Top Banner
Microsoft Project 101: How to Build a Project Plan
45

Microsoft_Project_101_How_to_Build_a_Project_Plan.

Jun 24, 2015

Download

Business

Microsoft_Project_101_How_to_Build_a_Project_Plan.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Microsoft Project 101: How to Build a Project Plan

Page 2: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Overview

After this course you will understand and be able to:

• Set up a project document using best practices• Enter task details• Enter durations against tasks• Link tasks• Assign resources• Baseline the plan• Manage the project plan and track progress

Page 3: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Project Setup Best Practices

– Iterative Saves and Versions– Project information dialog box– Project defaults (check them before starting a

new project)– Project calendar adjustments (holidays, etc..)– Task Sheet View for initial task entry – Add columns

Page 4: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Project Information

Page 5: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Project Defaults

Page 6: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Project Defaults

Page 7: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Project Calendars

Page 8: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Views and Columns

• Task Sheet view• Add or hide a columns as necessary• Suggested columns:

– Task Name– % Complete– Duration– Work – Start – Finish– Resources

Page 9: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Exercise 1

• Setting project defaults

Page 10: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Tasks

• Project Summary Task

• Summary Tasks

• Sub-tasks

• Task Types – Fixed Units– Fixed Work– Fixed Duration (recommended)– Effort driven

Page 11: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Project Summary Task

• The project summary task has unique characteristics:– ID = 0– Unique ID = 0– Outline Level = 0– Summary – Yes

• Only project summary tasks can be created at Outline Level 0.

Page 12: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Summary Tasks

Page 13: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Subtasks

Page 14: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Types

• Fixed units – tasks where the resources are a fixed value & changes to the amount of work or the duration do not affect the resources

• Fixed work – tasks where the amount of work is a fixed value & changes to the duration or the number of resources do not affect the work.

• Fixed duration (recommended) – tasks where the duration is a fixed value & changes to the work or the resources don't affect the duration.

• Effort Driven – the duration of a task shortens or lengthens as resources are added or removed from a task while the effort (work) remains the same.

Page 15: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Types

Page 16: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Exercise 2

• Entering tasks

Page 17: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Information

• Task Information Form

• Milestone tasks

• Durations

• Constraints

• Dependencies (predecessors)

Page 18: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Information Form

Page 19: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Information Form

Page 20: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Information Form

Page 21: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Information Form

Page 22: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Information

Page 23: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Milestones

Page 24: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Duration

• When entering task durations, enter the amount of time expected to complete the task

• Duration abbreviations– M = Minutes– H = Hours– D = Days– W = Weeks– M = Months

Page 25: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Constraints

• Field dependencies• Constraint types

– As late as possible– As soon as possible– Finish no earlier than– Finish no later than– Must finish on– Must start on– Start no earlier than– Start no later than

Page 26: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Dependencies

• Predecessors– Finish to Start (FS default)– Start to Finish (SF)– Start to Start (SS)– Finish to Finish (FF rarely used)

Page 27: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Exercise 3

• Setting constraints, durations and predecessors

Page 28: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Resources

• Resource types

• Entering resources

• Assigning resources to a task

• Understanding “work”

Page 29: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Resource Types

• Work (people)

• Material (expenditures)

• Rates (hourly rate or cost of hardware)

Page 30: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Entering Resources

• Best done after tasks are entered and linked

• Assign names and work effort for each individual

• Duration is the length of time the task will take to complete, entered in days

• Work is the amount of effort needed to complete the task, entered in hours

Page 31: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Exercise 4

• Entering Resources

Page 32: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Tracking

• Base lining the project

• Entering actual information

Page 33: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Base lining the Project

• Purpose of base lining

• How to do it– Tools, Tracking, Save Baseline– Remember to baseline the ENTIRE project!

Page 34: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Entering Actuals

• Task sheet view

• Enter actual start date– Break links as needed

• Enter actual duration

• Enter actual time commitments

• Set task completion at 100%

• Sequence is VERY important

Page 35: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Exercise 5

• Base lining

• Entering Actuals

Page 36: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Views, Tables & Filters

• Views– Task Views– Gantt Chart– Tracking Gantt Chart– Custom Views

• Tables

• Filters and Groups

Page 37: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Task Sheet

• Task Sheet

• Used for reporting

• Basis for most custom forms

Page 38: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Gantt Chart View

Page 39: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Tracking Gantt

Page 40: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Custom Views

• Views are made up of– Tables– Filters– Groupings

• It is highly recommended that you copy the view AND any tables, filters and groups that are used to achieve that view.

Page 41: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Tables

• A table is the actual spreadsheet presentation of the rows and columns

• It stores which fields you see and how the columns are ordered

Page 42: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Filters & Groups

• Filters - a way to select a subset of tasks to be shown in a view.

• Groups - a way to organize rows based on field content.

• Filters and groups can be used together to order the data or they can be used independently.

• Filters and groups can be created using one or more conditions

Page 43: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Exercise 6

• Views

Page 44: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Summary

• Tip of the iceberg (much more capability).

• MS Project is a tool that aids planning, it won’t plan for you.

• Need to invest in mastering the tool.• MS Project training guides located at

http://www.k-state.edu/InfoTech/epm/training/index.html

• Iterative saves

Page 45: Microsoft_Project_101_How_to_Build_a_Project_Plan.

Contact Information

• Peer support – call if you need help• Chuck Gould

532- [email protected]

• Lloyd Walker532- [email protected]

• Ashley [email protected]