Page 1 of 62 (230 th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 1 of 62 Minutes of the 230 th meeting of the State Level Expert Appraisal Committee held on 24/03/2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. The 230 th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 24 th March, 2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting: 1. Shri T. P. Singh, Chairman, SEAC. 2. Shri V. C. Soni, Member, SEAC. 3. Dr. Mayuri Pandya, Member, SEAC. 4. Shri Natarajan Pratap, Member, SEAC. 5. Shri V.N.Patel, Member, SEAC. 6. Shri R. J. Shah, Member, SEAC. 7. Shri K. C. Mistry, Secretary, SEAC. The agenda of TOR/Scoping/Category 8 (a) cases, appraisal cases, TOR amendment case, TOR validity extension case and EC Validity extension case was taken up. Eleven (11) cases of TOR/Scoping/Category 8 (a), three (3) appraisal cases, one (1) TOR validity extension case, one (1) TOR amendment case and one (1) EC validity extension case i.e total seventeen cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A, EIA report and other reports. Additional information submitted by the project proponents of twenty five (26) projects were also taken up as agenda item. 1. Aarti Industries Ltd. (Unit-II) Plot No:756/4: A&B, 756/5: A&B, 756/6 & 779, GIDC –Jhagadia, Dist.: Bharuch Appraisal Project / Activity No.: 5(f) Project status: Expansion Chronology of EC Process: This project proposed by M/s: Aarti Industries Ltd. (Unit-II) (herein after Project Proponent – PP) has submitted Application vide their letter dated 21/05/2013. The project was considered for TOR finalization in the meeting of the SEAC held on 20/07/2013. EIA Report was submitted on 09/02/2015. Project / Activity Details: M/s. Aarti Industries Ltd. (Unit-II) has proposed to manufacture basic organic chemicals at Plot No:756/4 A&B, 756/5: A&B, 756/6 & 779, GIDC –Jhagadia, Dist. Bharuch. . The list of proposed products is shown table below :
62
Embed
Minutes of the 230th meeting of the State Level Expert Appraisal ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 1 of 62
Minutes of the 230th meeting of the State Level Expert Appraisal Committee held on 24/03/2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.
The 230th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 24th March, 2015 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting:
1. Shri T. P. Singh, Chairman, SEAC.
2. Shri V. C. Soni, Member, SEAC.
3. Dr. Mayuri Pandya, Member, SEAC.
4. Shri Natarajan Pratap, Member, SEAC.
5. Shri V.N.Patel, Member, SEAC.
6. Shri R. J. Shah, Member, SEAC.
7. Shri K. C. Mistry, Secretary, SEAC.
The agenda of TOR/Scoping/Category 8 (a) cases, appraisal cases, TOR amendment case, TOR validity extension case and EC Validity extension case was taken up. Eleven (11) cases of TOR/Scoping/Category 8 (a), three (3) appraisal cases, one (1) TOR validity extension case, one (1) TOR amendment case and one (1) EC validity extension case i.e total seventeen cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A, EIA report and other reports.
Additional information submitted by the project proponents of twenty five (26) projects were also taken up as agenda item.
This project proposed by M/s: Aarti Industries Ltd. (Unit-II) (herein after Project Proponent – PP)
has submitted Application vide their letter dated 21/05/2013.
The project was considered for TOR finalization in the meeting of the SEAC held on 20/07/2013.
EIA Report was submitted on 09/02/2015.
Project / Activity Details:
M/s. Aarti Industries Ltd. (Unit-II) has proposed to manufacture basic organic chemicals at Plot No:756/4A&B, 756/5: A&B, 756/6 & 779, GIDC –Jhagadia, Dist. Bharuch. . The list of proposed products is shown table below :
Page 2 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 2 of 62
SR NO LIST OF PRODUCTS QUANTITY IN MT/MONTH (TOTAL)
I Chlorination Products 1 Monochlorobenzene/
Ortho dichloro benzene/ Para dichloro benzene OR
6000
2 123/124 Trichloro benzene OR 3 Ortho chloro toluene /
Para chloro toluene OR 4 2-Chloro 4-Nitro Toluene OR 5 6-Chloro 2-Nitro toluene/
4-Chloro 2-Nitro Toluene OR 6 Pivalyl Chloride OR 7 2-Ethyl Hexanyl Chloride OR 8 Iso Nonyl Chloride OR 9 Di Isopropyl Benzene OR 10 Similar Range of Aromatic Chlorinated Products II Hydrogenated Products
1 Ortho Toludene OR 3000
2 Meta/Ortho/Para Chloro Aniline OR 3 3,4 Di Chloro Aniline/ 2,3 Di Chloro Aniline / 2,5
Di Chloro Aniline OR 4 2,4 Di Chloro Aniline/ 2,6 Di Chloro Aniline / 3,5
Di Chloro Aniline OR 5 2,4,5 Tri Chloro Aniline OR 6 Meta /Ortho / Para Phenylene Di Amine OR 7 3,4 Diamino Diphenyl Ether / 4,4 Diamino
Diphenyl Ether OR 8 Ortho /Para/ Meta Anisidine OR 9 Chloro Fluoro Aniline OR 10 Ortho / Para / Meta Cumidine OR 11 Para/ Meta Amino Phenol OR 12 Toludines OR 13 Aniline OR 14 Para/Meta/Ortho Floro Anilin OR 15 Di Floro Aniline (1:3) OR 16 Di Floro Benzene (1:3) OR 17 4-Floro-N-Isopropyl Aniline OR 18 4-Chloro-Nlsopropyl Aniline OR 19 2 Methoxy 4 Nitro Aniline (Scarlet R- from
partial hydrogenation of 24 Dinitro Anisole) OR 20 2,4 Di Amino Anisole OR 21 N-N Dises Butyl PPDA OR 22 Meta Xilidine OR 23 4 Chloro 2,5 Dimethoxy Aniline OR 24 N,N Di Sec tertiary Butyl Paraphenylene
Diamine OR 25 Other reduction products III Nitration Products 1 3,4 Di Chloro Nitro Benzene/2,5 Di Chloro Nitro
Benzene/2,3 Di Chloro Nitro Benzene OR 2000
2 2,4,5 Tri Chloro Nitro Benzene/2,3,4 Tri Chloro Nitro Benzene
Page 3 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 3 of 62
3 4-Nitro N- methyl Phthalimide 4 2 EHN (Ethyl Hexanol Nitration) IV Nitro Anisoles 1 Ortho Nitro Anisole OR
1200
2 Para Nitro Anisole OR 3 2,4-Di Nitro Anisole OR 4 2 Methoxy 5 Chloro Nitro Benzene (from 25
DCNB) V Calcium Chloride (90% basis) Or HCI (30%) 6000 or 12106 VI De Nitro Chlorination 1 2,6 Di Chloro Floro Benzene
Phenol of 41 MT/Month will be sent to M/s: Apex Pharmachem Pvt. Ltd. plot no. 193/1, Phase-II, GIDC
Vapi.
Observations/Discussions:
The project was appraised as per the prescribed TOR, EIA report, information submitted and presentation
made by the project proponent. While discussing about compliance of the existing environmental
conditions, PP informed that they have been issued 3 notices by GPCB. On asking about the reason and
compliance, PP could not furnish the copies of the same and compliance report thereof. Committee asked
to submit the copies and point wise compliance report of notices served by the GPCB. Safety aspects of
the inflammable and toxic chemicals have been discussed. PP presented that hydrogen and liquid
chlorine will be taken through pipeline. The committee suggested to provide proper height and barrier for
the transportation of Chlorine and to take all safety measures related to chlorine conveyance. The
committee also suggested to provide automatic shut-off mechanism linked with pressure increase in
chlorine pipeline. Committee noted that PP has not covered baseline study of VOC which is a project
specific parameter. Committee asked to submit compliance of relevant TOR regarding baseline study. It
was observed that they have not included Coal linkage, type of coal, coal handling management, fly ash
management etc in the EIA report.
The study period considered for EIA was March 2014 to May 2014. Air quality monitoring was carried out
at six locations. The average concentration of PM10, PM2.5, SO2 and NOx, HCl are within prescribed limit
at all locations. As per the metrological data it shows that the average wind speed during study period
was 2.76 m/s with wind direction blowing to NE. The HCl and Chlorine are monitored on project site only
and values were found 6 μg/m3 and 1 μg/m3 respectively. The soil samples of various locations at and
around the project site are analyzed and reported in EIA. Report reveals that the soil quality is appropriate
Page 5 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 5 of 62
and no abnormality in terms of soil contaminants is reported. Estimation of emissions from the plant has
been made by Industrial Source Complex – Short Term (ISC-ST3) model. Dispersion modeling studies
reveals that the maximum GLC occurs in the NE, East & South direction. The maximum incremental
increase in concentration at a distance of 1 Km for SO2 & PM is 3.0 and 1.7 μg/m3, whereas in NOx it is
1.1 μg/m3 at a distance of about 1 Km in the East. Concentration of HCl & Cl2 was observed to be 0.07
μg/m3 & 0.011 μg/m3 at a distance of 383 m in the east. Unit has also included Risk Assessment, Disaster
Management Plan, Occupational Health and Safety management in EIA report. Scenarios identified for
consequence analysis are Release of Solvents, Release of Hydrogen and Chlorine. While discussing
about spent solvent, PP informed that solvent recovery will be apprx.98% which will be carried out in-
house. After detailed deliberations the Committee decided to appraise the project on satisfactory
submission of the following:
1. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure notices etc. served by the GPCB to the existing unit in last five years and actions taken thereafter for prevention of pollution. Give Point wise compliance status of all the conditions stipulated in CTE/CCA of GPCB.
2. Baseline study for VOC in the study area, Modelling indicating the likely impact on ambient air quality due to proposed activities and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
3. Complete water balance diagram (including reuse-recycle) i.e. Exact quantity of Fresh water requirement and quantity of water to be recovered from evaporator, RO permeate, steam condensate, process condensate etc. Give characteristics of treated waste water to be utilised for gardening/plantation on land within premises.
4. Technical details of proposed STP and details about availability of sufficient open land and suitability for utilizing treated effluent for plantation / gardening. How it will be ensured that treated effluent won't flow outside the premises linked with storm water during high rainy days.
5. A confirmed coal linkage along with the supportive documents (Copy of the firm MOU signed between the coal supplier and the project proponent) of long term supply of coal for the project requirements should be provided. Give quantity (MT/day) and quality (CV, Sulphur content, Ash content, etc,) of coal to be used along with flue gas emission details.
6. Plan for compliance to coal handling guidelines of the GPCB. Detailed plan for prevention and control of fugitive emission / dusting at each and every stage of coal handling including unloading / loading, transportation, stacking/storage/conveyance/ transfer within the plant along with detailed specifications & schematic diagram of water sprinkler system arrangement.
7. Technical details of ESP along with its adequacy, details of its operational controls with DCS, system for online monitoring of the pollutants from the stack etc. Details of provisions to be kept in ESP to ensure that in any case the air emission does not cross the GPCB norms including provision of standby field in the ESP, preventive maintenance, failure / tripping control system, guarantee from the ESP supplier, alternative arrangements in case of the failure / tripping of the ESP etc.
8. Fly ash management plan and copies of MOU / agreements done with actual consumers regarding utilization of fly ash & bottom ash etc. should also be incorporated.
9. Complete Management plan for By-products/Spent acids to be generated along with characteristics of the by-products and feasibility of their actual use in respective products as a raw material. Copies of agreement / MoU / letter of intent from end-users/buers showing their willingness to accept said by-
Page 6 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 6 of 62
product / waste with their monthly requirements.
10. Proposal for provision of online monitoring system for monitoring of the pollutants from the flue gas and process gas stacks with an arrangement to reflect gaseous emission parameters on company's server, which can be accessed by the GPCB on real time basis and time bound action plan for the same.
2. Glade One Vill:Modasar & Nani Devti, Sanand, Ahmedabad
Appraisal
It is a proposed township and area development project comprising of 517 nos. of villas, a restaurant with
100 seats capacity and golf club. Land area of the project is 9,82,688.0 m2 and built up area will be
73,441.49 m2. The proposed project falls in project activity 8(b) as per the schedule of EIA
Notification,2006.
The project was taken up in the SEAC meeting held on 18/07/2014 and during the meeting, the project proponent was asked to submit the exact aerial distance of the project site from the Nal Sarovar Bird Sanctuary. The project proponent was instructed not to carry out any construction or enabling activities in violation of the EIA Notification, 2006 before obtaining Environmental Clearance from the SEIAA-Gujarat. After detailed discussion, the project proponent was asked to include the Terms of Reference, prescribed during the meeting, in the EIA study to be done covering 5 km radius from the boundary of the proposed project site.
The project proponent submitted the EIA report prepared by Ramans Enviro Services Pvt. Ltd. to this office on 12/02/2015.
Details of the proposed project as presented before the committee is tabulated below:
Sr. No.
Particulars Details
1. Proposal is for New Project 2. Type of Project Residential 3. Project / Activity
No. [8(a) or 8(b)] 8(b)
4. Name of the project
“Glade One” Development of Residential area with Golf Course
5. Name of Developer
Safal Construction Pvt. Ltd.
6. Estimated Project Cost (Rs. In Crores)
@ Rs 300 Crores
7. Whether construction work has been initiated at site? If yes, details thereof
Construction work has not yet been started.
8. Project Details Luxurious bungalows for higher income group in a plot area @ 525 m2. It will also have golf course and mixed use areas like restaurant, event lawns, internal roads and other such benefits of the residents of the proposed project area.
9. Building Details Nos. of Buildings: 1 for club house with area around 1,825 m2. Nos. of residential plots: @517 units(No construction to be carried out by the
Page 7 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 7 of 62
builder) Scope of buildings/blocks: The Residential plot will accommodate bungalows of G+1. No. & type of Commercial Units: Nil Details of amenities if any : Golf Course, restaurant, internal roads.
10. No. of expected residents / users
At full occupancy number of persons will be 2585. However, being a weekend residential project considering 30% occupancy number of users during weekend will be 776.
11. Water & waste water details during construction phase
Water requirement (KL/day): 44.5 Source of water: By Borewell Waste water generation quantity (KL/day): 10.53 Mode of disposal: Soak pit Details of reuse of water, if any: W/W generated from washing of
equipment will be reused for curing after necessary treatment.
12. Water & waste water details during operation phase
Total water requirement (KL/day): 1401.78 (residential-139.68 KL/day, restaurant-5.60 KL/day, function/event lawn-35.0 KL/day, estate staff & visitors-19.5 KL/day, Golf course maintenance & green belt development – 1,202.0 KL/day)
Fresh water requirement (KL/day): 1,241.96 Source of water: Narmada Water Resource Supply & Kalpsar Department Waste water generation quantity (KL/day): 160.0 Mode of disposal: will be treated in the proposed onsite STP and treated
sewage will be reused for green belt development. In case of STP provision, capacity of STP: 8 nos. of decentralized STP of
50 KL/day capacity. STP Technology: MBBR technology followed by MBR and disinfection
system. Purposes for treated water utilization: Green belt development. Quantity of treated water to be reused:159.82 KL/day Provision of dual plumbing system (Yes/No): No Quantity and type (treated/untreated)of water to be discharged: Treated
sewage will be used for development of greenbelt and during the monsoon season the treated sewage confirming to GPCB norms will be discharged into the storm water drain.
13. Status of water supply and drainage line
Water requirement will be met through water supply from Narmada Water Resource Supply & Kalpsar Department. Sewage to be generated will be treated in the proposed onsite decentralized STPs within premises and treated sewage will be used for greenbelt development.
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil
There will be generation of @ 5.83 lacs m3 of surplus soil during excavation which will be 100% utilized for filling, leveling as well as
landscaping purposes within the project site.
Other excavated earth Construction debris Steel scrap Discarded packing materials
Page 8 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 8 of 62
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste The municipal solid waste will be around 1.5 MT/day considering 10% occupancy for the
weekend residential plots. STP sludge will be used as manure.
Wet waste STP Sludge
Details of segregation if to be done: No Capacity and no. of community bins to be placed within premise: 2 nos. of
bins with 20 lit. capacity to each of residential plot. Landfill site where waste will be ultimately disposed by local authority: It
will be sent to the Sanitary Landfill Site of AMC through to recognized contractor.
15. Parking Details There will be a provision of at least 2 cars parking space for each residential plot and for club house(accommodating about 200 persons max.) there will be a provision for car parking as per the NBC requirement.
16. Traffic Management
Traffic survey was carried out at the approach road i.e Sanand- Bavala road in the vicinity of the proposed project site for describing traffic density. The traffic survey shows existing traffic @ 81 PCU/hour for sanand -bavala road. These roads can accommodate @ 1500 PCU/ hour as per specification given IRC 86:1983.
17. Energy Requirement, Source and Conservation
Power supply: From Uttar Gujarat Vij Company Limited Maximum demand:100 KVA during construction phase and during the
operation phase it will be 3200 KVA(To be availed in phased manner along with the development of residential plots)
DG Sets: No. and capacity of the DG sets: 1×125 KVA Fuel & its quantity: LDO - 15 lit/hr.
18. Fire and Life Safety Measures
All the necessary fire fighting arrangements will be made as per the requirement of NBC.
19. Rain Water Harvesting (RWH)
Details on proposed rain water harvesting system along with a calculation on available rain water will be a part of EIA report.
20. Green area details
Total Green belt/Green Area will be @ 1 lakh sq.m. Which is @10% of the total plot area. There will be development of Golf Course in @ 2.98 lakh sq.m area which will add to the lawn covered area of the project site.
21.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Budgetary allocation of Rs. 9 lakhs /annum is proposed for monitoring of ambient air quality, soil quality, noise, raw & treated sewage.
During the meeting, it was presented that the project site is at a distance of about 32 km from Nal Sarovar Bird Sanctuary & about 23 km from Thol Bird Sanctuary. The committee was of the view that the project proponent should ensure that fresh water utilization for maintenance of Golf course is as minimum as possible by use of harvested rain water for the purpose. At this the project proponent replied that provision of 12 artificial lakes, which are interconnected, has been made to store the rain water which will be used for maintenance of Golf course. After detailed discussion, it was decided to further appraise the project only after submission of the following:
Page 9 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 9 of 62
1. How it will be ensured that the utilization of fresh water from Narmada Water Resource Supply & Kalpsar Department for maintenance of Golf Course shall be minimized by use of harvested rain water. Complete back up details of the artificial lakes to be created within the premise like number of lakes, their volume & size, water storage capacity, mode of interconnection of the lakes with its line diagram, annual & daily water requirement for maintenance of Golf Course, break up of fresh water & harvested rain water to be used for maintenance of Golf Course etc.
2. Plan for rain water harvesting and ground water recharge with proper scientific calculations considering rainfall in the region, catchment area, land / soil characteristics, ground water recharge rate, duration of rain water harvesting etc. Details of provisions of pre-treatment of the rainwater in the case of surface run off is to be harvested.
3. How it will be ensured that treated/untreated sewage shall not find its way to storm water drain.
4. Detailed survey of endangered species including their habitat, if any in the study area, impacts of the proposed project on the same along with mitigation measures and conservation measures like proposal for creating wetland patches, artificial nests etc. in the project.
The SEIAA, Gujarat has accorded environmental clearance to M/s Indo Overseas Construction Company vide order no. SEIAA/GUJ/EC/8(b)/301/2012 dated 25/10/2012 for the commercial building construction project with total built up area of 1,36,375.29 m2 at T.P.S.No.35, B.No.137,138,187,136,133/2,135,140,38,39, F.P.No.263,264,265,273,316, 317, Moje-Saroli, Ta. Choryasi, Dist:Surat.
The project proponent vide their letter dated 18/04/2014 requested for amendment in the Environmental Clearance order dated 25/10/2012 for the proposed changes in the scope and planning of the project. It was stated that the built up area of the project will be 4,39,628.26 m2 after the proposed changes in the project.
The request of amendment was taken up during the SEAC meeting held on 28/08/2014 and during the meeting it was observed that the built up area of the project after the proposed changes will be 4,39,628.26 m2 which is more than 1,50,000 m2 and covered under the project activity 8(b) as per the schedule of the EIA Notification-2006. During the meeting, after detailed discussion, the Terms of Reference were prescribed for the EIA study to be done covering 5 Km radial distance from the project boundary.
The project proponent submitted the EIA report prepared by M/s Earthcare Enviro Solutions Pvt. Ltd. to this office on 18/02/2015.
Comparison of existing & proposed project details is tabulated below: AS PER GRANTED EC REVISED EC DATA Total Plot Area 69,010.00 m2 69,031.00 m2 Net Plot Area 64,837.00 m2 69,031.00 m2 Built Up Area 1,36,375.29 m2 4,39,628.26 m2 F.S.I. Area 1,13,410.57 m2 2,76,063.97 m2 Ground Coverage Area 18,208.29 m2 30,017.84 m2 Basement Area 14,322.68 m2 1,28,200.62 m2 No. of Floors G + 07 + Basement [Bldg. A]
G + 02 [Bldg. B]
G + 09 [Bldg. A & B & C] Double Basement [Bldg. A, B & C]
Page 10 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 10 of 62
Total No. of Building and Textile Houses (T.H)
Total no. of Bldg.: 02 Nos. Total no. of T.H. : 2732 Nos.
Total no. of Bldg.: 03 Nos. Total no. of T.H. : 3451 Nos.
Maximum Bldg. Height 36.69 m 49.70 m Parking Area 43,761.93 m2 1,41,833.76 m2 Lawn Area 6,902.01 m2 6,902.01 m2 Tree Plantation Area 1,238.85 m2 1,238.85 m2 Total Greenbelt Area 8,140.86 m2 8,140.86 m2 D. G Set 4 x 125 KVA 6 x 125 KVA
CONSTRUCTION PHASE: Water Requirement 15.00 m3/day 16.50 m3/day Wastewater Generation 2.60 m3/day 3.60 m3/day Municipal Solid Waste Generation
45.00 kg/day 60.0 kg/day
Disposal mode of Sewage Soak Pit Soak Pit OPERATION PHASE:
Details of the project as presented before the committee is tabulated below:
Sr. No
Particulars Details
1. Proposal is for Expansion
2. Type of Project Commercial / Township / Area Development
3. Project / Activity No. [8(a) or 8(b)]
8(b)
4. Name of the project
Radha Raman Textile Market
5. Name of Developer
M/s. Indo Overseas Construction Company
6. Estimated Project Cost (Rs. In Crores)
Rs. 427.2 Crore
7. Whether construction work has been initiated at site? If yes, details thereof
Under Construction as per EC granted
Page 11 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 11 of 62
8. Project Details Land / Plot Area (m2): 69,031.0 Net Plot Area (m2): 69,031.0 FSI area (m2): 2,76,063.97 Non FSI area (m2): 1,30,934.18 Total BUA (m2): 4,39,628.2
Permissible Proposed FSI Area 2,77,000 2,76,063.97 Ground Coverage 31,063.95* 30,017.84 Common Plot Area 6,907.21 8140.86 Max. building height -- 49.70
9. Building Details
No. of Buildings: 3 No. of Blocks: 3 Scope of buildings/blocks: Commercial textile houses for textile traders to
store their grey/Finished cloth. 2 level basement + ground floor + 9 floors. No. & size of Residential Units: -- No. & type of Commercial Units: 3451 Nos. of textile houses Details of amenities if any: -
11. Water & waste water details during construction phase
Water requirement (KL/day): 16.50 Source of water: By Borewell Waste water generation quantity (KL/day): 3.60 Mode of disposal: Soak pit Details of reuse of water, if any: W/W generated from washing of equipment
will be reused for curing after necessary treatment. 12. Water & waste
water details during operation phase
Total water requirement (KL/day): 541.0 Fresh water requirement (KL/day): 328.0 Source of water: water supply from S.M.C Waste water generation quantity (KL/day): 433.0 Mode of disposal: U/G drainage line of SMC In case of STP provision, capacity of STP: STP Capacity – 500 KL/Day STP Technology: Anaerobic treatment followed by high oxidation Purposes for treated water utilization: Treated sewage will be utilized for
gardening and toilet flushing Quantity of treated sewage to be reused:1.Gardening (KL/day): 33 2. Flushing (KL/day): 180 Provision of dual plumbing system (Yes/No): Yes Quantity and type (treated/untreated)of water to be discharged: 233.0
KL/day treated sewage will be discharged into the SMC drainage line. Mode of disposal: U/G drainage line of SMC
13. Status of water supply and drainage line
SMC water supply and drainage lines are @ 200.0 m away from the plot boundary.
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 4,070.0 4,070.0 Reuse for developing garden area
Other excavated earth
3,91,011.89 7,396.03 will be used for
Disposed to other project sites
Page 12 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 12 of 62
refilling the low lying
areas within the premises.
Construction debris
4616 2198 Reused as a filler up to plinth level or reused in outer road development
Steel scrap 176 -- Sold to local scrap vendors
Discarded packing materials
110 -- Sold to local vendors
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 1,655.00 Blue colour bucket
Through S.M.C door to door waste collection system
Wet waste 415.60 Green colour bucket
Through S.M.C door to door waste collection system
STP sludge What so ever The settled sludge from the bottom of the collection tank will be used as manure for the garden.
Details of segregation if to be done: Separate bins will be provided to collect dry and wet waste.
Capacity and no. of community bins to be placed within premises: 2.0 m3 in each building
Landfill site where waste will be ultimately disposed by local authority: Khajod Landfill Site of S.M.C.
15. Parking Details Total parking area requirement for the project as per GDCR: 82,819 m2
Parking area requirement for Commercial units as per GDCR: 82,819 m2 Total number of CPS requirement for the project as per NBC : 1,105 Number of CPS requirement for commercial units as per NBC: 1,105 Total Parking area provided (m2) & No. of ECS: 1,41,833.76 m2 & 4,636 ECS Parking area provided in basement (m2) & No. of ECS: 1,25,226.76 m2 &
3,914 ECS Parking area provided in hollow plinth (m2) & No. of ECS: -- Parking area provided as open surface (m2) & No. of ECS: 16,607.00 m2 &
722 ECS. 16. Traffic
Management Width of adjacent public roads: 24.00 m wide road is passing in N direction
and 18.00 m wide road is passing in S direction. Number of Entry & Exit provided on approach road/s: 4 Width of Entry & Exit provided on approach road/s: 7.5 m Minimum width of open path all around the buildings for easy access of fire
tender (excluding the width for the plantation): 7.5 m Width of all internal roads: 7.5 m.
Page 13 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 13 of 62
17. Details of Green Building measures proposed.
Use of fly ash based material, provision of flush tank instead of direct flushing in toilets, provision of aerated cock (foam type) in wash basin and pressure reducing valves in water pipeline, provision of STP, provision of rain water harvesting & ground water recharge schemem.
18. Energy Requirement, Source and Conservation
Power supply Maximum demand: 15000 KVA Connected load: 25 HP Source: D.G.V.C.L
Energy saving measures: Use of LED light and solar light for common area lighting.
DG Sets No. and capacity of the DG sets: 06 x 125 KVA Fuel & its quantity: Low Sulphur High speed Diesel (HSD) & quantity - 55 L/h in each.
19. Fire and Life Safety Measures
Fire extinguishers at each Floor, hose reel, wet riser opening at each floor, yard hydrant, automatic sprinkler system at all floors in passages of both the buildings & in basement. (quantity: 7821 nos., 50 m3 per head cap.) , manually operated electric fire alarm system, automatic fire detection & alarm system, underground static water storage tank of 150 KL capacity, terrace water storage tank of 15 KL
20. Details on staircase
Bldg.
No.
No. of floor
Floor Area (m2)
No. of staircase/ Escalators
Width of
Staircase
(m)
No. of Fire lift Propos
ed
No. of passeng
er Lift
No. of Good
s Lift
Maximum TravelDistance up to the Staircase
A G+09 13949.8
9
06 – Staircases
2.00 04 02 08 28.41
03 – Escalators
1.50
B G+09 13949.8
9
06 – Staircases
2.00 04 02 08 28.41
03 – Escalators
1.50
C 4th - 9th floor
2118.06 03 –
Staircases 2.00 -- -- -- 27.36
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 27 m No. & dimensions of RWH tank(s) : 18 no. of RWH tanks;
Size of pit: 4m x 3m x 3m Size of Bore: 350 mm dia. Size of pipe: 150 mm dia.
No. and depth of percolations wells: 18 no. of percolating wells, depth will kept 5 m above ground water table.
Details on Pre-treatment facilities: A de-silting chamber will be provided to de-silt and remove floating material through bar screen.
Page 14 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 14 of 62
22. Green area details
Tree covered area (m2) : 1,238.85 Area covered by shrubs and bushes (m2): -- Lawn covered area (m2): 6,902.01 Total Green Area (m2): 8,140.86 Green Area % of plot area: 11.80 % No. of trees and species to be planted: 207 nos. trees will be planted. Tree
species like Asopalav, Bamboo bas, coconut palm, neem, champa, jambudi, gulmohar, saragvo etc.
23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Rs. 121.0 lacs and Rs. 7.0 lacs are proposed as capital cost and recurring cost per annum for the activities like rain water harvesting & ground water recharge, green belt development, solid waste generation & management, water & air pollution management.
24. Dust control measures.
Regular water sprinkling, covered shed for cement unloading, covering the excavated earth with tarpaulin sheet etc.
25. Use of Eco friendly building materials
Use of fly ash bricks, aerated blocks, paving blocks, lead free paints etc.
26. Details on the amenities to be provided to construction workers.
Provision of Personal Protective Equipments, first aid box, free medicines, doctor service along with the basic amenities like tap water, sanitation & drinking water facilities, lunch space etc.
27. Documents related to land possession
N.A order for B. Nos. 137,138,187,136,133/2,135,140 is in the name of M/s Indo-Overseas Construction Company. A copy of subregistrar’s index shows N.A land of B.No.39 in the name of the developer. Sale deed between the land owners and the developer for non agricultural land of block no. 38 has been submitted.
28. Details of EIA report
Study period: 9th March 2014 to 9th June 2014 Study area: 5 km radial area from the boundary of the project site. Environmental attributes considered for EIA study: Air, water (surface &
ground water), noise, land, land use, biological environment, socio-economic aspects etc.
Observations: baseline ambient air quality in terms of PM10, PM2.5, SOx & NOx was well within the NAAQM standards. All physico-chemical parameters for surface & ground water were within the desirable limits of BIS 10500 for drinking water. Noise level at all the eight sampling locations were found well within the norms prescribed by CPCB.
Traffic study: Traffic study carried out on Surat-Kadodara 60 m wide road shows that the existing Level Of Service (LOS) of Excellent “A” will be changed to LOS of Very Good “B” after the proposed project comes into existence.
29. Other details A copy of order from Urban Development and Urban Housing Department of Government of Gujarat has been submitted which shows that the additional FSI of about 3.7 is allowed for the project and for the exceeding beyond permissible limit shall be charged @ of 40% of jantry shall have to paid to the competent authority.
Structural stability certificate for construction of buildings with basement + ground floor + 9 floors has been submitted.
During the meeting, the project proponent was asked to install fire proof certified electrical fittings for the
Page 15 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 15 of 62
proposed project. Further they were suggested to make provision of CO sensors with alarm system and
adequate air ventilation & lighting in the basement, to which the project proponent replied that they have
already proposed to make the provision of the same. They were also asked to make sure that the fire
water reserve should not be used for any purpose other than fire fighting. After detailed discussion on
various aspects regarding the project it was decided to recommend the project to SEIAA Gujarat for grant
of Environmental Clearance.
4. ONGC Ltd. Hazira Hazira Process Plant, Hazira Notified rea, Nr. Vill : Bhatpore, Dist : Surat
TOR Validity Extension
Project / Activity No.: 1(d)
Chronology of EC Process:
M/s: Oil and Natural Gas Corporation Ltd., Hazira (herein after Project Proponent – PP) had submitted application vide their letter dated 15/05/2012.
The project was considered for TOR finalization in the meeting of the SEAC held on 27/06/2012.
TOR amended in the SEAC meeting dated 24/06/2013.
PP has applied for extension of validity of TOR with revised Form-1 vide their letter dated 26/02/2015.
The project proponent was issued TOR to set up stand-by gas based Combined Cycle Power Plant
(CCPP) of 51 MW capacity near the existing Cogeneration plant at Hazira gas processing complex vide
SEAC’s letter dated 27/06/2012 and subsequently amended vide SEAC’s letter dated 22/06/2013.
The project proponent vide their letter dated 23/01/2015 requested the SEAC to extend the validity of
TOR by one year. During the meeting, it was presented that the EIA study is in progress and additional
time is required for completing the report and finalization of the EIA report. It was also presented that
there is no change in project components and environmental set up of the project area. Considering that
the additional TOR were prescribed in the SEAC meeting held on 24/06/2013, which was valid for two
years and considering that additional time is required for completing EIA study and & finalization of EIA
report, the committee decided to extend the validity of the TOR for further one year subject to the
condition that validity shall not be extended further. The TOR shall therefore lapse on 23/06/2016.
5. Gujarat State Fertilizers & Chemicals Limited
P.O.Fertilizernagar, Vadodara TOR Amendment
Project / Activity No.: 5(f)
Chronology of EC Process:
M/s: Gujarat State Fertilizers & Chemicals Limited (herein after Project Proponent – PP) has submitted application vide their letter dated 17/05/2014.
The project was considered for TOR finalization in the meeting of the SEAC held on 27/08/2014.
PP has applied for amendment in TOR with revised Form-1 & Pre Feasibility Report vide their letter dated 23/02/2015.
Page 16 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 16 of 62
Project / Activity Details:
This is an existing integrated multi-products manufacturing complex and now unit has proposed to expand
Unit is having CC&A from GPCB which is valid upto 06.06.2016 for existing products. Proposed
expansion will be carried out within the existing premises and no additional land is required. Approx. 7952
sq. m area will be made available by scrapping of old Ammonia plant-I & II within the existing premises.
The proposed cost of project will be Rs. 900 Crores. GSFC have two Melamine plants (I & II) with
capacity 5000 MTPA and 10000 MTPA at existing complex. Now the unit proposes for expansion of
Melamine plant with additional 40000 MTPA. Thus total capacity of Melamine plant after expansion will be
55000 MTPA. Basic raw materials are Ammonia, Carbon Dioxide & Caustic Soda (NaoH). By-products
from existing unit are Argon, Phosphogypsum, Ammonium Sulphate & Nitric Acid. There will be no By-
products from the proposed expansion.
Total water requirement after the proposed expansion will increase from 32000 KL/day to 36126.8 KL/day
( i.e. additional fresh water requirement is 4133.8 KL/day) which includes industrial Industrial- 4126.8
Page 18 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 18 of 62
KL/day & Domestic- 7 KL/day, which will be met through existing water supply source French well at
Mahi River. At present GSFC have installed two ETP for treatment of existing effluent from varios plants.
At present dilute liquid streams from urea, Capro-I, Utility, SA, CEO utility are collected in New Pump
House (NHP) pond along with treated effluent from old BOD & NETP while other streams like Cooling
tower blow down, storm water, treated sewage are collected in Old Pump House (OPH) pond. Then
composite treated effluent from NPH & OPH is disposed to common channel of Vadodara Enviro Channel
Limited (VECL) for ultimate disposal to estuary of Mahi River. Total 1922.4 KL/day of effluent will be
generated from the proposed expansion. 210 KL/day of effluent generated from steam condensate will
be directly reused in Melamine plant. 1922.4 KL/day of effluent (CT blow down & waste water from
manufacturing process) will be further treated in RO plant of capacity 1950 KL/day. RO permeate
(1345.68 KL/day) will be reused inCooling tower while RO reject (576.72 KL/day) will be disposed to
VECL common channel along with treated effluent of existing plants. Additional domestic waste water-6
KL/day will be sent to existing STP of capacity 3175 KL/day within existing premises made for GSFC
Township.
At present natural gas is used as fuel in Salt Furnace of Melamine plant –I & II. Consumption of natural
gas will be increased from 675 SCM/hr to 1784 SCM/hr in Melamine plant-I & II. Unit has proposed one
gas fired heater furnace & one DG set (Cap. 900 KVA) in addition to existing 12 DG sets. Consumption of
HSD will be increased from 1950 Lit./hr to 2250 Lit./hr. At present Filters are provided as APCM with
existing Dryer outlets of Melamine plant-I & II. Unit has proposed Ammonia scrubbers & filters as APCM
for scrubbing of Ammonia and Melamine Dust respectively. At present ETP sludge, Used oil Discarded
containers, Spent catalyst, Organic waste & Sulphur muck are the hazardous waste generated. After
proposed expansion additional haz. Waste generation categories will be Activated Carbon, Molten Salt &
Dowtherm.
Observations/Discussions:
Technical presentation by the PP included general information, details of products and raw materials,
Waste generation, hazards & control, analysis of pollution parameters before and after treatment,
resource consumption and conservation, Risk estimation, proposed ToRs etc. On asking about the need
for revised ToR, PP informed that Technology for Melamine production process adopted in this new plant
is high pressure (HP) technology and reaction is non-catalytic compared to existing plant technology
which is low pressure, gas phased and catalytic reaction. The proposed plant will be using Ammonia and
CO2 as main raw material to produce Melamine in high pressure reactors and off gases from this process
are recycled back to minimize the raw material consumption. Molten urea derived as an intermediate
product will be used as raw material for captive consumption in existing plant. PP further informed that
this being a non-catalytic reaction, the quality of the product can be achieved faster and shutdown
requirement to maintain quality in the existing plant technology will be avoided. Committee noted the
expected changes like Project capital cost, utility, raw materials consumption, by-product, water
requirement, water balance, mass balance etc. Committee emphasized on safety aspect for this new high
pressure liquid phase reactions. Committee discussed about occupational health hazard due to existing
activities and proposed expansion. On asking about ammonia leakage, PP informed that they are having
sensors with auto cut off system to control any leakages. Project proponent informed that they have
completed baseline environmental monitoring during March 2014 to May-2014. Further PP requested that
proposed expansion will be within the existing industry which is located in notified industrial area and thus
Page 19 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 19 of 62
public hearing shall be exempted as per MoEF&CC Office Memorandum no. J – 11013/36/2014-IA-I
dated 10/12/2014. Committee noted that GSFC (Baroda) is established and notified prior to 14/09/2006
and hence, the exemption from public consultation is available to this project as per the OM dated
10/12/2014. After deliberation on various aspects it was decided to delete ToR no. 48 and following
additional TOR were prescribed in addition to the TOR prescribed previously in the SEAC meeting held
on 27/08/2014:
1. Detailed technical justification for the proposed change in technology to be used for Melamine plant and relevant changes.
2. Description of High Pressure (HP) Melamine Technology along with management plan of molten urea, scrubbed ammonia and the off gases produced as a result of the reaction.
3. Identification of hazards in HP melamine technology along with handling, processing and storage of hazardous material and safety system provided to mitigate the risk.
4. Details of existing Occupational & Safety Hazards. What are the exposure levels of above mentioned hazards and whether they are within Permissible Exposure level (PEL). If these are not within PEL, what measures the company has adopted to keep them within PEL so that health of the workers can be preserved.
5. Annual report of health status of workers with special reference to Occupational Health and Safety.
6. Plan and fund allocation to ensure the occupational health & safety of all contract and casual workers.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be considered as
generic TORs for preparation of the EIA report in addition to all the relevant information as per the
generic structure of EIA given in Appendix III in the EIA Notification, 2006. The project shall be appraised
on receipt of the EIA/EMP report.
6. Jetpur Dyeing & Printing Association
Jetpur Dyeing and Printing Association, Kanakia Plot, Jetpur, Dist: Rajkot.
EC Validity Extension
Project / Activity No.: 7(h)
Chronology:
SEIAA, Gujarat has accorded Environmental clearance to M/s: Jetpur Dyeing and Printing Association (JDPA) for setting up of Common Effluent Treatment Plant vide vide letter no. SEIAA/GUJ/EC/7(h)/246/2009, dated 01/09/2009.
PP has applied for extension of validity of Environmental Clearance vide their letter dated 13/08/2014.
During the meeting, It was observed that the environmental clearance to the project was accorded for for
setting up of Common Effluent Treatment Plant at (i) Survey No. 143/P-2, Bhatgam, Taluka: Bhesan,
District: Junagadh -30 MLD capacity (ii) Survey No. 969/P-2/P2 and 969/P2/P3, Jetpur (Monpar Derdi),
District: Rajkot-20 MLD capacity.The said environmental clearance vide letter no.
SEIAA/GUJ/EC/7(h)/246/2009, dated 01/09/2009 which was valid for five years from the date of issue i.e.
31/08/2009.
Page 20 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 20 of 62
On asking about the present status, PP informed that as per the Environmental Clearance JDPA had
constituted SPV unit namely Bhatgam Washing Ghat Sudhikaran Yojna Pvt. Ltd. and they have already
constructed CETP with 30 MLD capacity at village Bhat and now they are planning to commission this
CETP at village Bhat. PP informed that they have not started the construction work at Village Derdi for
proposed CETP. Committee asked the reason for not starting the work at village Derdi. PP informed that,
they could not start the construction work at vill. Derdi due to objection raised by the people of Vill. Derdi
and matter is pending with Honorable High Court of Gujarat. Committee referred the Honorable High
Court order dated 03/02/2015. According to the Honourable High Court order dated 03/02/2015, the
Honourable court extended one opportunity to the respondents i.e. JDPA to comply with the direction with
regard to the Derdi or to submit alternative plan. The committee was of the view that the issues have
been raised as far as the village Derdi was concern, before consideration of the case for extension of
validity of environmental clearance, Jetpur Dyeing and Printing Association (JDPA) should submit the
documents showing that there is no dispute in the vicinity especially by the farmers for the CETP.
After detailed deliberations the Committee unanimously decided for further consideration of their case for
extension of validity of environmental clearance only after satisfactory submission of the following:
1. An affidavit from the People of Derdi village regarding “No Objection” for this proposed CETP at village Derdi.
7. Span Chemicals) Plot No:27,C/1,B-6 Pandesara, Chorasi, Surat
Screening & Scoping
Project / Activity No.: 5(f)
M/s: Span Chemicals (herein after Project Proponent – PP) has submitted application vide their letter dated 13/08/2014.
Project Proponent did not remain present in the SEAC meeting dated 18/10/2014.
Project status: Expansion
Project / Activity Details:
This is an existing unit engaged in Dyes intermediates and now proposes for expansion and addition of new products as below:
Total plot area is 800.8 sq. m. The total cost of the proposed expansion is 1.60 Crores. Total water
Page 21 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 21 of 62
consumption after proposed expansion will be 15.5 KL/day (Existing: 4.35 KL/day + Proposed: 19.55
KL/day). Fresh water will be sourced from GIDC water supply. Total industrial effluent generation will be
17.61 KL/day (Existing: 4 KL/day + Proposed: 13.61 KL/day) which will be treated in existing ETP.
Necessary modifications and/up gradation will be carried out in existing ETP. Domestic waste water will
be treated along with industrial effluent. Treated effluent will be sent to the CETP of M/s. Pandesara
Infrastucture Ltd. (PIL) for further treatment and final disposal.There is no Boilers/heaters and no fuel
requirement at present and for the proposed expansion. Unit has proposed scrubber system for control of
process gaseous emissions from Sulphonator.Hazardous waste to be generated will be ETP sludge (45
MT/Year), Used Oil (0.07 MT/Year) and Discarded containers/Bags/Liners (5 MT/Year). Unit has obtained
membership of TSDF of BEIL.
Observations/Discussions:
Technical presentation by the PP included general information, details of products and raw materials,
Waste generation, hazards & control, analysis of pollution parameters before and after treatment,
resource consumption and conservation, Risk estimation etc. PP has mentioned unrealistic data of
hazardous waste quantity which was vied seriously by Committee and asked to correct the relevant data.
Safety aspects during Storage & Handling of Chlorine & Oleum have been discussed and asked to make
provision of emergency transfer arrangements. The committee desired to have MSDS of materials to be
handled, information on storage of each hazardous chemical and safety measures thereof. After detailed
discussion, the following additional Terms of Reference were prescribed for the EIA study to be done
covering 5 Km radial distance from the project boundary.
1. Need for the proposed expansion should be justified in detail.
2. Demarcation of proposed expansion activities in lay out of the existing premises. Layout maps indicating existing unit as well as proposed unit indicating storage area, plant area, greenbelt area, utilities etc. Lay out of industrial area (GIDC) indicating location of unit within the Industrial area/Estate.
3. Exact details about additional infrastructural facilities, plant machineries etc. required for the proposed expansion
4. Detailed manufacturing process along with chemical reactions and mass balance (including reuse-recycle, if any).
5. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the proposed expansion. Copy of permission obtained from GIDC/SMC for additional water supply.
6. Water consumption and consumption of each raw material per MT of each product.
7. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream to be generated. A detailed treatability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated.
8. Characteristics of the combined effluent and treated water to be sent to CETP of PIL.
9. Complete waste water management plan for existing as well as proposed production. Detailed effluent treatment scheme and disposal method.
10. Technical details of the ETP including size of each unit, retention time etc. including modifications / up
Page 22 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 22 of 62
gradation to be done in existing ETP to take care of increased effluent quantity along with its adequacy report. Provision of online continuous pH meter, TOC analyser and flow meter at the final outlet of the ETP with an arrangement to reflect the results on company's server, which can be accessed by the GPCB on real time basis along with the time bound program for installation of the same.
11. Details of CETP of GECL (1) Capacity of the CETP (2) Booked and spare capacity of CETP (3) Mode of transportation of waste water from industry to common facility (4) Manifest system for sending waste water to common facility and record keeping, (5) Acceptance criteria of common facility and copy of terms & conditions etc.
12. Plan for management and disposal of waste streams to be generated from spillage, leakages, occasional reactor washing and exhausted media from Scrubber etc.
13. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.
14. One season site-specific meteorological data including temperature, relative humidity, hourly wind speed and direction and rainfall shall be provided. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 5 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
15. One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
16. Modelling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modelling should be provided. The air quality contours may be shown on location map clearly indicating the location of project site, habitation, sensitive receptors, if any. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modelling should be superimposed on satellite image / geographical area map.
17. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate emission from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.
18. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized.
19. Methodology of de-contamination and disposal of discarded containers and its record keeping.
Page 23 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 23 of 62
20. Membership of Common Environmental Infrastructure including the CETP, TSDF / Common Hazardous Waste Incineration Facility (CHWIF), Common MEE along with an assessment to accommodate the additional quantity of wastes to be generated.
21. Complete Management plan for By-products/Spent acids to be generated, (if any) from the project including their quantity, quality, characteristics, end use etc. along with the name and address of end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said by-product from the proposed project. Also give characteristics of the by products and feasibility of their actual use in respective products as a raw material.
22. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.
23. Data on air emissions, wastewater generation and solid / hazardous waste generation and management for the existing plant should also be incorporated. (Comparative data in tabular format).
24. Details of measures proposed for the noise pollution abatement and its monitoring.
25. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.
26. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.
27. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment (PPE) to be provided to the workers. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical check up of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.
28. MSDS of all the raw materials and products.
29. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impact.
30. Details of quantity of each hazardous chemical to be stored, material of construction of major hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture, Storage & Import of Hazardous Chemicals (MSIHC) Rules of major hazardous chemicals.
31. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.
32. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the map clearly showing which of the facilities and surrounding units would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.
Page 24 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 24 of 62
33. Details of fire fighting system including provision for flame detectors, temperature actuated heat detectors with alarms, automatic sprinkler system, location of fire water tanks & capacity, separate power system for fire fighting, details of qualified and trained fire personnel & their job specifications, nearest fire station & time required to reach the proposed site. Submit line diagram of the fire hydrant network.
34. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.
35. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.
36. Copies of analysis report of the water samples of final outlet of ETP collected by GPCB (Last 3 years).
37. Consent to Establish, Consent to Operate orders obtained in past along with point wise compliance status of all the conditions stipulated therein.
38. Copy of Environmental Clearance obtained for the existing project and a certified report of the status of compliance of the conditions stipulated in the environmental clearance for the existing operation of the project by the Regional Office of the MoEF.
39. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure notices etc. served by the GPCB to the existing unit in last five years and actions taken then after for prevention of pollution.
40. Details of fatal / non-fatal accidents, loss of life or man hours, if any, occurred in the existing unit in last three years and measures proposed to be taken for avoiding reoccurrence of such accidents in future.
41. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report. (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.
42. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions. Details of this system may be given.
43. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.
44. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.
45. A tabular chart with index for point-wise compliance of above TORs.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be considered as
generic TORs for preparation of the EIA report in addition to all the relevant information as per the
generic structure of EIA given in Appendix III in the EIA Notification, 2006. The project shall be appraised
on receipt of the final EIA report.
Page 25 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 25 of 62
M/s: Dhariyal Chemicals (herein after Project Proponent – PP) has submitted application vide their letter dated 13/08/2014.
Project Proponent did not remain present in the SEAC meeting dated 18/10/2014.
Project status: New
Project / Activity Details:
This is a new unit proposes the manufacturing of following Synthetic Organic Chemicals:
Sr. No. Product Name Quantity (MT/Month)
1. Polymers & Biopolymers 312
2. Micro Crystalline Cellulose Powder (MCCP) 33.3
3. Polysaccharides Derivatives 884
4. Croscarmellose Sodium (CCS) 21.84
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Total plot area is 4861.89 sq. m. Expected project cost is Rs. 6.49 Crores. Total water consumption for
proposed project will be 36.1 KL/Day (3 :KL/day for Domestic & 33.1 KL/day for Industrial) which will be
sourced from GIDC water supply. Industrial waste water generation will be 19.56 KL/day, which will be
treated in proposed Primary, Secondary & Tertiary treatment plant followed by RO. RO permeate will be
partly (2.5 KL/day) reused in washing/purification process and remaining quantity (7.5 KL/day) will be
used for Gardening purpose within premises and RO reject (4.56 KL/day) will be sent to Common MEE).
Domestic waste water (3 KL/day) will be disposed off into soak pit system. Flue gas generation will be
from one Boiler (0.3 TPH), HAG (40 Lacs Kcal) and one DG set (200 KVA). PNG (550 SCM/day) will be
used as fuel for Boiler and TFH. LDO (50 lit/hr) will be used as fuel for DG set. No process gas emission
is envisaged. Hazardous waste generated from the manufacturing activity will be ETP sludge (10
MT/Year), Discarded containers (2000 no.s /Year) and Used oil (20 lit./Year).
Observations/Discussions:
Technical presentation by the PP included general information, details of products and raw materials,
Waste generation, hazards & control, analysis of pollution parameters before and after treatment,
resource consumption and conservation, Risk estimation etc. On asking about the common MEE facility,
PP was not aware about nearby common MEE facility. However, PP assured to obtain membership of
nearby common MEE. Committee suggested to explore the possibilities to achieve Zero discharge by
treatment within premises only. After detailed discussion, the following additional Terms of Reference
were prescribed for the EIA study to be done covering 5 Km radial distance from the project boundary.
1. Copy of plot holding certificate obtained from GIDC Dahej.
2. Present land use pattern of the study area shall be given based on satellite imagery.
Page 26 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 26 of 62
3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.
4. Details of manufacturing process / operations of each product along with chemical reactions, mass balance, consumption of raw materials etc. Details on strategy for the implementation of cleaner production activities. (Give specific details about source of effluent generation).
5. Chemical name of each proposed product to be manufactured. Details on end use of each product.
6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream from the processes.
7. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the project. Permission obtained from the GIDC for supply of raw water. Undertaking stating that no bore well shall be dug within the premises.
8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.
9. Quality and quantity of waste water to be generated from the manufacturing process of each product to be manufactured along with mass balance.
10. Stream wise qualitative & quantitative analysis of each waste stream (including process water, cooling tower blow down, boiler blow down, washing effluent etc.) to be generated. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated. The characteristic on which treatability is based shall also be stated.
11. Details of the ETP units including its capacity, size of each unit, retention time and other technical parameters. Details regarding provision of online continuous pH meter, TOC analyser and flow meter at the final outlet of the ETP.
12. Details of Common MEE including (1) Total capacity of the MEE (2) Actual load at present per day) (3) Spare capacity of MEE with adequacy report.
13. Plans for management, collection and disposal of waste streams to be generated from spillage, leakages, vessel washing, used container washing etc. Measures proposed for preventing effluent discharge during unforeseen circumstances.
14. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be incorporated.
15. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 5 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
16. One complete season base line ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind
Page 27 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 27 of 62
direction at a location where maximum ground level concentration is likely to occur.
17. Modelling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modelling should be provided. The air quality contours may be shown on location map clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modelling should be superimposed on satellite image / geographical area map.
18. Base line status of the noise environment, impact of noise on present environment due to the project and proposed measures for noise reduction including engineering controls.
19. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.
20. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized. Methodology of de-contamination and disposal of discarded containers and its record keeping.
21. Membership of Common Environmental Infrastructure including CETP, TSDF, Common Hazardous Waste Incineration Facility (CHWIF), MEE etc. (Whichever is applicable)
22. Complete Management plan for By-products/Spent acids to be generated, (if any) from the project including their quantity, quality, characteristics, end use etc. along with the name and address of end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said by-product from the proposed project. Also give characteristics of the by products and feasibility of their actual use in respective products as a raw material.
23. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.
24. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/Year earmarked for environment pollution control measures.
25. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.
26. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical checkup of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.
Page 28 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 28 of 62
27. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the plant layout map clearly showing which of the facilities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.
28. MSDS of all the products and raw materials.
29. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impacts. This shall include the details of Antidotes also.
30. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals, size of the biggest storage tank to be provided for each raw material & product etc. How the manual handling of the hazardous chemicals will be minimized?
31. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.
32. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.
33. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.
34. Detailed socio-economic development measures including community welfare program most useful in the project area for the overall improvement of the environment. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions for the next five years and activities proposed to be carried out; specific to the current demographic status of the area.
35. A tabular chart for the issues raised and addressed during public hearing/consultation and commitment of the project proponent on the same should be provided. An action plan to address the issues to be raised during public hearing and the necessary allocation of funds for the same should be provided.
36. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.(b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.
37. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.
38. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.
39. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be
Page 29 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 29 of 62
incorporated in the EIA Report.
40. A tabular chart with index for point-wise compliance of above TORs.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for synthetic organic chemical industry shall be considered as generic
TORs for preparation of the EIA report in addition to all the relevant information as per the generic
structure of EIA given in Appendix III in the EIA Notification, 2006. The draft EIA report shall be submitted
to the Gujarat Pollution Control Board for conducting the public consultation process as per the provisions
of the EIA Notification, 2006. The project shall be appraised on receipt of the final EIA report.
9. Kejriwal Integrated Textile Park Pvt. Ltd. (KITPPL)
Survey no. 328,333,40,341,342, 343,344,357,358, Vill:Kareli, Ta.: Palsana, Dist. Surat
Screening & Scoping
Project / Activity No.:
M/s: Kejriwal Integrated Textile Park (herein after Project Proponent – PP) submitted Application vide their letter dated 18/10/2014.
Project status: New Project / Activity Details: This is a new proposed textile park with Common Effluent Treatment Plant (CETP) which falls under the
project/activity 7(c) & 7 (h) as per the schedule of the EIA Notificaiton-2006.
The textile park will be set up in 212481.88 sq. m. (Buildings 130203 sq. m, Common infrastructure –
4593505 sq. m & Green space 24330 sq. m, Common facilities – 12013.38 sq. m). Total cost of the
project will be 121.28 Crores. This unit has proposed to develop Integrated Textile Park at Survey no.
340,342,343,344,328,333,357,358 at village Kareli, Ta. Palsana, District: Surat for developing following
kinds of Industries. (PFY/FDY 1 unit, Texturising – 7 units, Water jet weaving – 17 units, Embroidery – 9
units). The textile park will houses 34 different units. The proposed activities in the textile park will (1)
TOR etc. During meeting PP requested to consider the project as B2 category project, which was not
considered by the committee and after deliberation on various aspects, the terms of reference proposed
by the project proponent were accepted and the project proponent was asked to include following
additional TOR for the EIA study to be done covering 5 Km radius surrounding the periphery of the project
:
1. NA permission letter for proposed site.
2. Land Possession Documents of the proposed site.
3. Project site specific details such as distance of the project site from the nearest (1) Village (2) Water Body: Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway (4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary / Reserve Forest shall be included. Give satellite image of 10 KM radius from the boundary of project premises.
4. Present land use pattern of the study area as well as the project area shall be given based on satellite imagery.
5. Layout plan of the Textile Park. Provision of separate entry, exit and continuous unobstructed open path within the project area for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the layout.
6. Exact scope of the project should be given in detail. Need for the proposed CETP shall be justified in detail.
7. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the Textile Park. Permission from the CGWA for extraction of the ground water. Details of proposed ground water recharge scheme should also be submitted.
8. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated along with adequacy and efficacy report. The characteristic on which treatability is based shall also be stated.
9. Explore use of Best Available Technology (BAT) incorporating latest features for the proposed CETP instead of providing conventional treatment units.
10. Details of the CETP units including its capacity, size of each unit, retention time and other technical parameters.
11. Techno-feasibility & adequacy for reuse / recycle of treated effluent by member units. Justifications of the economic viability of the treated effluent reuse / recycle. Details of the scheme for total recycle-reuse of the treated effluent. Details regarding the percentage of waste water to be reused / recycled by each member units.
12. Application wise break-up of treated effluent quantity to be recycled / reused in various applications and green belt development etc. Details about availability of sufficient open land and suitability for
Page 31 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 31 of 62
utilizing treated effluent for plantation / gardening. How it will be ensured that treated effluent won't flow outside the premises linked with storm water during high rainy days.
13. Detailed layout of effluent conveyance pipeline within the Textile Park along with distances and all technical specifications, line diagram and total capacity of the pipeline to convey effluent. Details of pumping stations, pumping capacity in each pumping station etc if any shall also be furnished.
14. List of the CETP members, their production capacity, effluent reuse / recycle capacity, effluent generation capacity, effluent characteristics and effluent quantity. Whether any future projections are envisaged for finalization of the CETP capacity and conveyance pipeline.
15. Undertaking that no dying and printing unit or process house shall be permitted as a member of the proposed CETP.
16. Details about the proposed inlet norms of the CETP. Give details of the mandatory treatment, if any required by the member units to achieve the inlet norms by the each unit.
17. Specific monitoring plan to ascertain that all the CETP member units send their effluent [contracted quantity] to the CETP and the effluent does not in any way find its way to other sources i.e. measures to eliminate by passing of the effluent.
18. Details of the pipeline maintenance program to avoid choking / overflow / leakage of the effluent conveyance pipeline and means to avoid the same.
19. Provision of flow meter at the outlet of the CETP; checks & balances to ensure that discharge quality and quantity never exceeds the prescribed limit.
20. Details of the monitoring plan of the member units to ensure compliance with the inlet norms of the CETP as well as to avoid shock loading in the system.
21. Justification / capacity of the project keeping in view the future effluent load from the additional member units.
22. Details of CETP management and maintenance of the CETP during operation phase including infrastructure, model of management, role of each stake holder, CETP effluent quality monitoring scheme etc.
23. Impact of the CETP installation and treated effluent conveyance & disposal system on the environment including the local hydrology, soil condition, floral and faunal bio-diversity of the region and the mitigation measures proposed.
24. Surface water quality and ground water quality in the study area.
25. Geological features and geo-hydrological status of the study area.
26. Details of emergency storage of effluent in the CETP for the monsoon season.
27. Details of R&D to be initiated by the CETP management for effective and viable treatment of the effluent received.
28. Details of total power load required for the CETP as well as details of dedicated power back up / D.G.Sets to be provided to take care of power requirements during power supply failure, to ensure that treatment units operate uninterrupted.
29. CETP management manual covering various management aspects during the effluent collection, transportation, treatment and disposal aspects for best management practices. The member units shall abide by various clauses in this regard to check problems during the collection, transportation, treatment and reuse / recycle / disposal of the effluent.
Page 32 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 32 of 62
30. CETP management manual covering various management aspects during the effluent collection, transportation, treatment and disposal aspects for best management practices. The member units shall abide by various clauses in this regard to check problems during the collection, transportation, treatment and reuse / recycle / disposal of the effluent.
31. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be incorporated.
32. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 5 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
33. One complete season base line ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
34. Modeling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modeling should be provided. The air quality contours may be shown on location map clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modeling should be superimposed on satellite image/ geographical area map.
35. Quantity of fuel required, its source and transportation. Fuel analysis to be provided (sulphur, ash content and heavy metals including Pb, Cr, As and Hg). A confirmed fuel linkage should be provided.
36. Specific details of (i) Details of the utilities required (ii) Flue gas emission rate from each utility (iii) Air Pollution Control Measures proposed to each of the utility along with its adequacy.
37. Impact of the project on local infrastructure of the area such as on road network due to transportation of fuel, ash etc. Whether any additional infrastructure would need to be constructed and the agency responsible for the same with time frame.
38. Details of flora and fauna duly authenticated should be provided. In case of any scheduled fauna, conservation plan should be provided.
39. Details of management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized.
40. Copy of membership certificate of Common Environmental Infrastructure like TSDF, if any taken, should be incorporated.
41. Details of measures proposed for the noise pollution abatement and its monitoring. Provisions to provide ear plugs / ear muffs to workers and to ensure its usage in high noise areas. Measures to ensure that the noise from the looms remains less than 80 dB(A). Undertaking to carry out Audiography of workers working near the looms, at least once in a year.
Page 33 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 33 of 62
42. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/annum earmarked for environment pollution control measures.
43. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided to the workers. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical check up of the workers exposed. Details of work zone ambient air quality monitoring plan as per Gujarat Factories Rules.
44. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenario related to fire and explosion issues due to storage and use of fuel should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site emergency plan should be provided.
45. Measures to guard against fire hazards including details of automatic fire detection and control system & detailed fire control plan showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc. should also be provided.
46. Provision to ensure sufficient water storage all the time for use during emergency situation.
47. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.
48. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.
49. Proposal for socio-economic development activities including community welfare program most useful in the project area for the overall improvement of the environment. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions for the next five years and activities proposed to be carried out; specific to the current demographic status of the area.
50. A tabular chart for the issues raised and addressed during public hearing/consultation and commitment of the project proponent on the same should be provided. An action plan to address the issues raised during public hearing and the necessary allocation of funds for the same should be provided.
51. Plan for compliance of CETP guidelines issued by the CPCB.
52. Whether any litigation pending and / or any direction / order passed by any Court of Law against the company, if so, details thereof.
53. Details of scheme for surface as well as roof top rain water harvesting and ground water recharge with proper scientific calculations considering rainfall in the region, catchment area, land / soil characteristics, ground water recharge rate, duration of rain water harvesting etc. Details of provisions of pre-treatment of the rainwater in the case of surface run off is to be harvested. Location of recharge percolation wells on the layout plan.
Page 34 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 34 of 62
54. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report (b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions? If so, it may be detailed in the EIA.
55. Disciplinary policy of CETP for member units.
56. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.
57. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.
58. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.
59. A tabular chart with index for point-wise compliance of above TORs.
60. Any further clarification on carrying out the above studies including anticipated impacts due to the project and mitigative measures, project proponent can refer to the model ToR available on Ministry website “http://moef.nic.in/manual/Industrial estate & CETPs”.
These additional TORs should be considered for the preparation of the draft EIA report in addition to all
the relevant information as per the generic structure of EIA given in Appendix III & Appendix III A of the
EIA Notification, 2006. The draft EIA report shall be submitted to the Gujarat Pollution Control Board for
conducting the public consultation process as per the provisions of the EIA Notification, 2006. The project
shall be appraised on receipt of the final EIA report.
During the meeting, committee noticed that in spite of submission of the notarized undertaking stating that the construction work started without obtaining prior Environmental Clearance has been stopped now and will be resumed again only after getting EC, they have continued with the construction activity at the project site. Such a gross violation was taken very seriously by the committee and decided not to hear the project. It was decided to take up the project in one of the upcoming SEAC meetings only after construction work has been completely stopped completely at the project site. 11. Star Manorath (A Project of
7 Star) TP-48,Block No:350,O.P. No.140, F.P.No.140, Kholvad, Choryasi, Surat
Screening & Scoping
Details of the proposed project as presented before the committee is tabulated below:
Sr. No.
Particulars Details
1. Proposal is for A new project 2. Type of Project A low rise residential cum commercial project 3. Project / Activity No.
[8(a) or 8(b)] Project / Activity No. 8(a)
4. Name of Project Star Manorath 5. Name of Developer 7-star company 6. Estimated Project Cost 20. Crores.
Page 35 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 35 of 62
(Rs. in Crores) 7. Whether construction
work initiated at site? If yes, details thereof
No
8. Project Details Land / Plot Area (m2): 17,125.60 FSI area (m2): 38,275.68 Non FSI area (m2): 4,305.15 Total BUA (m2): 50,827.8
Permissible Proposed FSI Area (m2) 38,275.68 33,970.46 Ground Coverage (m2) 7449.60 7449.22 Common Plot Area (m2) 1712.56 1713.25 Max. building height (m) As per rule 27.05
9. Building Details No. of Buildings:13 (A to M) No. of Blocks:30 Scope of buildings/blocks: Basement + hollow plinth/ground floor +
5 floors No.& size of Residential Units: 564 units No. & type of Commercial Units:14 shops Details of amenities if any: a banquet hall, home theatre, library,
gym and indoor games in block M. 10. No. of expected
residents / users 2820 person residence 56 person commercial Total: 2876 person
11. Water & waste water details during construction phase
Water requirement (KL/day): 20 Source of water: Bore Well Waste water generation quantity (KL/day): 8.0 Mode of disposal: Temporary septic tank & soak pit Details of reuse of water, if any: Nil
12. Water & waste water details during operation phase
Total water requirement (KL/day): 360.0 Fresh water requirement (KL/day): 160.0 Source of water: water supply from SUDA Waste water generation quantity (KL/day): 350.0 Mode of disposal: will be treated in the proposed onsite STP and
treated sewage after its reuse for gardening & flushing will be discharged into the drainage line of SUDA.
In case of STP provision, capacity of STP: 500 KL/day STP Technology: Conventional Purposes for treated water utilization: Gardening & flushing. Quantity of treated water to be reused:1.Gardening (KL/day): 5.0
2. Flushing (KL/day): 195.0 Provision of dual plumbing system (Yes/No): Yes
Quantity and type (treated/untreated)of water to be discharged: treated sewage after its reuse for gardening & flushing purposes will be discharged into the drainage line of SUDA.
13. Status of water supply
and drainage line SUDA has developed water supply & drainage line in the area. On getting BUC, the water supply and drainage connection will be
Page 36 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 36 of 62
made available to the project. 14. Solid waste
Management Construction Phase:
Generation (m3)
Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 2250 Will be reused on 0.4 m3 layer over 1800 m2 gardening area
Nil
Other excavated
earth
20000 6,000 m3 will be used in plinth filling & in footing foundation & for preparing internal road
14,000 m3 will bereused in filling of dispersed land.
Construction debris
Nil Used in column, footing and foundation
----
Steel scrap Nil
Used in column, footing and foundation
----
Discarded packing
materials
Cement & Plastic Bags
Cement bag partly reuse in curing purpose & partly sale out in open market while plastic bag sale out to the registered recycler or vendor
----
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste & Wet waste
1200 Dustbin SUDA
Details of segregation if to be done: No Capacity and no. of community bins to be placed within premises:
300 bins having volume 0.25 m3 Authority / agency involved in waste disposal : SUDA Landfill site where waste will be ultimately disposed by local
authority: nearby MSW landfill/dumping site of SUDA
Page 37 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 37 of 62
15. Parking Details Requirement Provision As per the NBC 290 ECS 695 ECS As per the GDCR 5351.81 m2 21422.31 m2
BREAK-UP OF PARKING AREA:
Location Car Parking Area 2 Wheeler Parking
Area (m2)
Visitors Parking
Area (m2)
Total Parking
Area (m2)
(m2) (CPS)
Open Surface
-- -- -- -- --
Hollow Plinth
6006.05 214 2957.71 968.98 21422.31
Basement 15416.26
482 -- -- --
Total 12252 695 2957.71 968.98 21422.31
16. Traffic Management Width of adjacent / approach road: 18 m No. of Entry and Exit: 1 gate on South side for entry & exit having
width 9.14 m Width of internal roads: 4.5 to 9.14 m Minimum width of open path all around the buildings for easy
access of fire tender: 3.0 m to 9.20 m. 17. Green building features
including measures for conservation of water & energy, use of eco-friendly building materials, etc.
Use of Autoclave Aerated blocks, RMC, aerated type water taps, solar based street lighting, various energy conservation measures viz. LED lightings fixtures and low voltage lightings in common areas, maximum use of natural ventilation & cross ventilation, use of energy saving electrical appliances & inverters i.e. 5 star rated
18. Energy requirement, source and conservation
Power supply- Connected load: Maximum demand 2500 KVA Source: DGVCL % of saving with calculation: 25% saving by using CFL & Star
rated energy efficient electronic appliances. DG Set: 2 × 100 KVA Fuel & it quantity: HSD-50 lit/day
19. Fire and Life Safety Measures
Fire fighting facilities as per the requirement of NBC shall be provided.
20. Details on staircase Type & no. of
buildings No. of
floors
Floor area
No. of staircas
e
Width of the staircase
Travel distance
(m)
Height (m)
Buildings A1, A2 & A3 Combined
5 687.83 3 1.22 12 25
Buildings B1, B2 & B3 Combined
5 687.83 3 1.22 12 25
Buildings C1, C2 & C3 Combined
5 687.83 3 1.22 12 25
Buildings D1, D2 & D3 Combined
5 687.83 3 1.22 12 25
Buildings E1, E2 & E3 5 687.83 3 1.22 12 25
Page 38 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 38 of 62
Combined Buildings F1, F2 & F3
Combined 5 687.83 3 1.22 12 25
Buildings G1 & G2 Combined
5 582.75 2 1.22 10 25
Buildings H1, & H2 Combined
5 582.75 2 1.22 10 25
Buildings I1 & I2 Combined
5 567.01 2 1.22 12 25
Buildings J1 & J2 Combined
5 567.01 2 1.22 12 25
Buildings K1 & K2 Combined
5 712.26 2 1.22 11 25
Building L 5 712.26 1 1.22 10 25 Building M 5 310.46 1 1.52 18 23.7
21. Rain Water Harvesting (RWH)
Level of the Ground water table: 30 feet in monsoon 45 feet in summer
No. and depth of percolations wells: 4 nos. & 40 feet Details on Pre-treatment facilities: Not Applicable
22. Green area details Tree covered area (m2) : 350 m2 Area covered by shrubs and bushes (m2): --- Lawn covered area (m2): 1,500 m2 Total Green Area (m2): 1,850.0 m2 Green Area % of plot area: 16% No. of trees to be planted: 275 nos. of Neem, Pipal, Mango,
Kadam, Ashoka, Gulmohar, Sevan, etc. 23. Dust control measures Spraying of water, peripheral barricading, covered shed for cement
loading area, covering the excavated earth with tarpaulin sheet etc. 24. Budgetary allocation for
Environmental Management Plan (Rs. in lacs)
Rupees 75 lacs for EMP including STP.
25. Details of eco-friendly building materials
Fly ash bricks, aerated blocks, fly ash paving blocks, maximum use of RMC, lead free paints etc.
26. Documents related to land possession
Village form no. 7/12 shows the land in the name of applicant.
During the meeting it was observed by the committee that parking area of 15,416.26 m2 proposed in basement is much more than the actual area available in the basement as per the project plans submitted. After detailed discussion it was decided to consider the project only after submission of the following:
1. Realistic details on parking area provision for the proposed project based on the actual area available in the basement for parking as per the project plans submitted.
2. Copy of permission obtained for non-agricultural use of the project site or a copy of correspondences made in t his regard.
12. Silver Stone Rivera F.P.No.48+49,S.P.No.1,R.S>No.40, 41/2,41/1/P, T.P.No.26(Singapore), Katargam, Surat
Screening & Scoping
Details of the proposed project as presented before the committee is tabulated below:
Page 39 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 39 of 62
Sr. No.
Particulars Details
1. Proposal is for New Project 2. Type of Project Residential 3. Project / Activity
No. [8(a) or 8(b)] 8(a)
4. Name of the project
Silver Stone Rivera
5. Name of Developer
Mr. Ankit Gagjibhai Koshiya
6. Estimated Project Cost (Rs. In Crores)
Rs. 35 crores
7. Whether construction work has been initiated at site? If yes, details thereof
No
8. Project Details Land / Plot Area (m2): 9,280.5 FSI area (m2): 20,649.52 Non FSI area (m2): 10,697.81 Total BUA (m2): 31,347.33
Permissible Proposed FSI Area 20,741.90 20,649.52 Ground Coverage 2,644.92 1,895.27 Common Plot Area 928.21 928.21 Max. building height 65 m 44.8 m
9. Building Details No. of Buildings:3 No. of Blocks:3 Scope of buildings/blocks: Basement + hollow plinth + 13 floors No.& size of Residential Units: 285 units No. & type of Commercial Units:-- Details of amenities if any: Club house and jogging track
10. No. of expected residents / users
1282
11. Water & waste water details during construction phase
Water requirement (KL/day):15 Source of water: water supply from SMC Waste water generation quantity (KL/day):2.1 Mode of disposal: SMC drain
12. Water & waste water details during operation phase
Fresh water requirement (KL/day):195 Source of water: water supply from SMC Waste water generation quantity (KL/day):147 Mode of disposal: disposed in to SMC drainage line
13. Status of water supply and drainage line
Both drainage and water supply line are exists at site
14. Solid waste Management
Construction Phase: Generation
(m3) Quantity to be reused (m3)
Mode of Disposal / Reuse
Top Soil 800 800 Will be
Page 40 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 40 of 62
utilized for greenbelt development
Excavated earth
3,200 3,200 Will be utilized for back filling and for levelling the low lying areas.
Construction debris
36 kg/day Nil Sold off to recyclers
Steel scrap Discarded packing materials
Operation Phase: Type of waste
Generation Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 450 kg/day Door to Door collection system of SMC
Disposal at Khajod Disposal Site
Wet waste 300 kg/day
Details of segregation if to be done: Separate bins for dry and wet waste will be provided to each unit
Capacity and no. of community bins to be placed within premises:3 nos of bins having capacity of 150 kg each for dry waste and 100 kg for wet waste will be provided to each building.
Landfill site where waste will be ultimately disposed by local authority: Khajod Disposal Site
15. Parking Details Total parking area requirement for the project as per GDCR: 3,097.43 m2
Parking area requirement for residential units as per GDCR: 3,097.43 m2 Total number of CPS requirement for the project as per NBC :169 Number of CPS requirement for residential units as per NBC: 169 Total Parking area provided (m2) & No. of ECS: 8,265.78 m² and 287 ECS Parking area provided in basement (m2) & No. of ECS: 4,905.88 m2 and 154
ECS Parking area provided in hollow plinth (m2) & No. of ECS: 1,830.93 m2 and 66
ECS Parking area provided as open surface (m2) & No. of ECS: 1,528.97 m2 and
67 ECS. 16. Traffic
Management Width of adjacent public roads:24 m and 12 m TP road Number of Entry & Exit provided on approach road/s:two gates will be
provided. Width of Entry & Exit provided on approach road/s:9 m Minimum width of open path all around the buildings for easy access of fire
tender (excluding the width for the plantation): 8 m Width of all internal roads: 9 m & 7.5 m
17. Details of Green Building measures
Provision of aerated coke (Foam Type) in wash basins, kitchen, low flush water closets in toilet, pressure reducing valves in water pipeline, rain water harvesting system and ground water recharge etc.
Page 41 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 41 of 62
proposed. 18. Energy
Requirement, Source and Conservation
Power supply: Maximum demand:1465 KW Connected load:1500 KW Source:Torrent power
Energy saving measures: maximum utilization of natural light,roof-top thermal insulation, CFL lighting fixtures in the common areas, appropriate design to shut out excess heat and gain loss, use of solar energy in external lighting (Landscape lighting), aerated block [Cement + Fly Ash + Air mixture] will be used to reduce heat stress inside building.
DG Sets: No. and capacity of the DG sets: 4 × 60 KVA Fuel & its quantity: Diesel (10 Liter/h) Note : - D.G. Sets will be used in-case of power failure or fire emergency
19. Fire and Life Safety Measures
During operation phase: Fire extinguishers at each floor, hose reel at each floor, wet riser opening at each floor, manually operated electric fire alarm system, terrace water storage tank of 20 KL, underground fire water storage tank of 100 KL, smoke detectors etc.
20. Details on staircase Type & no. of buildings
No. of floors
Floor area
No. of staircase
Width of the staircase
Travel distance (m)
A
13 423.56 m2
1 1.5m Less than 15 m
B 13 866.59 m2
3 1.5m Less than 15 m
C 13 590.06 m2
2 1.5m Less than 15 m
21. Rain Water Harvesting (RWH)
Level of the Ground water table:10 m No. & dimensions of RWH tank(s) :- No. and depth of percolations wells :3 Details on Pre-treatment facilities :only roof top rainwater harvesting is
proposed 22. Green area
details Tree covered area (m2) :1,200 Area covered by shrubs and bushes (m2):400 Lawn covered area (m2):800 Total Green Area (m2): 2,000 Green Area % of plot area:21.55 % No. of trees and species to be planted: 500
23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
Green belt development : 60 Lacs Drainage and rain water harvesting: 50 Lacs Solar and energy saving: 30 Lacs Total: 140 Lacs
24. Proposed dust control measures during the construction phase
Loading & transportation in covered trucks, covered shed provided for cement unloading activity, temporarily wind screen around the project site, sprinkling of water on roads and in vicinity of storage area.
25. Eco friendly building material usage details.
Fly ash bricks, aerated blocks, paving block, RMC, lead free paints etc.
Page 42 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 42 of 62
26. Details on the amenities to be provided to construction workers.
Drinking water, tap water, sanitation facilities, first aid box, free medicines, doctor service, PPEs etc.
27. Documents related to land possession.
N.A order for both the F.P.Numbers shows the land in the name of land owners. Document of Deputy collector stamp duty vibhag-1 shows that the non-agricultural land of F.P.No.49 in the name of applicant. Satakhat between the land owners and the developer for F.P.No.48 has been submitted.
During the meeting, it was noticed by the committee that the project site is at a distance of 108.87 m from the bank of river Tapi. Further, while asking by the committee, it was informed by the project proponent that the area was flooded up to 15 ft. with water at the time of flood in the year 2006. It was presented that they have not proposed any residential unit at ground floor. Residential units will be on the 1st floor at 2.86 m above the High Flood Level. The project proponent committed to plant about 500 trees within premises. After detailed discussion it was decided to recommend the project to SEIAA, Gujarat for grant of Environmental Clearance.
M/s: Sandhya Plasticizers and Chemicals (herein after Project Proponent – PP) has submitted application vide their letter dated 07/01/2015.
Project status: New
Project / Activity Details:
This is a new unit proposes to manufacture various types of Plastic & Paint additives, Organic
Phosphates and PVC stabilizers & Stearates as below:
Sr.
no.
Products/By-Products Quantity
MT/Month
1. Plastic and Paint Additives (Organic Phosphite) Tri Phenyl Phosphite, DiphenylIsodecylphoshite, Diphenyl 2-ehtyl hexyl phosphite, Phenyl Di-IsodecylPhosphite, Tri –DecylPhosphite, Tri TrisdecylPhosphite, TrisNonyl Phenyl Phosphite, etc.,
300
2. Organic Phosphates Tri aryl and Alkyl Phosphate (Triphenyl Phosphate, Tricrisyl Phosphate, Tributyl Phosphate, CresylDiphenyl Phosphate, etc.)
150
3. Plastic stabilizers and stearates (Metallic Octoate, Metallic Stearate, PVC Stabilizers, Organo tin Stabilizers)
500
By products :
1. Hydrochloric Acid( 30 % Solution) 414.90
2. Phenol 146.50
1511.40
Page 43 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 43 of 62
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Total plot area is 5040 sq. m and unit has proposed 1512 sq m area for the green belt development/Tree
plantation.Expected project cost is Rs.3.5 Crores. Total water consumption for proposed project will be 39
KL/D (5 :KL/day for Domestic, 5 KL/day for Gardening & 29 KL/day for Industrial) which will be sourced
from GIDC water supply. Industrial waste water generation will be 6 KL/day, which will be treated in
proposed Primary, Secondary & Tertiary treatment plant and treated waste water will be discharged into
GIDC underground drainage system for further treatment and disposal to Arabian Sea. Domestic waste
water (4 KL/day) will be disposed off into soak pit system.
Flue gas generation will be from one Steam Boiler (1 TPH), one TFH (6000 Kcal/hr) and one D.G. sets
(200 KVA).Agro waste (Baggasse Briquettes- 3 MT/day) will be used as fuel for Boiler and TFH. HSD (50
Lit./hr) Unit has proposed Cyclone separator followed by Bag filter as APCM. Gaseous HCL will be
scrubbed in Water scrubbers attached to the reactors and generated HCL Solution (30 %) will be sold out
as By-product. Hazardous waste generated from the manufacturing activity will be ETP sludge (10
MT/Year), Process residue (27 MT/Year), Discarded containers/Bags/Liners (3400 no.s/Year) and Used
oil (100 Lit. /Year).
Observations/Discussions:
Technical presentation by the PP included general information, details of products and raw materials,
Waste generation, hazards & control, analysis of pollution parameters before and after treatment,
resource consumption and conservation, Risk estimation etc. Safety aspects of Phosphorous Trichloride,
Phosphorus Oxychloride and other hazardous chemicals have been discussed. The committee desired to
have MSDS of materials to be handled, information on storage of each hazardous chemical and safety
measures thereof. Occupational health related issues due to lead compounds and other toxic chemicals
have been discussed and committee asked to provide necessary Personal Protective Equipments [PPEs]
and requisite first aid measures. Committee suggested reuse/recycle of treated waste water to the
maximum extent and minimizes the effluent discharge to the CETP. After detailed discussion, the
following additional Terms of Reference were prescribed for the EIA study to be done covering 5 Km
radial distance from the project boundary.
1. Copy of plot holding certificate obtained from GIDC Sarigam.
2. Present land use pattern of the study area shall be given based on satellite imagery.
3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.
4. Details of manufacturing process / operations of each product along with chemical reactions, mass balance, consumption of raw materials etc. Details on strategy for the implementation of cleaner production activities. (Give specific details about source of effluent generation).
5. Chemical name of each proposed product to be manufactured. Details on end use of each product.
6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream from the processes.
7. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the project. Permission obtained from the GIDC for supply of raw water. Undertaking stating that
Page 44 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 44 of 62
no bore well shall be dug within the premises.
8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.
9. Quality and quantity of waste water to be generated from the manufacturing process of each product to be manufactured along with mass balance.
10. Stream wise qualitative & quantitative analysis of each waste stream (including process water, cooling tower blow down, boiler blow down, washing effluent etc.) to be generated. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated. The characteristic on which treatability is based shall also be stated.
11. Details of the ETP units including its capacity, size of each unit, retention time and other technical parameters. Details regarding provision of online continuous pH meter, TOC analyser and flow meter at the final outlet of the ETP.
12. Details of CETP- Sarigam including (1) Total capacity of the CETP (2) Actual load at present (Qualitative and Quantitative – per day) (3) CETP Up gradation scheme, if any (4) Last 6 analysis Reports of GPCB for Inlet and outlet of CETP (5) Spare capacity of CETP with treatability and feasibility report.
13. Plans for management, collection and disposal of waste streams to be generated from spillage, leakages, vessel washing, used container washing etc. Measures proposed for preventing effluent discharge during unforeseen circumstances.
14. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be incorporated.
15. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 5 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
16. One complete season base line ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
17. Modelling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modelling should be provided. The air quality contours may be shown on location map clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modelling should be superimposed on satellite image / geographical area map.
18. Base line status of the noise environment, impact of noise on present environment due to the project and proposed measures for noise reduction including engineering controls.
Page 45 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 45 of 62
19. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.
20. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized. Methodology of de-contamination and disposal of discarded containers and its record keeping.
21. Membership of Common Environmental Infrastructure including CETP, TSDF, Common Hazardous Waste Incineration Facility (CHWIF). (Whichever is applicable)
22. Complete Management plan for By-products/Spent acids to be generated, (if any) from the project including their quantity, quality, characteristics, end use etc. along with the name and address of end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from them, showing their willingness to purchase said by-product from the proposed project. Also give characteristics of the by products and feasibility of their actual use in respective products as a raw material.
23. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.
24. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/Year earmarked for environment pollution control measures.
25. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.
26. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical checkup of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.
27. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the plant layout map clearly showing which of the facilities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.
28. MSDS of all the products and raw materials.
29. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impacts. This shall include the details of Antidotes also.
Page 46 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 46 of 62
30. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals, size of the biggest storage tank to be provided for each raw material & product etc. How the manual handling of the hazardous chemicals will be minimized?
31. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.
32. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.
33. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.
34. Detailed socio-economic development measures including community welfare program most useful in the project area for the overall improvement of the environment. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions for the next five years and activities proposed to be carried out; specific to the current demographic status of the area.
35. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.(b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.
36. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.
37. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.
38. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.
39. A tabular chart with index for point-wise compliance of above TORs.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be considered as
generic TORs for preparation of the EIA report in addition to all the relevant information as per the
generic structure of EIA given in Appendix III in the EIA Notification, 2006. The project shall be appraised
M/s: Uniform Synthetics Unit II (herein after Project Proponent – PP) has submitted application vide their letter dated 07/01/2015.
Project status: New
Project / Activity Details:
This is a new unit proposes the manufacturing of following Synthetic Organic Chemicals:
Sr. No. Product Name Quantity (MT/Month)
5. Ketonic Resin 200.00
6. Phenolic Resin 50.00
7. Alkyd Resin 200.00
8. Acrylic Resin 100.00
9. Poly Urethane Resin 50.00
10. Polyamide Resin 100.00
11. Paints 100.00
12. Liquid Gum Rosin of various grade (By mixing and
blending) 100.00
TOTAL 900.00
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
Total plot area is 1122.50 sq. m & unit has proposed 243.41 sq. m area for green belt development/Tree
plantation. Expected project cost is Rs. 1.30 Crores. Total water consumption for proposed project will be
37.50 KL/D (5 :KL/day for Domestic, 2 KL/day for Gardening & 30.5 KL/day for Industrial) which will be
sourced from GIDC water supply. Industrial waste water generation will be 24 KL/day, which will be
treated in proposed Primary, Secondary & Tertiary treatment plant and treated waste water will be
discharged into closed drainage line to CETP, GIDC, Sarigam. Domestic waste water (4 KL/day) will be
Page 49 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 49 of 62
disposed off into soak pit system. Flue gas generation will be from one TFH (4 Lac Kcal/hr) and one stand
by DG set. Natural gas (265 SCM/day) or LDO (50 lit/hr) will be used as fuel for TFH and HSD (50 lit/hr)
will be used as fuel for DG set. No process gas emission is envisaged. Hazardous waste generated from
the manufacturing activity will be ETP sludge (15 MT/Year), Discarded containers (300 no.s /Year) &
Discarded bags/liners (600 no.s/Year) and Used oil (100 lit./Year).
Observations/Discussions:
Technical presentation by the PP included general information, details of products and raw materials,
Waste generation, hazards & control, analysis of pollution parameters before and after treatment,
resource consumption and conservation, Risk estimation etc. Committee discussed about the
performance of the CETP Sarigam and suggested reuse/recycle of treated waste water to the maximum
extent and minimizes the effluent discharge to the CETP. After detailed discussion, the following
additional Terms of Reference were prescribed for the EIA study to be done covering 5 Km radial
distance from the project boundary.
1. Copy of plot holding certificate obtained from GIDC Sarigam.
2. Present land use pattern of the study area shall be given based on satellite imagery.
3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.
4. Details of manufacturing process / operations of each product along with chemical reactions, mass balance, consumption of raw materials etc. Details on strategy for the implementation of cleaner production activities. (Give specific details about source of effluent generation).
5. Chemical name of each proposed product to be manufactured. Details on end use of each product.
6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative and quantitative analysis of the each waste stream from the processes.
7. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the project. Permission obtained from the GIDC for supply of raw water. Undertaking stating that no bore well shall be dug within the premises.
8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes. Details of methods to be adopted for the water conservation.
9. Quality and quantity of waste water to be generated from the manufacturing process of each product to be manufactured along with mass balance.
10. Stream wise qualitative & quantitative analysis of each waste stream (including process water, cooling tower blow down, boiler blow down, washing effluent etc.) to be generated. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to be generated. The characteristic on which treatability is based shall also be stated.
11. Details of the ETP units including its capacity, size of each unit, retention time and other technical parameters. Details regarding provision of online continuous pH meter, TOC analyser and flow meter at the final outlet of the ETP.
12. Details of CETP- Sarigam including (1) Total capacity of the CETP (2) Actual load at present (Qualitative and Quantitative – per day) (3) CETP Up gradation scheme, if any (4) Last 6 analysis
Page 50 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 50 of 62
Reports of GPCB for Inlet and outlet of CETP (5) Spare capacity of CETP with treatability and feasibility report.
13. Plans for management, collection and disposal of waste streams to be generated from spillage, leakages, vessel washing, used container washing etc. Measures proposed for preventing effluent discharge during unforeseen circumstances.
14. One season Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall should be incorporated.
15. Anticipated environmental impacts due to the proposed project/production may be evaluated for significance and based on corresponding likely impacts VECs (Valued Environmental Components) may be identified. Baseline studies may be conducted within the study area of 5 km for all the concerned/identified VECs and likely impacts will have to be assessed for their magnitude in order to identify mitigation measures.
16. One complete season base line ambient air quality data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall be in accordance with the revised National Ambient Air Quality Standards as well as project specific parameters. Locations of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors. There should be at least one monitoring station in the upwind direction. There should be at least one monitoring station in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.
17. Modelling indicating the likely impact on ambient air quality due to proposed activities. The details of model used and input parameters used for modelling should be provided. The air quality contours may be shown on location map clearly indicating the location of sensitive receptors, if any, and the habitation. The wind rose showing pre-dominant wind direction should also be indicated on the map. Impact due to vehicular movement shall also be included into the prediction using suitable model. Results of Air dispersion modelling should be superimposed on satellite image / geographical area map.
18. Base line status of the noise environment, impact of noise on present environment due to the project and proposed measures for noise reduction including engineering controls.
19. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed measures to control it.
20. Details on management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling, its utilization and disposal etc. How the manual handling of the hazardous wastes will be minimized. Methodology of de-contamination and disposal of discarded containers and its record keeping.
21. Membership of Common Environmental Infrastructure including CETP, TSDF, Common Hazardous Waste Incineration Facility (CHWIF). (Whichever is applicable)
22. Complete Management plan for By-products/Spent acids to be generated, (if any) from the project including their quantity, quality, characteristics, end use etc. along with the name and address of end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from
Page 51 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 51 of 62
them, showing their willingness to purchase said by-product from the proposed project. Also give characteristics of the by products and feasibility of their actual use in respective products as a raw material.
23. Name and quantity of each type of solvents to be used for proposed production. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency feasibility of reusing the recovered solvents etc. for each type of solvent.
24. A detailed EMP including the protection and mitigation measures for impact on human health and environment as well as detailed monitoring plan and environmental management cell proposed for implementation and monitoring of EMP. The EMP should also include the concept of waste-minimization, recycle/reuse/recover techniques, energy conservation, and natural resource conservation. Total capital cost and recurring cost/Year earmarked for environment pollution control measures.
25. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.
26. Occupational health impacts on the workers and mitigation measures proposed to avoid the human health hazards along with the personal protective equipment to be provided. Provision of industrial hygienist and monitoring of the occupational injury to workers as well as impact on the workers. Plan for periodic medical checkup of the workers exposed. Details of work place ambient air quality monitoring plan as per Gujarat Factories Rules.
27. Risk assessment including prediction of the worst-case scenario and maximum credible accident scenarios should be carried out. The worst-case scenario should take into account the maximum inventory of storage at site at any point of time. The risk contours should be plotted on the plant layout map clearly showing which of the facilities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan should be provided.
28. MSDS of all the products and raw materials.
29. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impacts. This shall include the details of Antidotes also.
30. Details of quantity of each hazardous chemical (including solvents) to be stored, Material of Construction of major hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals, size of the biggest storage tank to be provided for each raw material & product etc. How the manual handling of the hazardous chemicals will be minimized?
31. Details of the separate isolated storage area for flammable chemicals. Details of flame proof electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control plan for flammable substances and processes showing hydrant pipeline network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.
32. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, manufacturing utility staff for safety related measures.
33. Detailed five year greenbelt development program including annual budget, types & number of trees to be planted, area under green belt development [with map], budgetary outlay; along with commitment of the management to carry out the tree plantation activities outside the premises at appropriate places in the nearby areas and elsewhere.
Page 52 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 52 of 62
34. Detailed socio-economic development measures including community welfare program most useful in the project area for the overall improvement of the environment. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions for the next five years and activities proposed to be carried out; specific to the current demographic status of the area.
35. (a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report.(b). Does the Environment Policy prescribe for standard operating process / procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If so, it may be detailed in the EIA.
36. What is the hierarchical system or administrative order of the company to deal with the environmental issues and for ensuring compliance with the EC conditions? Details of this system may be given.
37. Does the company have a system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism should be detailed in the EIA Report.
38. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be incorporated in the EIA Report.
39. A tabular chart with index for point-wise compliance of above TORs.
The above mentioned project specific TORs/additional TORs and the model TORs available in the
MoEF’s sector specific EIA Manual for Synthetic Organic Chemical industry shall be considered as
generic TORs for preparation of the EIA report in addition to all the relevant information as per the
generic structure of EIA given in Appendix III in the EIA Notification, 2006. The project shall be appraised
The proposed production activity falls in the project/activity 5(f) as per the schedule of the EIA
Notificaiton-2006.
The location of the unit is outside the notified area. As per amendment to EIA Notification, 2006 vide SO
1599 (E) dated 25.06.2014, small units are categorized as Category “B” projects. Small units are defined
Page 53 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 53 of 62
as with water consumption less than 25 M3/day; Fuel consumption less than 25 TPD; and not covered in
the category of MAH units as per the Management, Storage, Import of Hazardous Chemical Rules
(MSIHC Rules), 1989. During presentation, PP informed that water requirement is 5.69 KL/day. Fuel
requirement is 2.3 MT/day and Chemicals to be used are not covered in MAH category. Hence, this
project falls under Category B of project activity 5(f) as per the EIA Notification 2006.
Total plot area is 1218.22 sq. m. Unit has proposed 452.62 sq mtr area for the green belt
development/Tree plantation.Expected project cost is Rs.1 Crores. Total water consumption for proposed
project will be 5.69 KL/D (0.5 KL/day for domestic, 0.8 KL/day for Gardening & 4.4 KL/day for Industrial
purpose) which will be sourced from Tanker supply. Industrial waste water generation will be 0.35 KL/day,
which will be treated in proposed Primary, treatment plant and treated waste water will be evaporated in
steam jacketed evaporator. Domestic waste water (0.45 KL/day) will be disposed off into soak pit system.
Flue gas generation will be from Steam Boiler (1 TPH), HAG and D.G. sets (50 KVA). Bio coal (2.3
MT/day) will be used as fuel. Unit has proposed Cyclone separator followed by Bag filter as APCM. No
process gas emission is envisaged. Hazardous waste generated from the manufacturing activity will be
ETP sludge (1.8 MT/Year), Discarded containers/Bags/Liners and Used oil.
Observations & Discussions: Presentation made by the proponent included the general information about the project, plant layout, raw
material & resource consumption, manufacturing process, water balance diagram & waste water
treatment scheme, hazardous waste generation and its disposal etc. The project proponent requested for
categorizing the project as B2 and to exempt them from carrying out detailed EIA study. Looking to the
small scale of the project, technical aspects of the project, low pollution potential and the details
presented during the meeting, after detailed elaboration, request was considered & the project was
categorized as B2 category project. Following additional information was sought for appraisal of the
project.
1. Land Possession Documents of the proposed site.
2. Project site specific details such as distance of the project site from the nearest (1) Village-Nearest residential area (2) Water Body: Creek / Nallah / Lake / Pond / Reservoir / Canal (3) National Highway (4) State Highway (5) Railway line (6) Heritage site (7) National Park / Wild Life Sanctuary (8) Aanganwadi/School/College/Institute etc. and likely impact on them due to the proposed project along with the mitigation measures proposed to minimize the likely impact. Give satellite image of 5 KM radius.
3. Legal Undertaking stating that unit is complying the three conditions [i.e. water consumption less than 25 M3/day; Fuel consumption less than 25 TPD; and not covered in the category of MAH units as per the Management, Storage, Import of Hazardous Chemical Rules (MSIHC Rules), 1989] as per the amendment to EIA Notification, 2006 vide SO 1599 (E) dated 25.06.2014.
4. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in the plant layout.
5. Proposed monthly production of each grade of resin and product wise monthly consumption of each raw material.
6. Manufacturing process along with chemical reactions, mass balance for each product.
Page 54 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 54 of 62
7. Assessment of source of the water supply with adequacy of the same to meet with the requirements for the project. Copy of permission letter obtained from the CGWA or concern authority for drawl of raw water.
8. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative analysis of each waste stream to be generated.
9. Plans for management and disposal of waste streams to be generated from spillage, leakages, vessel washing, used container washing etc. Measures proposed for preventing effluent discharge during unforeseen circumstances.
10. Details of the ETP including size of each unit, retention time, other technical parameters etc. and its adequacy and efficacy report. Treatment of phenol in the effluent, if any. Action plan for ‘Zero’ discharge of effluent shall be included.
11. Explore the possibility of reuse / recycle and other cleaner production options for reduction of wastes and to conserve fresh water.
12. Details of provisions to be made for evaporation of industrial effluent. Technical details of effluent evaporation system including evaporation capacity, steam required for evaporation, adequacy of the boilers to supply steam for evaporation in addition to the steam required for the process etc. Techno-economical viability of the evaporation system.
13. Details of possibility of chemical seepage & consequent soil contamination & mitigation measure proposed for the same for the proposed project.
14. Specific details of (i) Details of the utilities required (ii) Type and quantity of fuel to be used for each utility (iii) Flue gas emission rate from each utility (iv) Air Pollution Control Measures proposed to each of the utility along with its adequacy (v) List the sources of fugitive emission along with its quantification and proposed measures to control it.
15. Specific details of fugitive emission from the unit along with its quantification and proposed measures to control it along with measures proposed to monitor VOC within work area. Details of ventilation system proposed in the work area. Measures proposed to keep the work area environment as per the norms of GFR.
16. Details of measures proposed for noise pollution abatement & its monitoring.
17. Details of management of the hazardous wastes to be generated from the project stating detail of storage area for each type of waste, its handling and its disposal. How the manual handling of the hazardous wastes will be minimized?
18. Methodology of de-contamination and disposal of discarded containers and its record keeping.
19. Measures proposed to be taken for the work area ambient air quality monitoring as per Gujarat Factories Rules.
20. A detailed EMP including the protection and mitigation measures for preventing impacts on human health and environment as well as detailed monitoring plan with respect to various parameters and responsible head for the environmental management cell and environmental management cell proposed for implementation and monitoring of EMP.
21. Detailed socio-economic development measures including community welfare program most useful in the project area for the overall improvement of the environment.
22. A detailed Green Belt Development Program including annual budget, types & number of trees to be planted, area under green belt development [with map]; along with commitment of the management to
Page 55 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 55 of 62
carry out the tree plantation activities outside the premises at appropriate places in the GIDC area and elsewhere.
23. Details of hazardous characteristics and toxicity of raw materials and products to be handled and the control measures proposed to ensure safety and avoid the human health impacts. This shall include the details of Antidotes also.
24. Details of quantity of each hazardous chemical to be stored, Material of Construction of major hazardous chemical storage tanks, threshold storage quantity as per schedules of the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals. How the manual handling of the hazardous chemicals will be minimized?
25. Details of the separate isolated storage area for chemicals. Details of fire extinguishers, flame proof electrical fittings, DCP extinguishers and other safety measures proposed.
26. Specific safety details / provisions for various hazardous chemicals and detailed fire control plan for flammable substances.
27. Details of possibilities of occupational health hazards from the proposed manufacturing activities and proposed measures to prevent them.
28. Detailed risk assessment report including prediction of the worst-case scenario and maximum credible accident scenario along with damage distances and preparedness plan to combat such situation and risk mitigation measures. Vulnerable zone demarcation.
29. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE, mfg utility staff for safety related measures.
30. A tabular chart with index for point-wise compliance of above details.
The project shall be appraised on satisfactory submission of the above.
17. Indraprasth Residency (Shlok Developers)
F.P.No.89,T.P.S>No.31, (University Campus), Vastrapur, West City, Ahmedabad
Screening & Scoping
Details of the proposed project as presented before the committee is tabulated below:
Sr. No. Particulars Details 1. Proposal is for Residential building construction project.
2. Type of Project “Indraprasth Residency” (4 BHK residential Apartments) 3. Project / Activity
No. [8(a) or 8(b)] Category ‘B’, 8(a)
4. Name of the project
Indraprasth Residency
5. Name of Developer
M/s. Shlok Developers
6. Estimated Project Cost (Rs. In Crores)
88 Crore
Page 56 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 56 of 62
7. Whether construction work has been initiated at site? If yes, details thereof
Construction Not Started
8. Project Details Land / Plot Area (m2) : 7,163.0 Total FSI area (m2): 28,637.02 Total BUA (m2): 48,394.20
Permissible Proposed FSI Area (m2) 28652 m² 28637m² Ground Coverage (m2) 3598.15 m² 3598.15 m²
Common Plot Area (m2) 716.30 m² 719.63 m² Max. building height (m) 45 m 45 m
9. Building Details No. of Buildings: 3 Buildings No. of Blocks: 3 Scope of buildings/blocks: 2 level basement + hollow plinth +14 floors. No. & size of Residential Units: 126 Flats, 211.75 m² floor area No. & type of Commercial Units: Not Applicable Details of amenities if any: Not Applicable
10. No. of expected residents / users
Fixed population = 630 persons Floating population = 224person
11. Water & waste water details during construction phase
Water requirement (KL/day): 25 Source of water: Local water tanker supplier/AMC Waste water generation quantity (KL/day): 4 Mode of disposal: Septic tank / Soak pit system Details of reuse of water, if any: None
12. Water & waste water details during operation phase
Fresh water requirement (KL/day): 102 Source of water: AMC Waste water generation quantity (KL/day): 76 Mode of disposal: Sewage will be discharged into AMC drainage
system 13. Status of water
supply and drainage line
AMC water supply/drainage line system is available in the area.
14. Solid waste Management
Construction Phase:
Generation (m3)
Quantity to be reused
(m3)
Mode of Disposal / Reuse
Top Soil 5,043 5043 Will be stored onsite and used for development of greenbelt.
Other excavated earth
44,593
44593
Will be used for re-filling of foundation & plinth, green belt and leveling low lying areas at project site itself, excess (if any) will be sent to another site where need may be exist.
Construction 800 800 Will be used for leveling,
Page 57 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 57 of 62
debris roads, pavements etc. Steel scrap Whatsoever -- Will be returned to supplier
or sold to scarp dealer/ end users.
Discarded packing materials
Whatsoever -- Will be returned to supplier /sold to authorized recycler
Operation Phase: Type of waste Generation
Quantity (Kg/day)
Mode of waste collection
Mode of Disposal / Reuse
Dry waste 315
Two separate bins (one for dry and one for wet waste) each of 10 L capacity will be provided to each unit. These bins will be emptied in to community bins to be provided at various locations.
The said common community bins will be regularly emptied by A.M.C.
Wet waste
Details of segregation if to be done: yes Two separate bins (one for dry and one for wet waste) each of 10 L
capacity will be provided to each unit. Capacity and no. of community bins to be placed within premises: 16
community bins of 80 lit capacity will be provided at various locations 15. Parking Details Total parking area requirement for the project as per GDCR:
5,730.4 m2 Parking area requirement for residential units as per GDCR:
5,730.4 m2 Total number of CPS requirement for the project as per NBC :
126 CPS Number of CPS requirement for residential units as per NBC :
126 CPS Total Parking area provided (m2) & No. of ECS:
9,006.82 m2 & 283 CPS Parking area provided in basement (m2) & No. of ECS:
8,407 m2 & 262 CPS Parking area provided in hollow plinth (m2) & No. of ECS:
599.82 m2 & 21 CPS 16. Traffic
Management Width of adjacent public roads: 18 m wide road Number of Entry & Exit provided on approach road/s:
Two entry/ exit will be provided. Width of Entry & Exit provided on approach road/s: 7.5 m & 6.0 m Minimum width of open path all around the buildings for easy access of
fire tender (excluding the width for the plantation): 3 m Width of all internal roads: Main internal approach road 7.5 m
Page 58 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 58 of 62
17. Details of Green Building measures proposed.
Use Fly ash paver blocks for pavements/walkways, most of the carpentry structures will be made up of processed engineering wood/ particle board instead of wood, solar lighting will be provided in common sunlit areas, aluminum window frame & marble door frame instead of wood, PVC electrical boards will be provided, maximum use of Portland Pozzolona Cement (PPC) - contains high amount of fly ash, maximum use of Ready Mix Concrete (RMC), rainwater harvesting by recharging the ground water table with provision for 5 percolation wells etc.
18. Energy Requirement, Source and Conservation
Power supply: M/s.Torrent Power Ltd. Maximum demand: Estimated requirement During construction phase: 35 kW and During operation phase: 0.6 MW. Connected load: --
Source: M/s.Torrent Power Ltd. Energy saving by Non-conventional Methods: Solar Lighting will be
provided in common areas Energy saving measures: Maximum use of LED lights, solar lighting in
common sunlit areas, use of variable frequency drive motors, maximum use of natural daylight as well as natural ventilation, use of building material having lower U-value and the insulating material having higher R-value to have optimum energy performance, maximize the use of light and silent colours in the building envelope so that UV absorption is reduced and associated cooling requirements are minimized etc.
DG Sets: Not Provided 19. Fire and Life
Safety Measures Nearest fire station is Bodakdev Fire Station approx. (2.0 km), Time
required for the fire tender to reach at the project site is 5-10 minutes.
During operation phase: Fire extinguishers, fire hydrant system, hose reels, down comers in common areas, manual alarm system, sprinkler system in basement, two nos. of underground water tank each having 100 KL capacity, overhead tanks of capacity 20 KL on each building,
During the construction phase: All electrical fittings/equipments will meet the relevant IS standards, Personal Protective Equipments like earplugs, dust masks, safety shoes, helmets, hand gloves etc. will be provided to all workers, completely concealed copper wiring, “H” frame scaffolds & ladders made of mild steel, all workers will be trained to use welding shields and follow safer practice, provision related to first aid for the construction workers, fire extinguishers in common areas, maintaining hoists and lifts, lifting machines, chains, ropes, and other lifting tackles in good condition, commit to register the project under “The Building & Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996”.
20. Details on staircase Type & no. of buildings
No. of floors
Floor area (m2)
No. of staircase
Width of the staircase
(m)
Travel distance
(m) 3 A G+14 635.27 2 2 16.5 m
(Max) B 635.27 2 2 C 635.27 2 2
Page 59 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 59 of 62
21. Rain Water Harvesting (RWH)
Level of the Ground water table: depth of water level 40m as per CGWB report
No. & dimensions of RWH tank(s): 2 nos. RWH structure of 0.45 m dia. and 40 m depth having rainwater catchment pit and sand filtration media will be provided.
No. and depth of percolations wells : 2 nos., 40 m
Details on Pre-treatment facilities : Before recharging rain water, suitable arrangements of filtering (preferably sand filtration media) will be provided. Gratings at mouth of each drainpipe will be provided on terraces to trap leaves, debris and floating materials. Filter media will be cleaned before every monsoon season. First rain separator will be provided to flush off first rains.During rainy season, the whole system (roof catchment, pipes, screens, first flush, and filters) will be checked before and after each rain and preferably cleaned after every dry period exceeding a month.
22. Green area details
Tree covered area (m2) : 972 Area covered by shrubs and bushes (m2):-- Lawn covered area (m2): 461 Total Green Area (m2): 1433 Green Area % of plot area: 20 % No. of trees and species to be planted: Local species such as
Asopalav, Neem, Gulmohar will be preferred for plantation. 23.
Budgetary allocation for Environmental Management Plan (Rs. in lacs)
(Please specify the activities and break up of budget allocation)
Description Cost (Rs. in Lacs)
Remarks
During Construction
Air pollution control
6 Training of workers to use welding shields and follow safe practice
Service of vehicles and PUC certificate
Provision of tarpaulin sheet covers
Provision of PPE to workers
Waste water management
2 Septic tank / soak pit system.
Solid waste management
2 Making Storage area, collection and disposal
Noise control 0.5 Ear plugs to workers Periodic checking of noisy
machinery Provision of sound enclosures
During Operation
Waste water management
2.0 AMC charges
Page 60 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 60 of 62
Solid waste management
2.0 Provision of bins, AMC charges
Greenbelt development
1 100 nos. of trees planted
Ground water recharge
3 Construction of 2 percolation wells, Water pre-treatment arrangements
Total 18.5 --
24. Dust control measures
Temporary windshield barriers, regular water sprinkling, covering the material with tarpaulin sheet covers during the transportation, Maximum use of Ready Mix Concrete (RMC), uniform piling of sand and proper storage to avoid dusting.
25. Eco friendly building materials
Use of RMC, fly ash paver blocks, carpentry structures made up of processed engineering wood instead wood
26. Details of basic amenities to be provided to construction workers
Adequate sanitation facilities, drinking water, bins for collection of municipal solid waste.
27. Documents related to land possession.
Registrar’s index shows the land in the name M/s Shlok Developers through its partner Shri Dineshbhai M. Patel.
During the meeting, after detailed discussion it was decided to consider the project only after submission of the following:
1. Copy of permission obtained for non-agricultural use of the project site or a copy of
correspondences made in this regard.
Table Agenda: The additional information received from the project proponents, which was sought during various SEAC meetings for granting Environmental Clearance to the projects. The said submissions by the project proponents were considered by the committee during the meeting and as it was found satisfactory, the committee decided to recommend the following projects for grant of environmental clearance.
576, 578,580,581,583/2,582,584 of Nasmed Village and 336,339, 346,347, 347/1, 347/p1, 347/p2,348,349,350,352/1,352/2353/1,353/2,355,355/1,356,357,357/1p1,357/1p2,358, 359/2,363,364,365/1,366,367,368,369,370,371,374,376,379/p1,379/2,351,335,375,365/2,337,338,360,361 of Adhana Village, Nasmed and Adhana, Kalol, Gandhinagar.
18. Agricultural Produce Market Committee (Retail and Wholesale Market) , Plot No:1651/A,1651/B,1707, 1711(Ward no.4), Surat.
19. Rahil Malaviya, Block No.128/p,129, Devadh, Choryasi, Surat. 20. Gokulam Bunglow, Block No:864, Moje:Mota, Bardoli, Surat. 21. Gokulam Twin Bunglow, Block No:862/P/1 & 862/P/2, Moje:Mota, Ta:Bardoli, Surat. 22. Shiv Shakti Township, S.No.88,89,90/1,166/2, Village:Saran, Ta:Pardi, Dist:Valsad 23. Akibah Heights (Myco Infra Pvt. Ltd.), R.S.No.593,F.P.No.49/1,O.P.No.49,S.P.No.1
2. Laxmi Enclave (A Project of Laxmi Shelter), T.P.No.19,S.No.271
F.P.No.122,Katargam, Surat.
3. Champakbhai M. Sopariwala, T.P.46(Jahangirpura) O.P.No.36, F.P.No.83, Block
No.96, Jahangirpura,Surat.
It was decided to call them (sr. no.2 & 3) in one of the upcoming meetings of SEAC.
The project proponents at sr. no. (1) above i.e. M/s: Sakar Glazed Tiles Pvt. Ltd. have submitted a letter for exempting them from obtaining environmental clearance.
As per their letter dated 20/08/2014, PP requested to exempt from obtaining
Page 62 of 62
(230th meeting of SEAC-Gujarat, Dated 24.03.2015) Page 62 of 62
environmental clearance as per the amendment in EIA notification dated 25/06/2014.
This project was for installing gas based power plant of 1 MW capacity. As per the
amendment in EIA notification dated 25/06/2014, Gas based power plants having
capacity less than 50 MW are exempted. In view of this, the request was considered by
the committee and it was decided to delist the proposal from the list of the applications
for getting Environmental Clearance pending with SEAC, Gujarat and to close the file.
Meeting ended with thanks to the Chair and the Members.