-
Module 2: Job-order costing
Required reading
Chapter 3, pages 69-99
Overview
This module introduces the distinctions between two methods of
determining unit costs of production job-order costing and process
costing and presents an overview of the design and operation of a
job-ordercosting system. (Module 3 focuses on process costing.)
Particular attention is given to the procedures forassigning
overhead costs to units of product. The module illustrates the flow
of costs through the system for atypical manufacturing company, and
addresses some of the problems of overhead application.
In this module, you complete the design of a worksheet to
calculate cost of goods manufactured and cost ofgoods sold using a
spreadsheet program.
Assignment reminder
Assignment 1 (see Module 5) is due at the end of week 5 (see
Course Schedule). It is a good idea to look at itnow in order to
familairize yourself with the requirements as you work through
Modules 2-4.
Topic outline and learning objectives
2.1 Job-order costing: Overview Compute predetermined overhead
rates, and explainwhy estimated overhead costs (rather than
actualoverhead costs) are used in the costing process.(Level 1)
2.2 Job-order costing: Flow of costs Prepare journal entries to
record the flow of directmaterials cost, direct labour cost, and
manufacturingoverhead cost in a job-order costing system. (Level
1)
2.3 Using pretedermined overhead rates Apply overhead cost to
Work in process by use of apredetermined overhead rate. (Level
1)
2.4 Complications of overhead application Compute any balance of
under- or overappliedoverhead cost for a period, and prepare the
journalentry needed to close the balance into the
appropriateaccounts. (Level 1)
2.5 Job-order costing in service companies Explain the role of
job-order costing in servicecompanies. (Level 1)
2.6 Scrap and rework Prepare journal entries to deal with scrap
and reworkof unacceptable production. (Level 1)
2.7 Computer illustration 2.7-1: Cost schedules Construct
worksheet templates to calculate schedulesof cost of goods
manufactured and cost of goods sold.(Level 1)
Module summary
Print this module
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.1 Job-order costing: Overview
Learning objective
Compute predetermined overhead rates, and explain why estimated
overhead costs (rather thanactual overhead costs) are used in the
costing process. (Level 1)
LEVEL 1
It is important that you understand the basic differences
between the job-order and process costing systemsand the types of
companies that would use each method. Note the following two
important items from thereading for this module:
Discussion of the forms usedDistinction between direct and
indirect materials
The job cost sheet (Exhibit 3-2) becomes the inventory subledger
card for work in process.
Labour costs may be recorded in many different formats. Study
the document used for recording direct labour(Exhibit 3-3).
Consider how this recording process might be made faster, or made
more accurate, if themachines used in the different tasks were
connected to a computer.
Note: The explanation of overhead in the text is crucial to much
of the rest of the course. You should clearlyunderstand the need
for, the approach to, and the effect of using predetermined
overhead rates.
To consider the question of why a predetermined overhead rate is
needed, ask why smoothing is desirableeven though a study of
financial accounting might suggest otherwise. Within a fiscal year,
production can andoften does fluctuate. If production volume is
unusually low for a given month, the unit cost of overheadassigned
to inventory would tend to be very large because some overhead
costs would not decrease inproportion to the decrease in
production. Because assets are future benefits and because selling
price, lesscosts to complete and sell (net realizable value), tends
to reflect this, the future benefits can be used to
justifynormalized (smoothed) overhead.
The greater unit cost resulting from the low production and the
fixed overhead costs would likely mean that awrite-down of the
inventory to market value (net realizable value) would be required.
Smoothing by the use ofa normalized overhead would prevent such
fluctuations in monthly inventory costs and incomes (due to
thewrite-downs). Sufficient accuracy in estimating would be needed
for costing and marketing.
Note the following equations:
Predetermined overhead rate Actual activity base = Overhead
charged (or applied) to work in process.
Manufacturing overhead is charged to Work in process at a
predetermined rate for the reasons mentioned onpage 78.
While the example in the textbook uses direct labour-hours as
the cost driver, other appropriate cost driverscan be used to apply
manufacturing overhead, such as machine-hours, beds occupied,
computer time, orflight-hours.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.2 Job-order costing: Flow of costs
Learning objective
Prepare journal entries to record the flow of direct materials
cost, direct labour cost, andmanufacturing overhead cost in a
job-order costing system. (Level 1)
LEVEL 1
The Work in process account is used to capture the costs of
manufacturing the products, and includes the costof direct
materials, direct labour, and manufacturing overhead. For direct
materials and direct labour, actualcosts are charged to Work in
process. As direct labour, direct materials, and manufacturing
overhead are used,they are debited to Work in process.
However, actual overhead costs must still be accounted for in
some manner. That is where the Manufacturingoverhead account comes
into play. It is called a clearing account because it is cleared or
emptied on a regularbasis.
The debit side of the Manufacturing overhead clearing account
captures the actual cost of the various types ofmanufacturing
overhead. These costs are, in turn, charged to specific jobs so the
credit will clear the account,eventually bringing costs forward to
Finished goods.
Activity 2.2-1 Job costing: The flow of costs
This activity introduces you to the flow of costs in a
manufacturing environment. Because it is important towork through
from start to finish, allow 10-15 minutes to complete the
activity.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.3 Using predetermined overhead rates
Learning objective
Apply overhead cost to Work in process by use of a predetermined
overhead rate. (Level 1)
LEVEL 1
The manufacturing overhead clearing account is cleared to Work
in process and charged to specific jobs basedon predetermined
overhead rates.
This system of charging overhead out at a predetermined overhead
rate is called a "normal costing system."
Ideally, the amount charged to specific jobs in this entry will
equal the actual costs incurred. If so, the accountwill have a zero
balance it will have been cleared. Topic 2.4 will describe how to
clear any remaining balanceif the amount charged to specific jobs
in the above entry does not equal the actual costs incurred.
Observe in Exhibit 3-11 how the Schedule of Cost of Goods
Manufactured handles predetermined overhead."Actual" overhead of
$95,000 is charged by first "applying" $90,000 and then adjusting
for "Underappliedoverhead" of $5,000 (the difference between actual
and applied overhead) to Cost of goods sold. If overheadhad been
overapplied, the difference would be subtracted from Cost of goods
sold.
Activity 2.3-1 Overhead application and journal entries
Work through this activity to reinforce your understanding of
the cost flows for a manufacturing concern.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.4 Complications of overhead application
Learning objective
Compute any balance of under- or overapplied overhead cost for a
period, and prepare thejournal entry needed to close the balance
into the appropriate accounts. (Level 1)
LEVEL 1
Determining whether a variance is underapplied or overapplied is
the first difficulty in overhead application. Todetermine the
answer, relate the actual overhead to the applied overhead. If
actual overhead is greater thanthe applied, the variance is
underapplied. Overapplied overhead is the reverse. Overapplied
overhead occurswhen the amount of overhead applied to jobs exceeds
the actual costs.
The closing, or disposition, of the overhead variance to Cost of
goods sold is illustrated in entry (14) on page92. This is the
required treatment for underapplied overhead. The CICA Handbook
Accounting recentlyissued section 3031, the Canadian equivalent to
International Financial Reporting Standards IAS 2. Section
3031states that for external reporting purposes, fixed overhead
costs should be allocated based on normal capacity.Normal capacity
is the production that is expected to be achieved on average over a
number of periods orseasons under normal circumstances. This takes
into account the time it takes to maintain equipment. Thismeans
that the denominator used to determine the overhead application
rate will always be based on thenormal capacity of the production
facility. (Anticipated actual production should only be used if
it"approximates" normal capacity.) Any production less than normal
capacity may result in unallocated overheadat the end of the
period. According to paragraph 3031.13, for external reporting
purposes this overhead isexpensed to Cost of goods sold for the
period. The same treatment applies to overapplied overhead.
However,in periods of abnormally high production the overapplied
overhead should be allocated to Work in process,Finished goods and
Cost of goods sold so that inventories are not measured above
cost.
For interim reports, the variance may be deferred. What if the
plant is a fruit processor operating for only sixmonths of the
year? Proration might be suggested except that, without inventories
from production, therewould be nothing to prorate to. If you
prepared interim statements, would you want a large loss from
theunderapplied overhead or would you defer the overhead on the
balance sheet as a deferred charge? While nodefinitive answer can
be given, many managers prefer to defer the overhead variance.
Method for proration
In periods where production is greater than normal capacity,
overhead may be overapplied. This will inflateinventory costs
beyond the actual manufacturing overhead incurred. In this case, to
reduce the balances inthese accounts you can use current period
production costs in Cost of goods sold, Work-in-process
inventory,and Finished-goods inventory as the basis for prorating
the overapplied overhead.
If the accountant can determine the exact amount of "overhead
applied" in each of the inventories and theCost of goods sold, it
is slightly more accurate to use these amounts (in the same way as
shown for total costs)in order to allocate the overhead variance.
Overhead and total costs may not be present in exactly the
sameproportions in inventories and in Cost of goods sold, resulting
in the increase in accuracy. In practice,materiality considerations
often lead to the more simplified approach shown in the
textbook.
When studying the example on pages 92-93 in the textbook, note
that the proration method of overhead willno longer be used for the
handling of underapplied overhead, only for overapplied overhead in
periods ofabnormally high production.
The equitable allocation of a single plant-wide overhead rate as
compared to multiple overhead rates is aninteresting point. The
method of working with one is the same as working with many.
Testing the effect on avariety of products would enable an
accountant to determine if multiple rates are equitable.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.5 Job-order costing in service companies
Learning objective
Explain the role of job-order costing in service companies.
(Level 1)
LEVEL 1
The principles of job-order costing apply equally in the service
sector, where direct labour and overhead aretypically the dominant
costs. While the textbook does not devote a separate discussion to
service companies,the review material at the end of the chapter
includes problems that relate specifically to service
companies.
The principles of job-order costing are also applied on the
international scene. However, the application of job-order costing
varies from country to country depending on the needs of managers
and the sophistication of themanagement process. (International
job-order costing is non-examinable.)
Chapter summary
This topic marks the end of the textbook coverage of job-order
costing. To ensure you understand this materialand the
corresponding terminology, read the summary on page 99 and work
through the review problem.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.6 Scrap and rework
Learning objective
Prepare journal entries to deal with scrap and rework of
unacceptable production. (Level 1)
LEVEL 1
A general problem in job costing is how to handle rejected
units, rework labour, and scrap recovery. Notecarefully the method
shown in the following example.
Example 2.6-1: Scrap and rework
1,000 units were started for Job 610.940 good units were
finished for Job 610.The total cost for Job 610 was $2,400.The
total cost has already been recorded in Work in process.
Situation A: Assuming no recovery on 60 bad units
Alternative approaches:
1. Charge rejects to good units. Under this approach, Work in
process for Job 610 will report the fullcost of $2,400. Therefore,
the actual cost of producing a good unit is $2.553, calculated
as$2,400 940.
or
2. Charge rejects to all jobs. Under this approach, the cost of
the defective units will be charged toManufacturing overhead and
not to Job 610. The following entry will be made to remove the
costof the defective units from Work in process for Job 610:
In the end, the cost of Job 610 will be reported at $2,256, that
is, $2,400 $144. The unit costfor the 940 good units is $2.40.
Technically, the second approach reallocates applied overhead
back to actual overhead becausethe 60 units have an applied
overhead component included in their cost. This could be avoided(if
significant) by removing only the material and labour costs for the
rejects and charging onlythese two elements in the preceding
journal entry.
Situation B: If scrap is recovered
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.7 Computer illustration 2.7-1: Cost schedules
Learning objective
Construct worksheet templates to calculate schedules of Cost of
goods manufactured and Cost ofgoods sold. (Level 1)
LEVEL 1
The following illustration uses a spreadsheet program to help us
prepare these schedules. The spreadsheetdemonstrates how to
organize information related to Cost of goods manufactured and Cost
of goods sold sothat a change can be readily incorporated without
redoing the actual schedules.
Material provided
A prebuilt worksheet M2P1, which you will complete.
A completed solution worksheet M2P1S, to which you can compare
your work.
Description
Chapter 3 (on pages 80-89) explains in detail the information
required to prepare the schedules of Cost ofgoods manufactured and
Cost of goods sold for the Rand Company.
Required
Complete the schedule of Cost of goods manufactured and Cost of
goods sold using this procedure.
Procedure: Cost schedules
First familiarize yourself with the information in the textbook
on Rand Company and how the various costs arecalculated and
recorded. Then perform the following steps:
1. Open the Excel file MA1M2P1.xls. (Before you begin working on
the data files in this course, youmust first download them and save
them to your hard drive. Click the Data files link in thenavigation
pane, then follow the instructions for downloading and saving the
files.)
2. Study the layout of the worksheet. Observe that cells A6 to
D27 form the data table. Nextexamine the schedule of cost of goods
manufactured, starting with row 28. Cells D51 to D55 arecurrently
empty.
3. Study the formulas in the worksheet (for example, refer to
the formula in cell C33). Pay particularattention to how the
formulas in the schedule of Cost of goods manufactured reference
the cellsin the data table (for example, refer to the reference in
cell C31).
4. Enter the missing formulas in cells D51 to D55. Do not enter
numeric values in these cells. Youmust enter formulas that will
result in the values shown in Exhibit 3-11 (page 89) of the
text.
5. Enter formulas in cells D63 to D67 to complete the schedule
of Cost of goods sold, which startsin row 59.
6. Save your completed worksheet.
7. Print a copy of your worksheet and compare it with the
solution worksheet by clicking on thesheet tab M2P1S. If you do not
obtain the same results, proceed to step 9; otherwise, go to
step
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
10.
8. Print a copy of the formulas and compare them with the
formulas of the solution worksheetM2P1S. Correct any errors.
9. Assume management decided that two changes were necessary in
the data table:
Direct labour from $60,000 to $70,000
Depreciation from $18,000 to $15,000
Click the M2P1S sheet tab for the solution. Change the values in
cells C15 and C22 to the newvalues. The Cost of goods manufactured
(cell D55) should now show $168,000 instead of$158,000, and the
adjusted Cost of goods sold (cell D67) should show $130,500 instead
of$123,500.
Note: According to IAS 16 paragraph 6, the systematic expensing
of the original cost of physical assets overtime is called
depreciation.
-
Module 2 summary
Job-order costing is used in organizations that offer a great
variety of different products or services.
One of the major issues is how to apply overhead to each order.
Topic 2.1 addresses the issue by introducingthe rationale of the
predetermined overhead rate which is based on estimates.
Topic 2.2 tracks the three basic cost components for each
job.
Topic 2.3 shows how to apply overhead cost to Work in
process.
Since the actual cost incurred during a period may differ from
the overhead applied, a difference usually occurs.Topic 2.4 deals
with the under or over application of overhead including how to
dispose of these differences.
The job-order costing method is versatile, and Topic 2.5
introduces its use in service companies.
Topic 2.6 deals with how to handle flawed units in job-order
systems.
Topic 2.7 consists of a computer exercise that summarizes the
flow of costs in a job-order system andprepares the schedules of
Cost of goods manufactured and Cost of goods sold essential
components of theincome statement.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Module 2 self-test
Question 1
Computer question
Before you attempt this question, you should work through
Computer illustration 2.7-1.
Description
The Atlantic Manufacturing Company operates a job-order cost
system and applies overhead cost to jobs onthe basis of direct
labour cost. In computing an overhead rate for the year, the
company's estimates were:manufacturing overhead cost, $480,000; and
direct labour cost, $640,000. The company's inventory accountsat
the beginning and end of the year were as follows:
January 1 December 31 (beginning of year) (end of year)Raw
materials $34,000 $26,000Work in process 84,000 78,000Finished
goods 152,000 144,000 The following actual costs were incurred
during the year: Purchase of raw materials (all direct)
$540,000Direct labour cost 680,000Manufacturing overhead costs:
Insurance, factory 35,000Depreciation of equipment 65,000Indirect
labour 160,000Property taxes 42,000Maintenance 50,000Rent, building
160,000
Required
Answer requirements 1, 4, and 5 manually. Use the following
procedure to answer requirements 2 and 3.
1. a. Compute the predetermined overhead rate for the year. b.
Compute the amount of under- or overapplied overhead for the year.
2. Prepare a schedule of cost of goods manufactured for the year.
3. Compute the cost of goods sold for the year. (Do not include any
under- or overapplied overhead in your
cost of goods sold figure.) What options are available for
disposing of under- or overapplied overhead? If you choose to
adjust Cost of goods sold, what would be your adjusted figure?
4. Job 189 was started and completed during the year. What price
would have been charged to the
customer if the job required $4,300 in materials and $6,600 in
direct labour cost, and the companypriced its jobs at 40% above
cost to manufacture?
5. Direct labour made up $29,640 of the $78,000 ending Work in
process inventory balance. Supply the
information missing below:
Direct materials $ ?
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Direct labour 29,640 Manufacturing overhead ? Work in process $
78,000
Procedure
1. Open the Excel file MA1M2Q1.
2. Examine the layout of the worksheet. Rows 6 to 24 form the
data table and contain the datafrom the problem. Rows 26 to 48
contain a schedule of cost of goods manufactured and rows 52to 60
contain a schedule of cost of goods sold.
To complete requirement 2
3. Enter in cell C23 the overhead rate and in cell C24 the
amount of overapplied or underappliedoverhead for the year as
calculated in requirement 1.
4. Enter in cells C29 to C32, D33, D34, C36 to C43, and D44 to
D48 the appropriate formulas tocomplete the schedule of cost of
goods manufactured.
To complete requirement 3
5. Enter the formulas in column D of rows 54 to 60 to complete
the schedule of cost of goods sold,and save your completed
worksheet.
6. Answer the rest of requirement 3.
Source: Ray H. Garrison, Eric W. Noreen, G.R. Chesley, and
Raymond F. Carroll, Managerial Accounting, SixthCanadian Edition,
Problem 3-19, page 129. Copyright 2004, by McGraw-Hill Ryerson
Limited. Adapted withpermission.
Solution
Question 2
Multiple choice
a. The predetermined overhead rate is $12.20 per direct-labor
hour. Job 360 required 415 direct-labour hours, of which 300 were
incurred during October. How much overhead should be appliedto Job
360 during October?
1. $1,4032. $3,6603. $4,3924. $5,063
b. Production reports for the second quarter show the following
data:
Month Direct machine- hours Direct labour- hours Labour cost
Materials costJanuary 18,000 24,000 $120,000 $64,000
February 24,000 20,000 100,000 57,000March 20,000 18,000 88,000
90,000
Actual overhead for January, February, and March was $45,020,
$60,000, and $50,100respectively. Which variable above would be the
most likely basis for allocating overhead?
1. Direct labour-hours2. Labour cost3. Direct machine-hours
-
4. Materials cost
c. A job has been completed and has incurred $10,000 of direct
material costs and $16,000 ofdirect labour. The customer wants to
take delivery of the completed job but actual factoryoverhead costs
will not be known until the end of the month. Which of the
following should thecompany do?
1. Charge the customer $26,000 plus a mark-up on direct
materials and direct labour.2. Withhold the product until actual
overhead costs are known.3. Allocate overhead to job using a
predetermined overhead rate.4. Send an adjusted invoice to the
customer when actual overhead costs are known.
d. The following information is available for April:
Job A Job B Job C
Direct costs balance, April 1 $4,000 $6,400 April manufacturing
costs 8,000 $3,600
Jobs A and B were finished and delivered to the clients. Job C
was not completed at April 30.What was April's Cost of goods
sold?
1. $3,6002. $11,6003. $14,4004. $18,400
e. Job 621 is the only job remaining in Work in process at the
end of June. The June 30 balance inWork in process is $24,000 of
which $6,000 is direct material. Manufacturing overhead isallocated
at the rate of $1.50 per $1.00 of direct labour. What is the amount
of direct labourcharged to Job 621?
1. $7,2002. $10,8003. $12,0004. $18,000
f. When overhead is underapplied, the correct adjusting entry is
which of the following?
1. Dr. Work in process and Cr. Cost of goods sold2. Dr. Cost of
goods sold and Cr. Manufacturing overhead3. Dr. Manufacturing
overhead and Cr. Cost of goods sold4. Dr. Cost of goods sold and
Cr. Work in process
g. Direct labour was $90,000 and factory overhead applied on the
basis of direct labour cost was$63,000. What was the predetermined
overhead rate?
1. 30%2. 43%3. 70%4. 143%
Use the following information to answer h) and i).
The following is an excerpt from DellCo's accounting information
system:
Indirect factory materials $ 48,000
Direct manufacturing materials 114,000Indirect office wages
14,000Manufacturing overhead applied 182,000
-
Factory depreciation 86,000
Office depreciation 14,000
Direct office wages 32,000Factory supervisors, salaries
36,000Supplies, factory 7,000
h. Based on the information above, what value will be debited to
the Manufacturing overheadaccount?
1. $177,0002. $182,0003. $191,0004. $205,000
i. Based on the information above, what value will be debited to
the Work in process accountregarding manufacturing overhead?
1. $177,0002. $182,0003. $191,0004. $205,000
j. The following data is available for the month of January:
JanuaryLabour cost $232,500
Actual Manufacturing overhead $273,060
If Manufacturing overhead is applied at the rate of 120% of
direct manufacturing labour costs,what would be the under- or
overapplied overhead?
1. $5,940 overapplied2. $40,560 overapplied3. $54,612
underapplied4. $95,172 overapplied
k. The overapplied balance of manufacturing overhead is
$720,000, a significant amount. Theending balances of wWork in
process, Finished goods, and Cost of goods sold are
$232,000,$162,400, and $185,600, respectively. Assuming that
$720,000 is to be allocated to each of theseaccounts based on
ending balances, which of the following is correct?
1. Work in process will be debited for $232,000.2. Finished
goods will be credited for $201,600.3. Finished goods will be
credited for $162,400.4. Cost of goods sold will be credited for
$185,600.
l. A $516,000 credit balance in Manufacturing overhead at the
end of the period means which ofthe following?
1. Manufacturing overhead is $516,000 overapplied.2.
Manufacturing overhead applied is $516,000.3. Manufacturing
overhead is $516,000 underapplied.4. Actual overhead is
$516,000.
Solution
Question 3
-
Textbook, Exercise 3-15, pages 110-111.
Solution
Question 4
Textbook, Problem 3-30, pages 122-123.
Solution
Question 5
Textbook, Problem 3-21, pages 114-115.
Solution
Question 6
Textbook, Problem 3-25, pages 118-119.
Solution
Question 7
Textbook, Question 3-2, page 104.
Solution
Question 8
Textbook, Question 3-18, page 105.
Solution
-
Self-test 2
Solution 1
Computer solution
Requirement 1
a. Estimated overhead cost Estimated direct labour cost =
$480,000 $640,000 = 75%
Actual manufacturing overhead costs:
Indirect labour $160,000
Property taxes 42,000
Depreciation of equipment 65,000
Maintenance 50,000
Insurance 35,000
Rent, building 160,000
Total actual costs $512,000
Applied manufacturing overhead costs:
$680,000 * 75% 510,000
Underapplied overhead (DR) ($2,000)
Requirement 2 and Solution printout
MA1: MODULE 2: QUESTION 1: requirements 2 and 3CGA-CANADA
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Requirement 3 and Formula printout
-
The manufacturing overhead variance is closed to the Cost of
goods sold account if the overhead isunderapplied for the period.
In periods of abnormally high production the overapplied overhead
should beallocated to Work in process, Finished goods, and Cost of
goods sold so that inventories are not measuredabove cost. Under-
or overapplied overhead can be deferred to the Balance Sheet when
interim financialstatements are produced during the year or where
large seasonal variations occur in output, but relatively
-
constant overhead costs exist and predetermined overhead amounts
are used to smooth out fluctuations inoverhead costs. Resulting
significant debits or credits can be carried forward to year-end,
and a finaldisposition of these amounts can be made using either of
the other two methods discussed above.
If the choice were made to adjust Cost of goods sold, the
adjusted figure would be $1,754,000
Requirement 4
Direct materials $ 4,300Direct labour 6,600Overhead applied
($6,600 75%) 4,950Cost to manufacture $ 15,850
$15,850 140% = $22,190 price to the customer
Requirement 5
The amount of overhead cost in ending Work in process would
be:
$29,640 direct labour cost 75% = $22,230
The amount of direct material cost in ending Work in process
would be:
Total ending Work in process $ 78,000Deduct: Direct labour
$(29,640) Manufacturing overhead 22,230 51,870 $ 26,130
The completed schedule of costs in ending Work in process would
be:
Direct materials $ 26,130Direct labour 29,640Manufacturing
overhead 22,230Total Work in process $ 78,000
Source: Ray H. Garrison, Eric W. Noreen, G.R. Chesley, and
Raymond F. Carroll, Solutions Manual toaccompany Managerial
Accounting, Sixth Canadian Edition. Copyright 2004, by McGraw-Hill
Ryerson Limited.Adapted with permission.
-
Self-test 2
Solution 2
Multiple choice
a. 2)
$12.20 300 = $3,660
b. 3)
Calculating an overhead rate based on machine-hours is the most
constant (about $2.50), whichindicates a strong cause and effect
relationship between the two costs.
c. 3)
Using a predetermined overhead rate provides a mechanism for
assigning overhead costs to jobsas they are completed.
d. 4)
$4,000 + $6,400 + $8,000 = $18,400 cost of goods sold for
April.
e. 1)
$18,000 = 1.5x + x$18,000 = 2.5xx = $7,200 direct labour
f. 2)
When overhead is underapplied, actual overhead incurred is
greater than what has been applied.Therefore, the underapplied
amount, equal to the difference between actual and applied, isadded
or debited to Cost of goods sold and credited to the Manufacturing
overhead account.
g. 3)
$63,000 $90,000 = .70 or 70% predetermined overhead rate.
h. 1)
The Manufacturing overhead account is debited for actual
overhead costs, which include thefollowing: Indirect factory
materials $48,000 + Factory depreciation $86,000 +
Factorysupervisors' salaries $36,000 + Supplies, factory $7,000 =
$177,000 debited to Manufacturingoverhead.
i. 2)
The Work in process account is debited for applied overhead of
$182,000.
j. 1)
$232,500 1.2 = $279,000 applied; $279,000 $273,060 = $5,940
overapplied.
k. 2)
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Work in process will be credited for a 40% share ($232,000
$580,000 = 40%) of the $720,000= $288,000; Finished goods will be
credited for a 28% share ($162,400 $580,000 = 28%) ofthe $720,000 =
$201,600; and Cost of goods sold will be credited for a 32% share
($185,600 $580,000 = 32%) of the $720,000 = $230,400.
l. 1)
The balance in Manufacturing overhead at the end of the period
reflects under- or overappliedoverhead. A credit balance of
$516,000 indicates that overhead applied was greater than
actualmanufacturing overhead by $516,000 (in other words, $516,000
overapplied).
-
Self-test 2
Solution 3
Exercise 3-15
Requirement 1
Milling Department:
Assembly Department:
Requirement 2
Overhead appliedMilling Department: 90 MHs $8.50 per MH
$765Assembly Department: $160 125% 200Total overhead cost applied
$965
Requirement 3
Yes; if some jobs required a large amount of machine time and
little labour cost, they would be chargedsubstantially less
overhead cost if a plantwide rate based on direct labour cost were
being used. It appears, forexample, that this would be true of job
407 which required considerable machine time to complete,
butrequired only a small amount of labour cost.
Source: Ray H. Garrison, G.R. Chesley, and Raymond F. Carroll,
Solutions Manual to accompany ManagerialAccounting, Eight Canadian
Edition. Copyright 2010, by McGraw-Hill Ryerson Limited. Reproduced
withpermission.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Self-test 2
Solution 4
Problem 3-30
Requirement 1
1.
$150,000 direct materials cost 160% = $240,000 applied.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
2.
3.
Southworth Company
-
Schedule of Cost of Goods Manufactured
Direct materials:
Raw materials inventory,
beginning............................................... $
18,000
Purchases of raw
materials..........................................................
142,000
Materials available for
use............................................................
160,000
Raw materials inventory,
ending...................................................
10,000
Materials used in
production.........................................................
$150,000
Direct
labour...............................................................................
216,000
Manufacturing overhead applied to work in
process......................................................................................
240,000
Total manufacturing
cost..............................................................
606,000
Add: Work in process,
beginning...................................................
24,000
630,000
Deduct: Work in process,
ending...................................................
40,000
Cost of goods
manufactured.........................................................
$590,000
4.
Cost of Goods
Sold................................................................
3,000
Manufacturing
Overhead.........................................................
3,000
Schedule of cost of goods sold:
Finished goods inventory,
beginning........................................ $ 35,000
Add: Cost of goods
manufactured........................................... 590,000
Goods available for
sale.........................................................
625,000
Finished goods inventory,
ending............................................ 25,000
Unadjusted cost of goods
sold................................................ 600,000
Add underapplied
overhead....................................................
3,000
Adjusted cost of goods
sold....................................................
$603,000
5.
Southworth CompanyIncome Statement
Sales...............................................................................
$1,000,000
Cost of goods
sold............................................................
603,000
Gross
margin....................................................................
397,000
Selling and administrative expenses:
Salaries
expense..............................................................
$145,000
Advertising
expense..........................................................
130,000
Depreciation
expense........................................................
5,000
Rent
expense...................................................................
18,000
Miscellaneous
expense......................................................
17,000 315,000
Operating
income..............................................................
$ 82,000
6.
Direct
materials.........................................................................................
$ 3,600
Direct labour (400 hours $11 per
hour).................................................... 4,400
Manufacturing overhead cost applied (160%
$3,600)................................. 5,760
Total manufacturing
cost............................................................................
13,760
-
Add markup (75%
$13,760)....................................................................
10,320
Total billed price of Job
218........................................................................
$24,080
$24,080 500 units = $48.16 per unit.
Source: Ray H. Garrison, G.R. Chesley, and Raymond F. Carroll,
Solutions Manual to accompanyManagerial Accounting, Eighth Canadian
Edition. Copyright 2010, by McGraw-Hill RyersonLimited. Reproduced
with permission.
-
Self-test 2
Solution 5
Problem 3-21
1. and 2.
3. Manufacturing overhead was overapplied by $3,000 for the
year. This balance would be allocated
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
between Work in Process, Finished Goods, and Cost of Goods Sold
in proportion to the currentperiod costs in these accounts. The
allocation would be:
Work in process, 12/31.................................... $
21,000 5.6 %
Finished goods, 12/31......................................
55,000 14.6
Cost of goods sold, 12/31.................................
300,000 79.8
$376,000 100.0 %
Manufacturing
overhead.......................................................
3,000
Work in process (5.6% $3,000)..................................
$ 168
Finished goods (14.6% $3,000)...................................
$ 438
Cost of goods sold (79.8% $3,000)..............................
$2,394
4.
Fantastic Props, Inc.Income Statement
For the year ended December 31
Sales.....................................................................................
$450,000
Cost of goods sold ($300,000
$2,394).................................... 297,606
Gross
margin.........................................................................
152,394
Selling and administrative expenses:
Salaries
expense.................................................................
$75,000
Depreciation
expense..........................................................
5,000
Insurance
expense..............................................................
800
Shipping
expense................................................................
40,000 120,800
Operating
income...................................................................
$ 31,594
Source: Ray H. Garrison, G.R. Chesley, and Raymond F. Carroll,
Solutions Manual to accompany ManagerialAccounting, Eighth Canadian
Edition. Copyright 2010, by McGraw-Hill Ryerson Limited. Reproduced
withpermission.
-
Self-test 2
Solution 6
1. Preparation Department predetermined overhead rate:
2. Fabrication Department predetermined overhead rate:
3. Preparation Department overhead applied: 350 machine-hours
$5.20 per machine-hour..................................
$1,820Fabrication Department overhead applied: $1,200 direct
materials cost 180%................................................
2,160Total overhead
cost...........................................................................
$3,980
Total cost of Job 127:
Preparation Fabrication TotalDirect
materials............................. $ 940 $1,200 $2,140Direct
labour................................. 710 980 1,690Manufacturing
overhead................. 1,820 2,160 3,980Total
cost..................................... $3,470 $4,340 $7,810
Unit product cost for Job 127:
4. Preparation FabricationManufacturing overhead cost
incurred............................. $390,000
$740,000Manufacturing overhead cost applied: 73,000 machine-hours
$5.20 per machine-hour......... 379,600 $420,000 direct materials
cost 180%........................ 756,000Underapplied (or
overapplied) overhead......................... $ 10,400
$(16,000)
Source: Ray H. Garrison, G.R. Chesley, and Raymond F. Carroll,
Solutions Manual to accompany ManagerialAccounting, Eighth Canadian
Edition. Copyright 2010, by McGraw-Hill Ryerson Limited. Reproduced
withpermission.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Self-test 2
Solution 7
Question 3-2
Job-order costing is used in situations where many different
products or services that require separate costingare produced each
period. Process costing is used in situations where a single,
homogeneous product, such ascement, bricks, or gasoline, is
produced for long periods.
Source: Ray H. Garrison, G.R. Chesley, and Raymond F. Carroll,
Solutions Manual to accompany ManagerialAccounting, Eighth Canadian
Edition. Copyright 2010, by McGraw-Hill Ryerson Limited. Reproduced
withpermission.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
-
Self-test 2
Solution 8
Question 3-18
Yes, predetermined overhead rates in general smooth product
costs when costs change during a year or whereproduction volume
varies. The predetermined overhead rate is computed by using the
yearly estimated totaloverhead divided by the estimated base for
the year. This rate is used to calculate the product cost for
eachperiod. The product cost becomes an average cost rather than an
actual cost which would include thefluctuations.
Source: Ray H. Garrison, G.R. Chesley, and Raymond F. Carroll,
Solutions Manual to accompany ManagerialAccounting, Eighth Canadian
Edition. Copyright 2010, by McGraw-Hill Ryerson Limited. Reproduced
withpermission.
Course Schedule Course Modules Review and Practice Exam
Preparation Resources
m02introLocal
DiskF:\Courses\2011-12\CGA\MA1\06course\m02intro.htm
m02t01Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t01.htm
m02t02Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t02.htm
m02t03Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t03.htm
m02t04Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t04.htm
m02t05Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t05.htm
m02t06Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t06.htm
m02t07Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02t07.htm
m02summaryLocal
DiskF:\Courses\2011-12\CGA\MA1\06course\m02summary.htm
m02selftestLocal
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftest.htm
m02selftestsol1Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol1.htm
m02selftestsol2Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol2.htm
m02selftestsol3Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol3.htm
m02selftestsol4Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol4.htm
m02selftestsol5Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol5.htm
m02selftestsol6Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol6.htm
m02selftestsol7Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol7.htm
m02selftestsol8Local
DiskF:\Courses\2011-12\CGA\MA1\06course\m02selftestsol8.htm