MONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 Montlake Triangle Project-The view looking northeast showing completed work on Pacific Place and Triangle area PREPARED BY
102

MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Jun 10, 2018

Download

Documents

dinhthuan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

MONTHLY MAJOR PROJECTS REPORT FOR

AUGUST 2015

Montlake Triangle Project-The view looking northeast showing completed work on Pacific Place and Triangle area

PREPARED BY

Page 2: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

TABLE OF CONTENTS

Project Number

Project Title Page

Glossary of Acronyms i

Major Projects Executive Summary iii

203928 Animal Research and Care Facility – Kurt Jensen 1

203835 Bothell Activities and Recreation Center – Steve Tatge 9

203801 Burke-Gilman Trail Corridor – Victoria Morris 17

202039 Denny Hall Renovation – Randy Everett 21

203880 Fluke Hall Renovation – Kurt Jensen 26

203512 Housing-Maple and Terry Halls – Troy Stahlecker 30

204746 Life Sciences Building – Troy Stahlecker 37

204110 Medical Center Expansion Phase II–Montlake Tower – Ross Pouley 43

203593 Montlake Triangle Project – Andy Casillas 52

204878 NanoEngineering and Sciences Building (NESB) – Eric McArthur 58

203007 New Burke Museum – Curtis Bain 64

204350 North Campus Student Housing – Victoria Morris 68

203612 Police Department Facility – Ken Kubota 72

204701 Tacoma Urban Solutions Center – Jeannie Natta 78

204685 West Campus Utility Plant – Steve Harrison 82

Page 3: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Revised 1/9/14 i

GLOSSARY OF ACRONYMS FROM MONTHLY REPORT

AC Architectural Commission A/E Architect/engineer AHU Air handling unit ASF Assignable square feet ASI Architect’s supplemental

information BEST Budget Evaluation Study Team BIM Building information modeling CAD Computer-aided design CD Construction document CDF Controlled density fill CMU Concrete masonry unit CO Certificate of Occupancy COP Change order proposal COR Change order request CPM Critical path method CPO Capital Projects Office CUP Central Utility Plant CSSCR Center for Social Science and

Research CUCAC City-University Community

Advisory Committee CY Cubic yard (also CUYD) DAHP WA State Department of

Archeology and Historic Preservation

D-B Design-build DBOM Design/build/operate/maintain DD Design development DPD Seattle Department of Planning

and Development DRB Disputes Resolution Board EH&S Environmental Health & Safety EIS Environmental Impact Statement ESCO Energy Services Company FRP Fiberglass reinforced polymer FCUFS Faculty Council on University

Facilities and Services FF&E Furnishings, fixtures and

equipment GC/CM General contractor/construction

manager GCC Guaranteed construction cost

GSF Gross square feet HFS Housing and Food Services HVAC Heating, ventilation, and air

conditioning JOC Job order contracting ICA Intercollegiate Athletics LEED Leadership in Energy and

Environmental Design MACC Maximum allowable construction

cost MEP Mechanical, electrical and

plumbing MHSC Magnuson Health Sciences

Center MOA Memorandum of Agreement MOC Management Oversight

Committee MNS Mass notification system MTP Montlake Triangle Project MUP Master use permit NIH National Institutes of Health NTP Notice to proceed OFM Office of Financial Management

(Olympia) OPB Office of Planning and Budgeting OUA Office of the University Architect PA Project Agreement PRB Project Review Board PT Post-tensioned PUD Planned Unit Development RFI Request for Information RFP Request for Proposal RFFP Request for Final Proposal RFQ Request for Qualifications SEIS Supplemental Environmental

Impact Statement SEPA State Environmental Policy Act SD Schematic design SDOT Seattle Department of

Transportation SFD Seattle Fire Department TCC Total contract cost

Page 4: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

ii

TCO Temporary Certificate of Occupancy

TI Tenant improvement TRIR Total recordable incident rate ULAC University Landscape Advisory

Committee UWMC UW Medical Center VRF Variable refrigerant flow WSDOT Washington State Department of

Transportation UWIT UW Information Technology UWPD UW Police Department UWTS UW Transportation Services

Page 5: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

iii

MAJOR PROJECTS EXECUTIVE SUMMARY August 2015

• Safety – The total recordable incident rates (TRIR) for calendar years 2013 and 2014

were .98 and 2.74 respectively. The TRIR to date for 2015 is 1.92 with 1,040,000 hours worked. CPO and its contractors have worked 123,000 hours without a lost time incident since July 27, 2015.

• Animal Research and Care Facility – The shoring and mass excavation work phase continues. The drilling and pile installation work is complete. The tie back lagging and excavation activities continue on all walls of the adjoining buildings. The tower crane and concrete placing boom foundation construction is underway. The dewatering well point installation has started. The Building Information Modeling (BIM) coordination efforts continue to support the ARCF prefabricated building components, detailing, and the procurement activities. The mock up of the prefabricated MEP Trade Racks has been completed for team review.

• Bothell Activities and Recreation Center – The mechanical, electrical, and plumbing trim installations are in the process of being finalized. Commissioning continued through the month of August. Close out activities are in progress.

• Burke-Gilman Trail Corridor Phase I Campus Reach – An award letter was issued to the responsive bidder with the lowest amount. The coordination with Puget Sound Energy (PSE) regarding a 12” gas line along the Lewis Lane Bridge has continued and an agreement to provide an updated easement is in process. The outreach regarding trail closure and detours was initiated.

• Denny Hall Renovation – THA prepared three options for the wall surrounding the site mounted Condenser Units. UW selected the CMU wall option which matches the existing CMU enclosure wall surrounding the adjacent trash/recycling bins. The project team continued to look for cost savings to align the construction cost with the project budget, including re-evaluation of exterior guardrails and handrails. THA continued working on completion of the remaining construction documents for Bid Package D. BNB advertised and received bids for GWB and Acoustical Assemblies and submitted their contract Amendment #2 for approval.

• Fluke Hall Renovation – The design team and the GC/CM have continued their work to complete the construction documents (CDs) for the project. The 90% CD review meeting was held and comments are being addressed in the final contract documents. The bidding of long lead mechanical equipment is complete and CPO is in the process of issuing the initial construction contract that will allow for equipment orders to be made by the mechanical subcontractor. Hoffman completed the prequalification process for electrical subcontractors.

Page 6: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

iv

• Housing-Maple and Terry Halls – The project reached substantial completion of

phase two on 8/7/15. The project has moved into closeout and the team is receiving the closeout submittals for review. The buildings should be fully occupied by the end of September.

• Life Sciences Building – The Design Development phase of the project progressed as planned. The LEAN pull planning workshop occurred and the project schedule and key project milestones were updated and confirmed. Schedules for early bid packages and permitting were refined. The design workshop and program meetings were aligned with the project budget and presented to the University stakeholders. Preliminary cost estimates from the Mechanical Contractor / Construction Manager (MC/CM) and Electrical Contractor / Construction Manager (EC/CM) were reconciled with AECOM and Skanska budgets. The reoccurring weekly project team meetings are focused on advancing the design development elements, program and technical mechanical / electrical infrastructure details.

• Medical Center Expansion Phase II – Design Package 04 - Testing and commissioning of the new emergency generator, chillers, cooling tower and air handling units for the Montlake Tower continued in August. The air handling units are moving air (in 2SA) and the filter systems have passed infection control testing. In 7EE, electrical termination/trim work continued as did flooring, casework and finish work. A pathway for the RF shielded rooms was approved, and a work plan submitted.

Montlake Tower work - 2SA - the 7 Operating Rooms and associated support areas were substantially completed, and turned over to the UWMC on 7/28/15 for Transplant Cleaning. The area received a certificate of occupancy on 8/26/15.

5SA, 6SA, 7SA; flooring installation work continued. The flooring contactor added additional workers, and that is helping, but the flooring is on the critical path, and the impacting the schedule. Patient door installation is underway, lighting fixture installation, electrical termination/trim work continued, painting, casework, locker installation, ceiling tile installation, bathroom ceramic tile and bathroom fixture installation continued. The terrazzo work on 7SA is nearing completion.

Design Package 07 - The amendment to add DP07 to the project has been executed and the submittal process is underway. Make ready work for DP07 will be performed by DP04 subcontractors until the DP07 subcontractors mobilize on site. The first element of work to move the Pharmacy on 2SA and renovate the evacuated space for the temporary OR Control Room is underway.

• Montlake Triangle Project – Punch list activity continued with a majority of punch list items being addressed. There is a potential for some late added work by SDOT on NE Pacific Street for road repair and along Montlake Blvd for game day bus loading activities. Discussions continue with SDOT.

Page 7: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

v

• NanoEngineering and Sciences Building (NESB) – The remaining bid packages for the interior tenant improvements were issued at the end of August. This work includes all the finishes, doors, walls and ceilings required to compete the project. The excavation has been completed down to the sub basement. All exterior shoring walls have been waterproofed. Structural basement walls were formed, reinforced and spray-shotcrete cast. Column and interior shear walls are in the process of being formed and placed. Work continues to be scheduled to accommodate research taking place in the adjoining Molecular Engineering & Sciences Building with the contractor bringing forces in at 4am and suspending operations by 3pm.

• New Burke Museum Renovation – The 50% construction drawings were published by the design consultants. Skanska commenced a constructability review and began estimating structural, mechanical and electrical scopes of work. Estimating of the remaining project components will be initiated when the 50% construction specifications are published in early September. The project team evaluated procurement options for early subcontractor involvement. Due to the uncertainty of the project funding, Skanska recommended deferring early bidding for the project until the funding was secured. The project team conducted pull planning sessions to model the completion of design, procurement, permitting, and contracting assuming the remaining funding for the project is obtained in early spring of 2016. Skanska, Sparling and WSP continued to resolve key scope details regarding the delivery of campus utilities to the new building and the required modification to the tunnel serving the existing museum. The City of Seattle completed the flow test of the fire hydrants; MKA will review the results and advise on any required changes to the scope of work. After informal review with UWAC, the university decided not to modify the southwest corner of the museum for a major signage component. The design team will continue to evaluate signage and museum identity opportunities along 15th Avenue and the new museum’s public entrance.

• North Campus Student Housing – The schematic design phase was completed with SD review comments forwarded to the design team. The proposals for the mechanical and electrical contractor construction managers were reviewed

• UW Police Department Facility – Construction continues with placement of the roof deck concrete PT slab. Mechanical ducts and plumbing are being installed on the lower basement level. The motor court site wall footings are installed. Site utilities for water, sewer, and storm were installed.

• Tacoma Urban Solutions Center – The design team reached a milestone of 100% design development for the core and shell and 30% schematic design for the interiors. In mid August the project team reviewed the design for quality control. Mortenson developed an estimate of the complete project based on these design documents. Early reviews of the estimate show the project to be on target. The faculty focus groups reviewed the schematic design of the interiors and provided

Page 8: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

vi

comments. UW T Information Technology and Campus Planning reviewed the audio visual needs for classrooms. The project team also met with UW Tacoma Facilities to review specific building operation needs. Access to the Old Spaghetti Factory allowed for further investigation work, including regulated building materials, surveying the floor elevations and researching the best location for the building entrance.

• West Campus Utility Plant – Installation of new chilled-water distribution system piping began and a substantial portion of the work that can be completed before removing the existing pipelines is done. City comments on the building permit were received and responded to. Detailed design was ongoing in support of trade work packages, the plant electrical design and permit application, and the sequence-of-operations including controls and instrumentation. A draft commissioning plan was published and is under UW review. Procurement efforts and construction-logistics planning were ongoing and continue.

Page 9: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

1

Animal Research and Care Facility Project #203928

August 2015 Project Manager: Kurt Jensen

Construction Manager: Jeff Angeley

PROJECT DESCRIPTION In 2010, the University of Washington identified the need to develop future facilities capable of supporting the UW’s commitment to outstanding research, education and animal care. Also identified was the need to increase the animal census at the UW and to implement a centralized operating model for animal care and procedures. As a result of the UW’s Animal Care Facilities Master Plan Feasibility Study, it was recommended the UW construct a new Animal Research and Care Facility (ARCF). This project is intended to provide a capacity solution for UW animal research for the next ten years.

The feasibility study identified a site in the Portage Bay Vista, just east of the William H. Foege Building, for a new, state-of-the-art ARCF. The concept plan for this facility is a two-story, below-grade building, connecting to both the Foege building and Hitchcock Hall at the first level below grade. The building will provide flexible housing

Page 10: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

2

for large and small animals (principally rodents) and non-human primates. The study also identified a preliminary program of space types, including laboratories, procedure rooms, imaging facilities; cage and equipment wash facilities, storage, and other support spaces. The planned size of the ARCF is 83,000 gross square feet (GSF). The project architect is a partnership of Zimmer-Gunsul-Frasca (ZGF) of Seattle, Washington and Flad Architect of San Francisco, California. The General Contractor/Construction Manager (GC/CM) is Skanska USA Building, located in Seattle WA. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The construction schedule has recovered 5 of the previously delayed fifteen (15) days (due to the site ground water and the soil condition impacts to the installation of the shoring and underpinning piles and the removal of a previously undiscovered underground storage tank and associated contaminated soils). The team continues to work to minimize impacts associated with the additional work activities by utilizing overtime allowances in the shoring and excavation sub-contracts and by looking for added opportunities to re-sequence the work. Work Accomplished This Period The shoring and mass excavation work phase continues. The north and south perimeter dewatering wells have been drilled, developed and are in service. The drilling and pile installation work is complete. The tie back lagging and excavation activities continue on all walls of the adjoining buildings. The tower crane and concrete placing boom foundation construction is underway. The dewatering well

Page 11: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

3

point installation has started. The Building Information Modeling (BIM) coordination efforts continue to support the ARCF prefabricated building components, detailing, and the procurement activities. The mock up of the prefabricated MEP Trade Racks has been completed for team review.

The project team has been reviewing and responding to the bid and procurement activities and working with the management team on budget control strategies.

Plans for Next 30 Days The tie-back, lagging and mass excavation work will complete. After the remaining soil is exported the large conveyor system will be demobilized. The contaminated soil removal will be completed. The dewatering design modification and efforts are responding to actual encountered site conditions. The well points will be drilled and installed under Foege and Hitchcock. The planning for both occupant and contractor operations and logistics at Foege, Hitchcock, J, K, and I wing loading dock will continue.

PROJECT BUDGET & COST Cost Overview There is no change to the project budget. However, the ARCF GC/CM’s scope of work has been modified to construct a new section of utility tunnel in order to support the distribution of utilities from the new West Central Utility Plant (West CUP). This work also includes replacing the existing PCB-contaminated transformers in Hitchcock Hall. This added work can be most cost-effectively delivered by the ARCF project, and additional funding from other UW sources will be provided to cover the cost. Several of the latest rounds of bid packages have come in over budget and the project team is looking at options to bring the project back on budget.

Page 12: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

4

CHANGES IN SCOPE The ARCF GC/CM is now under contract to construct a new section of utility tunnel to provide a new pathway from the West CUP to the ARCF project and other buildings in the Magnuson Health Sciences Center. It is anticipated that the ARCF GC/CM will also install connecting utilities in the new tunnel section. The GC/CM will also replace existing PCB contaminated transformers in Hitchcock Hall. It has been determined that both of these scopes of work can be best coordinated with the ARCF site logistics and performed most cost effectively by the ARCF GC/CM. BUYOUT STATUS

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$71,579,165 $20,590,783 $92,170,748 78%

Variance to Date (+ over / – under)

$14,664,748

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 80 50

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 13,503 69,028

Total Recordable Incident Rate 0 0

Page 13: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

5

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 33 $2,127,076

Change Order Proposals Pending 64 4,165,357

Change Order Requests Pending 6 $577,464

PROJECT COMMUNICATIONS Number Average Turnaround

Requests for Information to Date 366 8 days

Submittals to Date (not including LEED) 204 11.5days OPPORTUNITIES & CHALLENGES The site has subsurface water runoff from upper campus, and much of the finished building will be below the water table. This will require special consideration by the design team relating to the building envelope and waterproofing systems, as well as additional efforts by the contractor during construction. The sloping site provides opportunities to bring natural light into the facility at strategic locations to improve the work environment for the staff. The below-grade construction will connect to the Foege Building, the Foege loading dock, and potentially Hitchcock Hall. The project team will need to address the potential impact on these existing buildings and associated operations during construction. The air intakes location and building exhaust is a challenge with a below-grade building. The building design must respect long-term plans for expanding the underground facility and for a future above-grade building adjacent to Hitchcock Hall. The facility design will need to be flexible to adapt to future trends in animal research and to changing regulatory requirements. It will be challenging to find the right balance between optimum flexibility and project budget constraints. This project also presents opportunities to enhance and enliven the Portage Bay Vista open space that will be restored following the building construction and to improve the connection across NE Pacific Street to the upper campus. The project is facing budget challenges due to the active Seattle construction market and bidding climate. Skanska and the project team are actively monitoring the situation and working with subcontractors to encourage broad subcontractor participation and competitive bidding.

Page 14: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 15: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

6

The pile drilling is complete and the tie-back and lagging operations continue at

building perimeter.

The construction of the tower crane and concrete placing boom foundations.

Page 16: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

7

The mechanical piping installation commenced in the Hitchcock tunnel system.

The ARCF design and construction team review the prefabricated MEP Trade Racks

mock up offsite.

Page 17: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Animal Research and Care Facility, #203928

8

The demobilization of the drill rig

Page 18: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

9

Bothell Activities and Recreation Center Project #203835

August 2015 Project Manager: Eric McArthur

Construction Manager: Jeff Johnson

Rendering of approach to the building from across Campus Way PROJECT DESCRIPTION This project will construct a new Student Activities Center (SAC) at UW Bothell (UWB) to provide spaces for food service, student leadership offices and clubs, fitness and recreation, casual study, and, potentially an events center. The facility will serve both UWB and Cascadia College. UWB has a growing enrollment of over 4,200 students (3,800 FTE) and has rapidly evolved into a four-year institution after initially accepting only upperclassmen and graduate students. The campus has opened its first student housing facility. The newly leased and renovated spaces in both the Beardslee Building and Husky Hall have further expanded the campus footprint. Given the enrollment growth and expanded facilities, the student population is currently underserved by traditional campus amenities, such as a student union building and fitness facilities. The proposed building is to be located immediately south of (and connected) to the existing North Creek Events Center (NCEC), and will be approximately 35,000 gross square feet (gsf).

Page 19: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

10

LMN Architects of Seattle is the project architect. The General Contractor/Construction Manager (GC/CM) is Skanska USA Building, Inc. of Seattle. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance None at this time. Work Accomplished This Period The mechanical, electrical, and plumbing trim installations were in the process of being finalized. The commissioning continued through the month of July. The final inspections for the various trades were completed and the City of Bothell issued a certificate of occupancy. Plans for the Next 30 Days The punch list work and commissioning will be finalized, and move-in activities will be completed.

Page 20: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

11

PROJECT BUDGET AND COST Cost Overview The project was slightly over budget prior to buying out the work, and it was hoped that favorable bid results would make up for the estimated overage. Unfortunately, the buyout results added to the overage, and UWB and Cascadia College (CC) students and administration were advised that either additional funds would be required to deliver their intended scope, or the scope would need to be reduced. Further, the bid scope included elements added to the construction project in lieu of being provided separately, and the project budget needed to be adjusted to reflect those costs. The administration, UWB and CC students agreed to fund up to the revised forecast. CPO has focused the team on managing construction to minimize the use of the construction contingency. Now that construction is nearly complete, contingency use has been well under forecast and the additional funds required will be less than what was committed to while still providing the fully desired scope.

Page 21: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

12

CHANGES IN SCOPE The scope of the project has been maintained throughout construction. No changes in the scope have occurred nor are any forecasted in the final two months of construction. BUYOUT STATUS Buyout is complete.

BUYOUT STATISTICS Awarded Remainin

g Total

% Complet

e Dollar Value of Subcontracts $12,913,770 0 $12,913,770 100% Variance to Date (+ over / – under)

+$808,538

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 35 40

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 7,550 50,873

Total Recordable Incident Rate 0.0 0.0

CONSTRUCTION ADMINISTRATION

Change Documents Number Value Change Orders Approved to Date 22 $160,273.00 Change Order Proposals Pending 31 $132,627.00 Change Order Requests Pending 0

Project Communications Number Average Turnaround Requests for information to date 186 9 days Submittals to Date 247 11 days

Page 22: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

13

OPPORTUNITIES AND CHALLENGES The challenges for this project include the compact site size, sloping site, varied and changing program requirements, and budget limitations. Having two institutions participate in the design process is also a unique challenge. Also, with the construction packages bid out and the construction ground work completed, the project is past the point of greatest risk. The team understands that the greatest risk for impacting the budget negatively will come from the owner scope requests. As such, there is an agreement with the team to actively manage this.

Page 23: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 24: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

14

ARC - Front Entry

Main Level - Shared Work Space

Page 25: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

15

Main Level - Student Alcove

Lower Level - Cardio Weight Area

Page 26: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Bothell SAC, #203835

16

Upper Level – Student Commons & Events Area

Page 27: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

17

Burke-Gilman Trail Corridor Phase I Campus Reach Project #203801

August 2015 Project Manager: Victoria Morris

Construction Manager: Jeff Johnson

PROJECT DESCRIPTION The Burke-Gilman Trail Corridor (BGTC), constructed in 1978, is a rails-to-trails bicycle and pedestrian thoroughfare that runs through the Seattle Campus west of Montlake Boulevard and north of NE Pacific Street. The trail is widely used by bicycle commuters coming to the University and passing through campus, and it serves as the backbone of a regional bicycling and pedestrian network in the northern part of Seattle. These multiple uses and cross-traffic between the campus community and the BGTC create conflicts and safety issues that need to be addressed for effective pedestrian and bicycle movement on and around the trail. The number of users on the trail has far exceeded initial projections. This project will develop design and construction documents for Phase I, Campus Reach, which will improve the trail from a point just west of the Rainier Vista to the east side of the 15th Avenue NE intersection of the University-owned portion of the BGTC. The construction of Phase I is also included as part of this project scope.

Page 28: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Burke-Gilman Trail Corridor, #203801

18

The project prime is KPFF Consulting Engineers (KPFF) of Seattle, Washington and PLACE Studio, LLC is the landscape design firm from Portland, Oregon. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance This project is 2 months behind its current schedule. The completion is currently anticipated in May 2016. Work Accomplished This Period The low bidder was determined to be non-responsive for not meeting the required Disadvantage Business Enterprise requirement. An award letter was issued to the second low bidder, C.A. Carey, as the responsive bidder. The coordination with Puget Sound Energy (PSE) regarding a 12” gas line along the Lewis Lane Bridge continues and an agreement to provide an updated easement is in process. The construction communication outreach regarding trail closure and detours was updated.

Page 29: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Burke-Gilman Trail Corridor, #203801

19

Plans for Next 30 Days The Issuance of the Notice to Proceed (NTP) for construction is planned. The amended easement agreement with PSE on the gas line will be finalized. The construction communication outreach will continue and detour routes will be implemented. PROJECT BUDGET & COST Cost Overview The original project budget for Phase I design and construction was estimated at $4.73 million, as part of the larger previous project that included the design of phase 2. The current cost forecast is $6.2 million, which is approximately 30 percent over budget. The elements of the increased project cost include; higher than anticipated costs for the base scope of work, redesign costs, bicycle shelter and enclosures, ADA upgrades, and escalation. The funding for this project is provided by UW Transportation Services (UWTS). With $3 million in federal grant funding, UW Transportation Services has confirmed that additional funding will be provided to cover the higher estimated project cost. The current funding is $6.2 million.

CHANGES IN SCOPE None this period.

Page 30: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Burke-Gilman Trail Corridor, #203801

20

BUYOUT STATUS The Phase 1 (Campus Reach) bids were received in July. The contract is being reviewed and processed by the low responsive bidder. SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 0

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 0

Total Recordable Incident Rate 0 0 CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 0 $0

Change Order Proposals Pending 0 $0

Change Order Requests Pending 0 $0

PROJECT COMMUNICATIONS Number Average

Turnaround Requests for Information to Date 0 0 days Submittals to Date (not including LEED) 0 0 days

OPPORTUNITIES & CHALLENGES Completing this work will provide a tremendous asset to the University with improved safety and mobility along the trail. The delay in bidding and the late bidding in the season will shift more work into the wet season and increase the construction duration. It is anticipated that the wet weather will lower productivity and the weather may delay the work further, increasing costs.

Page 31: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

21

Denny Hall Renovation Project #202039

August 2015 Project Manager: Randy Everett

PROJECT DESCRIPTION Constructed in 1895, Denny Hall is the oldest building on the Seattle campus and is eligible to be listed in the Washington State Heritage Register. Denny Hall was prioritized as part of the University’s “Restore the Core” renovation program to restore and modernize buildings in greatest need of renovation. The last major structural and interior renovation of this 100-year-old building occurred in 1956-57. The slate roof was replaced and the cupola was restored in 2005. The 86,414 gross square foot building currently houses offices and programs for the College of Arts and Sciences, including the Departments of Anthropology, Classics, Germanics, and Near Eastern Languages & Civilization, as well as the College’s Language Learning Center. Denny also houses 12,000 square feet of general assignment classrooms totaling 765 seats. This project will upgrade all major building systems, correct seismic deficiencies, improve accessibility, and abate hazardous materials. In accordance with the

Page 32: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Denny Hall Renovation, #202039

22

requirements of the State of Washington, the project will be designed to achieve Leadership in Energy and Environmental Design (LEED) Silver certification. Hacker (previously known as THA) of Portland, Oregon, is the project architect. SiteWorkshop is the landscape architect, and BNBuilders (BNB) is the General Contractor/Construction Manager (GC/CM). Both are located in Seattle, Washington. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project remains on schedule for occupancy at the start of Autumn Quarter 2016 based on an accelerated construction schedule. Work Accomplished This Period Hacker prepared three options for the wall surrounding the site mounted condenser units. The UW selected the CMU wall option, which matches the existing CMU enclosure wall surrounding the adjacent trash/recycling bins. The project team continued to look for cost savings to align the construction cost with the project budget, including re-evaluation of exterior guardrails and handrails. Hacker continued working on completion of the remaining construction documents for Bid Package D. BNB advertised and received bids for GWB and Acoustical Assemblies and submitted its contract Amendment #2 for approval.

Page 33: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Denny Hall Renovation, #202039

23

Plans for Next 30 Days Hacker will continue to complete the construction documents for all remaining bid packages. BNB will advertise the remaining bid packages, including Architectural Casework, Doors, Frames & Hardware, Aluminum Systems & Glazing, Floorcoverings, Painting & Coatings, Miscellaneous Specialties, Window Treatments, Lab Casework & Equipment, and Irrigation/Landscape. BNB will submit the final documentation in support of its contract Amendment #2. Construction Accomplishments This Period The asbestos abatement continues. The construction of the new shear walls is progressing well with some walls proceeding up the building, with others in the foundations phase. BNB started the waterproofing of the building foundation. Because of the rough stone foundation a shotcrete layer was applied over the stone and a bentonite waterproofing system was the outer layer. PROJECT BUDGET & COST Cost Overview The project is on budget with the bidding phase going well. The project is fully funded for $52,892,000.

CHANGES IN SCOPE None this month.

Page 34: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Denny Hall Renovation, #202039

24

BUYOUT STATUS The structures and early work packages were estimated and bid higher than the design development estimate. The design development forecast was less than the construction budget and there was some shifting of costs between packages. While the initial bids were higher than the design development estimate, latter bids were under budget. The current forecast for the buyout is under the construction budget.

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$20,692,268 $8,483,600 $29,175,868 71%

Variance to Date (+ over / – under)

$487,533

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 64 43

Lost Time Incidents 0 0

Recordable Incidents 0 1

Total Hours Worked 10,794 22,450

Total Recordable Incident Rate 0 8.9

CONSTRUCTION CONTRACT ADMINISTRATION

OPPORTUNITIES & CHALLENGES With the support of Hacker and the UW, BNB is up to the challenge of completing the renovation of this 120 year old building by the start of Autumn Quarter 2016. The new interior will reflect the timeless beauty of the exterior, but will update the infrastructure, meeting the needs of research and teaching for years to come.

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 0 0

Change Order Proposals Pending 4 $44,500

Change Order Requests Pending 1 $25,000

PROJECT COMMUNICATIONS

Number Average

Turnaround

Requests for Information to Date 30 5 days Submittals to Date (not including LEED)

132

8 days

Page 35: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 36: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Denny Hall Renovation, #202039

25

Typical shotcrete install for waterproofing

The concrete placement for the shear wall installation

Page 37: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

26

Fluke Hall Renovation Project #203880

August 2015 Project Manager: Kurt Jensen

Construction Manager: Jim Vincent

PROJECT DESCRIPTION This project will renovate the Washington Nano Fabrication Facility (WNF) located on the first floor of Fluke Hall. The scope of work includes roof replacement and refurbishment of other existing building infrastructure to allow the building to serve as a long-term core UW research facility supporting academic research, industry partnership, and a commercialization incubator. The renovations of the existing second floor laboratories have been removed from the original scope of work in order to achieve project budgetary goals. The portions of this building will remain occupied during construction, requiring the work to be performed in multiple phases. The project architect is HDR Architecture of Seattle. The new General Contractor/Construction Manager (GC/CM) is Hoffman Construction also of Seattle. Holiday Parks is the new MC/CM (Mechanical Contractor/Construction Manager) on the project.

Page 38: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Fluke Hall, #203880

27

PROJECT STATUS SUMMARY Preliminary Schedule Overview

Schedule Variance The designer and contractor have developed a new schedule for completing the design and construction of the project. The revised milestones are shown above. Work Accomplished This Period The design team and the GC/CM have continued their work to complete the construction documents (CDs) for the project. The 90% CD review meeting was held and comments are being addressed in the final contract documents. The bidding of long lead mechanical equipment is complete and CPO is in the process of issuing the initial construction contract that will allow for equipment orders to be made by the mechanical subcontractor. Hoffman completed the prequalification process for electrical subcontractors. Plans for Next 30 Days HDR will complete the construction documents for the project. The GC/CM will finalize their MACC estimate and begin preparing bid packages for the remaining subcontract work. The CPO construction manager and GC/CM will finalize plans for site logistics and begin preparations for mobilizing construction trailers on site.

Page 39: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Fluke Hall, #203880

28

PROJECT BUDGET & COST Cost Overview The Board of Regents (BOR) approved a project budget of $28.5 million in May 2012 with the understanding that this preliminary budget may change following completion of the schematic design phase. The administration committed to returning to the BOR for final budget approval prior to the start of construction. The predesign study indicated all of the planned scope may not be achievable within the available funding, which was later confirmed. The cost reduction alternatives have been developed through value engineering (VE). The project team agreed to accept the majority of the VE recommendations, resulting in a total project cost forecast and new target budget of $31.5 million. At the end of the design development (DD) phase, the cost estimate, along with code interpretations from the City, showed that the anticipated VE cost savings could not be fully realized. In addition, the result of the field investigation by the MC/CM and the Electrical Contractor/Construction Manager (EC/CM) subcontractors discovered additional information that has also added to the estimated construction cost. The estimated total project cost at the end of the DD phase was approximately $38 million. The project scope has now been significantly reduced and the new cost estimate and budget forecast is $37M.

Page 40: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Fluke Hall, #203880

29

CHANGES IN SCOPE No changes in the scope this period. BUYOUT STATUS, SAFETY STATISTICS, AND CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES This project presents an opportunity to improve the quality and reliability of the mechanical and electrical systems supporting the cleanroom and laboratory uses as well as reduce the ongoing facility operations and maintenance costs. The use of Building Information Modeling (BIM) and the collaborative GC/CM process during design and construction enhance the opportunity for the design team to maximize the project scope, quality, and schedule to avoid changes during construction. The challenges include successfully implementing the scope and cost reduction measures required to bring the project cost within budget. The requirement for the existing occupants to remain in the building during construction is a significant challenge for the design team and the contractors. Developing a phasing plan and strategy to allow for continued operation of the labs and cleanrooms during the renovation is complicating the design and puts added pressure on the project budget and schedule. The continuing schedule delays are increasing the risk that uncertain market conditions and escalating construction costs will further impact the project budget.

Page 41: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

30

Housing–Maple and Terry Halls Project #203512

August 2015 Project Manager: Will Sigman

Construction Manager: Steve Folk

Perspective of Maple Hall, looking toward northwest from Lincoln Ave PROJECT DESCRIPTION The project scope includes demolition of the existing Center Building and Terry Hall and the construction of two new residential buildings named Maple and Terry Halls. The new seven-story buildings will include five stories of housing consisting of two-bedroom suites with private bathrooms. The lower two floors of each building will be occupied by Housing and Food Services (HFS) administrative offices, common space for students, and some additional two-bedroom suites. A below-grade parking garage connecting to the Lander Hall garage and loading dock will extend below Maple and Terry Halls. The new facility will total 390,000 gross square feet and provide 1,090 beds. The sustainability goal is to achieve Leadership in Energy and Environmental Design (LEED) silver certification. Originally, Terry Hall and the 1101 Café/Center building located on NE Campus Parkway, immediately west of Lander Hall were planned as a renovation. The buildings were constructed in 1952 and needed substantial infrastructure replacement and improvements. The costly seismic and infrastructure upgrades, as well as the current high-rise code requirements, demonstrated that new construction would be a more cost-effective option. This change also presents an opportunity to

Page 42: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Maple-Terry Halls, #203512

31

better integrate these facilities into the vision of the west of 15th Avenue NE master plan and to significantly improve the student life experience in the residence halls. Mithun is the project and landscape architects. W.G. Clark is the General Contractor/Construction Manager (GC/CM). Both firms are located in Seattle, Washington. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project is on track for occupancy at the start of Autumn Quarter. There have been several construction delays. W.G. Clarke has done very well to manage and mitigate the impacts. Phase 1 (HFS offices in Terry Hall) substantial completion was achieved June 5, 2015 and Phase 2, substantial completion was completed on August 7, 2015. Housing & Food Services occupied the Phase 1 area in June. Work Accomplished This Period The testing and inspections were completed to support achieving substantial completion on August 7, 2015. Plans for Next 30 Days The project has moved into the closeout phase; we are receiving the closeout submittals for review. The punch list, commissioning, and final testing will be on going. The buildings should be fully occupied by the end of September.

Page 43: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Maple-Terry Halls, #203512

32

PROJECT BUDGET AND COST Cost Overview The forecast cost to complete is $13.6M below the budget a result of an excellent team effort to manage the project and costs. The budget includes HFS costs for furnishings, fixtures, and equipment. The project funding is from the University’s Internal Lending Program to be repaid with HFS revenues.

CHANGES IN SCOPE None this period BUYOUT STATUS The buyout was completed 0.5% below the construction budget.

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$70,573,535 0 $70,573,535 100%

Variance to Date (+ over / – under)

($3,455.725)

Page 44: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Maple-Terry Halls, #203512

33

SAFETY STATISTICS WG Clark and its team achieved a TRIR of less than 1.0. This is a tremendous achievement and reflects the commitment of the entire team to creating a safe work environment.

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 75 172

Lost Time Incidents 0 1

Recordable Incidents 0 3

Total Hours Worked 3,801 520,821

Total Recordable Incident Rate 0 0.81

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 360 $6,036,159 Change Order Proposals Pending 5 $30,000 Change Order Requests Pending 0

$0

PROJECT COMMUNICATIONS Number Average

Turnaround Requests for Information to Date 1,247 5 days Submittals to Date (not including

782 10 days

OPPORTUNITIES AND CHALLENGES The project is in closeout. Our goal is to receive the final redline drawings by the end of October and begin the final record drawings.

Page 45: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 46: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Maple-Terry Halls, #203512

34

Maple Hall Courtyard with “Spinners”

Maple Hall great room

Page 47: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Maple-Terry Halls, #203512

35

Maple Hall Level 1 Game Pod Entry

Maple Hall Level 8 Lounge

Page 48: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Maple-Terry Halls, #203512

36

Terry Hall Roof Terrace

Page 49: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

37

Life Sciences Building Project #204746

August 2015 Project Manager: Troy Stahlecker

PROJECT DESCRIPTION The Life Sciences Building (LSB) project will provide new laboratory and office space to allow the Department of Biology to increase its faculty size to meet major increases in undergraduate student demand. In addition, a new greenhouse of approximately 20,000 gross square feet (GSF) will be constructed as part of the LSB project. The project site is a combination of existing greenhouses and landscaped area located east of Kincaid Hall, and the area bounded by NE East Stevens Way to the north, the landscaped area just north of the MHSC T-Wing overpass, and the Burke Gilman Trail to the south. The existing greenhouse and associated buildings will be demolished and the LSB of approximately 169,000 GSF will be constructed on the site. The LSB will have five floors above grade with a mechanical penthouse and two below-grade floors to support 30 to 40 principal investigators with laboratory space, associated offices and conference spaces, three authentic undergraduate research/teaching laboratories, growth chambers, and animal care facilities. The LSB, together with a new, larger greenhouse, which will replace the current 65-year old greenhouse, offers the Department of Biology and its faculty the opportunity to take its truly integrated approach to Biology and its highly collaborative culture to a new level. The LSB allows Biology the opportunity to hire 10-12 new faculty members and strengthen key areas of interdisciplinary research by bringing together faculty,

Page 50: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Life Sciences Building, #204746

38

postdocs, graduate students, and undergraduates with overlapping research interests. Perkins + Will is the project architect, Gustafson Guthrie Nichol (GGN) is the Landscape Architects, and Skanska USA is the General Contractor / Construction Manager (GC/CM). All firms are located in Seattle, Washington. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project is on schedule. Work Accomplished This Period The Design Development (DD) phase of the project progressed as planned. The LEAN pull-planning workshop occurred and the project schedule and key project milestones were updated and confirmed. The schedules for early bid packages and permitting were refined. The design workshop and program meetings were aligned with the project budget and presented to the University stakeholders. The preliminary cost estimates from the Mechanical Contractor / Construction Manager (MC/CM) and Electrical Contractor / Construction Manager (EC/CM) were reconciled and AECOM and Skanska budgets. The reoccurring weekly project team meetings are focused on advancing the design development elements, program and technical mechanical / electrical infrastructure details.

Page 51: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Life Sciences Building, #204746

39

Plans for Next 30 Days The results of the schematic design budget reconciliation will be finalized for reporting to the Board of Regents. The Environmental Impact Statement (EIS) has been finalized. The project will be presented to the Architectural Commission and Landscape Advisory board for approval of the Design Development phase. The Skanska, P+W, and AECOM weekly cost log meetings, will continue assuring the design, decision making, are managed within the project budget. The Building Information Modeling (BIM) phase of the project will begin with McKinstry (MC/CM) and Veca (EC/CM) actively participating in the process. PROJECT BUDGET & COST Cost Overview The current project forecast is $160.5 million of which $4.1 million has been funded.

CHANGES IN SCOPE The additional scopes of work are being considered for: changes to the mechanical systems for improved long term cost savings, flexibility, and occupancy comfort; expanded utility infrastructure and increased building size to support additional planned growth chambers; purchasing 25% of the growth chambers; an additional learning space; and shelling an electron microscope and low vibration room.

Page 52: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Life Sciences Building, #204746

40

BUYOUT STATUS, SAFETY STATISTICS, AND CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The building was sited to preserve the deodar cedars along East Stevens Way NE (Stevens Way) and the grove of trees adjacent to Garfield Lane between Stevens Way and the Burke-Gilman trail. These trees are significant and are character-defining features of the site. An opportunity to enhance pedestrian access includes improvements to the Lewis Lane pedestrian path from Stevens Way to the Hitchcock Overpass on the east side of Kincaid Hall. The integration of the LSB and greenhouse within the existing campus connectivity is being designed. Other opportunities include integrating the Life Science Building with the greenhouse and the Burke Gilman Trail improvements into a cohesive plan. Maintaining the project cost within the forecast budget will be a challenge given the tight market place for construction.

Page 53: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 54: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Life Sciences Building, #204746

41

Rendered Image West Elevation – View from Kincaid

Rendered Image South West Elevation

Page 55: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Life Sciences Building, #204746

42

Rendered Image North Elevation – View from Stevens Way

Page 56: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

43

UWMC Expansion Phase II Montlake Tower Project #204110

August 2015 Project Manager: Ross Pouley

Construction Manager: Bob Dillon

PROJECT DESCRIPTION This project will provide the interior structure, systems, and finishes for a second phase of expansion at the University of Washington Medical Center (UWMC). This phase will increase safety and quality of service to patients in a modern, high-performance environment. It will allow a more streamlined, integrated organizational structure for the interventional services, including surgery, cardiology, and diagnostic radiology, as well as peripheral supporting areas. Additional in-patient beds will also be provided. To support this goal, the Phase II project will build out 107,000 gross square feet (GSF) of shelled spaces within the new Montlake Tower and will renovate 137,000 GSF for both inpatient and outpatient services in the Pacific and Muilenburg Towers. The scope will include new operating rooms (ORs) on Level 2 and intensive care or medical surgery units on Levels 5, 6, and 7. The renovation work will consolidate and organize clinics in wings 7EE and 8SE and will provide the support space and infrastructure necessary to make each component fully operational. To maintain continuous hospital operations throughout construction, the project has been organized sequentially in multiple construction phases. These incremental

Page 57: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

44

occupancy milestones may be adjusted to allow for patient and operational needs or infrastructure requirements. The project architect is NBBJ of Seattle, and the General Contractor/Construction Manager (GC/CM) is Mortenson Construction of Kirkland. PROJECT STATUS SUMMARY Schedule Overview

Design Package 07 (DP07) subcontracts have been awarded, and the submittal process is underway. The DPO7 consists of approximately 47,000 sf of phased remodel to Pacific and Muilenburg Towers on Level 2 and associated infrastructure modifications. The new program includes a 42 bay central prep/hold/recovery department, 4 new ORs, a pharmacy, a frozen section/grossing lab, a stat lab, and other perioperative support spaces. Schedule Variance Design Package 01 (3EE, 7NN, 7SE & 8SE): The DP01 work was substantially completed on June 22, 2015.

Page 58: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

45

Design Package 04 (Montlake Tower Floors & 7EE): The construction completion for the entire Design Package is scheduled for 1/20/16. This is 8 days later than reported last month due to casework revisions and a shortage of qualified flooring installers. However, the individual floors/areas included in the package will have incremental completion dates that coincide with the sequencing of the work at the start of construction. These incremental dates are as follows: For 7EE EEG; the completion is scheduled for 11/11/15. For 2SA; the seven ORs were completed and the Certificate of Occupancy was received on 8/26/15. For 5SA ICU Bed Floor; the completion is scheduled for 11/6/15. For 6SA ICU Bed Floor; the completion is scheduled for 11/25/15. For 7SA Bed Floor; the completion is scheduled for 1/20/16. (Eight days later than reported last month). Design Package 07: The second floor work in the Pacific & Muilenburg Towers is planned for a phased renovation (L2B, C & D). The construction completion for the entire Design Package is 10/2017. The incremental dates for the phased areas are as follows: For L2B Prep Hold Recovery North & South; will start on 11/13/15 and will complete on 7/20/16. For L2C ORs 1-4, Locker Rm, Frozen Section; will start on 7/21/16 and will complete on 6/01/17. For L2D Prep Hold Recovery Central & West Corridor; will start on 2/24/17 and will complete on 10/11/17. Work Accomplished This Period Design Package 01 The final elements of DP01 work was completed on 6/22/15. Design Package 04 The testing and commissioning of the new emergency generator, chillers, cooling tower and air handling units for the Montlake Tower continued in August. The air handling units are moving air (in 2SA), and the filter systems have passed infection control testing. In 7EE, electrical termination/trim work continued. The flooring, casework and finish work continued. A pathway for the RF shielded rooms was approved, and a work plan was submitted. Montlake Tower work:

1. For 2SA - the 7 Operating Rooms and associated support areas were substantially completed, and turned over to the UWMC on 7/28/15 for Transplant Cleaning. The area received a certificate of occupancy on 8/26/15.

Page 59: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

46

2. For 5SA, 6SA, 7SA; the flooring installation work continued. The flooring contactor added additional workers, and that is helping, but the flooring is on the critical path, and impacting the schedule. The patient door installation is underway, lighting fixture installation, electrical termination/trim work continued. The painting, casework, locker installation, ceiling tile installation, bathroom ceramic tile and bathroom fixture installation continued. The terrazzo work on 7SA is nearing completion.

Design Package 07 The amendment to add DP07 to the project has been executed, and the submittal process is underway. The make-ready work for DP07 will be performed by the DP04 subcontractors until the DP07 subcontractors mobilize the site. The first element of work is to move the Pharmacy on 2SA. The work to renovate the evacuated space for the temporary OR Control Room is underway. Plans for Next 30 Days The testing and commissioning of the mechanical & electrical work will continue in the CUP and the MLT floors. The painting, flooring & other finish work will continue on 7EE. The grounding system work will be completed. The wireless access will be extended into the 2SA ORs. The Temporary Control Room work will continue. The flooring, mechanical, electrical, and plumbing (MEP) rough-in & terminations, painting, ceilings, flooring prep, flooring install in the MLT bed Floors will continue. PROJECT BUDGET & COST Cost Overview The project forecast is on budget at $186.3 million. The early estimates for DP07 that forecast the costs for the package to be higher than anticipated did materialize in the bid process. The budget analysis/reconciliation and VE procedures employed to mitigate the overage on this specific package of work have succeeded in preserving the overall budget.

Page 60: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

47

CHANGES IN SCOPE None anticipated this period. BUYOUT STATUS The buyout for the first three major phases of construction are now complete and within the project budget. This work represents approximately sixty-seven percent of the total value of all subcontracts.

BUYOUT STATISTICS Awarded Remaining Total %

Complete

Dollar Value of Subcontracts

$75,474,138 $2,363,809 $76,831,036 97%

Variance to Date (+ over / – under)

+$2,959,986

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 145 175

Lost Time Incidents 0 1

Recordable Incidents 1 13

Total Hours Worked 35,721 491,458

Total Recordable Incident Rate 5.6 5.3

Page 61: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

48

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 207 $8,319,683 Change Order Proposals Pending 161 $6,646,652

Change Order Requests Pending (included in COPs)

PROJECT COMMUNICATIONS Number Average Turnaround

Requests for Information to Date 1,400 7 days Submittals to Date 785 13 days

The change orders include $529,655 related to 7SE. The COPs have yet to include the Sterile Holding or 5NN areas. OPPORTUNITIES AND CHALLENGES For DP07; will introduce a new group of subcontractors into the Medical Center in the months ahead, and they will be trained on our culture of safety and quiet.

Page 62: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 63: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

49

7EE ceiling elements in progress

5SA nurse station in progress

Page 64: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

50

5SA nurse station

5SA patient door installation

Page 65: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UWMC Expansion Phase I, Montlake Tower, #204110

51

5SA patient bathroom

Page 66: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

52

Montlake Triangle Project Project #203593

August 2015 Project Manager: Andy Casillas

Construction Manager: Andy Casillas

PROJECT DESCRIPTION The Montlake Triangle Project (MTP) is a multi-agency effort consisting of three subprojects centered on the intersection of Pacific Street and Montlake Boulevard. The project scope includes lowering NE Pacific Place and constructing a land bridge that will connect the Montlake Triangle and the lower Rainier Vista with a seamless pedestrian experience. Transit patrons will access the triangle via a combination of existing crosswalks and a new bridge across Montlake Boulevard. The MTP subprojects will be constructed sequentially and scheduled to minimize impact to adjacent work projects. These subprojects consist of the following elements: · Montlake Pedestrian Bridge--Subproject 1 (SP1) – This project will provide

pedestrian and bicycle connections between the future light rail station at Husky Stadium and the Montlake Triangle. Sound Transit is managing design and construction of this $11.4 million project.

· Rainier Vista Land Bridge--Subproject 2 (SP2) – This bridge will span Pacific Place and connect the Montlake Triangle to Rainier Vista. The UW is managing design and construction of this $20.8 million project.

· Rainier Vista Land Bridge Site Improvements--Subproject 3 (SP3) – This project will provide landscaping, hard surfacing, lighting, and other site improvements from Stevens Way through the Montlake Triangle. The UW is managing design and construction of this $4.5 million project.

Page 67: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Montlake Triangle Project, #203593

53

The funding for these projects will be provided by the Washington State Department of Transportation (WSDOT) ($22M), Sound Transit ($12M), and the University ($4M), with an additional $5 million in contingency reserve funded by WSDOT. The designer is KPFF Consulting Engineers of Seattle. The landscape architect is Gustafson Guthrie Nichol. The General Contractor/Construction Manager (GC/CM) is a joint venture of Sellen Construction and Gary Merlino Construction, both located in Seattle. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance The project is complete with Beneficial Occupancy achieved on June 30, 2015. Work Accomplished This Period All major construction activities were completed in June. The punch list activity continues with the majority of the punch list items addressed. There is a potential for some late added work by SDOT on NE Pacific Street for road repair and along Montlake Blvd for game day bus loading activities. The discussions continue with SDOT. Plans for Next 30 Days The work will focus on project closeout, including finalizing punch list and project documentation.

Page 68: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Montlake Triangle Project, #203593

54

PROJECT BUDGET AND COST Cost Overview The following are the approved subproject budgets:

Montlake Pedestrian Bridge—SP1 (by Sound Transit): $13.9 million Rainier Vista Land Bridge—SP2: $23.3 million Rainier Vista Land Bridge Site Improvements—SP3: $4.5 million The project budget includes two subproject components as outlined above. The combined SP2/3 budget is $27.8 million. With the numerous changes encountered, the team reviewed the project estimate to complete forecasting along with the updated Risk Register Log. Based on these updates, the project requested and received additional funding up to $2.5M from WSDOT. A MOU Amendment was executed modifying the funding agreement to increase the project funding up to an additional $2.5M.

CHANGES IN SCOPE Currently, the project is awaiting direction from SDOT on NE Pacific Place roadway repairs outside the project limits.

Page 69: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Montlake Triangle Project, #203593

55

BUYOUT STATUS The full GC/CM contract was executed in December 2013. The subcontractor’s buyout total is over the MACC. SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 0 30

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 92,304

Total Recordable Incident Rate 0 0

CONSTRUCTION ADMINISTRATION

CHANGE DOCUMENTS Number Value Change Orders Approved to Date 138 $2,680,840 Change Order Proposals Pending 10 $183,426 Change Order Requests Pending 1 $40,000

PROJECT COMMUNICATIONS Number Average

Turnaround Requests for Information to Date 268 7 days Submittals to Date 136 12 days

OPPORTUNITIES AND CHALLENGES The project is proceeding quickly as anticipated. The submittals and closeout documentation is in progress. However, minor additional work items may slow down the quick closeout that was anticipated.

Page 70: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 71: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Montlake Triangle Project, #203593

56

An aerial view of the site from the southeast – May 14, 2015.

The view looking northeast showing completed work on Pacific Place and Triangle area – July 7, 2015.

Page 72: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

Montlake Triangle Project, #203593

57

The view of Pacific Place looking east is showing the completed work along Pacific Place, the Burke Gilman Trail, and Triangle Garage entry– July 7, 2015.

Page 73: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

58

NanoEngineering & Sciences Building Project #204878

August 2015 Project Manager – Eric McArthur

Construction Manager – Mark Sweeters

PROJECT DESCRIPTION The Nano Engineering & Science Building (NESB) project will consist of a new, approximately 78,000 gross square foot, 6-story building adjacent and connected to the existing Molecular Engineering & Sciences Building (MolES) on the main University of Washington campus. The project will construct a warm shell building and complete the build-out of 13,000 assignable square feet (asf) to accommodate the currently impacted spaces. The first floor of 12,000 gross square feet will be constructed as a warm shell for anticipated future completion for academic general purpose use. This warm shell work will be funded by Central Funds. To offset this loss of floor space, the currently designed basement level floor will expand to the north and add 9,000 gross square feet of ground contact area. The balance of the shell space will be available to provide build-out space for future College of Engineering vibration and EMI sensitive programs, currently estimated at an additional 27,000 asf by the year 2021.

The project architect is a partnership of Zimmer-Gunsul-Frasca (ZGF) of Seattle, Washington and Flad Architect of San Francisco, California. The General Contractor/Construction Manager (GC/CM) is Hoffman Construction Co, located in Seattle WA.

Page 74: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

NanoEngineering and Sciences Building (NESB), #204878

59

PROJECT STATUS SUMMARY Schedule Overview

SCHEDULE VARIANCE The substantial completion has a contract date of November 1, 2016. The GC/CM is currently showing a variance of 6 days on the construction schedule due to sequencing issues during the excavation and shoring of the below-grade work as well as excessive rain on 8/14/2015 which impacted the site excavation. All trades suspended work that afternoon and the following Saturday was used to dewater the site. The GC/CM is currently working on resequencing the work to bring the schedule back into alignment. The rain incident will be tracked throughout construction to determine if a contract day is required to be added to the construction contract. WORK ACCOMPLISHED THIS PERIOD The remaining bid packages for the interior tenant improvements were issued at the end of August. This work includes all the finishes, doors, walls and ceilings required to complete the project. The excavation has been completed down to the sub basement. All exterior shoring walls have been waterproofed. The structural basement walls were formed, reinforced, and shotcreted. The column and interior shear walls are in the process of being formed and concrete placed. The work continues to be scheduled to accommodate the research taking place in the adjoining Molecular Engineering &

Page 75: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

NanoEngineering and Sciences Building (NESB), #204878

60

Sciences Building with the contractor bringing forces in at 4am and suspending operations by 3pm. This follows the agreement between the construction team and the MolES researchers established to end disruptive construction activities by 3 pm each day and to resume no earlier than 8 pm in the evening. PLANS FOR NEXT 30 DAYS The project will return to the Board of Regents in September for approval of an expanded scope. The College of Engineering (CoE) has recently hired and is forecasting additional hires in the next academic year which is pressing the need to create new space. What the CoE envisioned as a future research activity years ago has become a present activity and the space has to grow to accommodate these needs. Therefore, the College has provided internal funds to fully build-out the instrumentation labs on Level G and the research Labs on Level 3. Level 4 is also added to support expanding the Institute for Protein Design (IPD) which is currently housed on Level 4 of MolES. The tenant improvement bid packages are scheduled to be opened on September 24th. The GC/CM has included in the Instructions to Bidders which will purchase the finishes for the expanded scope stated above. This is to generate additional buying power by purchasing a greater scope of work as well as to avoid future escalation while the complete design is finalized.

The design team will begin planning sessions with the College and the IPD. This design and documentation work will continue through the end of the year.

The construction activities are continuing on the lower level and level G. The lower level walls will be backfilled. The under slab utilities will be installed while the columns and shear walls are formed, reinforced and placed.

PROJECT BUDGET & COST Cost Overview The current budget and forecast cost is $61.3 million, of which $53 million is in hand. The variance of $8.3 million will be reduced to 7.1 million through cost reduction items being captured in contract change order and reductions in contingencies. The project team continues to review opportunities for cost reduction while still maintaining the approved project scope.

Page 76: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

NanoEngineering and Sciences Building (NESB), #204878

61

CHANGES IN SCOPE A variety of measures are being implemented to reduce the cost of the project, but no programmatic scope changes are involved. BUYOUT STATUS

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$21,584,458 $18,323,358 $39,907,816 54%

Variance to Date (+ over / – under)

$8,114,197

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 60 34

Lost Time Incidents 0 0

Recordable Incidents 1 1

Total Hours Worked 10,709 34,953

Total Recordable Incident Rate 18.7 5.7

Page 77: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

NanoEngineering and Sciences Building (NESB), #204878

62

CONSTRUCTION ADMINISTRATION Change Documents Number Value

Change Orders Approved to Date 0 0 Change Order Proposals Pending 10 $139,000 Change Order Requests Pending 0 0

Project Communications Number Average

Turnaround Requests for information to date 49 3 days Submittals to Date 100 11 days

OPPORTUNITIES & CHALLENGES The construction market is currently experiencing increased escalation and volatile market conditions as the Seattle economy continues to boom. The ongoing and upcoming projects throughout the region are straining the labor pool for construction trades and consequently limiting the pool of bidders able to perform work. The NanoEngineering project and other university construction work are seeing younger tradesfolk on the jobsite which can affect the quality of work and the project schedule. The Construction Manager is aware of this and is actively monitoring and working with their subcontractors to manage this issue. These market conditions are also significantly impacting the bid results of the project.

The site is restricted and will be affecting vehicular circulation around the site. The tight fence boundaries and the increasing number of students that flow through this area of the campus present a challenge to the contracting team to preserve safety while still maintaining traffic and the ingress of materials. A UWPD officer has been retained to help direct traffic through the Grant Lane and Stevens Way intersection. This is the primary point for materials to enter the site and is also where most pedestrian traffic will cross.

Page 78: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

NanoEngineering and Sciences Building (NESB), #204878

63

Most footings have been placed, with the wall and column formwork beginning. Underground utilities have begun in the east end of the site.

Page 79: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

64

New Burke Museum Project #203007

August 2015 Project Manager: Curtis Bain

PROJECT DESCRIPTION This project will construct a new Burke Museum located along NE 15th Ave NE to the west of the existing Burke Museum within a development site identified in the UW Campus Master Plan. The new museum will be approximately 110,000 gross square feet with three-stories and a partial daylight basement. This project will replace the existing Burke Museum, constructed in 1962. This project will address the limitations and shortcomings of the existing building, which are no longer adequate to meet the programmatic vision, capacity for research collections, public outreach, and education missions of the Burke Museum. The new building will accommodate the museum’s program and will enhance connections to the community and neighborhood. It will be located and configured to better anticipate potential future development on the site and have a much stronger appeal to potential donors. The new building will celebrate the museum’s goals to: a) foster understanding and inspire wonder about the Northwest and our place in the world; b) emphasize the power of object-based learning to inspire curiosity, generate new knowledge, and foster understanding of the role collections play in our shared natural and cultural heritage; and c) emphasize the connection between people and the environment in every aspect of the museum, from research, exhibits, and programming to the museum’s building, grounds, and business practices.

Page 80: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

New Burke Museum, #203007

65

The project will be an architecturally noteworthy facility that reflects the museum's core institutional values of sustainability, excellence, respect, stewardship, creativity, and community engagement; makes the collections and research accessible and engaging; integrates a cross-disciplinary approach to achieving the museum's vision; and facilitates meaningful visitor engagement with exhibitions, on-site programs, public amenities, and outreach services. The accessibility will be integrated into the new facility to meet ADA requirements. The project will also address issues of long-term flexibility in the design of galleries and public spaces and will implement sustainable design practices to achieve a facility that functions efficiently and can be maintained with limited resources. A Leadership in Energy and Environmental Design (LEED) Platinum certification is the aspirational goal. The project architect is Olson Kundig Architects (OKA), Gustafson Guthrie Nichol (GGN) is the Landscape Architects, and Skanska USA is the General Contactor/ Construction Manager (GC/CM), all are located in Seattle. PROJECT STATUS SUMMARY Schedule Overview

Receiving less than the 56% of the needed funding from the 2015 legislative session will delay the start of construction from the fall to possibly the summer of 2016 or later, depending upon the Legislatures funding priorities. The design of the project will be complete around the start of the New Year, at which time the project will pause until additional funding is secured.

Page 81: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

New Burke Museum, #203007

66

Schedule Variance The ongoing cost reduction pressures on the project design delayed the start of the construction documents until April 2015. Work Accomplished This Period The design consultants published the 50% construction drawings. Skanska commenced a constructability review and began estimating structural, mechanical and electrical scopes of work. The estimating of the remaining project components will be initiated when the 50% construction specifications are published in early September. The project team evaluated procurement options for early subcontractor involvement. Due to the uncertainty of the project funding, Skanska recommended deferring early bidding for the project until the funding is secured. The project team conducted pull-planning sessions to model the completion of design, procurement, permitting, and contracting assuming the remaining funding for the project is obtained in early spring of 2016. Skanska, Sparling and WSP continued to resolve key scope details regarding the delivery of campus utilities to the new building and the required modification to the tunnel serving the existing museum. The City of Seattle completed the flow test of the fire hydrants; MKA will review the results and advise on any required changes to the scope of work. After informal review with UWAC, the university decided not to modify the southwest corner of the museum for a major signage component. The design team will continue to evaluate signage and museum identity opportunities along 15th Avenue and the new museum’s public entrance. Plans for Next 30 Days The university has decided to bring the design work for the project to a close until the construction funding is received. Skanska will complete an estimate of the 50% construction documents. If the estimated construction costs grossly exceed the project budget, the project team will identify recommendations to modify the scope and design of the project when the project is restarted in the future. The Master Use Permit (MUP) for the project will be obtained from the City of Seattle as previously planned. Skanska, with the support of the design consultants, will complete the site and logistics planning and coordination associated with Phase II of the project (the interim museum relocation period between completion of the new building and the demolition of the existing building). PROJECT BUDGET & COST Cost Overview The legislature approved $26 million of the necessary 46.2 million needed for the project. The University will seek to submit a request for the 2016 legislative session for the additional funding.

Page 82: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

New Burke Museum, #203007

67

CHANGES IN SCOPE None anticipated this period. BUYOUT STATUS, SAFETY STATISTICS, AND CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The funding continues to be a challenge. It will be a major challenge to plan for the displacement of staff and collections during the transition phase when they move from the existing facility into the new building. The project budget did not support Leadership in Energy & Environmental Design (LEED) Platinum certification; the project team will continue to work towards a LEED Gold certification. The project will meet LEED Silver certification standards at a minimum.

Page 83: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

68

North Campus Student Housing Project #204350

August 2015 Project Manager: Victoria Morris Construction Manager: Steve Folk

PROJECT DESCRIPTION The North Campus Student Housing project Phase IV (will replace McCarty Hall with three buildings, identified as buildings B, C and D with occupancy planned for the start of Autumn Quarter 2018. The construction typology of buildings B, C, and D will be 5-stories of wood-frame construction above a two-story concrete podium. The steeply sloped site makes it challenging to achieve the desired 1,870 beds programmed for these buildings. The lower concrete levels of the building will include residence hall amenities such as entry lobbies, regional desk, dining, game center, and meeting rooms. The upper wood framed levels will be residential suites with private or communal bathrooms. The landscape improvements include internal courtyards, a central urban plaza, an entry court, new and refreshed pedestrian access and circulation from the north, south, east and west. There will be open spaces for wide- ranging passive and active recreational uses, and the relocation of a portion of Whitman Court roadway. The cumulative changes are designed to create a new character for this part of the

Page 84: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

North Campus Housing, #204350

69

campus that retains the woodland nature of the existing area. It will be better served by connections within it and connecting to the broader campus. The project is targeting, at a minimum, a Silver level certification for new construction through the U.S. Green Building Council’s Leadership in Energy & Environmental Design (LEED). Kieran Timberlake of Philadelphia, Pennsylvania is the architect, Olin Studios of Philadelphia is the Landscape Architect, and W.G. Clark of Seattle is the General Contractor/Construction Manager (GC/CM). PROJECT STATUS SUMMARY Schedule Overview

Phase IV (a)

Schedule Variance None, the project remains on schedule. Work Accomplished This Period The schematic design phase was completed with SD review comments forwarded to the design team. The proposals for the mechanical and electrical contractor construction managers were reviewed. Plans for Next 30 Days The design development phase will begin, which includes refinement to program elements, building fenestration studies, material selections and site landscape. The landscape elements, site circulation and plaza features will be further refined and detailed. The active construction market resulted in fewer than the desired responses

Page 85: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

North Campus Housing, #204350

70

from the mechanical subcontractors. The Electrical Contractor /Construction Manager (EC/CM) process will move into the interview phase of the process. PROJECT BUDGET AND COST Cost Overview The project has been funded at $1,920,000 for preliminary design. The funding will be increased to address a later than planned Fall approval by the Board of Regents for the funding, budget, and site approval. The funding will be increased to complete the schematic design and a portion of the design development phase. The funding for this work is from Housing & Food Services (HFS) reserves. The project forecast is $235 million. This is above the previous forecast of $216 million. This is due to site conditions, moving beds from Phase IV(b) to this phase, and higher than estimated costs. The team will be studying options to reduce cost and potentially increasing the project budget.

CHANGES IN SCOPE Not applicable at this time. BUYOUT STATUS, SAFETY STATISTICS, CONSTRUCTION ADMINISTRATION Not applicable at this time.

Page 86: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

North Campus Housing, #204350

71

OPPORTUNITIES AND CHALLENGES The early selection of the general contractor along with early selections of the mechanical and electrical subcontractors, follow the successful format of the design participation that occurred on the West Campus Housing projects. This early involvement has proven to enhance the 3D modeling and coordination of the design. The project will be challenging with the cost of construction increasing and shortages of qualified craft trade workers to construct the project due to the increase in construction activity in the Seattle area. It is an exciting opportunity to create a new vision for the residential housing village for this part of the campus that retains the woodland nature, which better serves internal and external connections to the campus and the connecting community.

Page 87: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

72

UW Police Department Facility Project #203612

August 2015 Project Manager: Ken Kubota

Construction Manager: Jeff Huebler

PROJECT DESCRIPTION This project will provide a new upgraded University of Washington Police Department (UWPD) facility in a more central location that will facilitate greater accessibility to the University community. The project site is just south of Gould Hall, occupying a portion of the W14 Parking Lot and the 3945 and 3937 buildings on 15th Avenue NE. The building will be located in the growing and increasingly lively west campus and near a primary campus entrance; the site offers improved visibility and access to the police station. The approximately 29,000 gross square foot building is envisioned to be architecturally significant, with a program that features to support a modern and highly capable UWPD operation for decades to come. The conceptual design envisions a two-story building with a basement level. The program includes; police offices, a dispatch and communications center, records storage, evidence room and lab, suspect processing, interview rooms, report taking rooms, juvenile waiting rooms, police lockers, fitness rooms, a community multipurpose meeting/training room, and fleet parking. The project sustainability goal is to achieve Leadership in Energy & Environmental Design (LEED) silver certification.

Page 88: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Police Department Facility, #203612

73

The architect is the Miller Hull Partnership of Seattle. The police facilities consultant is McClaren, Wilson & Lawrie of Phoenix, Arizona. The General Contractor/Construction Manager (GC/CM) is BNBuilders of Seattle. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance There are no changes this period. The project remains on schedule. Work Accomplished This Period The construction continues with the placement of the concrete post-tensioned (PT) roof deck. The mechanical ventilation ducts and plumbing are being installed on the lower basement level. The motor court site wall footings are installed. The site utilities for water, sewer, and storm were installed. Plans for Next 30 Days The parapet, stair, and elevator shafts to the roof will be installed topping out the building. The ground floor electrical rough-in will begin. The ground floor CMU walls will begin. The formwork for the roof level will be removed with stressing of the PT cables. This also allows for the shoring posts to be removed throughout the building. The mechanical and plumbing rough-in continues on the second and third levels. The fence wall foundations will be placed in the motor court. The landscape and irrigation bid package will be bid. This is the last bid package. The alley work will start and be completed in conjunction with the West Campus Utility Plant (WCUP) Project and Seattle City Light (SCL); the scheduling of SCL will be dependent upon its crew availability.

Page 89: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Police Department Facility, #203612

74

PROJECT BUDGET AND COST Cost Overview The project cost forecast remains on budget at $19.5 million.

CHANGES IN SCOPE None this period. BUYOUT STATUS

BUYOUT STATISTICS Awarded Remaining Total %

Complete Dollar Value of Subcontracts

$11,784,661 $ <23,600> $11,761,061 99%

Variance to Date (+ over / – under)

$303,438

Page 90: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Police Department Facility, #203612

75

SAFETY STATISTICS

SAFETY STATISTICS This Month Project to Date

Average Daily Work Force 31 19

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 5,213 17,299

Total Recordable Incident Rate 0 0

CONSTRUCTION ADMINISTRATION

OPPORTUNITIES AND CHALLENGES The UW Police Department facility is one of the few buildings on campus that is open 24-hours a day, seven days a week. This project will make the UW Police Department more visible, as many students, faculty, and staff do not know its current location at the Bryants Building. The design team and the contractor are managing the project to stay within the available budget. Just south of the UWPD site is the site of the separate WCUP project that will require close coordination. The WCUP project is no longer providing the emergency power to the UWPD. The WCUP project is funding the emergency power coming from the West Receiving Station. The increasing construction costs as well keeping the project on budget will be challenging.

CHANGE DOCUMENTS Number Value

Change Orders Approved to Date 6 116,502

Change Order Proposals Pending 8 379,000

Change Order Requests Pending 1 394,000

PROJECT COMMUNICATIONS

Number Average

Turnaround

Requests for Information to Date 117 4 days

Submittals to Date (not including LEED)

187 9 days

Page 91: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

PROJECT PHOTOS

Page 92: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Police Department Facility, #203612

76

North Elevation- Concrete to Roof

–North Elevation to Roof Level

Page 93: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Police Department Facility, #203612

77

Motor Court /Site Laydown - West

Page 94: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

78

UW Tacoma Urban Solutions Center Project #204701

August 2015 Project Manager: Jeannie Natta

PROJECT DESCRIPTION The former Tacoma Paper and Stationery Building is the last of the historic large warehouse buildings on the UW Tacoma campus to be renovated. The building features a 10,000 gross square foot daylight basement and three upper floors for a total of 40,000 gross square feet. Currently, the building is unoccupied other than for storage uses and by the Old Spaghetti Factory restaurant, which has been a mainstay in downtown Tacoma for decades. Consistent with its mission as an urban-serving university, the UW Tacoma seeks to renovate this building to further preserve the historic fabric of its downtown Tacoma environs, and to ultimately house programs in the building which bring together academic, commercial, non-profit, government, and student entities in one place to study, research, analyze, debate, and develop solutions for a variety of issues in the South Sound region. Originally, the project was to be completed in two phases: (1) a ‘warm shell’ and core renovation, (2) a full build-out of the interior space. Based on UW Tacoma’s current projections of 4%-6% student growth per year, the UW Tacoma Campus Planning Office intends to complete the project in a single phase. The pre-design and design work has been funded by a $1.9M capital request in the 2013 Legislative session. A capital request for core and shell construction was funded

Page 95: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Tacoma Urban Solutions Center, #204701

79

by the Legislature at $16M. The UW Tacoma funded the interior design and construction at $10.1M from the UW Tacoma Reserves. The architect is the Miller Hull Partnership, located in Seattle. Mortenson Construction, located in Kirkland, Washington, has been selected as the General Contractor/Construction Manager (GC/CM). PROJECT STATUS SUMMARY

Schedule Variance The schedule has been revised with anticipation of when the building may be vacated. We anticipate starting construction January 2016. Work Accomplished This Period The design team reached a milestone of 100% design development for the core and shell and 30% schematic design for the interiors. In mid August the project team reviewed the design for quality control. Mortenson developed an estimate of the complete project based on these design documents. Early reviews of the estimate show the project to be on target. The faculty focus groups reviewed the schematic design of the interiors and provided comments. UW T Information Technology and Campus Planning reviewed the audio visual needs for classrooms. The project team also met with UW Tacoma Facilities to

Page 96: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Tacoma Urban Solutions Center, #204701

80

review specific building operation needs. Access to the Old Spaghetti Factory allowed for further investigation work, including regulated building materials, surveying the floor elevations and researching the best location for the building entrance. Plans for Next 30 Days The project team meets in early September for a complete review of the construction estimate to confirm that the design intent is captured in the estimate and consider cost saving options. The estimate and design options will be presented to UW Tacoma at the September 24 core team meeting. The two important review meetings are scheduled for the middle of the month. The first is with the Office of the University Architect to review the project. The second is an over the shoulder review by UW Tacoma Facilities of the mechanical, electrical and plumbing design. The next LEED charrette is also scheduled for mid September. The team plans to finalize the LEED score sheet and define the commissioning scope. We plan to bring the commissioning agent on board at the end of the month. The design team will have two sessions with faculty focus groups to further develop the interior design. An all faculty design open house is also scheduled for the end of the month to share the design progress. PROJECT BUDGET & COST Cost Overview The total project budget is $28,000,000, pending Regent approval at their September meeting. $1,900,000 has been appropriated by the Legislature in 2013-2015 budget for predesign and design of the core and shell. $16,000,000 has been appropriated by the Legislature in 2015-2017 budget for construction of the core and shell. $10,100,000 has been appropriated from UW Tacoma Reserves in 2015 to complete the design and construction of the interior.

Page 97: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

UW Tacoma Urban Solutions Center, #204701

81

CHANGES IN SCOPE No changes from last month. BUYOUT STATUS Not applicable at this time. SAFETY STATISTICS Not applicable at this time. CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The project offers the chance to complete the major renovation of UW Tacoma’s warehouse building stock and fill in a ‘missing tooth’ in the heart of the campus. The building has a number of infrastructure challenges to overcome. There is also known contaminated soil within the footprint of the building and economically addressing that issue may be an additional challenge. The predesign provided a strong foundation moving forward. Now that the Prairie Line Trail is completed, the design team is also able to envision how the new Urban Solutions Center will tie into the trail. At this time the team is proceeding with the understanding the building will be unoccupied. If this assumption changes and the building remains partially occupied during the core and shell renovation, scope and schedule would be impacted if the budget is to be maintained.

Page 98: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

82

West Campus Utility Plant Project #204685

August 2015 Project Manager: Steve Harrison

PROJECT DESCRIPTION This current project includes a building of approximately 17,000 gross square feet (GSF) containing generators, chillers, cooling towers, and associated equipment. The building will be constructed above the existing campus utility tunnel, allowing direct access to the tunnel for distribution of electrical cabling and chilled water (CW) piping. When fully built out, the plant will have capacity to produce 12 megawatts (MW) of emergency power and 10,500 tons of CW. In phase 1 the construction of the building will be complete as well as the installation of equipment to produce 6 MW and 3,000 tons of CW. This phase will also provide space and infrastructure for the future full equipment build-out, and run distribution systems to the south campus. The emergency power and CW will be distributed to the tunnel intersection vault SW-1, at which point the ARCF project will pick up those services for connection and distribution within the facility and to the existing distribution lines nearby. The West Campus Utility Plant (WCUP) is envisioned to be an architecturally significant building, given its prominent location on the west campus. The careful attention given will ensure that the design fits contextually with the surrounding community and is representative of its importance as a gateway building at the southwest approach to the campus. The design will incorporate a demonstration

Page 99: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

West Campus Utility Plant, #204685

83

display element that will enable access by students and the public to gain an understanding of the University’s commitment to the environment and energy conservation. The Board of Regents authorized the use of the design-build (D-B) contracting method for this project. PROJECT STATUS SUMMARY Schedule Overview

Schedule Variance None this period. Work Accomplished This Period The installation of the new chilled-water distribution system piping began and a substantial portion of the work that can be completed before removing the existing pipelines is done. The city comments on the building permit were received and responded to. The detailed design was ongoing in support of trade work packages, the plant electrical design and permit application, and the sequence-of-operations including controls and instrumentation. A draft commissioning plan was published

Page 100: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

West Campus Utility Plant, #204685

84

and is under UW review. The procurement efforts and construction-logistics planning were ongoing and continue. Plans for Next 30 Days The distribution system pipeline installation will continue. The preparations for plant construction will continue. The design-builder will establish working trailers and begin the second round of procurement (the major electrical and mechanical trade partners have already been on board for many months). The formal design efforts will be completed and the professional firms will begin their construction administration duties. A handful of change orders will be advanced and possibly executed including 3 scopes of work that were originally envisioned to be part of the future phases of the CUP and associated distribution system upgrades. These scopes may be moved into the current ‘Phase 1’ work (i.e. they may be ‘accelerated’) in order to be able to serve the Life Sciences Building, which is now in design, and to reduce the ultimate cost of developing the plant in general. The work to shepherd the MUP and the building permit and to prepare for plant construction will continue. PROJECT BUDGET & COST Cost Overview The current approved budget is $36.2 million. The increase from the original project budget of $30.5 million was approved by the Board of Regents at the March 2015 meeting. Adding a number of identified scope enhancements will provide flexibility for the future by increasing the building footprint, a partial basement and equipment enhancements. This increase will better allow the facility to respond to potential future sustainability initiatives such as thermal storage, lake water cooling and campus system conversion from steam to hot water.

Page 101: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

West Campus Utility Plant, #204685

85

CHANGES IN SCOPE An increase in mechanical and electrical scopes is anticipated within the next 30 days. This is all ‘accelerated Phase 2 scope’, see discussion above. BUYOUT STATUS Not applicable at this time. SAFETY STATISTICS

SAFETY STATISTICSSAFETY STATISTICS

This Month Project to Date

Average Daily Work Force 0 0

Lost Time Incidents 0 0

Recordable Incidents 0 0

Total Hours Worked 0 0

Total Recordable Incident Rate 0 0 CONSTRUCTION ADMINISTRATION Not applicable at this time. OPPORTUNITIES & CHALLENGES The permitting-related schedule risks previously identified still exist, but are diminishing in number with time and progress. A few city comments related to the Building and Master Use permits still have the potential to cost time and money. The budget risks generally associated with assuring quality and completeness in the constructed product under a design-build delivery system while market costs are escalating are beginning to emerge. However, the collaborative design effort has effectively controlled them to date. The ‘accelerated Phase 2’ scopes of work discussed above are important opportunities in that they have the capacity to save

Page 102: MONTHLY MAJOR PROJECTS REPORT FOR …cpd.uw.edu/sites/default/files/file/August Monthly report_0.pdfMONTHLY MAJOR PROJECTS REPORT FOR AUGUST 2015 ... EIS Environmental Impact Statement

West Campus Utility Plant, #204685

86

money in other projects and in regard to future plant and distribution build out. There is a risk emerging in regard to work by another UW project in the alley adjacent to the CUP site. That project intends to move overhead power lines into a new underground duct bank. The coordination with, and cooperation from, Seattle City Light is required and if the work is delayed, then CUP construction may be impacted by the presence of the power lines.