 2012 20 June 2012 100%
Cores at Ground Floor 17 July 2012 10 June 2012 100%