Top Banner
Minutes of 191 st SEAC Meeting Date: 14/09/2014 The 191 st meeting of SEAC was held in Directorate of Environment, U.P. on 14/09/2014. Following members were present in the meeting along with Secretary, SEAC: 1. Dr. M. S. Khan, Chairman 2. Dr. S. N. Singh, Member 3. Dr. A. K. Singh, Member 4. Shri S. C. Brahmachari, Member 5. Dr. D. C. Gupta, Member 6. Dr. R.K. Sardana, Secretary The Chairman welcomed the members to the 191 st SEAC meeting. The Members of SEAC unanimously taken following decisions on the agenda points discussed: 1- IT Building at Plot No-A-46, Sec.-62, Noida, UP. M/S HSL Software Pvt. Ltd., E-20 Lajpat Nagar-III, New Delhi. File No. 114/DD-Sh. The committee noted that the application for environmental clearance on above project was submitted to SEIAA on dated 08/05/2014. Project proponent through letter dated 11/08/2014 submitted that the project has been submitted for green building certification from Indian Green Building Council (IGBC). A presentation was made by the Ms. Richa Singh, Project proponent along with their consultant M/s ENV Developmental Assistance Systems Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee that:- 1. The environmental clearance is sought for proposed IT Building Project “Proplarity Bizlife” at Plot No-A-46, Sec.-62, Noida, UP. M/S HSL Software Pvt. Ltd. 2. Area details of the project is as follows: S. No. AREA STATEMENT % 1. Type of Building Institutional 2. Plot Area 20,000.0 m 2 100 3. Permissible Ground Coverage (30%) 6000 m 2 30 4. Proposed Ground Coverage (29.9%) 5998.19 m 2 29.9 5. FAR Area Allowed (2.5) 50,000 m 2 6. Extra Permitted FAR for LEED Gold Rating (5% of FAR) 2,500 m 2 7. Service Area (15% of FAR) 7500 m 2 8. Extra FAR due to 10% compounding 5,000 m 2 9. Extra FAR due to METRO (5% of FAR) 2500 m 2 10. Total Permissible FAR (3.38) 67,500 m 2
50

Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Jun 09, 2018

Download

Documents

dinhkien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Date: 14/09/2014

The 191st meeting of SEAC was held in Directorate of Environment, U.P. on 14/09/2014.

Following members were present in the meeting along with Secretary, SEAC:

1. Dr. M. S. Khan, Chairman

2. Dr. S. N. Singh, Member

3. Dr. A. K. Singh, Member

4. Shri S. C. Brahmachari, Member

5. Dr. D. C. Gupta, Member

6. Dr. R.K. Sardana, Secretary

The Chairman welcomed the members to the 191st SEAC meeting.

The Members of SEAC unanimously taken following decisions on the agenda points discussed:

1- IT Building at Plot No-A-46, Sec.-62, Noida, UP. M/S HSL Software Pvt. Ltd., E-20 Lajpat

Nagar-III, New Delhi. File No. 114/DD-Sh.

The committee noted that the application for environmental clearance on above project was

submitted to SEIAA on dated 08/05/2014. Project proponent through letter dated 11/08/2014 submitted

that the project has been submitted for green building certification from Indian Green Building Council

(IGBC). A presentation was made by the Ms. Richa Singh, Project proponent along with their consultant

M/s ENV Developmental Assistance Systems Pvt. Ltd. The proponent, through the documents

submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for proposed IT Building Project “Proplarity Bizlife” at

Plot No-A-46, Sec.-62, Noida, UP. M/S HSL Software Pvt. Ltd.

2. Area details of the project is as follows:

S. No. AREA STATEMENT %

1. Type of Building Institutional

2. Plot Area 20,000.0 m2

100

3. Permissible Ground Coverage (30%) 6000 m2

30

4. Proposed Ground Coverage (29.9%) 5998.19 m2

29.9

5. FAR Area Allowed (2.5) 50,000 m2

6. Extra Permitted FAR for LEED Gold

Rating

(5% of FAR)

2,500 m2

7. Service Area (15% of FAR) 7500 m2

8. Extra FAR due to 10% compounding 5,000 m2

9. Extra FAR due to METRO (5% of FAR) 2500 m2

10. Total Permissible FAR (3.38) 67,500 m2

Page 2: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 2 of 50

11. FAR Area proposed 59,999.8 m2

(2.99)

12. NON FAR

Basement (Level 1)

Basement (Level 2)

Services

Total Non-FAR

15046.272 m2

15828.759 m2

23229.8 m2

54104.84 m2

13. Built up Area 1,14,104.64 m2

14. Open Area 14001.81 m2

70

15. Landscape Area (50% of Open Area) 7000.91 m2

35

17. Area Under Roads and Parking 7000.0 m2

35

16. Number of Trees Required (One tree per 100 m2

of

open space) Number of Trees Provided

140 150

18. Parking Facilities Required: 1200 ECS Provided: 1200 ECS Basement (Level 1) : 423 ECS Basement (Level 2) : 448 ECS Ground Floor: 242 ECS Open Space: 84 ECS

19. Power Requirement and Source Backup Power

5000 kVA, (Noida Power

Corporation Ltd) 1010 kVA x 5 DG sets

3. Water calculation details of the project is as follows:

S. No. Particulars Total Population Fresh

water

(KLD)

Recycling/

Flushing water

(KLD)

Total

Domestic

water

(KLD)

1. IT/ITES

@ 45 lpcd

15000

450

@ 30 lpcd

225

@ 15 lpcd

675

2. Service Staff

@ 45 lpcd

1000 30

@ 30 lpcd

15

@ 15 lpcd

45

Total Domestic Water Requirement 480 240 720

Horticulture @ 1L/sqm (7000.91 sq m) 7 7

DG cooling @ 0.9/kVA/no. of hrs (6 hrs) of

operation

27 27

HVAC (Capacity – 1900 TR, 9 litres per tonnage of

18 hrs of operation)

309 309

Total water requirement 480 583 1063

4. Water and waste water details of the project is as follows:

Fresh water 480 KLD

Flushing 240 KLD

Horticulture / Landscape 7 KLD

HVAC 309 KLD

Page 3: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 3 of 50

DG set cooling 27 KLD

Total water requirement 1063 KLD

Waste water 648 KLD

Source of water - Municipal Water Supply/ Recycle of treated effluent

STP Capacity – 780 KLD (20 % extra for future expansion)

5. Solid waste generation details of the project is as follows:

S.No. Particulars Population Waste generated

(kg/day) 1. IT/ITES Offices (@ 0.2 kg/day) 15,000 3000

2. Service Staff (@ 0.2 kg/day) 1000 200

Total Solid waste generated Approx. 3.2 Tones/day

Horticulture Waste (0.0037 kg/sq m/ day) 20 Kg/Day

E-Waste (0.15 kg/C/Yr) 6 Kg/Day

STP Sludge (20%of waste water) 120 Kg/Day

6. 05 nos. of rain water harvesting pits is proposed for the project.

7. The project proposals are covered under category 8”a” of EIA Notification, 2006.

The committee discussed the matter and directed the project proponent to submit following

information/clarifications:

1. Copy of development authority's documents through which FAR has been allowed.

2. Compounding FAR cannot be taken for granted at inception stage itself. Revised area

statement and commensurate proposals should be submitted excluding compounding FAR.

Clarification for inclusion of compounding FAR at inception stage should be provided.

3. Specify the permitted uses of the proposed project site as per zoning of Noida Master Plan.

4. Area statement with block wise, floor wise details should be submitted.

5. On scale map showing approach road with reference to project site.

6. Site layout plan with dimensions should be submitted. All road widths should be clearly

mentioned in the layout plan.

7. Structural design map alongwith certificate for structural safety.

8. All services maps i.e. sewage, drainage, external electrification, rain water harvesting,

parking, uses of solar energy etc.

9. Solar energy provisions for street lighting and stair case lighting should be made and plans

submitted.

10. The project proponent has proposed for zero discharge. It may be reviewed by the proponent

in light of discussions held in the meeting. Scenario for monsoon period should also be

considered while proposing for zero discharge.

11. STP is proposed in basement. For basement, only modular STP shall be accepted. No civil

construction in basement for STP shall be allowed.

12. Section drawing for roads showing all services i.e. footpath/parking/sewage/drainage.

13. Parking entry and exit have been proposed on same road. Provision for separate entry/exit

roads may be explored.

14. Plan for use of CSTP water for construction purposes and undertaking from the proponent.

15. A CSR Plan with Rs. 2.5 crore should be prepared and details submitted.

16. Reflecting paints are to be used on top terrace and side walls.

17. No objection certificate from competent authority regarding fire fighting.O.H.T.to be

proposed with capacity of water as per NOC.

Page 4: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 4 of 50

18. Provision of composting to be processed at site.

19. Affidavit regarding wild life sanctuary within 5 KM to be given.

20. Provision to be made for all facilities like convenient shops, play school, community Hall.

The matter shall be discussed after submission of information as above.

2- Group Housing Project at Plot No-7D/GH-03, Awadh Vihar Yojna, Sultanpur Road,

Lucknow. File No. 2300/DD-DS

The committee noted that the application for environmental clearance on above project was

submitted to SEIAA on dated 09/05/2014. Project proponent through letter dated 11/08/2014 submitted

that the project has been submitted for green building certification from Indian Green Building Council

(IGBC). A presentation was made by Ms. Richa Singh, Project Proponent along with their consultant

M/s ENV Developmental Assistance Systems Pvt. Ltd. The proponent, through the documents

submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for proposed Group Housing Project at Plot No-7D/GH-

03, Awadh Vihar Yojna, Sultanpur Road, Lucknow. M/s Certa Infrastructure Pvt. Ltd.

2. Area details of the project is as follows:

Items Details % of plot

area

Total Plot area 8,260.00 sq mt (2.04 acres) 100 %

Ground Coverage Permissible: 2,891 sq mt (35%)

Proposed: 1,744.32 sq mt

35%

21%

FAR Permissible: 32,007.50 sqm (@ 3.875)

(basic FAR- 2.5

Additional FAR- 1.25

FAR due to Green Rating- 0.125)

Proposed: 30977.52 sqm

Total Basement area (2 layer) 6,004.02 x 2 = 12,008.04 sq mt

Total Built up area 42,985.56 sq mt

Total open & green area 6,515.68 sq mt 79%

Green belt Area Required: 1,240 sq mt (15% of plot area

Proposed: 1,240 sq mt (15% of plot area; i.e. 19% of

Total open & green area)

No. of Trees

(Required-1 Tree/100 sqm of

open area)

Required: 65 Trees

Proposed: 103 Trees

Total Dwelling Units Residential: 269

EWS: 100

Estimated Population Residential – 1,345 (@ 5 person per unit)

EWS- 500 (@ 5 person per unit)

Floating – 150; Staff-100

Area utilization 4 Towers

Basement+20 Floors

Page 5: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 5 of 50

Maximum Height Approx 62 m

3. Salient features of the project is as follows:

Items Details

Parking Required (including

Parking provided visitors parking)

440 ECS

440 ECS

Power requirement& source Power requirement: 3000 KVA from U.P State Electricity

Board (UPSEB).

Power backup (DG Sets) 1 DG sets having capacity 750 KVA

Water requirement & source Fresh water: 129 KLD (Groundwater supply till municipal

supply is available)

Reuse of treated effluent from STP: 57 KLD

Total water requirement: 186 KLD

Sewage treatment & disposal The waste water generated from entire complex is 154 KLD,

which will be treated in the STP of 185 KLD capacity at site.

57 KLD wastewater will be treated up to tertiary level for

reuses in the complex like toilet flushing, cooling of DG sets

and horticulture purposes. Rest of Secondary treated water is

discharged into Municipal sewer.

Total solid waste generated Approximately 966 Kg/ day – Municipal solid waste

including horticultural waste will be generated, segregated

and disposed as per MSW Rules, 2000 through hired agency

for Handling & disposal of solid waste.

Total no. of rain water harvesting pits 02 Pits

4. Water requirement details of the project is as follows:

Total Water Requirement/ Waste water Details Fresh water 129 KLD

Flushing 42 KLD

Horticulture / Landscape 4 KLD

DG set cooling 6 KLD

Filter Backwash 5 KLD

Total water requirement 186 KLD

Waste water 154 KLD

Source of water - Groundwater till municipal supply is available

STP Capacity – 185 KLD (20 % extra for future expansion)

5. Solid waste generation and its management details is as follows:

S.No. Particulars Population Waste generated in kg/day

1. Residential (@0.5kg/day)

(including EWS)

1845 923

2. Visitors (@0.15kg/day) 150 23

3. Staff (@ 0.15kg/day) 100 15

Total Solid waste generated Approx. 961 kg/day

Horticulture Waste (@ .0037 kg/sq m/day) 5 Kg/Day

E-Waste (0.15 kg/C/Yr) < 1 Kg/Day

Sludge (20% of Waste Water ) 31 kg/day

6. The project proposals are covered under category 8”a” of EIA Notification, 2006.

Page 6: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 6 of 50

The committee discussed the matter and directed the project proponent to submit following

information/clarifications:

1. Copy of ownership documents regarding the project.

2. Copy of development authority's documents through which FAR has been allowed.

3. Specify the permitted uses of the proposed project site as per zoning of Lucknow Master

Plan.

4. Area statement with block wise, floor wise details should be submitted.

5. Copy of sanctioned plans/maps as approved by Lucknow Development Authority.

6. On scale map showing approach road with reference to project site.

7. Site layout plan with dimensions should be submitted. All road widths should be clearly

mentioned in the layout plan.

8. Lucknow Development Authority bye-laws for basement parking should be submitted.

9. Landscape/green plan.

10. Structural design map alongwith certificate for structural safety.

11. All services maps i.e. sewage, drainage, external electrification, rain water harvesting,

parking, uses of solar energy etc.

12. Solar energy provisions for street lighting and stair case lighting should be made and plans

submitted.

13. STP is proposed in basement. For basement, only modular STP shall be accepted. No civil

construction in basement for STP shall be allowed.

14. Section drawing for roads showing all services i.e. footpath/parking/sewage/drainage.

15. A CSR Plan with Rs. 2.5 crore should be prepared and details submitted.

16. Reflecting paints on roof top and side walls.

17. All plans related to sewer Drainage external electrification landscape plan rain water

harvesting water supply to be submitted.

18. No objection for firefighting from competent authority.

19. Horticulture waste processing at site.

20. Submit copy of letter from competent regarding exemption of LIG /EWS plan.

21. Proposal regarding Convenient shop/ Play school/ATM/community Hall as per norms.

The matter shall be discussed after submission of information as above.

3- Township Project “Emami Nature” at Khelar, Jhansi, U.P. Sri Rajesh Bansal, Director, 687,

Andndapur, EM Bypass, IInd Floor, Kolkatta. File No. 2125/JDCA-S A presentation was made by the project proponent and along with their consultant M/s GRC

India Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed

the committee that:-

1. The environmental clearance is sought for proposed Township Project “Emami Nature” at

Khelar, Jhansi, U.P. M/S Emami Realty Limited.

2. Area details of the project is as follows:

S. No. PARTICULARS Area (m2

)

1. Total Land Area 4,43,076.43

2. Area under Roads 53,534.00

3. Net Plot Area 3,89,542.43

4. Area under Plots (287 plots) 2,66,631.72

5. Area under Resort 20829.00

6. Permissible Ground Coverage 3,31,111.062

Page 7: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 7 of 50

Plotted Area (@ 45% of net plot area)

Resort Area (@ 40% of net plot area for 3-star)

1,75,294.09

1,55,816.972

7. Proposed Ground Coverage Ground Coverage for Plots (16.24% of net plot area)

Ground Coverage for Resort (0.25% of net plot area)

64,246.97 63,266.97

980.00

8. Permissible FAR

For Plots (@1.25 of net plot area)

For Resort (@ 1.50 of net plot area for 3-star)

10,71,241.685

4,86,928.04

5,84,313.645

9. Proposed FAR

Plots (@0.162)

Resort (@ 0.50 for 3-star)

65,226.97

63,266.97

1,960.00

10. Total Open Area 3,25,295.46

11. Total Green Area (50% of open area) 1,62,647.73

12. Area under Utility & Services 2,827.00

13. Total Built-up area 68,053.97

3. Salient features of the project is as follows:

PROJECT FEATURES DESCRIPTION Estimated Population 4,364 Nos. (3,875 Residents, 80 Guests, 12 Staff

& 397 Visitors) Estimated Water Requirement

Construction Phase Operation Phase

340 ML 519 KLD (Fresh water = 276 KLD) (Agency:

Ground Water Resources)

Estimated waste water Generation Approx. 304 KLD Power Demand Power Back-up

1,860 KVA (State Electricity Board) 2 no of DG sets of 480 (1 x 100 + 1 x 380) kVA

Source of Power State Electricity Board (SEB)

Rain Water Harvesting Rain water Harvesting Ponds and adequate quantity of Rain Water collection tanks

Solid Waste Generation 2,049 kg/day

Parking Facilities Required Proposed

Each Plot will have its own arrangement of

parking within their plots, visitors parking will be provided on street carriage way. As per MoEF norms: 10 ECS (For Resort)

As per UP Bye Laws : 20 ECS (For Resort) 23 ECS

4. Water requirement details of the project is as follows:

S.

N.

Description

Nos. / Area

(in m2

)

Total

Occupancy

Rate of water

demand

(lpcd)

Total Water

Requirement (KLD)

A. Domestic Water

• Residen

ts

• Guests

3,875

80

86

180

333.25

14.4

• Staff 12 30 0.36

• Visitors 397 15 5.955

Total domestic water demand (A) 353.965 KLD say 354 KLD

B. Horticulture and 1,62,647.73 1 l/sqmt 163

Page 8: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 8 of 50

Landscape

development m

2

C. Make UP water for

swimming pool

(Resort)

2

Grand Total (A+B) = 519 KLD

A) DURING CONSTRUCTION PHASE

1. Agency: Private water Tankers 2. Approx. Water Demand: 340 ML 3. Sullage Generation: 9 KLD (@ 45 lpcd for 200 workers)

1. The site drainage shall be planned in such a way

that there is no accumulation of waste water

within the project premises or in the vicinity of

the site. 2. Mobile type sulabh shauchalayas to be provided

for construction laborers.

B) DURING OPERATION PHASE

1. Agency: Municipal Supply 2. Total Water Demand = 519 KLD Fresh water Demand = 276 KLD Domestic water = 354 KLD Horticulture = 26 KLD Make up water for swimming pool = 2 KLD 3. Waste water Generation = 304 KLD

1. STP of 20% higher capacity proposed to treat

wastewater. 2. Treated sewage shall be used for Horticulture &

flushing. 3. Use of Water efficient fixtures to conserve water.

5. Solid waste generation details is as follows:

SI. No. Category Waste generated (Kg per capita per day)

Waste generated

(kg/day) 1. Residents 3,875 @ 0.5 kg/capita/day 1,938

2. Guests 80 @ 0.5 kg/capita/day 40

3. Staff 12 @ 0.25 kg/capita/day 3

4. Visitors 397 @ 0.15 kg/capita/day 59.55

5. Landscape waste (40.19 acres) @ 0.2 kg/acre 8.038

Total Municipal Waste generated = 2,048.588 kg/day say 2,049kg/day

6. The project proposals are covered under category 8”a” of EIA Notification, 2006.

The committee discussed the matter and directed the project proponent to submit following

information/clarifications:

1. Orchha Wildlife Sanctuary has been mentioned at a distance of 8.48 K.M. An application for

NBWL clearance should be made and copy submitted.

2. Copy of ownership documents regarding the project.

3. Area chart should include total area of scheme, total plotted area, total open area, area under

roads, area under shops, area under public amenities like toilets/urinals/dustbins.

4. Area statement in % format should also be included with reference to total area for all uses.

5. Copy of development authority's documents through which FAR has been allowed.

6. Specify the permitted uses of the proposed project site as per zoning of Jhansi Master Plan

and map showing the proposed site in Jhansi Development Authority Master Plan.

Page 9: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 9 of 50

7. Copy of sanctioned plans/maps as approved by Jhansi Development Authority.

8. Proposals relate to township development. Calculation sheet regarding estimation of built-up

area should be submitted.

9. Enumerate facilities/developments which are proposed by developer/project proponent and

for which environmental clearance is required.

10. It is proposed that 137 KLD treated sewage shall be discharged to the nearby plots after

meeting the prescribed standards. Identify the plot nos. proposed for this purpose and

consent/permission of their plot owners in this regards.

11. Details for water supply scheme and provisions of overhead tank for drinking

purpose/firefighting.

12. On scale map showing approach road with reference to project site.

13. Site layout plan with dimensions should be submitted. All road widths should be clearly

mentioned in the layout plan.

14. Jhansi Development Authority bye-laws for basement parking should be submitted.

15. Landscape/green plan.

16. Plan for organize green and playing ground should be reconsidered and submitted. It is

proposed that spaces between backyards of plots shall be used as green spaces. Plan for

maintenance of these green spaces should be submitted.

17. Location of proposed pond may be changed in accordance to natural contour of the area.

18. Width of all internal roads should be as per building bye-laws.

19. All services plans/maps i.e. sewage, drainage, external electrification, rain water harvesting,

parking, uses of solar energy etc.

20. 100% solar energy provisions for street lighting and stair case lighting should be made and

plans submitted.

21. A CSR Plan with Rs. 02 crore should be prepared and details submitted.

22. Provision of convenient shops/play school/community Hall /ATM

23. Parks and open spaces proposed should be placed at better location.

24. Uses details permissible as per Jhansi Master Plan.

The matter shall be discussed after submission of information as above.

4- Group Houing at “Alsonia” at Plot No-10, Sector-PL1&2, Greater Noida. Sri Varun Sharma,

B-111, Sector-5, Noida. File No. 2126/DD-Y

The project proponent did not appear. The committee directed to close the case and to

reopen only, if a request to this effect is received from the project proponent.

5- Expansion of Group Housing Project “Spring Meadows” at Plot No-GH-07-A, Techzone-4,

Greater Noida, Sri Gajen Jain, Director0 16-17FF,Konark Building RDC, Raj Nagar,

Ghaziabad. File No. 2127/AD-Sub. The committee noted that the application for environmental clearance on above project was

submitted to SEIAA on dated 10/03/2014. A presentation was made by Shri Piyush Kant Jain, General

Manager, representative of project proponent along with their consultant M/s GRC India Pvt. Ltd. The

proponent, through the documents submitted and the presentation made, informed the committee that:-

1. The environmental clearance is sought for expansion of proposed Group Housing Project

“Spring Meadows” at Plot No-GH-07-A, Techzone-4,Greater Noida, U.P. M/s Pigeon

Buildhome Pvt. Ltd.

2. M/s. Pigeon Buildhome Pvt. Ltd. has obtained Environmental Clearance for Group Housing

Project “Spring Meadows” from SEIAA, U.P. vide Letter Ref. no. 1677/Parya/

Page 10: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 10 of 50

SEAC/1636/2013/AD(H) dated: 11th October, 2013 on plot area & Built-up area of 31,413.93

sqm and 1,44,145.96 sqm respectively.

3. Now due to increase in FAR, above said project again comes in purview of Environmental

Clearance as per EIA Notification 2006 & its amendments.

4. Area details of the project is as follows:

S.

N.

Particulars EC

Accorded

Area

(in m2

)

Revision

after

Total

Area

Reduced

(in m2

)

Additional

Area

proposed

(in m2

)

Total

Area

(in m2

)

Percentage

(%)

1. Total Plot Area 31,413.93 3,354 28,059.93 100%

2. Permissible Ground

Coverage

(@ 35% of total plot area)

-

9,820.98

3. Proposed Ground Coverage

(@ 21.23% of total plot

area)

5,084.77 - 872.52 5,957.29 21.23%

4. Permissible FAR (@ 3.5 of

total plot area)

77,164.80 - 21,040.77 98,209.75

5. Proposed FAR (@ 3.49 of

total plot area)

• Residential

Group

Housing FAR

• Villas FAR

• Commercial

FAR

77,164.76

76,393.16

-

771.6

- 21,040.77

19,571.05

1,259.22

210.5

98,205.53

95,964.21

1,259.22

982.10

6. Basement Area • Lower

Basement

• Upper

Basement

47,628.2 23,814.1 23,814.1

1,235.20 617.60 617.60

- 46,393.00 23,196.50 23,196.50

7. Stilt Area 19,353.00 484.20 - 18,868.80

8. Club Built up area (Free of

FAR)

- - - 400.00

9. Service Area - - - 92.50

10.

Built Up Area 1,44,145.96 - 19,813.87 1,63,959.

83

11. Open Area 22,975.16 872.52 - 22,102.64 78.77%

12.

Landscape Area (@ 50 % of

the Open Area)

11,487.58 436.26 - 11,051.32 39.38%

(included in

open area)

13.

Parking Areas

• Surface

2,112.50

Page 11: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 11 of 50

Parking

• Stilt Parking

• Upper

Basement

• Lower

Basement

18,868.80

22,838.06

22,838.06

14.

Maximum Height in meters 67.75 m

5. Salient features of the project is as follows:

PROJECT

FEATURES

Values in Accorded

EC

Revision Expansion Total

(Expansion &

Revision)

Plot area 31,413.93 m2

3,354 m2

28,059.93 m2

Net Planned Area 28,059.93 m2

28,059.93 m2

Built Up area 1,44,145.96 m2

19,813.87

m2

1,63,959.83 m2

Estimated Population 5,640 1,529 7,169

Fresh Water

Requirement

324 KLD 53 KLD 395 KLD

Sludge Generation 388 KLD 92 KLD 480 KLD

Solid Waste

Generation

2,576 kg/day 613 kg/day 3,189 kg/day

Power Demand

Power Back-up

2,980 kVA

2,000 (3x600 + 1x200 kVA) & 1 DG set of 750 kVA on standby

Source of Power Noida Power Company Limited

Parking Facilities

Proposed

2,008 ECS - 249 2,257 ECS

6. Water requirement during operational phase (after revision & expansion) :

S.

No.

Description Area

(in m2

)

Total

Occupancy

Rate of water

demand (lpcd)

Total Water

Requirement

(KLD)

A. Domestic Water

• Residential 5,943 86 511

• Staff 321 30 10

• Visitors 905 15 14

Domestic Water Requirement Sub Total (A) 535

B. Horticulture and Landscape

development

11,051.32

m2

1 ltr./sqm/day 11

C. Filter Backwashing 15

D. Make up water for Swimming

pool

5

E. Recreational Purpose & Road 10

Page 12: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 12 of 50

Washing

Grand Total (A+B+C+D) = 576 KLD

7. Waste water generation details after expansion:

Domestic Water Requirement 535 KLD

• Fresh (@ 70% of domestic) 375 KLD

• Flushing (@ 30% of domestic) 160 KLD

Waste Water Generated (@ 80% fresh + 100% flushing + 100% filter backwashing +

100% swimming pool make up water)-Waste water generated is

83.33% of total water demand

300 + 160 + 15 + 5 = 480 KLD

Total Fresh Water (Domestic Fresh water + Swimming pool make

up water + Filter Backwashing)- Fresh water demand is 68.58% of

total water demand.

375 + 5 + 15 = 395 KLD

STP Capacity 580 KLD

8. The project proposals are covered under category 8”b” of EIA Notification, 2006.

The committee discussed the matter and recommended following TORs and general guidelines

for conducting EIA studies regarding the proposals:

Additional TORs

1. Compliance of environmental clearance dated 11/10/2013.

2. Revised structural plan to be submitted.

3. Use of reflecting paints on top roof and side walls of all buildings.

4. Plan for 100% use of solar energy on all roads and common place.

5. Letter of development authority through which FAR has been revised.

6. Details of revision proposed tower wise, floor wise, flat wise, unit wise.

7. Area details tower wise, floor wise, flat wise alongwith % format.

8. A site plan showing the project site and its surroundings with physical features and topographical

details, such as land use, contours and drainage pattern, along with photographs of the site from

all four sides, should be included in the background information.

9. Sanctioned plan/maps regarding the project with all services plans.

10. All plans and elevation sections/all service plan/landscape plan/standard electrification

plan/drainage/sewerage plan.

11. Examine in detail the proposed site with reference to impact on infrastructure covering water

supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw wastes from

the complex on land/water body and into sewerage system.

12. Details of activities that is proposed/likely to come up in the project.

13. Water requirement and water management plan alongwith necessary permissions for discharge.

14. Hydro-geological investigations be carried out and obtain permission from Central Ground

Water Authority for withdrawal of ground water.

15. Consider soil characteristics and permeability for rainwater harvesting proposals, should be made

to prevent ground water contamination. Maximize use of treated water by recycling and

Page 13: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 13 of 50

utilization of rainwater.

16. Make provision for safety against failure in the operation of wastewater treatment facilities.

Identify acceptable outfall for treated effluent.

17. Details of green belt as a measure for mitigation of dust and noise and buffer between habitation

and proposed project.

18. Landscape plan, green belts and open spaces may be described separately.

19. Study the existing flora and fauna of the area and the impact of the project on them.

20. Examine existing crèche, education, health facilities, police, post Office, Banks and other

services and make adequate provisions in the proposal.

21. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.

22. Application of renewable energy/alternate energy, such as solar and wind energy may be

described including solar water heating in the guidelines for entrepreneurs.

23. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.

24. Identification of recyclable wastes and waste utilization arrangements may be made.

25. Explore possibility of generating biogas from biodegradable wastes.

26. Arrangements for hazardous waste management may be described as also the common facilities

for waste collection, treatment, recycling and disposal of all effluent, emission and refuse

including MSW, biomedical and hazardous wastes. Special attention should be made with

respect to bird menace.

27. Provisions made for safety in storage of materials, products and wastes may be described.

28. Disaster management plan should be prepared.

29. Traffic management plan including parking and loading/unloading areas may be described.

Traffic survey should be carried out both on weekdays and weekend.

30. Parking provision is to be made for higher ECS worked out either as per state bye-laws or

construction manual of the MoEF

31. Exclusive Parking area in the basement (excluding other facilities) and surface is to be clearly

mentioned

32. Provide service road for entry and exit to project site.

33. Use of local building materials should be described.

34. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with

provisos of sampling port for monitoring be described.

35. Work out MGLC for the combined capacity of DG sets.

36. Provide for conservation of resources, energy efficiency and use of renewable sources of energy

in the light of ECBC code.

37. Application of resettlement and rehabilitation policy may be described. Project affected persons

should be identified and rehabilitation and resettlement plan should be prepared.

38. Examine separately the details for construction and operation phases both for Environmental

Management Plan and Environmental Monitoring Plan.

39. Environment Corporate Responsibility (ECR) plan along with budgetary provision of minimum

07 crore as discussed in meeting shall be submitted on need base assessment study in the study

area.

Page 14: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 14 of 50

40. Details of all internal and peripheral roads width.

41. Source and quantity of required water during construction and management of generated waste

water.

42. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National

Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

General Guidelines

a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by

Public Notary, stating that:

I. “There is no litigation pending against the project and/or land in which the project is proposed

to be set up (please give name & ownership etc. of the project) and that for any such litigation

what so ever, the sole responsibility will be borne by the Project proponent.”

II. “No activity relating to this project (i.e. name of the project) including civil construction has

been undertaken at site except fencing of the site to protect it from getting encroached and

construction of temporary shed(s) for the guard(s). (if fencing has not been done, then the same

may be deleted).

III. “I/We hereby give undertaking that the data and information given in the application, enclosures

and other documents are true to the best of my knowledge and belief and I/We am/are aware

that if any part of the data and information submitted is found to be false or misleading at any

stage, the project will be rejected and clearance given, if any to the Project will be revoked at

our risk and cost.”

IV. Project does not fall under any buffer zone of no-development as declared /identified under any law.

b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been complied

with (to be deleted if not applicable) & (b) that details and the data presented are factually correct”,

as per MoEF circular dated 04.08.2009 is also to be submitted along with EIA.

c. Current, site photographs viewing towards the project area from four directions indicating date of

photograph taken, direction from which taken, name of the project, and signature of Project

proponent along with consultant with seal should be submitted, so as to ensure that no construction

has been started before the grant of EC.

d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of 2006

and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of

representativeness and reliability of baseline environmental attributes detailed under EIA manual

January, 2001 and other guidelines in the matter.

e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically

mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is

prepared.

f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with

their complete details including their accreditation, if any shall be indicated.

g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the

preparation of these reports and the Name of laboratory through which the samples have been got

analysed should be stated in the report. It shall clearly be indicated whether said laboratory is

accredited by NABL or approved under the Environment (Protection) Act, 1986 (Please refer

Page 15: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 15 of 50

MoEF office memorandum dated 4th

August, 2009). The name project leader of the EIA study

shall also be mentioned.

h. The EIA document shall be printed on both sides, as for as possible.

The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted

within 15 days from the date of receipt of the letter and remaining of the information’s is to be submitted

along with the EIA.

Project proponent also submitted through letter dated 09/09/2014 that they have conducted an

EIA study for the premonsoon season March-May, 2014 incorporating the model terms of reference

issued in the TGM of construction and building by MoEF. the committee deliberated that the related

rules for use of model terms of reference for preparation of EIA should be submitted for consideration of

their letter dated 09/09/2014 alongwith work order communicated to consultant by the project proponent

for data collection and conducting the EIA study.

6- Group Housing at Sport City, Sec-150, Noida. Sri K K Sharma, H-198, Value Group, Sec- 63,

Noida. File No. 2128/DD-Sh.

The project proponent did not appear. The committee directed to close the case and to

reopen only, if a request to this effect is received from the project proponent.

7- Group Housing at Khasra N0 1119& 1125, Vill-Noor Nagar, Ghaziabad. Sri B.K. Jain, CEO,

VVIP Addresses, Raj Nagar Ext. Ghaziabad. File No. 2129/AD-H

The project proponent did not appear. The committee directed to close the case and to

reopen only, if a request to this effect is received from the project proponent.

8- Group Housing at “Jaype Sports City”, Greater Noida, G B Nagar. Sri S. Sodi, 56/5, Sector-62,

Noida. File No. 2148/AD-Sub.

The project proponent did not appear. The committee directed to close the case and to

reopen only, if a request to this effect is received from the project proponent.

9- Group Housing at “Regency Park”, Plot No- GH-03B, Sector-16C, Greater Noida, G B Nagar.

Sri Arun Mittal, MD, 301, Krishna Apra Business, Pitampura, New Delhi. File No. 2149/DD-

Sh.

The committee noted that the application for environmental clearance on above project was

submitted to SEIAA on dated 11/03/2014. A presentation was made by the project proponent along with

their consultant M/s GRC India Pvt. Ltd. The proponent, through the documents submitted and the

presentation made, informed the committee that:-

1. The environmental clearance is sought for revision of Proposed Group Housing Project at

“Regency Park”, Plot No- GH-03B, Sector-16C, Greater Noida, G B Nagar, U.P. M/s Aarcity

Infrastructure Pvt. Ltd.

Page 16: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 16 of 50

2. The proposed project has already received Environmental Clearance from SEIAA, U.P. (Letter

No. 2465/Env/SEAC/777/2011/AA(S) dated 31st October, 2011) for the built-up area of

81,816.15 sq.m.

3. Now, there is increase in FAR, so, built-up area has been increased from 81,816.15 m2 to

1,01,934.980 m2; above said project again comes in purview of Environmental Clearance as per

EIA Notification 2006.

4. Area details of the project is as follows:

S.

No.

Particulars Existing (m2

) Revision &

Expansion (m2

)

Total Area

(After revision

& expansion)

(m2

)

Percentage

(%)

1. Plot Area 20,620.930 100%

2. Permissible Ground

Coverage

(@ 35% of plot area)

7217.32

3. Proposed Ground

Coverage

(@ 25% of plot area)

4,673.504 483.225 5,156.729 25%

4. Ground Coverage for

swimming Pool

1,039.9

5.

Permissible FAR

(@ 3.5)

56,707.5575 15,465.69 72,173.25

6. Proposed FAR

(@ 3.499)

Residential FAR

Commercial FAR

56,688.201 15,481.617 72,169.818

71,448.088

721.73

7. Permissible

Additional 15%

F.A.R

8,506.134 2,319.85 10,825.98

8. Proposed Additional

15% F.A.R

3,765.135 3,765.135

9. Non-FAR

Basement Area

including club area

Stilt Area

Balcony Area

14,421.895

2,199.919

-

-716.315

-46.577

-

24,960.123 13,705.58

2153.342

9,101.201

10. Built-up area 81,816.15 19,078.926 1,00,895.076

11. Open Parking 5,629.297 -1,301.718 4,327.579

12. Basement Area

including Club area

14,421.895 -716.315 13,705.58

13. Basement Parking 11,841.876 -103.06 11,738.816

14. Stilt Area 2,199.919 - 46.577 2,153.342

15. Stilt Parking 5,629.297 -3,476.955 2,152.342

16. Total Landscape Area 8,228.677 -524.857 7,703.82 37.36% (part

Page 17: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 17 of 50

(@ 50% of open area) of open area)

17. Tallest Building 45 m 14.92 m 59.925 m

18. Open Area 15,947.426 -483.225 15,464.201 75%

5. Tower wise area details of the project is as follows:

S.NO DESCRIPTION F.AR

(sq.m)

ADDITIONAL

15% F.A.R

(sq.m)

BALCONY

AREA

(sq.m)

AREA

(sq.m)

TOTAL AREA

(sq.m)

1 TOWER-A 10,559.95 500.303 1,272.665 12,332.918

2 TOWER-B 17,834.308 698.197 2,784.015 21,316.52

3 TOWER-C 17,014.735 856.059 2,443.818 20,314.612

4 TOWER-D 9,228.518 511.412 1,052.874 10,792.804

5 TOWER-E 8,823.793 599.582 780.419 10,203.794

6 TOWER-F 8,708.514 599.582 767.41 10,075.506

7 BASEMENT

AREA

INCLUDING

CLUB HOUSE

13,705.58 13,705.58

8 STILT AREA 2,153.342 2,153.342

GRAND TOTAL 72,169.818 3,765.135 9,101.201 15,858.922 1,00,895.076

6. Salient features of the project is as follows:

PROJECT FEATURES DESCRIPTION

Estimated Population EC accorded = 2,488 Nos. (2,138 Residents,

130 Staff & 220 Visitors) After revision & expansion = 3,373 Nos.

(2,939 Residents, 140 Staff & 294 Visitors)

Estimated Water Requirement Construction Phase Operation Phase

505 ML (Agency: Treated water from STP of

NOIDA) EC accorded: 211 KLD (Fresh water = 137

KLD) After revision & expansion: 288 KLD (Fresh

water = 195 KLD) (Agency: Municipal

Supply)

Estimated waste water Generation EC accorded: 168 KLD After revision & expansion: Approx. 238

KLD

Power Demand Power Back-up

EC accorded: 3,504.5 KVA After revision & expansion: 4,227.5 KVA 2 Nos. DG set each of 750 KVA and one no.

of 1,010 KVA

Source of Power Noida Power Company Limited (NPCL)

Rain Water Harvesting Pits 6 Pits

Solid Waste Generation EC accorded: 1,134.5 kg/day After revision & expansion: 1,556 kg/day

Parking Facilities EC accorded:

Page 18: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 18 of 50

Parking required: As per MoEF norms: 567 ECS

As per Greater Noida Bye Laws : 709 ECS Parking proposed: 1143 ECS (Stilt – 73 ECS,

Surface- 281 ECS, Basement (multi level car

parking – 789 ECS)

After Revision & Expansion: Parking required: As per MoEF norms: 715 ECS

As per Greater Noida Bye Laws : 893 ECS Parking proposed: 904 ECS (Stilt – 72 ECS,

Surface- 216 ECS, Basement– 335 ECS,

Mechanical Parking – 281 ECS)

7. Water requirement during operational phase (after revision & expansion):

S.

No.

Description Occupancy Per Capita

Demand (lpcd)

Total Water

Requirement

(KLD)

1. Domestic Water Requirement

Apartment @ 4.5 Person Per

main DU & @ 2.25 person

per servant’s quarter

2,939 86 252.754

Visitors 294 15 4.41

Staff 140 30 4.2

Sub Total 262.364 say 262

KLD

2. Horticulture Water

Requirement

7,703.82 Sq.m 1 lt./Sq.m/day 7.7

3. Swimming Pool 7

4. Filter Backwash 5

5. Recreational purposes 6

TOTAL WATER REQUIRMENT(1+2+3+4+5) 287.7 KLD say

288 KLD

8. Water and waste water details is as follows:

SI. No. Description Values in Accorded

EC Revision and Expansion

1 Total Water Requirement 211 KLD 288 KLD

2 Total Domestic Water Requirement 195 KLD 262 KLD

3 Total Fresh Water Requirement 137 KLD 183 KLD

4 Waste water Generated 168 KLD 195 KLD

5 STP capacity 200 KLD 290 KLD

9. The project proposals are covered under category 8”a” of EIA Notification, 2006.

The committee discussed the matter and recommended grant of environmental clearance along

with all the general conditions as prescribed by the Authority for construction project and following

specific conditions:

Page 19: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 19 of 50

1. Install online water quality monitoring devices with recycled water line along with flow measuring

device.

2. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National

Board for Wild Life (NBWL) even if the eco-sensitive zone is not earmarked

3. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more capacity

than waste water generated during operation phase.100% waste water is to be treated in captive

STP conforming to prescribed standards of receiving body for designated use. Monitoring of STP

to be done daily till its stabilization.

4. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be used in

house as manure and surplus manure should be managed by giving to end users.

5. SWM organic converter drawing, design and cost estimate has to be submitted within 03 months

from issuance of the Environmental Clearance

6. Approved site plan from authority to be submitted within 03 months from issuance of the

Environmental Clearance.

7. A CSR Plan with Rs. 4.5 crore should be prepared and details submitted.

8. Provision for play school should be included and plan submitted.

9. Provision of play school/convenient shops, community hall as per population.

10. Provision for 100% solar energy on all roads and public places.

11. Use of reflecting paints on top floor and all side walls.

12. Isolated place for Municipal Solid Waste handling and the disposal shall be provided.

13. LEDs should be used in all common areas and corridors. Solar light is to be provided in the open

areas with 50% of them may be with dual power.

14. Parking guideline as per Greater Noida authority should be followed.

15. All entry/exit point should be bell mouth shaped.

16. To discharge excess treated waste water into public drainage system permission from the

competent authority to be taken prior to any discharge.

17. All internal roads should not be less than 9 m wide.

18. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only from

the roof top. RWH from green and other open areas shall be done only after permission from

CGWB.

19. Height of the stack should be provided as discussed based on combined DG sets capacity and be

6mt higher than the tallest building.

20. Post project monitoring for air, water (surface+ ground), Stack noise of D.G. sets, STP to be

carried out as CPCB Guidelines.

21. Wheel wash arrangement is to be made at exit point during construction phase.

22. Crèche to be provided during the construction/operation phase.

23. Provision of separate room for senior citizen with proper amenities.

24. Parking for disabled persons should be explored.

25. Protection shall be provided on the windows of the high rise flats for security of residents.

26. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for

construction work.

27. Dual plumbing should be adopted.

28. Unless and until all the environmental issues are sorted out the occupancy will be restricted and

would be only allowed after achieving the Permission from the competent authority.

29. The project proponent shall ensure that the project site does not attract/infringe any buffer zone of

no activity identified/declared under law.

Page 20: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 20 of 50

30. Ground water should not be extracted for the purpose of construction or otherwise. In case of

default the Environmental Clearance will deem to be cancelled.

31. Sprinkler to be used for curing and quenching and ready mix concrete may be used for

construction.

32. Cement Bags should be used for road making.

33. LIG & EWS housing to be provided as per Greater Noida bye- laws/letter of land allotment.

34. Possibilities of use of treated waste water for irrigation purposes should be explored.

35. No fresh water will be used for irrigation purpose. Fresh Water will only used for drinking, bathing

and in swimming pool.

36. Decision made in any litigation pending in the Courts of Law shall be binding on project

proponent.

37. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if

preferred, within a period of 30 days as prescribed under Section 11 of the National Environment

Appellate Authority Act, 1997.

10- Group Housing Project at Plot No-3, Sector-12, Vrindavan Yojna-3, Lucknow. Sri Rajendra

Kr Sharma, Project Director, Flat No- 501, Tulip Apartment, 8-B, Ashok Marg, Lucknow. File

No. 2175/DDY

The committee noted that the application for environmental clearance on above project was

submitted to SEIAA on dated 10/03/2014. A presentation was made by the project proponent along with

their consultant M/s Eko Pro Engineers Pvt. Ltd. The proponent, through the documents submitted and

the presentation made, informed the committee that:-

1. The environmental clearance is sought for proposed Group Housing Project at Plot No-3, Sector-

12, Vrindavan Yojna-3, Lucknow, U.P. M/s Amazing Construction Pvt. Ltd.

2. Salient features of the project is as follows:

FEATURES PROPOSED PROJECT

Total Plot Area 8425.50 sq. m

Permissible FAR@ 3.32 % 28014.79 sq. m.

Achieved FAR@ 3.09 % 26065.802 sq. m.

Height of Building 36 mt

Green Area 579.34 sq. m.

No. of Towers 6

No. of Floors Block A1 - Stilt+ 9 Floor + Duplex

Block A2 - Stilt+ 9 Floor + Duplex

Block B1- Stilt+ 9 Floor

Block B2- Stilt+ 9 Floor

Block C- Stilt+ 9 Floor + Duplex

Utility Block- Stilt+ 4 Floors.

Total Built up Area 26065.802 sq. m

Estimated Population 960

Total Water Requirement 126 KLD

Fresh Water Requirement 60 KLD

Treated Waste Water use from STP 66 KLD

STP Capacity 140 KLD

Page 21: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 21 of 50

Parking 392 ECS

Total Solid Waste Generation 594.4 kg/day

Power requirement and source 1100 KW (UPSEB)

Backup Power Supply 02 nos. of DG Sets

(2x 500 KVA &1 x 250 KVA)

3. The project proposals are covered under category 8”a” of EIA Notification, 2006.

The committee observed that the project report has not been communicated to Members. The

committed directed to communicate the same to all members. The committee further directed to submit

following information:

1. Approved map from housing board.

2. Structural design.

3. All services plan i.e. sewer, water, drainage, external electrification, rain water harvesting, STP,

Green belt, solar energy.

4. It shall be ensured that the project site does not lie on flood plain.

5. Area details should include tower wise/ floor wise area details.

6. Provisions made for EWS/LIG housing alongwith related Govt. orders.

7. Provision of over head tank for firefighting with minimum 1% of total water requirement.

8. Drawings presented in the meeting should be clear and with dimensions.

9. CSR Plan with Rs. 02 crore should be prepared and submitted.

The matter shall be discussed after submission of information as above.

11- Group Housing Project “Palm Olympia” at plot No- GH-02,Sector-16C, Greater Noida, U.P.

Sri Madan Lal, Director, 309, Jaipura Plaza, Sector-26, Noida. File No. 1483/DD-Y The committee noted that:

1. Proposal for Group Housing Project “Palm Olympia” at plot No- GH-02,Sector-16C, Greater

Noida, U.P. was submitted to SEIAA through letter dated 21/01/2013 for environmental

clearance.

2. The matter was discussed in SEAC meeting dated 26/02/2013 and terms of reference were

issued. Again, the matter was reviewed in SEAC meeting dated 29/04/2013 wherein the

committee reviewed the matter and directed also to initiate legal action for violation of E.P.

Act, 1986 as per MoEF OM dated 12/12/2012 for construction at site has been undertaken

without obtaining environmental clearance.

3. State Govt. through letter dated 03/06/2014 directed UPPCB to take necessary legal action in

the matter. Member Secretary, UPPCB through his letter dated 22/07/2014 informed that the

case has been filed in the CJM Court, Gautam Budh Nagar.

Now after initiation of legal action, the matter is eligible to be discussed by the committee as

per provisions of MoEF OM dated 12/12/2012.

A presentation was made by the project proponent along with their consultant M/s GRC India

Pvt. Ltd. The project proponent informed that EIA report has been submitted to Authority through letter

dated 04/07/2013. The proponent, through the documents submitted and the presentation made,

informed the committee that:-

Page 22: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 22 of 50

1. The environmental clearance is sought for proposed Group Housing Project “Palm Olympia” at

plot No- GH-02, Sector-16C, Greater Noida, U.P. M/s Sam India Abhimanyu Housing.

2. Salient features of the project is as follows:

S. No. Particulars Area (in m

2

) Area in (%)

1. Plot Area 1,01,264.00 100 %

2. Permissible Ground Coverage (@ 40%) 40,505.60 40 %

3. Proposed Ground Coverage (@ 23.17 %) 23,464.12 23.17 %

4. Permissible FAR (@ 3.50 ) 3,54,424.00

5. Proposed FAR (@ 3.49)

• Residential FAR

• Convenient shop FAR

3,54,230.50

3,50,686.26

3,544.24

6. Permissible Ancillary Area (@ 15% of FAR) 53,163.60

7. Proposed Ancillary Area (@ 10.88% of FAR) 38,545.37

8. Basement area (2 Basements) 1,00,614.43

9. Stilt Area 18,131.93

10. Mumty Area 1,348.30

11. Non FAR Area 73.40

12. Built Up Area 5,12,943.93

13. Open Area 77,799.88 76.83 %

14. Landscape Area (@ 50.00 % of open area) 38,899.94 38.41%

included in

open areas

3. FAR area breakup details of the project is as follows:

S.No. Tower F.A.R area

(in m2

)

No. of

units

Non FAR area

(in m2

)

Ancillary Area

(in m2

)

1. Tower A with servant

unit (G+19)

15,674.00 142.50 1,286.08

2. Tower B (G+19) 13,290.61 152.00 1,422.15

3. Tower C (G+19) 13,290.61 1,462.15

4. Tower D (G+19) 13,281.5 1,345.21

5. Tower E (G+19) 12,961.04 1,248.30

6. Tower F (G+19) 15,690.67 1,352.02

7. Tower G (G+19) 13,983.04 1,248.49

8. Tower H (G+19) 13,281.5 1,450.21

9. Tower I (G+19) 14,290.41 1,222.13

10. Tower J (G+19) 14,290.61 1,483.13

11. Tower K with servant

unit (G+19)

15,774.00 1,396.08

12. Tower L with servant

unit (G+19)

15,359.51 1,386.12

13. Tower M (G+24) 23,068.69 2,579.22

14. Tower N (G+24) 21,599.16 2,851.14

4. Salient features of the project is as follows:

PROJECT FEATURES DESCRIPTION

Page 23: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 23 of 50

Estimated Population 17958 Nos.

Estimated waste water Generation Approx. 1196 KLD Power Demand Power Back-up

9,930 KVA 12 D.G sets of 7,200 KVA (12 X 600 KVA each).

Source of Power Noida Power Company Limited

Rain Water Harvesting 20 nos Solid Waste Generation 8,364.00 kg/day Parking Proposed 4,600 ECS

5. Water and waste water details of the project is as follows:

SI. No. Likely Impact Management /

Mitigative Measures

A) DURING CONSTRUCTION PHASE

1 2. 3.

Agency: Tankers hired from safe areas Approx. Water Demand = 2,565 ML Waste Water Generation = 5.4 KLD

1. The site drainage shall be planned in such a

way that there is no accumulation of waste

water within the project premises or in the

vicinity of the site. 2. Mobile type sulabh shauchalayas to be

provided for construction laborers.

B) DURING OPERATION PHASE 1 2 3

Agency: Greater Noida Industrial

Development authority Total Water Demand = 1,469 KLD Total Fresh water Demand = 974 KLD Domestic = 1,391KLD Flushing = 417KLD Wastewater Generation = 1,196 KLD

1. STP of 20% higher capacity proposed to treat

wastewater. 2. Drip & Spray irrigation shall be done for

reducing water demand. 3. STP Treated Water shall be used for

Horticulture, flushing, DG cooling .

6. The project proposals are covered under category 8”b” of EIA Notification, 2006.

The project proponent also submitted location map, site plan, 500 m around the site map,

toposheet map showing the project site, contour plan, land use, drainage map, site photographs, dual

plumbing plan, landscape plan, parking plan, traffic circulation plan for the project. A structural stability

certificate from IIT, Roorkee was also submitted. A presentation was made by the project proponent on

EIA. The committee discussed the matter and recommended grant of environmental clearance along

with all the general conditions as prescribed by the Authority for construction project and following

specific conditions:

1. Install online water quality monitoring devices with recycled water line along with flow measuring

device.

2. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National

Board for Wild Life (NBWL) even if the eco-sensitive zone is not earmarked

3. Adequate green cover not less than 33% of the plotted area should be provided within the

premises.

4. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more capacity

than waste water generated during operation phase.100% waste water is to be treated in captive

Page 24: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 24 of 50

STP conforming to prescribed standards of receiving body for designated use. Monitoring of STP

to be done daily till its stabilization

5. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be used in

house as manure and surplus manure should be managed by giving to end users.

6. SWM organic converter drawing, design and cost estimate has to be submitted within 03 months

from issuance of the Environmental Clearance

7. Approved site plan from authority to be submitted within 03 months from issuance of the

Environmental Clearance.

8. Environmental Corporate Responsibility (ECR) plan along with budgetary provision amounting to

2% of total project profit shall be submitted (within the month) on need base assessment study in

the study area. Income generating measures which can help in upliftment of weaker section of

society consistent with the traditional skills of the people identified. The programme can include

activities such as old age homes, rain water harvesting provisions in nearby areas, development of

fodder farm, fruit bearing orchards, vocational training etc. In addition, vocational training for

individuals shall be imparted so that poor section of society can take up self-employment and jobs.

Separate budget for community development activities and income generating programmers shall

be specified.

9. Isolated place for Municipal Solid Waste handling and the disposal shall be provided.

10. LEDs should be used in all common areas and corridors. Solar light is to be provided in the open

areas with 50% of them may be with dual power.

11. Parking guideline as per Greater Noida authority should be followed.

12. All entry/exit point should be bell mouth shaped.

13. To discharge excess treated waste water into public drainage system permission from the

competent authority to be taken prior to any discharge.

14. All internal roads should not be less than 9 m wide.

15. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only from

the roof top. RWH from green and other open areas shall be done only after permission from

CGWB.

16. Height of the stack should be provided as discussed based on combined DG sets capacity and be

6mt higher than the tallest building.

17. Post project monitoring for air, water (surface+ ground), Stack noise of D.G. sets, STP to be

carried out as CPCB Guidelines.

18. Wheel wash arrangement is to be made at exit point during construction phase.

19. Crèche to be provided during the construction/operation phase.

20. Provision of separate room for senior citizen with proper amenities.

21. Parking for disabled persons should be explored.

22. Protection shall be provided on the windows of the high rise flats for security of residents.

23. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for

construction work.

24. Dual plumbing should be adopted.

25. Unless and until all the environmental issues are sorted out the occupancy will be restricted and

would be only allowed after achieving the Permission from the competent authority.

26. The project proponent shall ensure that the project site does not attract/infringe any buffer zone of

no activity identified/declared under law.

27. Ground water should not be extracted for the purpose of construction or otherwise. In case of

default the Environmental Clearance will deem to be cancelled.

Page 25: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 25 of 50

28. Sprinkler to be used for curing and quenching and ready mix concrete may be used for

construction.

29. Cement Bags should be used for road making.

30. LIG & EWS housing to be provided as per Greater Noida bye- laws/letter of land allotment.

31. Possibilities of use of treated waste water for irrigation purposes should be explored.

32. No fresh water will be used for irrigation purpose. Fresh Water will only used for drinking, bathing

and in swimming pool.

33. Decision made in any litigation pending in the Courts of Law shall be binding on project

proponent.

34. Any appeal against this environmental clearance shall lie with the National Green Tribunal, if

preferred, within a period of 30 days as prescribed under Section 11 of the National Environment

Appellate Authority Act, 1997.

12- Commercial Complex “The Tempean” at plot No- C-171/1, Sector-15, Noida, G B Nagar, U.P

Sri Roop Mohan, M.D., D-13, Defence Colony, New Delhi. File No. 1800/OSD-T

The committee noted that the matter was earlier discussed in 180th

SEAC meeting dated

06/06/2014 wherein the project proponents were directed to submit following information:

1. Approved plan for building, structural design, proposed services, drainage and greens.

2. Justification regarding difference in area statements as given in application for environmental

clearance and Noida Authority letter no. 693 dated 06/09/2013.

3. Copy of submission of charges to Noida Authority regarding EDC, IDC.

4. Status of project in view of its proximity to Kalindi Bird Sanctuary.

5. Water requirement for fire fighting and its management should be specifically mentioned.

The project proponents submitted their replies through undated letter received in the Directorate

dated 25/08/2014. The project proponent submitted plans for building structural design proposed

services, drainage and greens.

PP has got approval for the building plans vide letter no. 1341/693, in which, total sanctioned built up

area is 1,53,943.856 m2

but the built up area applied for the Environmental Clearance was 1,48,896.06

m2

. However, the total deduction area amounts to 5,047.80 m2 from commercial and parking area. An

Affidavit stating that the built up area will not exceed 148896.056 m2 was enclosed with reply.

Further, it is ensured that in future any construction will be undertaken beyond 1, 48,896.056 m2

area;

separate Environmental clearance will be obtained by SEIAA, UP as an expansion of the earlier.

The following tables give the area statement and the other calculations in the built-up area deduction.

Table 1: Area Statement

S.

No.

Particulars Area (in m2) Area after

reduction (in m2)

1 Total Plot Area 15205.75 -

2 Permissible Ground Coverage (50% of plot area) 7602.875 -

3 Proposed Ground Coverage (@ 44.93 % of total plot

area)

6833 -

4 Permissible FAR (@5) 76028.75 -

5 Proposed FAR (@ 4.98) 75946.725 74085.935

Page 26: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 26 of 50

Table 2: Total reduced area

S. No Particulars Area (in m2)

1. Commercial area 4022.099

2. Parking area (Part of proposed FAR) 3187.01

3. Total 5047.80

Table 3: Deduction Area Chart:

Particulars Commercial Area Parking Area Total Area

Ground FL 504.78

1st FLOOR 504.78

2nd FLOOR 504.78

3rd FLOOR 346.45 158.33

4th FLOOR 504.78

5th FLOOR 504.78

6th FLOOR 504.78

7th FLOOR 504.78

8th FLOOR 504.78

9th FLOOR 504.78

TOTAL 1860.79 3187.01 5047.80

Copy of receipts regarding payment of Water and sewerage charges have been submitted. Further, an

acknowledgement copy from NBWL seeking permission as the project lies at a distance of about 04

K.M. from the Kalindi Bird Sanctuary has also submitted. The project proponent also submitted that the

total water for firefighting purposes would be 5% of the total water requirement (20 KLD) which is an

adequate amount. An affidavit stating that zero water discharge will be maintained during non-rainy

season within the project premises was also submitted.

The committee noted that a map with built-up area 1,49,130 sqm has been submitted to Noida

Authority for approval (as informed by project proponent) whereas the proponent has presented the

matter to committee with built-up area 1,48,896.06 sqm. The committee directed that copy of revised

Proposed FAR of service apartments

Proposed FAR for Commercial

Retail

19357.515

33011.41

23,577.8

19357.515

31150.62

23,577.8

6 Built Up Area 153943.86 1,48,896.06

7 Basement Area-I 9309.640 -

8 Basement Area -II 9309.640 -

9 Service Area 10697.60 -

10 Non FAR 69460.78 66,273.774

11 Open Area 8,372.75 -

12 Landscape Area (@ 53.44 % of open area) 4474.61 -

Page 27: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 27 of 50

plan as submitted to Noida Authority with 1,48,896.06 sqm built-up area as finally proposed by project

proponent should be submitted. Revised form-1 with according change in area statement should also be

submitted. The matter shall be discussed after submission of information as above.

13- Proposed Sethi Venice Project at Plot No-SC-01/A-04, Sector-150, Noida, U.P. Sri C.M. Sethi,

Director, Sethi Group, 2nd Floor, Angel Mega Mall, Kaushambi, Ghaziabad, U.P. File No.

2096/DD-Y

The committee noted that the matter was earlier discussed in 183rd

SEAC meeting dated

27/06/2014 wherein the project proponents were directed to submit following information:

1. Proposed TOR as the total built up area is above 150,000 sq mts.

2. Detailed scheme of STP and the water recycle system.

3. An under taking from the Municipal Authority for the water supply.

4. A separate map of the proposed green Belt should be provided.

5. A corrected water balance indicating the actual daily fresh water requirement. Also provide the

details of the utilities to be provided based on energy and the water consumption.

The project proponents submitted their replies through letter dated 07/07/2014. A presentation

was made by the project proponent along with their consultant M/s Ascenso Management and

Consulting Services Pvt. Ltd.

The project proponent informed that the Form 1, Form 1a and conceptual plan was submitted on

11/10/2013 and the built up area was 1,86,451.0 m2. But due to modification in the design of the

building, the built up area of the project has been changed to 1, 48,320.42 m2 and revised Form 1, Form

1a and conceptual plan with the data variation sheet has been submitted on 20/03/2014.

The committee directed that sanctioned copy of building plan with revised built-up area should

be submitted alongwith revised services plans. The committee also directed that civil construction for

STP in the basement shall not be allowed. If, the project proponent does not propose modular STP in

basement, they should submit plans with specific locations for STP on surface with civil structure. The

committee also discussed decision dated 11/08/2014 of Hon'ble NGT regarding Sport City in sector-150,

Noida (application no. 128/2014 Raghuveer Singh V/s Union of India and Ors.) which relates to matter

of construction on no development zone at the river bank in the interest of environment and ecology.

The committee directed that the project proponent should also submit a note regarding their project

location in view of above decision of Hon'ble NGT.

The matter shall be discussed after submission as above.

14- Expansion of “Supreme Court Bar Association” at plot No- GH-4 & 5, Sector-99, Noida.Sri

G.K. Sinha, CEO, Supreme Court Bar Association, Multi-State Co-Opp. Group Housing

Society Ltd. M.C. Setalved New Lawyer’s Chambers, New Delhi. File No. 2233/AD-Sub.

The committee noted that the matter was earlier discussed in 187th

SEAC meeting dated

05/08/2014 wherein the project proponents were directed to submit following information:

1. Compliance to SEIAA letter no. 943/SEAC/DDS/80, dated 09/06/2009 through which

environmental clearance was accorded to the original project.

2. Submit the statement regarding sanctioned map and added area as increased by revising the

plan is to be submitted.

3. A parameter wise chart explaining proposed expansion, where expansion is being made.

4. Approved map of project by Noida Authority.

Page 28: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 28 of 50

5. An inspection should be made by Deputy Director, Regional Office, Meerut regarding

compliance to earlier E.C. and status of proposed expansion and report should be submitted

within 15 days.

6. An affidavit regarding the discharge/reuse of the domestic effluent with clear cut plan shall

have to be submitted within 15 days time.

A site inspection was undertaken by Shri Devendra Sinhg, Deputy Director, Regional Office,

Directorate of Environment, Meerut. The committee discussed the inspection report and observed that

construction work regarding the proposed project has been started without obtaining prior environmental

clearance. The committee directed the project proponent to submit compliance of MoEF OM dated

12/12/2012 for violation of EP Act, 1986. List of Board of Directors with their address and details of

year wise construction without obtaining environmental clearance should be submitted. Secretary,

SEAC shall make necessary communication to State Govt. for issuing directions to UPPCB for initiation

of legal action in this regards. The matter shall be discussed by the committee after receipt of

information from UPPCB regarding initiation of credible legal action.

15- Group Housing Project “Sports City” at Plot No-SC-01/A2, Sector-79, Noida, U.P. Sri Vinod

Kr. Goel, G.M. Tech., C-22/28, Sector-57, Noida. File No. 2337/OSD-T

A presentation was made by the project proponent and along with their consultant M/s Ind Tech

House Consult. The proponent, through the documents submitted and the presentation made, informed

the committee that:-

1. The environmental clearance is sought for proposed Group Housing Project “Sports City” at Plot

No-SC-01/A2, Sector-79, Noida, U.P. M/s Arena Superstructure Pvt. Ltd.

2. Salient features of the project is as follows:

SN Description Details Unit

AREA DETAILS

1 Plot Area 50000 SQM

2 Proposed Built Up Area 214482 SQM

3 Cost of The Project 323.19 CR

4 Height of Tallest Tower 107.35 M

5 No. of Floors 2B+ST+32 NOS

6 Permissible Ground Coverage (@ 28%) 14000 SQM

7 Proposed Ground Coverage 5743.56 SQM

8 Permissible FAR Area including 5% for green rating 144375 SQM

9 Proposed FAR Area (@274.0) 137454.44 SQM

10 Stilt Area 3845 SQM

11 Total Basement Area 51770.46 SQM

12 Ancillary Area 1615.85 SQM

13 Green Area Required (50% of Open Area) 22128.22 SQM

14 Green Area Proposed (51% of Open Area) 22643.330 SQM

POPULATION & WATER REQUIREMENT

Page 29: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 29 of 50

15 Total No. of DU’s 1080 NOS

16 Expected Population 5683 PERSONS

17 Total Water Requirement 512 KLD

18 Fresh Water Requirement (Municipal Water Supply) 330 KLD

19 Waste Water Generation 368 KLD

20 STP Capacity 440 KLD

21 Treated Water Available for Reuse/Used 294 KLD

22 Surplus Treated Water 112 KLD

RAIN WATER HARVESTING PIT DETAILS

23 Proposed quantity of rainwater to be harvested 19772.76 CUM

24 No. of RWH Pits Proposed 6 NOS

PARKING

25 Parking required as /bylaws 1805 ECS

26 Parking Proposed 1879 ECS

27 Surface Parking 305 ECS

28 Basement Parking 1575 ECS

WASTE GENERATION

29 Municipal Solid Waste Generation 2.52 TPD

30 Quantity of e-waste generation 17 KG/DAY

31 Quantity of Hazardous Waste Generation 1904 LTS/ANNUM

32 Quantity of Sludge generated from STP 132.5 KG/DAY

Waste Water Management Plan � Estimated Sewage Generation: 368 KLD

� Waste water generated will be treated on site

� Proposed treatment methodology : MBBR

� Proposed STP (Capacity): 440 KLD (In basement)

� Treatment up to tertiary level.

� Treated waste water will be used for horticulture, flushing, and DG cooling

POWER REQUIREMENT

33 Total Power Requirement (Source of Power Supply:

Uttar Pradesh State Electricity Board)

6839 KW

34 DG sets Backup

� Height of D.G Stack – 113.35 Mt (6mt. Above

tallest tower)

9520 ( 6 No x

1250+ 2 No x

1010)

KVA

3. Water requirement of the project is as follows:

S. No. Water Uses Occupancy/

Capacity/Area

Rate Total Water

Demand (KLD)

A. Domestic Water Requirement

(i) Residential 4860 @86 lpcd 418

(ii) Non Residential

(Employees/Workers)

94 @45 lpcd 4.4

(iii) Visitors 729 @15 lpcd 11

Total Domestic Water Requirement 433

Page 30: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 30 of 50

B. DG cooling 9520 KVA @ 0.9

lt/hr/KVA

51

C. Green Area 22643.33 sq m @ 1 lt/Sq.m. 23

D. Swimming pool

(Makeup Water)

1 LS 5

Total Water Requirement 512

4. The project proposals are covered under category 8”b” of EIA Notification, 2006.

The committee discussed the matter and recommended following TORs and general guidelines

for conducting EIA studies regarding the proposals:

Additional TORs

1. Letter of development authority through which FAR has been revised.

2. Area details tower wise, floor wise, flat wise alongwith % format.

3. A site plan showing the project site and its surroundings with physical features and topographical

details, such as land use, contours and drainage pattern, along with photographs of the site from

all four sides, should be included in the background information.

4. Sanctioned plan/maps regarding the project with all services plans.

5. All plans and elevation sections/all service plan/landscape plan/standard electrification

plan/drainage/sewerage plan.

6. Examine in detail the proposed site with reference to impact on infrastructure covering water

supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw wastes from

the complex on land/water body and into sewerage system.

7. Details of activities that is proposed/likely to come up in the project.

8. Details of hazardous wastes.

9. Water requirement and water management plan alongwith necessary permissions for discharge.

10. Hydro-geological investigations be carried out and obtain permission from Central Ground

Water Authority for withdrawal of ground water.

11. Consider soil characteristics and permeability for rainwater harvesting proposals, should be made

to prevent ground water contamination. Maximize use of treated water by recycling and

utilization of rainwater.

12. Make provision for safety against failure in the operation of wastewater treatment facilities.

Identify acceptable outfall for treated effluent.

13. Details of green belt as a measure for mitigation of dust and noise and buffer between habitation

and proposed project.

14. Landscape plan, green belts and open spaces may be described separately.

15. Study the existing flora and fauna of the area and the impact of the project on them.

16. Examine existing crèche, education, health facilities, police, post Office, Banks and other

services and make adequate provisions in the proposal.

17. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.

18. Application of renewable energy/alternate energy, such as solar and wind energy may be

described including solar water heating in the guidelines for entrepreneurs.

Page 31: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 31 of 50

19. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.

20. Identification of recyclable wastes and waste utilization arrangements may be made.

21. Explore possibility of generating biogas from biodegradable wastes.

22. Arrangements for hazardous waste management may be described as also the common facilities

for waste collection, treatment, recycling and disposal of all effluent, emission and refuse

including MSW, biomedical and hazardous wastes. Special attention should be made with

respect to bird menace.

23. Provisions made for safety in storage of materials, products and wastes may be described.

24. Disaster management plan should be prepared.

25. Traffic management plan including parking and loading/unloading areas may be described.

Traffic survey should be carried out both on weekdays and weekend.

26. Parking provision is to be made for higher ECS worked out either as per state bye-laws or

construction manual of the MoEF

27. Exclusive Parking area in the basement (excluding other facilities) and surface is to be clearly

mentioned

28. Provide service road for entry and exit to project site.

29. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with

provisos of sampling port for monitoring be described.

30. Work out MGLC for the combined capacity of DG sets.

31. Provide for conservation of resources, energy efficiency and use of renewable sources of energy

in the light of ECBC code.

32. Application of resettlement and rehabilitation policy may be described. Project affected persons

should be identified and rehabilitation and resettlement plan should be prepared.

33. Examine separately the details for construction and operation phases both for Environmental

Management Plan and Environmental Monitoring Plan.

34. Environment Corporate Responsibility (ECR) plan along with budgetary provision of minimum

07 crore as discussed in meeting shall be submitted on need base assessment study in the study

area.

35. Source and quantity of required water during construction and management of generated waste

water.

36. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National

Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked. Since the project site

is 07 KM away from Okhla Bird Sanctuary additional ToRs, which are annexed as annexure-1 to

these minutes, should also be complied as per MoEF OM No. J-11013/41/2006-IA-II(I)(Part)

dated 20/08/2014.

General Guidelines

a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by

Public Notary, stating that:

I. “There is no litigation pending against the project and/or land in which the project is proposed

to be set up (please give name & ownership etc. of the project) and that for any such litigation

what so ever, the sole responsibility will be borne by the Project proponent.”

Page 32: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 32 of 50

II. “No activity relating to this project (i.e. name of the project) including civil construction has

been undertaken at site except fencing of the site to protect it from getting encroached and

construction of temporary shed(s) for the guard(s). (if fencing has not been done, then the same

may be deleted).

III. “I/We hereby give undertaking that the data and information given in the application, enclosures

and other documents are true to the best of my knowledge and belief and I/We am/are aware

that if any part of the data and information submitted is found to be false or misleading at any

stage, the project will be rejected and clearance given, if any to the Project will be revoked at

our risk and cost.”

IV. Project does not fall under any buffer zone of no-development as declared /identified under any law.

b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been complied

with (to be deleted if not applicable) & (b) that details and the data presented are factually correct”,

as per MoEF circular dated 04.08.2009 is also to be submitted along with EIA.

c. Current, site photographs viewing towards the project area from four directions indicating date of

photograph taken, direction from which taken, name of the project, and signature of Project

proponent along with consultant with seal should be submitted, so as to ensure that no construction

has been started before the grant of EC.

d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of 2006

and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of

representativeness and reliability of baseline environmental attributes detailed under EIA manual

January, 2001 and other guidelines in the matter.

e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically

mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is

prepared.

f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with

their complete details including their accreditation, if any shall be indicated.

g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the

preparation of these reports and the Name of laboratory through which the samples have been got

analysed should be stated in the report. It shall clearly be indicated whether said laboratory is

accredited by NABL or approved under the Environment (Protection) Act, 1986 (Please refer

MoEF office memorandum dated 4th

August, 2009). The name project leader of the EIA study

shall also be mentioned.

h. The EIA document shall be printed on both sides, as for as possible.

The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted

within 15 days from the date of receipt of the letter and remaining of the information’s is to be submitted

along with the EIA.

Page 33: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 33 of 50

16- Proposed Group Housing Project "Ace parkway" at plot No-SC-01/B-08, Sector-150 Noida,

U.P. M/s ACE Infracity Developers Pvt. Ltd. File No. 2473/OSD-T

A presentation was made by the project proponent and along with their consultant M/s Ind Tech

House Consult. The proponent, through the documents submitted and the presentation made, informed

the committee that:-

1. The environmental clearance is sought for Proposed Group Housing Project "Ace parkway" at

plot No-SC-01/B-08, Sector-150 Noida, U.P. M/s ACE Infracity Developers Pvt. Ltd.

2. Salient features of the project is as follows:

S.N. Description Details Unit

AREA DETAILS

1 Plot Area 45603.63 SQM

2 Proposed Built Up Area 197735.89 SQM

3 Cost of The Project 297.95 CR

4 Height of Tallest Tower 69.10 M

5 No. of Floors 2B+G+21 NOS

6 Permissible Ground Coverage 13441.5 SQM

7 Proposed Ground Coverage 9722.68 SQM

8 Permissible FAR Area 120774.07 SQM

9 Proposed FAR Area 120034.29 SQM

13 Green Area Required (50% of Open Area) 17940 SQM

14 Green Area Proposed (63% Of The Open Area) 22898 SQM

POPULATION & WATER REQUIREMENT

15 Total No. of DU’s 970 NOS

16 Expected Population 5321 PERSONS

17 Total Water Requirement 438 KLD

18 Fresh Water Requirement (GNIDA ) 299 KLD

19 Waste Water Generation 333 KLD

20 STP Capacity 400 KLD

21 Treated Water Available for Reuse/Used 267 KLD

22 Surplus Treated Water 128 KLD

RAIN WATER HARVESTING PIT DETAILS

23 Proposed quantity of rainwater to be harvested 17604.75 CUM

24 No. of RWH Pits Proposed 13 NOS

PARKING

25 Parking required as /bylaws 1510 ECS

26 Parking Proposed 2087 ECS

27 Surface Parking 451 ECS

28 Basement Parking 1636 ECS

WASTE GENERATION

29 Municipal Solid Waste Generation 2.29 TPD

30 Quantity of e-waste generation 14.95 KG/DAY

31 Quantity of Hazardous Waste Generation 756 LIT/ANNUM

32 Quantity of Sludge generated from STP 120 KG/DAY

POWER REQUIREMENT

33 Total Power Requirement 3700 KW

Page 34: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 34 of 50

34 DG sets Backup 3260

[2@ 380+ 2@ 500 +

2@ 750)

KVA

3. Water requirement details of the project is as follows:

S. No. Description Occupancy / Capacity /

Area

Rate Total Water

Demand

(KLD)

A. Domestic Water Requirement

(i) Residents 4365 @ 86 lpcd 375

(ii) Non Residents 83 @ 30 lpcd 2.49

(iii) Visitors 873 @ 12 lpcd 10.476

Total Domestic Water Requirement 387.966

B. DG cooling 3260 KVA @ 0.9 lit/hr/KVA 17.60

C. Green Area 22898 sq m @ 1 lit/Sq m 22.89

Total Water Requirement 437.72 ~ 438

4. Water calculation details is as follows:

USES QTY % WRT TOTAL WATER

REQUIREMENT

TOTAL WATER REQUIREMENT 438 KLD

FRESH WATER REQUIREMENT 299 KLD 68.3

TREATED WATER REQUIREMENT 267 KLD 61

WATER FOR FLUSHING 98 KLD

GARDENING 23 KLD

DG COOLING 18 KLD

WASTE WATER GENERATION (80% of

total domestic fresh water demand + 100%

of Flushing Water)

333 KLD

CAPACITY OF STP 400 KLD

TREATED WATER GENERATION 139 KLD

SURPLUS TREATED WATER (294-182) 128 KLD

WATER REQUIRED FOR FIRE

SUPRESSION

475 KL 108

UG TANK 200 KL

OVER HEAD TANK @ 25000/TOWER

FOR11 TOWERS

275 KL

5. The project proposals are covered under category 8”b” of EIA Notification, 2006.

The committee discussed the matter and recommended following TORs and general guidelines

for conducting EIA studies regarding the proposals:

Additional TORs

1. Letter of development authority through which FAR has been revised.

2. Area details tower wise, floor wise, flat wise alongwith % format.

3. A site plan showing the project site and its surroundings with physical features and topographical

Page 35: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 35 of 50

details, such as land use, contours and drainage pattern, along with photographs of the site from

all four sides, should be included in the background information.

4. Sanctioned plan/maps regarding the project with all services plans.

5. All plans and elevation sections/all service plan/landscape plan/standard electrification

plan/drainage/sewerage plan.

6. Structural plan is to be submitted signed by qualified structural designer.

7. All service plans like sewer drainage water supply rain water harvesting fire fighting landscape

plan is to be submitted.

8. Play school convenient shops community hall to be provided.

9. Examine in detail the proposed site with reference to impact on infrastructure covering water

supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw wastes from

the complex on land/water body and into sewerage system.

10. Details of activities that is proposed/likely to come up in the project.

11. Water requirement and water management plan alongwith necessary permissions for discharge.

12. Hydro-geological investigations be carried out and obtain permission from Central Ground

Water Authority for withdrawal of ground water.

13. Consider soil characteristics and permeability for rainwater harvesting proposals, should be made

to prevent ground water contamination. Maximize use of treated water by recycling and

utilization of rainwater.

14. Make provision for safety against failure in the operation of wastewater treatment facilities.

Identify acceptable outfall for treated effluent.

15. Details of green belt as a measure for mitigation of dust and noise and buffer between habitation

and proposed project.

16. Landscape plan, green belts and open spaces may be described separately.

17. Study the existing flora and fauna of the area and the impact of the project on them.

18. Examine existing crèche, education, health facilities, police, post Office, Banks and other

services and make adequate provisions in the proposal.

19. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.

20. Application of renewable energy/alternate energy, such as solar and wind energy may be

described including solar water heating in the guidelines for entrepreneurs.

21. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.

22. Identification of recyclable wastes and waste utilization arrangements may be made.

23. Explore possibility of generating biogas from biodegradable wastes.

24. Arrangements for hazardous waste management may be described as also the common facilities

for waste collection, treatment, recycling and disposal of all effluent, emission and refuse

including MSW, biomedical and hazardous wastes. Special attention should be made with

respect to bird menace.

25. Provisions made for safety in storage of materials, products and wastes may be described.

26. Disaster management plan should be prepared.

27. Traffic management plan including parking and loading/unloading areas may be described.

Traffic survey should be carried out both on weekdays and weekend.

Page 36: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 36 of 50

28. Parking provision is to be made for higher ECS worked out either as per state bye-laws or

construction manual of the MoEF

29. Exclusive Parking area in the basement (excluding other facilities) and surface is to be clearly

mentioned

30. Provide service road for entry and exit to project site.

31. Use of local building materials should be described.

32. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with

provisos of sampling port for monitoring be described.

33. Work out MGLC for the combined capacity of DG sets.

34. Provide for conservation of resources, energy efficiency and use of renewable sources of energy

in the light of ECBC code.

35. Application of resettlement and rehabilitation policy may be described. Project affected persons

should be identified and rehabilitation and resettlement plan should be prepared.

36. Examine separately the details for construction and operation phases both for Environmental

Management Plan and Environmental Monitoring Plan.

37. Environment Corporate Responsibility (ECR) plan along with budgetary provision of minimum

07 crore as discussed in meeting shall be submitted on need base assessment study in the study

area.

38. Details of all internal and peripheral roads width.

39. Source and quantity of required water during construction and management of generated waste

water.

40. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from National

Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

General Guidelines

a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by

Public Notary, stating that:

I. “There is no litigation pending against the project and/or land in which the project is proposed

to be set up (please give name & ownership etc. of the project) and that for any such litigation

what so ever, the sole responsibility will be borne by the Project proponent.”

II. “No activity relating to this project (i.e. name of the project) including civil construction has

been undertaken at site except fencing of the site to protect it from getting encroached and

construction of temporary shed(s) for the guard(s). (if fencing has not been done, then the same

may be deleted).

III. “I/We hereby give undertaking that the data and information given in the application, enclosures

and other documents are true to the best of my knowledge and belief and I/We am/are aware

that if any part of the data and information submitted is found to be false or misleading at any

stage, the project will be rejected and clearance given, if any to the Project will be revoked at

our risk and cost.”

IV. Project does not fall under any buffer zone of no-development as declared /identified under any law.

Page 37: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 37 of 50

b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been complied

with (to be deleted if not applicable) & (b) that details and the data presented are factually correct”,

as per MoEF circular dated 04.08.2009 is also to be submitted along with EIA.

c. Current, site photographs viewing towards the project area from four directions indicating date of

photograph taken, direction from which taken, name of the project, and signature of Project

proponent along with consultant with seal should be submitted, so as to ensure that no construction

has been started before the grant of EC.

d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of 2006

and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of

representativeness and reliability of baseline environmental attributes detailed under EIA manual

January, 2001 and other guidelines in the matter.

e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically

mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is

prepared.

f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with

their complete details including their accreditation, if any shall be indicated.

g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the

preparation of these reports and the Name of laboratory through which the samples have been got

analysed should be stated in the report. It shall clearly be indicated whether said laboratory is

accredited by NABL or approved under the Environment (Protection) Act, 1986 (Please refer

MoEF office memorandum dated 4th

August, 2009). The name project leader of the EIA study

shall also be mentioned.

h. The EIA document shall be printed on both sides, as for as possible.

The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted

within 15 days from the date of receipt of the letter and remaining of the information’s is to be submitted

along with the EIA.

The committee also discussed decision dated 11/08/2014 of Hon'ble NGT regarding Sport City

in sector-150, Noida (application no. 128/2014 Raghuveer Singh V/s Union of India and Ors.) which

relates to matter of construction on no development zone at the river bank in the interest of environment

and ecology. The committee directed that the project proponent should also submit a note regarding their

project location in view of above decision of Hon'ble NGT.

17- Engine based power production manu. Unit M/s Honda Siel Power Products, at Plot No-5,

Sector-41, Kasna, Greater Noida, U.P Sri Rajeev Sharma, Vice President, Plot No-5, Sector-41,

Kasna, Greater Noida, U.P. File No. 2389/DD-Y

A presentation was made by the project proponent and along with their consultant M/s Perfact

Enviro Solutions Pvt. Ltd. The proponent, through the documents submitted and the presentation made,

informed the committee that:-

1. The environmental clearance is sought for Engine based power production manu. Unit at Plot

No-5, Sector-41, Kasna, Greater Noida, U.P. M/s Honda Siel Power Products.

2. Salient features of the project is as follows:

Page 38: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 38 of 50

Description Existing (Sqm) Proposed (Sqm) Total (Sqm)

Plot Area 101247.2 101247.2 101247.2

G.C (Per) (50%) 50623.57 - 50623.57

G.C (Ach) (32.7 %) 33124.42 14866.86 47991.29

F.A.R (Per) (60%) 60748.29 - 60748.29

F.A.R (Ach) (33.53 %) 33945.78 15246.59 49192.37

Built up Area 33945.78 15246.59 49192.37

Open Area

(Total Plot Area-

Permissible G.C)

38566.36 SQM 38566.36 –

16803.8 sqm

21762.56 sqm

Green Area 25311.78 462.22 25774

Surface Parking Area 4244.64 sqm 1474.72 sqm 5719.36 sqm

No. of Floors G+1 G+1 G+1

No. of Block 20 1 21

Height of building 12.5 m 12.5 m 12.5 m

No. of Rain water

Harvesting collection

tanks with pit

6 5 11

Office & Maintenance

Staff 792 168 960

Visitors 40 0 40 TOTAL POPULATION 832 168 1000 Total Power load (KVA) 1000 KVA, 1x 1.1MW

gas generator 500 KVA 1500 KVA, 1x 1.1MW

gas generator No. of DG sets 1 x 1000 (KVA)

2 x 500 (KVA)

1 x 250 (KVA)

2 x 1000 (KVA)

1 x 125 (KVA) 3 x 1000 (KVA)

2 x 500 (KVA)

1 x 250 (KVA)

1 x 125 (KVA) Parking required 229 ECS

3. Raw material and its daily consumption details of the are as follows:

S.No. Process Raw Material Daily Consumption

1. Press Shop Extra deep drawing quality sheet 4.0 MT

2. Alternator Shop Copper wire 1.3 MT

Coil Varnish 0.2 MT

3. Paint Shop Paints 0.2 MT

Thinner 0.1 MT

4. Die Casting Aluminum Ingot 6.0 MT

5. Others Oil (Lubricant) 40 liters

Grease 0.01 MT

4. Water requirement of the project is as follows:

PROCESS EXISTING PROPOSED TOTAL

Water

Requirement

(Kld)

Waste

Water

Generation

Water

Requirement

(Kld)

Waste

Water

Generation

Water

Requirement

(Kld)

Waste

Water

Generati

Page 39: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 39 of 50

(Kld) (Kld) on

(Kld)

Industrial Process 50 35 65 45 115 80

Cooling 48 0.3 252 1.4 300 1.7

Boiler Feed 6 0.1 8 0.2 14 0.3

Washing 15 15 19 19 34 34

Domestic Drinkin

g

50 40 66 53 117 94

Flushing 60 60 78 78 138 138

Gardening 100 nil 0 0 100 0

Total 329 KLD 150.4 KLD 488 KLD 196.6 KLD 817 KLD 348

KLD

STP-150 KLD,ETP-75 KLD STP- 150 KLD, ETP-75 KLD 2 ETP- 75 KLD and 75

KLD

2 STP- 150 KLD, 150 KLD

5. Water management details are as follows:

Source of Water Bore Wells at the site Total Water Requirement 817 KLD

Net Fresh Water Requirement 254 KLD Total Wastewater Discharge 348 KLD

STP Capacity Existing Proposed 150 KLD 150 KLD

ETP Capacity 75 KLD 75 KLD

6. Municipal solid waste generation details is as follows:

SOLID WASTE GENERATION Population MSW IN KG/DAY

Office & Maintenance Staff 960 144

Visitors 40 6

Total 1000 150 KG/DAY

7. Hazardous waste details of the project is as follows:

Hazardous waste

generated

Existing Proposed Total

1) Paint Sludge 9.1 tons/year 12.9 tons/year 22.8 tons/year

1) ETP sludge 17.1 tons/year 19.3 tons/ year 36.4 tons/year

1) Phosphating

Sludge

0.62 ton/year 0.6 tons/year 1.22 ton/year

Electronic Waste Black with

Label/

Hazardous

Waste

It is being given to approved

vender of SPCB as per

Electronic Wastes (Management/

Handling) Rules, 2011 effective

from 01-05-2012

40 KG/

Month

Page 40: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 40 of 50

The committee discussed the matter and directed that following information/clarification

should be sought from proponent:

1. Process details.

2. List of finished products and steps involved.

3. Why the application should not be treated under category 3"a" while the proposal includes

establishment of 02 MCH furnaces and 02 Paintshop ovens also.

The matter shall be discussed after submission of information as above.

18- Proposed Cement Grinding Unit of KLK Cement Pvt. Ltd., at Plot N0-E-18,19,20, UPSIDC

Sidhwan, Jaunpur, U.P. Sri Pradeep Kumar, director, Balia Agency, Ram Lila Maidan, Naya

Chowk, Balia, U.P. File No. 2335/DD-DS

A presentation was made by the project proponent and along with their consultant M/s Prakriti

Consultants Services. The proponent, through the documents submitted and the presentation made,

informed the committee that:-

1. The environmental clearance is sought for Proposed Cement Grinding Unit at Plot N0-E-18, 19,

20, UPSIDC Sidhwan, Jaunpur, U.P. M/s KLK Cement Pvt. Ltd.

2. Salient features of the project is as follows:

� Land Area 3510 sqm in Industrial Area, Rampur Sidhwan, Jaunpur

� Type of unit Cement Grinding Unit

� Capacity 30,000 TPA ( 100 TPD) (300 Working day)

� Raw Material Clinker - Reeva, MP, Gypsum – Kanpur,Fly Ash- Renukoot

� Variety of Cement OPC (Ordinary Portland Cement),

PPC (Portland Pozzolona Cement)

� Water requirement 1 KLD

� Source of water Bore Well (Ground Water)

� Electric requirement 400 KVA for 100 TPD Cement Plant

� Worker & Staff 17 nos.

3. The project proposals are covered under category 3”b” of EIA Notification, 2006.

The committee discussed the matter and recommended following TORs and general guidelines

for conducting EIA studies regarding the proposals:

Additional TORs

1. Approved plan from Jaunpur Industrial Development Authority.

2. Details of total area, covered area, open area, factory area, lab area, raw material store yard.

3. Environment Impact study must be done (by a consultant registered/certified as per QCI

notification/MoEF directives) in an area of 15 km radius with inclusion of following aspects:

4. Present land use based on satellite imagery should be included. Study area should be 10 Km radius.

5. Details of location of wildlife sanctuary and national parks within 10 km radius of the plant and

plan for conservation and protection of the same should be included.

6. Manufacturing process details for the cement plant should be included.

7. Mass balance for the raw material and products should be included.

Page 41: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 41 of 50

8. Energy balance data for all the components should be incorporated.

9. Site-specific micro-meteorological data for temperature, relative humidity, hourly wind speed and

direction and rainfall including inversion height and mixing height should be included.

10. Collection of baseline data on air, water (surface and ground water), soil, noise, demography etc. for

one season other than monsoon should be included and the Methods of Monitoring and analysis

(Annexure-IV): Guidance for assessment of representativeness and reliability of baseline

environmental attributes detailed under EIA manual January, 2001 and other guidelines in the

matter.

11. Ambient air quality at 8 locations within the study area of 10 km., aerial coverage from project site

with one AAQMS in downwind direction should be carried out.

12. The suspended particulate matter present in the ambient air must be analyzed for the presence

of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of

RSPM and incorporating of RSPM data.

13. Ambient air quality modeling for cement plant should be included. Air quality modeling for all the

plants proposed for specific pollutants needs to be done. APCS for the control of emissions from the

kiln and WHRB should also be included.

14. Ambient air quality monitoring modeling along with cumulative impact should be included

for the day (24 hrs) for maximum GLC along with following:

i. Emissions (g/second) with and without the air pollution control measures.

ii. Meteorological inputs (wind speed, m/s), wind direction, ambient air temperature, cloud

cover, relative humidity & mixing height) on hourly basis.

iii. Model input options for terrain, plume rise, deposition etc.

iv. Print-out of model input and output on hourly and daily average basis.

v. A graph of daily averaged concentration (MGLC scenario) with downwind distance at every

500 m interval covering the exact location of GLC.

vi. Details of air pollution control methods used with percentage efficiency that are used for

emission rate estimation with respect to each pollutant.

vii. Applicable air quality standards as per LULC covered in the study area and %

contribution of the proposed plant to the applicable Air quality standard. In case of expansion

project, the contribution should be inclusive of both existing and expanded capacity.

viii. No. I-VII is to be repeated for fugitive emissions and any other source type relevant and

used for industry.

ix. Graphs of monthly average daily concentration with down-wind distance.

x. Specify when and where the ambient air quality standards are exceeded either due to the

proposed plant alone or when the plant contribution is added to the background air quality.

xi. Fugitive dust protection or dust reduction technology for workers within 30 m of the plant

active areas.

15. Sources of secondary emissions, its control and monitoring as per the CPCB guidelines should be

included.

16. Details of fugitive emissions and control technologies should be provided.

17. Action plan for solid/hazardous waste generation, storage, utilization and disposal particularly slag

from any sources.

18. Chemical characterization of RSPM and incorporation of RSPM data should be included.

Location of one AAQM station should be in downwind direction.

19. Presence of an aquifer(s) within 1 km of the project boundaries and management plan for recharging

the aquifer should be included.

20. Source of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph), metal trace

Page 42: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 42 of 50

element (as above) chemical analysis for water to be used. If surface water is used from river,

rainfall, discharge rate, quantity, drainage and distance from project site should also be included.

21. Ground water analysis with bore well data, litho-logs, drawdown and recovery tests to quantify the

area and volume of aquifer and its management.

22. Ground water modeling showing the pathways of the pollutants should be included.

23. Column leachate study for all types of stockpiles or waste disposal sites, at 20oC-50

oC should be

conducted and included.

24. Permission for the drawl of water 94 KLD water from the concerned authority and water balance

data including quantity of effluent generated, recycled and reused and discharged is to be

provided. Methods adopted/to be adopted for the water conservation should be included.

25. Efforts made to minimize use of ground water along with an action plan should be provided.

26. A chapter on hydrology study by the State Govt. may be included.

27. Action plan for surface as well as roof top rainwater harvesting and ground water recharge should be

included.

28. Scheme of proper storage of fly ash, gypsum, clinker should be included.

29. Action plan for 100% fly ash utilization should be included.

30. Impact of transportation of raw materials and the details of mitigation measures should be included.

31. Ambient air quality monitoring modeling along with cumulative impact should be included for

the day (24 hrs) for maximum GLC along with emissions (g/second) with and without the air

pollution control measures and A graph of daily averaged concentration (MGLC scenario) with

downwind distance at every 500 m interval covering the exact location of GLC.

32. An action plan to control and monitor secondary fugitive emissions from all the sources as per the

latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated 30th May, 2008.

33. Detailed description of the flora and fauna (terrestrial and aquatic) should be given with special

reference to rare, endemic and endangered species.

34. Risk assessment and damage control should be included.

35. If the site is within 10 km radius of any major river, A note on the impact of drawl of ground water

on recharge potential.

36. If the site is within 10 km radius of any major river, Surface water quality of nearby River (60 m

upstream and downstream) and other surface drains at eight locations must be ascertained.

37. If the site is within 10 km radius of any major river, Flood Hazard Zone Mapping is required at

1:5000 to 1:10,000 scale indicating the peak and lean river discharge as well as flood occurrence

frequency.

38. A note on treatment of wastewater from different plants, recycle and reuse for different purposes

should be included.

39. Provision of traps and treatment plants are to be made, if water is getting mixed with oil, grease and

cleaning agents.

40. If the water is mixed with solid particulates, proposal for sediment pond before further transport

should be included. The sediment pond capacity should be 100 times the transport capacity.

41. The pathways for pollution via seepages, evaporation, residual remains are to be studied for surface

water (drainage, rivers, ponds, lakes), sub-surface and ground water with a monitoring and

management plans.

42. Ground water monitoring minimum at 8 locations and near solid waste dump zone, Geological

features and Geo-hydrological status of the study area are essential as also Ecological status

(Terrestrial and Aquatic) is vital.

43. Geo-technical data by a bore hole of up to 40 mts. in every One sq. km area such as ground water

level, SPTN values, soil fineness, geology, shear wave velocity etc. for liquefaction studies and to

Page 43: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 43 of 50

assess future Seismic Hazard and Earthquake Risk Management in the area.

44. End use of solid waste and its composition should be covered.

45. All stock piles will have to be on top of a stable liner to avoid leaching of materials to ground water.

46. Studies on amount of CO2 emission (daily monitoring), Hydrocarbons, other contamination, if any,

and their management.

47. Occupational health of the workers needs elaboration including evaluation of noise, heat,

illumination, dust, any other chemicals, metals being suspected in environment and going into

body of workers either through inhalation, ingestion or through skin absorption and steps taken

to avoid Musculo-Skeletal Disorders (MSD), backache, pain in minor and major joints, fatigue etc.

Occupational hazards specific pre-placement and periodical monitoring and periodical monitoring

should be carried out. The detailed plan to carry out above mentioned activity should be mentioned.

48. Action plan for the green belt development plan in 33% area should be included. The green belt

should be around the project boundary and a scheme for greening of the traveling roads should also

be incorporated. All rooftops/terraces should have some green cover.

49. Demography of the area and socio-economic development activities need to be elaborated

upon.

50. Scheme for compliance to the recommendations mentioned in the CREP guidelines for cement

plants should be included.

51. A note on identification and implementation of Carbon Credit project should be included.

52. Detailed Environment management Plan (EMP) with specific reference to details of air pollution

control system, water & wastewater management, monitoring frequency and implementation plan

for mitigation measure should be provided.

53. EMP should include the concept of waste-minimization, recycle/reuse/recover techniques, energy

conservation and natural resource conservation.

54. Total capital cost & recurring cost/annum for environmental pollution control measures.

55. Any litigation/court case pending against the proposal or land should also be included.

56. A tabular chart of the TORs and compliance index should be incorporated in EIA/EMP.

57. Project falling with in 10 km. area of Wild Life Sanctuary is to obtain a clearance from National

Board Wild Life (NBWL) even if the eco-sensitive zone is not earmarked.

58. The proposal is exempted form public hearing by categorizing in B-2 category due to use of energy

efficient technology, on clinker manufacturing at the proposed site, no sensitive area within 10 km.

radius, "zero" effluent discharge, utilization of all the solid waste in the process itself including

utilization of fly ash etc.

59. Besides the above, the general points mentioned below should also to be followed during

preparation of EIA/EMP:

• All documents to be properly referenced with index, page numbers and continuous page

numbering.

• Where data are presented in the report especially in tables, the period in which the data were

collected and the sources should be indicated.

As decided by the State Expert Appraisal Committee the above TORs should be considered for

preparation of EIA/EMP report for the Cement Plant; in addition to all the relevant information as

per the Generic Structure of EIA given in Appendix III and IIIA in the EIA Notification, 2006.

Page 44: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 44 of 50

19- Proposed Cement Grinding Unit M/s Durgashree Bricks Pvt. Ltd., at Plot N0-D-22, Industrial

Area, Sikandarabad, Bulandshahar, U.P. Sri Gautam Kanodia, Director, T-8, Aditya City

Centre, Vibhav Khand, Indirapuram, Ghaziabad. File No. 2336/AD-VB

The committee noted that the application for environmental clearance was made by consultant

through letter dated 23/05/2014. The application should be made by project proponent himself. The

committee deliberated that project proponent should apply under his signature. The committee directed

to defer the matter till a application as above is received in this regards.

20- M/s Omega International, Unit-4, Plot No-B-11/c & B-11/D, UPSIDC Industrial Area, Site-II,

Unnao – Sri Asfand Akhtar, M/s Omega International, Unit-4, Plot No-B-11/c & B-11/D,

UPSIDC Industrial Area, Site-II, Unnao. File No. 2421/AD-Sub.

A presentation was made by the project. The proponent, through the documents submitted and

the presentation made, informed the committee that:-

1. The environmental clearance is sought for raw leather to finish leather having capacity 2250

hide/day at plot no. B-11/C and B-1/D, UPSIDC Industrial Area, Site-II, Unnao, M/s Omega

International.

2. Area statement of the project is as follows:

Land use Total Area % of total plot

Area under plots 7316

Road and Parking Area 700 10

Common Facilities plant and machinery 2676 36

Green spaces 2500 33

ETP, Salt recovery and chrome recovery unit 1200 16

Basement 576

3. List of raw material used in the proposed project is as follows:

No of raw hides 2250 hides

Per hide weight 20 KG

Sodium Sulphite 900 KG

Lime 3150 KG

Amonium Sulphate 1125 KG

Salt 1575 KG

Salphuric Acid 675 KG

BCS 1350 KG

Formate 225 KG

Pesarvative 22 KG

Soda Bi Carb 900 KG

OC 27 KG

WT 94 KG

A-1 400 KG

177 670 KG

606 1690 KG

Acid Bate 17 KG

Neutrigun 135 KG

Page 45: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 45 of 50

Soda Bi Carb 270 KG

Formate 270 KG

Amonia Bi Bard 200 KG

LSW 67 KG

HS 67 KG

MA-30 135 KG

1093 135 KG

Liq. Amonia 67 KG

Basyntan UR 270 KG

Dye 135 KG

Relugan D 135 KG

Formic Acid 470 KG

Pesarvative 40 KG

4. Total water requirement of the project is proposed as 1300 m3/day which shall be sourced from

ground water.

5. Solid waste generation details of the project is as follows:

S. No. Type of Waste Quantity Generation

(MT/Month)

1. Coal Ash (Generated through Boiler) 4-5

2. ETP Sludge 100-115

3. Used oil (Generated through Stand by DG Sets) 20 liter/month

4. Small pieces of leather 2-3

6. The project proposals are covered under category 4"f" of EIA Notification, 2006.

The committee discussed the matter and deliberated that following terms of reference for the

tannery project may be issued regarding the proposals:

1. Compliance of the conditions a stipulated under charter on "Corporate Responsibility for

Environmental Protection (CREP).

2. Greenbelt plan showing 33% of total plot area and pattern.

3. Location of proposed site in Unnao Master Plan of UPSIDC area.

4. Details about infrastructure facilities in the proposed area with specific reference to pollution

control measures.

5. Waste management including waste treatment, waste recycling and waste application on land.

6. Drainage infrastructure facilities.

7. Width of approach road is to shown in map/lay out plan.

8. Public hearing regarding the proposed activity should be undertaken as per law and report

submitted to the SEIAA/SEAC.

9. Sources of water and its availability.

10. Water Conservation measures proposed in the project.

11. Plans for effluent treatment and disposal including Chrome recovery

12. Emergency Plan for effluent management during process disturbances.

13. Plans for Hazardous and solid waste management/disposal and authorization.

Page 46: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 46 of 50

14. Plans for rooftop rain water harvesting.

15. Ground water Quality around ETP. Guard pond, solar evaporation pond and landfill site.

16. Plans for annual environmental auditing.

17. Plans for infrastructure facilities such as water supply, fuel, sanitation etc for construction

workers so as to avoid felling of trees and pollution of water.

18. Noise levels in and around the plant area.

19. Occupational health surveillance plan for the workers.

20. Environmental Corporate Responsibility (ECR) plan along with budgetary provision amounting

to 2% of total project cost shall be submitted on need base assessment study in the study area.

21. EIA should strictly follow the methods of monitoring and analysis, Annexure-IV: guidance for

assessment of the representativeness and reliability of baseline environmental attributes detailed

under EIA manual. January, 2001 and the other guidelines in the matter.

21- Expansion of Billet Manufacturing Plant from 30000 TPA to 60000 TPA at Vill-Malaysia,

Tehsil-Dhanaura, Distt-Amroha Sri Devinder Singh Bindra, Director, Vill-Malaysia, Tehsil-

Dhanaura, Distt-Amroha. File No. 2449/DD-Y

The project proponent did not appear. The committee directed to close the case and to

reopen only on a request to this effect from the project proponent.

22- Group Housing Project “CASA GREEN EXOTICA” at Plot No-09, Sector-17, UP Avas evm

Vikas Parisad, Vrindavan Yojna No-4, Rae Bareli Road, Lucknow, U.P. File No. 2360/AD-Sub.

A presentation was made by the project proponent along with their consultant M/s Ind Tech

House Consult. The proponent, through the documents submitted and the presentation made, informed

the committee that:-

1. The environmental clearance is sought for Group Housing Project “Casa Green Exotica” at Plot

No-09, Sector-17, UP Avas evm Vikas Parisad, Vrindavan Yojna No-4, Rae Bareli Road,

Lucknow, U.P. M/s Radhey Krishna Technobuilt Pvt. Ltd.

2. Area statement of the project is as follows:

SN Description Details

1 Gross Plot Area 7225 sq m (1.78 Acres)

2 Proposed Built Up Area 26048.1 sq m

3 Permissible Ground Coverage (@35% Plot Area) 2528.8 sq m

4 Proposed Ground Coverage (@22.223% Plot Area) 1606.2 sq m

5 Permissible FAR (@ 250 of Plot Area) 18062.5 sq m

6 Proposed FAR (@ 249.9) 18052.3 sq m

7 Total Basement Area 5028.198 sq m

8 Stilt and Podium Area 2668.1 sq m

9 Non FAR Area (Mumty, Machine Room, Watchman Post) 213.25 sq m

10 Surface Parking Area 1684.93 sq m

11 Podium Parking 2668.14 sq m

Page 47: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 47 of 50

12 Basement Parking 5028.198 sq m

13 Green Area required (@ 10% of plot Area) 722.5 sq m

14 Green Area Proposed(@10.774% of plot Area) 778.5 sq m

3. Salient features of the project is as follows:

SN Description Details Unit

1 Gross Plot Area 7225 SQM

2 Proposed Built Up Area 26048.1 SQM

3 Parking 360 ECS

4 Total Nos. of DU’s 252 NOS

5 Expected Population 1421 PERSONS

6 Total Water Requirement 116 KLD

7 Fresh water requirement 83 KLD

8 Waste water Generation 94 KLD

9 STP Capacity 120 KLD

10 Treated Water Available for Reuse/Used 75 KLD

11 Surplus treated water 42 KLD

12 Proposed quantity of Rainwater to be Harvested 5425 CUM

13 No. of RWH Pits Proposed 2 NOS

14 Total Power Requirement (UPSEB) 1100 KW

15 DG set backup 02 nos. (1no X 250 KVA + 1no. X 500 KVA) 750 KVA

16 Municipal Solid Waste Generation 0.5 TPD

17 Quantity of E-Waste Generation 2.6 KG/DAY

18 Quantity of Hazardous waste Generation 150 LTS/ANNUM

19 Quantity of Sludge Generated from STP 32 KG/DAY

20 Total Earth Excavation 20112.8 CUM

21 Ground Water Table-Pre Monsoon 22.0 M

22 Ground Water Table-Post Monsoon 20.5 M

4. Water requirement and source of the project is as follows:

S.

No.

Water Uses Occupancy/

Capacity/Area

Rate Total Water

Demand

(KLD)

A. Domestic Water Requirement

(i) Residential 1260 @86 lpcd 108.36

(ii) Non Residential

(employees/workers)

35 @30 lpcd 1.05

(iii) Visitors 126 @12 lpcd 1.52

Total Domestic Water Requirement 111

B. DG cooling 750 KVA @ 0.9 lt/hr/KVA 4

C. Green Area 778.5 sq m @ 1 lt/Sq.m. 0.78

Total Water Requirement 115.76 Says

Page 48: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 48 of 50

116

Uses Source Qty UGT OHT

Fresh Water Requirement Municipal Water Supply 83 KLD 54 KL 29 KL

Treated Water Requirement On site STP 33 KLD 5 KL (For

Gardening &

DG Cooling)

28KL (For

Flushing)

Water Required for Fire

Fighting

Municipal Water Supply 130 KL 100 KL 30 KL

Emergency Water

Requirement

Bore well (With permission

from CGWA)

- - -

5. Solid waste generation details is as follows:

Details Population Duration of

Use in Hrs

Waste

Generation

Rate Kg/Person

Total Waste

TPD

Residential 1260 24 0.04 0.5

Non Residential 35 8-10 0.25 0.009

Visitors 126 1-1.5 0.1 0.012

Total Waste 0.52

Organic / Biodegradable Waste

(60% of Total Waste)

0.29

6. The project proposals are covered under category 8”a” of EIA Notification, 2006.

The committee discussed the matter and directed the project proponent to submit following

information/clarifications:

1. Copy of ownership documents regarding the project.

2. Copy of development authority documents through which FAR has been allowed.

3. Specify the permitted uses of the proposed project site as per zoning of Lucknow Master

Plan.

4. Area statement with block wise, floor wise details should be submitted.

5. Copy of sanctioned plans/maps as approved by Competent Development Authority.

6. On scale map showing approach road with reference to project site.

7. Site layout plan with dimensions should be submitted. All road widths should be clearly

mentioned in the layout plan.

8. Development Authority bye-laws for basement parking should be submitted.

9. Landscape/green plan.

10. Structural design map alongwith certificate for structural safety.

11. All services maps i.e. sewage, drainage, external electrification, rain water harvesting,

parking, uses of solar energy etc.

12. Solar energy provisions for street lighting and stair case lighting should be made and plans

submitted.

Page 49: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 49 of 50

13. For basement, only modular STP shall be accepted. No civil construction in basement for

STP shall be allowed. According plans should be submitted.

14. Section drawing for roads showing all services i.e. footpath/parking/sewage/drainage.

15. A CSR Plan with 2% of project cost should be prepared and details submitted.

The matter shall be discussed after submission of information as above.

23- Group Housing Project “KDA Dream” at near Shatabdinagar Phase-4, Jawaharpuram, Panki,

Kanpur, U.P. File No. 2364/AD(VB)

The committee noted that the project proponent or their authorized representative was not

present in the meeting. The committee deferred the matter for next meeting. The committee also noted

that the Committee Members have not received project reports yet and directed the consultant present in

the meeting to ensure communication of the reports to all Members immediately.

24- Group Housing Project “KDA Greens” at beside Water Park, Mainawati Road, near Singhpur

Tiraha, Kanpur, U.P. File No. 2365/OSD(T)

The committee noted that the project proponent or their authorized representative was not

present in the meeting. The committee deferred the matter for next meeting. The committee also noted

that the Committee Members have not received project reports yet and directed the consultant present in

the meeting to ensure communication of the reports to all Members immediately.

25- Group Housing Project “KDA Heights” at beside Surajdevi Public School, Navsheeldham,

Bittur Road, Kanpur, U.P. File No. 2366/DD(Y)

The committee noted that the project proponent or their authorized representative was not

present in the meeting. The committee deferred the matter for next meeting. The committee also noted

that the Committee Members have not received project reports yet and directed the consultant present in

the meeting to ensure communication of the reports to all Members immediately.

26- Group Housing Project at Sector-14, Vrindavan Yojna No-4, Tehsil & Distt-Lucknow. File No.

2444/DD(Y)

The project proponent did not appear. The committee directed to close the case and to

reopen only, if a request to this effect is received from the project proponent.

27- Discussion on Petition at Hon'ble Supreme Court for Special Leave to appeal (Civil) No.

21522-29 of 2014 (Sachchidanand Gupta etc. V/s Sushil Kumar Dwivedi etc.) with prayer for

interim relief.

The Secretary, SEAC informed the committee that a copy of petition at Hon'ble Supreme Court

for Special Leave to appeal (Civil) No. 21522-29 of 2014 (Sachchidanand Gupta etc. V/s Sushil Kumar

Dwivedi etc.) has been received by the Directorate. SEIAA and SEAC have been made party no. 7 and

19 in the matter.

Page 50: Minutes of 191st - seiaaup.inseiaaup.in/Uploads/MeetingMinutePdfs/20141009010514PM.pdf · Page 3 of 50 DG set cooling 27 KLD Total water requirement 1063 KLD Waste water 648 KLD Source

Minutes of 191st SEAC Meeting Dated 14/09/2014

Page 50 of 50

The petitioner has filled the petition for Special Leave due to being aggrieved by decisions made

by Hon'ble High Court, Allahabad and Lucknow Bench of Hon'ble High Court, Allahabad.

A specific condition imposed by EIA Authority and quashed by the Hon'ble High Court without

any contrary material on record or counter affidavit of the EIA Authority, which reads as under

"The mining work will be opencast and exclusively manual. No mechanical work or drilling/blasting

be involved at any stage."

The committee discussed the matter and directed that the matter should be put-up to next committee

meeting with relevant documents. The committee also suggested that Standing Counsel as designated by

the State Govt. for the purpose of SEIAA/SEAC should be directed to pray the Hon'ble Court for some

more time to file the replies in the matter.

(Dr. M. S. Khan)

Chairman, SEAC,UP

(Dr. S.N. Singh)

Member, SEAC, UP

(S.C. Brahmachari)

Member, SEAC, UP

(Dr. Asheesh Kumar Singh)

Member, SEAC, UP

(Dr. D. C. Gupta)

Member, SEAC, UP

(Dr. R.K. Sardana)

Secretary, SEAC, UP