HAZARD AND RISK MANAGEMENT PROCEDURE
WORK METHOD STATEMENT(Additional Mini Platform CPPProject)
1. SCOPE OF WORK This work method provides a base guideline for
contractor personnel to do the additional Mini Platform CPP Project
in CPPlocation.The scope covers:1. Prepared material, tools and
equipment.2. Install scaffolding.3. Install lifting gear.4. Install
Mini Platform structure, grating and handrail5. Modification
existing hand rail.6. Remove scaffolding.2. REFERENCE DRAWING
H-054/S/14: Mini Platform
Drawing 2.1 Mini Platform 01 (Dim : 1,5 mtr x 4mtr).
Drawing 2.2 Mini Platform 06 (Dim : 5 mtr x 2 mtr).
Drawing 2.3 Mini Platform 02 (Dim : 1,5 mtr x 1,2 mtr).
Drawing 2.4 Mini Platform 03 (Dim : 1,5 mtr x 3mtr).
Drawing 2.5 Mini Platform 04 (Dim : 1,5 mtr x 4mtr).
Drawing 2.6 Mini Platform 05 (Dim : 1,5 mtr x 6mtr).
Drawing 2.6 Equipment layout looking North.
3. GENERAL3.1 PurposeThe purpose of this procedure is to
describe the general requirement for Lifting / Rigging to Deck
Extension and follow safety procedure.3.2 Tools and Equipment
RequirementA. Tool and equipment which is provided by SAKA Energy.
Ltd Web Sling Capacity 2 Ton x 4 Meter Length c/w Master Link.6 Ea
Chain block SWL 3 Ton2 Ea Chain block SWL 2 Ton1 Ea Chain block SWL
1 Ton2 Ea Beam Clamp SWL 3 Ton3 Ea Shackles Capacity 4 Ton4 Ea Hand
Tools such as Wrench, Hammer, etc.1 Set Manila Rope (@=10 Meter
Length)4 Ea Hand pallet (trolley)2 EaB. Tool and equipment which is
provided by PT. Gearindo Prakarsa Combinasion Wrench size M22
(32mm)2 Ea Combinasion Wrench size M14 (21mm)2 Ea Hummer Wrench
size M22 (32mm)2 Ea Hummer Wrench size M14 (21mm)2 Ea Adjustable
Wrench size 12 1 Ea Rachet Wrench 2 Ea Hand Saw1 Ea
3.3 Man Power RequirementMan power requirement which is provided
by PT. Gearindo Prakarsa. Supervisor1 Person Fitter1 Person Rigger
(Certificate)2 Person Scaffolder4 Person Helper 2 Person
4. WORK METHODSequence of work will be described as follow:A.
Preparation 1. Prepare material, tools and equipment.2. Moving
tools & equipment to work area.
B. Install Scaffolding1. Prepare scaffolding material tools
& equipment and put at near work area.2. Install scaffolding
for work access.3. Install the scaffolding at all work area.
C. Install Lifting gear1. Prepare lifting tools& equipment
and put at near work area.2. Install lifting gear for lift mini
platform3. Lifting gear function test
D. Install mini platform frame structure, grating and handrail1.
Prepare material tools & equipment and transfer material from
lay down area to work area (Main deck).
Pic. 4.1 Laydown Area CPP Upper Deck2. Transfer material Mini
platform at work area using trolley. Work area is above of gang
way.
Pic. 4.2 Trolley at CPP Uper Deck.
Pic. 4.3 Routing of Trolley (width of gang way 1,5 mtr)3.
Lifting and install leg support mini platform. (make sure
scaffolding has been installed).4. Lifting structure frame mini
platform and install or join with leg support.5. Install grating to
frame structure mini platform.6. Install hand rail and ladder to
frame structure mini platform.E. Work Area Picture
Picture 4.4 Work area mini platform 01
Picture 4.5 Work area mini platform 02
Picture 4.6 Work area mini platform 03
Picture 4.7 Work area mini platform 03
Picture 4.8 Work area mini platform 05
Picture 4.9 Work area mini platform 06