ID Task Name Duration Start Finish
1 REHABILITAS LANTAI SATU 1 day? Sat 3/26/16 Sat 3/26/16
2 PEKERJAAN PERSIAPAN DAN BONGKARAN 1 day? Sat 3/26/16 Sat 3/26/16
6
7 LANTAI 1 1 day? Sat 3/26/16 Sat 3/26/16
8 PEKERJAAN BONGKARAN DAN URUGAN 7 days Mon 5/30/16 Mon 6/6/16
9 Pek. Bongkar lantai keramik tangga 7 days Mon 5/30/16 Mon 6/6/16
10
11 PEKERJAAN PASANGAN 49 days Wed 6/29/16 Fri 8/19/16
12 Pas. Dinding bata m erah Toilet 13 days Wed 6/29/16 Tue 7/12/16
13 Pas. Plesteran + acian dinding bata Ad. 1 : 4 8 days Tue 7/12/16 Thu 7/21/16
14 Pas. Keram ik Lantai 40 x 40 cm corak setara 45 days Sun 7/3/16 Fri 8/19/16
15 Pas. Keram ik Lantai 20 x 20 cm corak setara 10 days Mon 7/18/16 Thu 7/28/16
16 Pas. Keram ik Dinding 20 x 25 cm setara rom 13 days Sun 7/24/16 Sat 8/6/16
17
18 PEKERJAAN INSTALASI AIR 21 days Mon 6/6/16 Tue 6/28/16
19 Pek. Bongkar kloset lama 3 days Mon 6/6/16 Wed 6/8/16
20 Pek. Pasang bongkar instalasi air bersih + air 3 days Thu 6/9/16 Sat 6/11/16
21 Pek. Pasang pipa air bersih PVC AW dia. 3/4" 4 days Sun 6/19/16 Thu 6/23/16
22 Pek. Pasang pipa air Kotor PVC AW dia. 2" 7 days Sun 6/12/16 Sun 6/19/16
23 Pek. Pasang pipa air Kotor PVC AW dia. 4" 6 days Sun 6/12/16 Sat 6/18/16
24 Pek. Pasang Kloset Jongkok 5 days Thu 6/16/16 Tue 6/21/16
25 Pek. Pasang Kran air bersih 3 days Thu 6/23/16 Mon 6/27/16
26 Pas. Urinoir lengkap 4 days Thu 6/23/16 Tue 6/28/16
27 Pas. Wastafel lengkap 2 days Thu 6/23/16 Sat 6/25/16
28 Pek. Pasang Wastafel Lengkap kaca cerm in 1 day Thu 6/23/16 Fri 6/24/16
29
30 PEKERJAAN KUSEN PERLENGKAPAN 49 days? Sun 7/10/16 Tue 8/30/16
31 Pas. Rolling Door 49 days Sun 7/10/16 Tue 8/30/16
32 Pas. Kusen Pintu KM 8 days Thu 7/21/16 Fri 7/29/16
33 Pas. Kusen Pintu Koboy 3 days Thu 7/21/16 Sun 7/24/16
34 Pas. Kusen pintu shaf 1 day? Thu 7/21/16 Fri 7/22/16
35
36 PEKERJAAN TANGGA SAMPING 1 day? Sat 3/26/16 Sat 3/26/16
37 TYPE.1 ( Lt Basement,Lt 1 dan Lt 2) 3 Unit 35 days Mon 6/6/16 Tue 7/12/16
38 Pek. Bongkar tangga lam a 4 days Mon 6/6/16 Thu 6/9/16
39 Galian Tanah Pondasi 4 days Fri 6/10/16 Tue 6/14/16
40 Lantai Kerja Untuk Pondasi tangga 2 days Tue 6/14/16 Thu 6/16/16
41 Pondasi Beton Bertulang Untuk tangga 4 days Thu 6/16/16 Mon 6/20/16
S M T W T F S S M T W T F S S MMay 29, '16 Jun 5, '16 Jun 12, '1
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
2/12
ID Task Name Duration Start Finish
42 Pek. Beton Plat Anak tangga 5 days Thu 6/23/16 Wed 6/29/16
43 Pek. Plat Beton Bordes tangga 5 days Tue 6/28/16 Sun 7/3/16
44 Pas. Batu bata M erah ( 1/2 bata Ad 1 : 4 ) Din 4 days Fri 6/10/16 Tue 6/14/16
45 Plesteran Dinding Pas. Bata Dinding Pengam 6 days Tue 6/14/16 Mon 6/20/16
46 Acian Dinding Pas bata Dinding Pengam an S 6 days Fri 6/17/16 Thu 6/23/16
47 Pengecatan Dinding Pengam an sam ping Tan 6 days Sat 6/25/16 Sat 7/2/16
48 Pek. Pasang Handriil pipa galvanis dia. 2" + 1 8 days Wed 6/29/16 Thu 7/7/16
49 Pas. Keram ik Tangga 30 x 40 cm corak setar 13 days Wed 6/29/16 Tue 7/12/16
50 Pek. Stepnosing Tangga 13 days Wed 6/29/16 Tue 7/12/16
51
52 TYPE.2 ( Lt Basement dan Lt.1) 35 days Mon 6/6/16 Tue 7/12/16
53 Pek. Bongkar tangga lam a 4 days Mon 6/6/16 Thu 6/9/16
54 Galian Tanah Pondasi 2 days Fri 6/10/16 Sat 6/11/16
55 Lantai Kerja Untuk Pondasi tangga 1 day Sun 6/12/16 Mon 6/13/16
56 Pondasi Beton Bertulang Untuk tangga 3 days Mon 6/13/16 Thu 6/16/16
57 Pek. Beton Plat Anak tangga 4 days Sun 6/19/16 Thu 6/23/16
58 Pek. Plat Beton Bordes tangga 4 days Sat 6/25/16 Thu 6/30/16
59 Pas. Batu bata M erah ( 1/2 bata Ad 1 : 4 ) Din 3 days Fri 6/10/16 Mon 6/13/16
60 Plesteran Dinding Pas. Bata Dinding Pengam 4 days Wed 6/15/16 Sun 6/19/16
61 Acian Dinding Pas bata Dinding Pengam an S 4 days Mon 6/20/16 Fri 6/24/16
62 Pengecatan Dinding Pengam an sam ping Tan 3 days Sat 6/25/16 Wed 6/29/16
63 Pek. Pasang Handriil pipa galvanis dia. 2" + 1 5 days Sat 6/25/16 Fri 7/1/16
64 Pas. Keram ik Tangga 30 x 40 cm corak setar 15 days Mon 6/27/16 Tue 7/12/16
65 Pek. Stepnosing Tangga 15 days Mon 6/27/16 Tue 7/12/16
66
67 PEKERJAAN PENGECATAN 35 days Sun 7/31/16 Tue 9/6/16
68 Pek. Pengerikan Cat Dinding Bagian dalam (b 23 days Sun 7/31/16 Wed 8/24/16
69 Pek. Pengerikan Cat Dak beton Bagian dalam 32 days Wed 8/3/16 Tue 9/6/16
70 Pek. Pengecatan Dinding Bagian dalam 2 x la 23 days Sun 7/31/16 Wed 8/24/16
71 Pek. Pengecatan Dak Beton Bagian dalam (ba 32 days Wed 8/3/16 Tue 9/6/16
72
73 REHABILITASI LISTRIK LANTAI SATU 49 days Sun 7/31/16 Tue 9/20/16
74 a. Pekerjaan Instalasi : 21 days Sun 7/31/16 Mon 8/22/16
75 1 Instalasi Titik Penerangan, Emg. & Fan 19 days Sun 7/31/16 Sat 8/20/16
76 2 Instalasi Titik Kotak Kontak 18 days Wed 8/3/16 Mon 8/22/16
77 b. Pekerjaan Pengadaan & Pemasangan Arma 28 days Sun 8/7/16 Tue 9/6/16
78 1 Arm. TL. TKO 1 X 18 WAT Setara PHILIPS 28 days Sun 8/7/16 Tue 9/6/16
79 2 Arm. TL. TKO 2 X 18 WAT Setara PHILIPS 12 days Sun 8/7/16 Sat 8/20/16
S M T W T F S S M T W T F S S MMay 29, '16 Jun 5, '16 Jun 12, '1
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 2
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
3/12
ID Task Name Duration Start Finish
80 3 Saklar Single 20 days Mon 8/15/16 Mon 9/5/16
81 4 Saklar Serie 6 days Mon 8/15/16 Sun 8/21/16
82 5 Kotak Kontak 20 days Mon 8/15/16 Mon 9/5/16
83 c. Pekerjaan Panel : 35 days Sun 8/14/16 Tue 9/20/16
84 1 PENGGANTIAN PANEL PENERANGAN U 15 days Sun 8/14/16 Tue 8/30/16
85 1 PENGGANTIAN PANEL PENERANGAN KI 15 days Tue 8/30/16 Wed 9/14/16
86 2 PENGGANTIAN HANTARAN 10 days Tue 8/30/16 Fri 9/9/16
87 3 PEMASANGAN METERAN TOKEN BARU 25 days Wed 8/24/16 Tue 9/20/16
88 4 PASANG MCB PENERANGAN UMUM 10 days Wed 8/24/16 Sun 9/4/16
89 d. Pekerjaan Kabel Feeder, Tray & Grounding : 14 days Sun 8/21/16 Mon 9/5/16
90 1 Kabel Feeder dari Panel Sambung - SDP.A 11 days Sun 8/21/16 Thu 9/1/16
91 2 Kabel Feeder dari Panel Sambung - SDP.B 11 days Wed 8/24/16 Mon 9/5/16
92 3 Tray Cable 100x100x2 mm, berikut Hanger 5 days Sun 8/21/16 Fri 8/26/16
93 4 Tray Cable 200x100x2 mm, berikut Hanger 5 days Fri 8/26/16 Wed 8/31/16
94 5 Asessories & Peralatan bantu 14 days Sun 8/21/16 Mon 9/5/16
95 e. Commisioning Test : 6 days Thu 9/22/16 Wed 9/28/16
S M T W T F S S M T W T F S S MMay 29, '16 Jun 5, '16 Jun 12, '1
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 3
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
4/12
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WJun 19, '16 Jun 26, '16 Jul 3, '16 Jul 10, '16 Jul 17, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 4
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
5/12
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WJun 19, '16 Jun 26, '16 Jul 3, '16 Jul 10, '16 Jul 17, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 5
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
6/12
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WJun 19, '16 Jun 26, '16 Jul 3, '16 Jul 10, '16 Jul 17, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 6
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
7/12
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TJul 24, '16 Jul 31, '16 Aug 7, '16 Aug 14, '16 Aug 21, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 7
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
8/12
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TJul 24, '16 Jul 31, '16 Aug 7, '16 Aug 14, '16 Aug 21, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 8
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
9/12
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TJul 24, '16 Jul 31, '16 Aug 7, '16 Aug 14, '16 Aug 21, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 9
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
10/12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Aug 28, '16 Sep 4, '16 Sep 11, '16 Sep 18, '16 Sep 25, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 10
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
11/12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Aug 28, '16 Sep 4, '16 Sep 11, '16 Sep 18, '16 Sep 25, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 11
Project: Project1 4Date: Sun 3/27/16
8/17/2019 Microsoft Office Project - Project1 2.pdf
12/12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Aug 28, '16 Sep 4, '16 Sep 11, '16 Sep 18, '16 Sep 25, '16
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 12
Project: Project1 4Date: Sun 3/27/16