MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001
41

MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

Jan 02, 2016

Download

Documents

Alberta George
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

MODELING AND ANALYSIS OFMANUFACTURING SYSTEMS

Session 12 MACHINE SETUP AND

OPERATION SEQUENCING E. Gutierrez-Miravete

Spring 2001

Page 2: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

INTRODUCTION

• WHOLE SYSTEM DESIGN STRATEGIES VS INDIVIDUAL CELL/WORKSTATION DESIGN STRATEGIES

• QUESTION: HOW TO TOOL THE MACHINE AND THEN SEQUENCE PRODUCTION ACTIVITIES IN IT?

• GOAL: MAXIMIZE PRODUCTIVITY

Page 3: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

OPORTUNITIES

• SEQUENCE BATCHES SO AS TO MINIMIZE TOOLING CHANGEOVERS

• SEQUENCE ACTIVITIES SO AS TO MINIMIZE IDLE TIMES

• OPTIMIZE CELL LAYOUT SO AS TO MINIMIZE ASSEMBLY TIME

Page 4: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

SEQUENCING AND OPTIMIZATION

MANY SEQUENCING PROBLEMS IN MANUFACTURING CELL PLANNING ARE CLASSIC OPTIMIZATION PROBLEMS

Page 5: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

CELL VS SYSTEM• BOTH, CLEVER SEQUENCING OF

OPERATIONS AND OVERALL SYSTEM DESIGN ARE IMPORTANT FOR SUCCESS IN MANUFACTURING

• TIME FRAMES– FOR OVERALL SYSTEM DESIGN: WEEKS

OR MONTHS (LONG TERM)– FOR SEQUENCE DESIGN:

MINUTES/HOURS (SHORT TERM)

Page 6: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TASK ASSIGNMENT

Page 7: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

LINEAR ASSIGNMENT PROBLEM

• GOAL:

– TO DISTRIBUTE N TASKS AMONG N WORKERS SO AS TO MINIMIZE COST

• CONSTRAINTS:

– 1 TASK PER WORKER

– 1 WORKER PER TASK

Page 8: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

COST MATRIX C

• ROWS: WORKERS

• COLUMNS: MACHINES

• SUMMARIZES THE ASSIGNMENT COSTS

Page 9: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

LAP: MATHEMATICAL FORMULATION

• minimize

Ci j cij xij

• subject to:

i xij = 1 (for all tasks)

j xij = 1 (for all workers)

Page 10: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

Facts

• IF A CONSTANT IS ADDED TO EVERY ELEMENT OF A ROW OR COLUMN

OF C, THE OPTIMAL SOLUTION DOES NOT CHANGE BUT ITS VALUE CHANGES BY THE ADDED CONSTANT

• IF ALL cij > 0, ANY SOLUTION WITH COST = 0 MUST BE OPTIMAL

Page 11: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

Hungarian Algorithm

• Proceeds by adding and substracting constants from rows and columns so as to maintan a non-negative cost matrix. When a feasible solution is found using only 0 cost cells, optimum has been found.

Page 12: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

HA Steps

• STEP 1: COST REDUCTION BY CONSTRUCTION OF THE REDUCED COST MATRIX. THE RCM IS OBTAINED BY SUBSTRACTING FIRST THE MINIMUM ELEMENT IN EACH ROW FROM ALL ELEMENTS IN THE ROW THEN DOING LIKEWISE WITH COLUMNS

Page 13: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

HA Steps cont’d

• STEP 2: SEARCH FOR A FEASIBLE SOLUTION USING ONLY THE 0’S IN THE RCM . IF THIS SUCCEEDS, OPTIMAL SOLUTION HAS BEEN FOUND. IF ALL 0’S CAN BE COVERED WITH LESS THAN n HORIZONTAL AND VERTICAL LINES, CONTINUE.

Page 14: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

HA Steps cont’d

• STEP 3: FURTHER REDUCTION. FIND THE MINIMUM UNCOVERED ELEMENT. SUBSTRACT THIS REDUCED COST FROM EACH UNCOVERED ELEMENT AND ADD IT TO EACH TWICE-COVERED ELEMENT. GO TO 2.

• Example 8.1, Table 8.1, Fig. 8.1, pp. 263-

Page 15: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TASK SEQUENCING

Page 16: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TWO CLASSES OF PROBLEMS

• EVALUATE CHANGEOVER COSTS WHEN COSTS ARE COMPLETELY DETERMINED BY THE CURRENT JOB SETUP AND THE NEXT JOB TO BE LOADED

• EVALUATE COSTS WHEN THE ENTIRE SEQUENCE OF JOBS MUST BE KNOWN

Page 17: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

COMPLETE CHANGEOVERS

• N JOBS ARE TO BE PERFORMED ON ONE MACHINE

• UNIT PROCESSING TIME AND BATCH SIZE DETERMINE TOTAL PROCESSING TIME

• CHANGEOVER TIMES DEPEND ONLY ON CURRENT AND NEXT PRODUCT

• TOTAL SETUP TIME DEPENDS ON JOB SEQUENCE

Page 18: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TRAVELING SALESMAN PROBLEM

• A SALESMAN MUST VISIT EVERY CITY IN HIS/HER TERRITORY THEN RETURN HOME IN SUCH A WAY THAT THE SMALLEST POSSIBLE TOTAL DISTANCE IS TRAVELLED.

• TSP CAN BE VISUALIZED WITH A GRAPH OF NODES (CITIES) AND ARC LENGTHS (DISTANCES)

Page 19: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TRAVELING SALESMAN PROBLEM

• DISTANCE BETWEEN CITIES i & j = cij

• ALL ARCS ARE BIDIRECTIONAL

• NO SUBTOURS ALLOWED

• FIVE CITY COMPLETE TSP GRAPH Fig 8.2a

• FIVE CITY POSSIBLE TOUR GRAPH Fig 8.2b

Page 20: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

SOLUTION OF THE TSP• CLASSICAL OPTIMIZATION

TECHNIQUES ARE HARD TO APPLY WHEN N IS LARGE (See Eqn 8.5-)

• HEURISTIC METHODS ARE MOST FREQUENTLY USED– NO SUBTOUR CONSTRAINT IS

TEMPORARILY RELAXED– SOLVE RESULTING OPTIMIZATION

PROBLEM

Page 21: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TSP BY CLOSEST INSERTION ALGORITHM

1.- SELECT A STARTING CITY

2.- PROCEED THROUGH N-1 STAGES ADDING A NEW CITY AT EACH STAGE. THE NEW CITY IS SELECTED FROM THOSE CURRENTLY UNASSIGNED SUCH THAT IT IS CLOSEST TO ANY CITY IN THE ACCUMULATED PARTIAL SEQUENCE

• Example 8.2; Fig 8.3, pp. 268-

Page 22: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TSP BY MINIMUM SPANNING TREE

• A MST IS ANY SET OF N-1 ARCS THAT TOUCH EACH NODE AND HAVE THE SMALLEST SUM OF COSTS FOR ANY SUCH SET

• BY MODIFYING THE MST SO THAT EACH NODE IS CONNECTED EXACTLY BY TWO ARCS IN A CONNECTED TREE OBTAIN TSP SOLUTION

Page 23: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

TSP BY SUBTOUR INTEGRATION

• START WITH A SOLUTION TO THE ASSIGNMENT PROBLEM

• TRY TO CONNECT TWO SUBTOURS AT A TIME BY SWITCHING ARCS

• ONCE ALL LAP SUBTOURS ARE COMBINED, GOT TSP SOLUTION

• Fig 8.4

Page 24: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

PARTIAL CHANGEOVERS• N JOBS ARE TO BE PERFORMED ON ONE

MACHINE CAPABLE OF HOLDING M TOOLS

• JOB j REQUIRES TOOLS Aj• TOTAL NUMBER OF TOOLS REQUIRED

EXCEEDS M (TOOL CHANGES REQUIRED)• NO JOB REQUIRES MORE THAN M TOOLS• AT EACH JOB COMPLETION SOME TOOLS

MAY HAVE TO BE REMOVED AND NEW TOOLS ADDED

• Fig 8.5

Page 25: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

OBJECTIVE

TO ORDER JOBS AND TOOL CHANGEOVERS TO MINIMIZE THE TOTAL NUMBER OF TOOLS CHANGED ON THE MACHINE

Page 26: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

NOTES

• ALWAYS KEEP M TOOLS ON MACHINE

• THE ORDERING FOR JOBS ON THE MACHINE IS GIVEN

• KEEP TOOL NEEDED SOONEST (KTNS) RULE IS OPTIMAL

• REMOVE ONLY “LONGEST UNTIL NEXT USE” TOOLS

Page 27: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

JOB ORDERING

• IF JOB r USES ONLY A SUBSET OF TOOLS USED BY ITS PREDECESOR s CHANGEOVER IS NOT INCREASED (i.e. OPTIMAL SEQUENCE)

• JOB SEQUENCING PROBLEM IS SIMILAR TO GROUP FINDING IN GT

• THE TOOL-JOB MATRIX

Page 28: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

JOB ORDERING

• SOLUTION METHODS– BINARY CLUSTERING

• Ex 8.3, Tables 8.3, 8.4

– TSP• Table 8.5

Page 29: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

SOLUTION OF THE PARTIAL CHANGEOVER

PROBLEM

• STEP 1: JOB COMBINATION (REDUCTION)

• STEP 2: JOB ORDERING

• STEP 3: TOOL SETUP PLANNING BY KTNS

Page 30: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

INTEGRATED ASSIGNMENT AND SEQUENCING

Page 31: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

QUESTION

• WHAT TO DO WHEN CELL SETUP (TOOLING) AND JOB SEQUENCING ARE RELATED BY NEITHER DICTATES THE OTHER?

• NEED TO:– MAKE A SEQUENCING DECISION and– MAKE A SETUP DECISION

Page 32: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

NOTES

• PROBLEM 1: PLAN SETUP AND OPERATION OF ASSEMBLY CELLS

• PROBLEM 2: SETUP AND SEQUENCE OF A MACHINE (INTERDEPENDENT TOOLS)

• GOAL: TO MINIMIZE CYCLE TIME

• SOLUTION TECHNIQUES: HEURISTICS

Page 33: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

ASSEMBLY CELL LAYOUT AND SEQUENCING

• ASSEMBLY ENVIRONMENTS– MASS PRODUCED SINGLE PRODUCT– MULTIPLE PRODUCTS PRODUCED IN

ALTERNATING LOTS WITH CHANGEOVER REQUIRED

– MIX OF PART TYPES ASSEMBLED SIMULTANEOUSLY IN CELL WITHOUT CHANGEOVER

Page 34: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

REQUIRED

• FIND HOW TO PERFORM THE SET OF TASKS THAT HAVE BEEN ASSIGNED TO A WORKSTATION

Page 35: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

SINGLE PART TYPE

• A SINGLE PRODUCT FRAME

• PRODUCT FRAME HAS N LOCATIONS WHERE PARTS ARE TO BE ADDED

• WORKSTATION HAS N BINS WHERE PART FEEDERS ARE PLACED

• Fig 8.6

Page 36: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

REQUIRED

• ASSIGN FEEDERS TO BINS

• DETERMINE THE ORDER IN WHICH PARTS ARE TO BE ADDED TO FRAME

• PROBLEM CAN BE MODELED AS A 2N-CITY TSP

Page 37: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

BIN ASSIGNMENT AND INSERTION SEQUENCING

• BIN ASSIGNMENT GOAL: MINIMIZE THE LOADED TRAVEL TIME (DISTANCE) FOR THE ASSEMBLER

• INSERTION SEQUENCING GOAL: MINIMIZE THE UNLOADED TRAVEL TIME (DISTANCE) FOR THE ASSEMBLER

• Ex 8.4, Tables 8.6 , 8.7; Ex 8.5, Table 8.8

Page 38: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

MIXED PRODUCTS

• TYPICALLY, SEVERAL PRODUCT TYPES ARE BEING PRODUCED SIMULTANEOUSLY IN THE SAME CELL

• DEMAND PROPORTIONS DETERMINED BY BILL OF MATERIALS FOR END PRODUCTS

Page 39: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

MIXED PRODUCT: UNPACED LINE

• ASSUME – RELATIVE DEMANDS ARE KNOWN– M FRAMES TO BE MADE– pm IS THE PROPORTION OF TYPE m

FRAMES– BINS KEPT ON SAME PLACE

• GOAL: MINIMIZE AVERAGE ASSEMBLY TIME OF PRODUCT

Page 40: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

MIXED PRODUCT: UNPACED LINE

• FOR EACH PART TYPE COMPILE TABLE OF TRAVEL TIMES (Table 8.7)

• COMBINE TABLES BY WEIGHTED AVERAGE

cij = m pm cijm

– pm proportion of type m frames– cijm total travel time per type m frame if

part i is assigned to bin j– Ex. 8.6, Tables 8.9, 8.10

Page 41: MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 12 MACHINE SETUP AND OPERATION SEQUENCING E. Gutierrez-Miravete Spring 2001.

CELL LAYOUT AND SEQUENCING:

INTERDEPENDENT TOOLS• THE NC PUNCH PRESS

– 36 TOOL TOOL TURRET (Fig 8.7)

– PARTS MAY REQUIRE UP TO 200 HITS

– HIT SEQUENCE MAY BE SUBJECT TO PRECEDENCE CONSTRAINTS

• GOAL: LOAD TOOLS AND SEQUENCE HITS TO MINIMIZE PRODUCTION CYCLE

• Ex 8.7, Fig. 8.8, Tables 8.11, 8.12