Top Banner
MIDTOWN SUBSTATION SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval Requested
23

MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

Aug 18, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

MIDTOWN SUBSTATION SITE RECOMMENDATION

PRESENTED BY:

LeeRoy PerezInterim Senior Director, Substation & Transmission

March 2, 2020

Approva l Reques ted

Page 2: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

2

OBJECTIVES & TAKEAWAYS

• PROVIDE UPDATE ON CUSTOMER INVOLVEMENT & FEEDBACK

• APPROVE RECOMMENDED SITE

Page 3: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

3

AGENDA

• PROJECT OVERVIEW

• CUSTOMER INVOLVEMENT

• BOARD PUBLIC INPUT SESSION

• RECOMMENDED LAYOUT

o VISUAL RENDERINGS

• BOARD ACTION

Page 4: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

4

OUR GUIDING PILLARS & FOUNDATION

SecurityCustomer

AffordabilityResiliency Safety

FINANCIALLYRESPONSIBLE

All business decisions are based on our commitment to being one of the best-managed and most financially responsible utilities in the nation!

ReliabilityEnvironmentalResponsibility

Page 5: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

5

MIDTOWN SUBSTATIONPROJECT NEED

• Serve Midtown & North Central regional areas - identified in CoSA’s SA Tomorrow plan

• Increase capacity in the northern downtown area to support residential and commercial growth

• Strengthen reliability

• Target date: Jan 2023

North Central & Midtown Area

Page 6: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

6

MIDTOWN SUBSTATIONSTUDY AREA

Study Area

• Boundary (~ 1.6 square miles)

Major Land Constraint

• Habitable structures

o Displacing of residents & businesses

Substation & transmission study areaExisting Comal to Olmos transmission line

LEGEND

Page 7: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

7

CUSTOMER INVOLVEMENTENGAGEMENT SUMMARY

Open House

•Introduce project need

•Communicate reliability improvements

•Discuss project constraints

Neighborhood Meetings

•Received & evaluated valuable feedback

•Strengthen community acceptance

Collaboration Efforts

•Councilman Roberto Treviño initiated discussions between the community, H-E-B & CPS Energy

Board Public Input Session

•Presented collaborated site layout

•Additional community feedback

•Gain community trust

Page 8: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

8

• Open House

o September 19, 2019

• Councilman Treviño & Neighborhood Association meetings

o October 29, 2019

o January 28, 2020

• Board Public Input Session

o February 4, 2020

• Additional Outreach Efforts

o Project website

o Project brochure/FAQ/Questionnaires

o Newspaper advertisement

o Social media – Facebook/Twitter/Blog

CUSTOMER INVOLVEMENT

Facebook blog page

Page 9: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

9

BOARD PUBLIC INPUT SESSIONFEEDBACK

Community expressed appreciation to CPS Energy, Councilman Roberto Treviño,

& H-E-B for our collaboration efforts

Board of Trustees Dr. Willis Mackey and Mr. Ed Kelley leads Board Public Input Session

Customer provides input during the Board Public Input Session

Topics for consideration:

Storm water drainage

Asphalt color

Trees/Grass

Driveway width

Lighting

Project liaison

Page 10: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

10Street view of existing conditions

EXISTING STREET VIEW

Page 11: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

11

EXISTING AERIAL VIEW

Aerial view of existing conditions

Page 12: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

12

TYPICAL SUBSTATION

36th Street substation

Page 13: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

13

STREET VIEW RENDERING

Recommended site & H-E-B parking lot – street view of proposed conditions

Page 14: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

14

AERIAL VIEW RENDERING

Recommended site & H-E-B parking lot – aerial view of proposed conditions

Page 15: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

15

REQUEST FOR APPROVAL

Project team requests Board approval to:

• Purchase the strategic site

• Execute property exchange and shifted layout with H-E-B

• Execute planning and construction of the Project

o Acquire associated right-of-way/easements

Board approval requested

Page 16: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

Thank You

Page 17: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

Appendix

Page 18: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

18

GOVERNANCE PROCESSMIDTOWN

We are here

Nov 2020

Mar 2020

Page 19: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

19

GAS-INSULATED TECHNOLOGYBENEFITS • Safety

o Arc-flash proof

• Securityo Physical security increased as system is in a building

• Environmentalo Protect against external wild lifeo Less impervious cover (drainage) o Sensors continuously monitor insulating gas

• Reliability/Resiliencyo Not susceptible to external elements o No major maintenance for 25 years under normal

operations conditionso Operating life cycle greater than 50 years

• Affordabilityo Less property required provides cost savings o Higher initial capital costs but lower O&M costso Cost savings of displacing of residents & businesses

A 145 kV class GIS operated at 115 kV located in an enclosure in an urban area (high-side arrangement)

Page 20: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

CUSTOMER FEEDBACKELECTRIC & MAGNETIC FIELDS• EMF exposure exists in homes and workplace

• *According to the National Institute of Environmental Health Services (NIEHS):

o 60 Hz is low frequency energy perceived as harmless

o No consistent pattern of biological effects from exposure to EMF has emerged from laboratory studies

o EMF produced by substation equipment is typically indistinguishable from background levels beyond the perimeter

• Existing 4.5 mile long transmission line adjacent to site across rail road tracks

• No federal or state EMF regulations exist

• Recommended shifted layout provides a spatial buffer

* https://www.niehs.nih.gov/health/topics/agents/emf/index.cfm 20

Page 21: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

21

PUBLIC INVOLVEMENTOPEN HOUSE INITIAL FEEDBACK

Flooding

Traffic

District 1 Councilman Roberto Treviño facilitated a meeting on October 29, 2019 with Monte Vista Terrace neighborhood association

• Electric & Magnetic Fields (EMF)

• Traffic

• Runoff & Drainage

• Aesthetics

Page 22: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

22

PUBLIC INVOLVEMENT NEIGHBORHOOD ASSOCIATION ADDITIONAL FEEDBACK

• Lighting

• Noise

• Radio interference

• Pocket park/green space

• Vegetative wall

• Alternative site

• Spatial buffer

• Shifting site onto neighboring property

District 1 Councilman Roberto Treviño facilitated a follow up meeting with Monte Vista Terrace neighborhood association on

Jan. 28, 2020

Page 23: MIDTOWN SUBSTATION SITE RECOMMENDATION...Mar 02, 2020  · SITE RECOMMENDATION PRESENTED BY: LeeRoy Perez Interim Senior Director, Substation & Transmission March 2, 2020 Approval

23

NEXT STEPS

• Notify customers of project approval & details of addressing Board public input session feedback

Mar 3, 2020

Project Manager will continue updating the community throughout the life of project