Monthly Progress Update October 2017
Monthly Progress Update
Monthly Progress Update
October 2017
Monthly Progress Update 2
Cricket Valley Energy Center Highlights
Community Benefits Package
Generation Station Construction Progress
Transmission Line Construction Progress
Questions/Closing
Today’s Topics
Monthly Progress Update
• Fully-permitted combined cycle natural gas-fired energy center• Previously abandoned, industrial-zoned site• 193 acres off Route 22, Dover, New York• 79 acres of wetlands will remain undisturbed• No fracking at this facility—CVE is a consumer, not a producer, of natural gas
• Now under construction • Compact design reuses existing industrial footprint• Air cooling technology will reduce water use by 98%+• No process water will be discharged into Swamp River
• Scheduled for completion first quarter 2020
3
Cricket Valley Energy Center Overview
Monthly Progress Update
• Limited site access
• Required safety training
• Security procedures
• Safety procedures and compliance
4
Steps for Safety
Monthly Progress Update
• $3 million during construction phase
• Over $150 million through 2049
5
Contributing to Dover’s Tax Base
Monthly Progress Update 6
• Well and filtration system at Thomas J. Boyce Park
• New Salt Shed and Pole Barn
• J.H. Ketcham Memorial Park improvements
• Mini-excavator, 10-wheel truck, and other equipment
• Joint Project/School District Scholarship program
• Athletic field lighting and sound system at Dover High School
• Annual contribution to Dover Educational Enrichment Program
• Annual contribution to Board of Education Discretionary Fund
• Air Quality Monitoring Station
• Pleasant Valley Little League Ball Field
Advancing Community Benefits in Dover & Pleasant Valley
Total Benefit Commitment: $2,432,235
Monthly Progress Update 7
Construction ProgressCricket Valley Energy Center
Monthly Progress Update 8
• Established electrical service for construction power
• Site Grading Continues
• Blasting• Completed switchyard area• Continue with pond 1 area
• Continued installation of underground utilities
• Started ACC foundations
Construction Progress
Monthly Progress Update 9
• Started Route 22 road improvements
• Started laydown yard grading
• Erected fence around laydown yard
• Started construction fence around project site
• Started erection of craft tent at main site
• Foundation complete• Structural erection started
Construction Progress
Monthly Progress Update 10
• Continue civil excavation work
• Continue blasting activities
• Continue with Site Entrance Improvements
• Continue underground piping and electrical installation
• Continue earthwork at Laydown Yard
• Continue formwork and rebar installation for Heat Recovery Steam Generator foundation Unit 1.
4 Week Look Ahead
Monthly Progress Update 11
Photos
HRSG Modules - Harp stacking Heat Recovery Steam Generator Drum
Monthly Progress Update 12
Photos
Generator - Stator Generator Rotor Forging
Monthly Progress Update 13
Photos
Intermediate Pressure Steam Turbine Rotor Forging
Low Pressure Steam Turbine Rotor Forging
Monthly Progress Update 14
• 250 craft workers currently onsite
• 8 active 1st and 2nd subcontractors are onsite today.
• C.B. Strain & Sons– Poughkeepsie, NY
• E-J/Perreca Electric – Newburgh, NY
• Tectonic Engineering & Surveying –Newburgh, NY
• Dutchess County Constructors – Dover Plains, NY
• O&G Industries. – Torrington, CT
• Baystate Blasting, Inc. – Ludlow, MA
• Empire Layout – Somers, NY
• Bay Crane – Long Island City, NY
Jobs for 1,100
Monthly Progress Update 15
Construction ProgressTransmission Upgrade
Monthly Progress Update 16
Conducted Danger Tree Survey
Commenced ROW and access road clearing
Commenced tree clearing
Transmission Line Progress Update
ROW and tree clearing near PV Substation
Monthly Progress Update 17
• Continue Survey for future construction activities
• Continue improvements to access roads
• Continue tree clearing
ROW and tree clearing
4 Week Look Ahead – Transmission Upgrade
Monthly Progress Update 18
• TEC Survey – Beacon, New York ROW Survey and Laydown Yards
• Crux – Foundation Design
• Real Time Engineering – Structure Design
• Supreme – Initial tree clearing and access road improvements
Active Sub-Contractors – Transmission Upgrade
ROW and tree clearing
Monthly Progress Update 19
• More Information?• Scott Curry, Project Manager• [email protected]